This document is a solicitation for refrigeration equipment replacement and door repair services at two buildings of the Corporal Michael J. Crescenz VA Medical Center in Philadelphia. The scope of work includes replacing condensers, evaporators, and doors in multiple walk-in refrigerators and freezers. The contractor must provide all labor, materials, and equipment to remove failing components and install new condensing units, evaporators, piping, and a replacement door. The work is to be completed within 150 days of award. This procurement is set aside exclusively for service-disabled veteran-owned small businesses. Interested parties are encouraged to attend a pre-bid site visit on September 8, 2022. The award will be made to the responsive and responsible bidder offering the lowest price.

View the file

Other files

File Type Posted
36C24422B0011 0001.docx DOCX document
Abstract of Offers.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C24422B0011 642-22-130 - Building 2, 30 – Refrigerator Condensing Unit and Refrigerator Door Repairs

A.1 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)

(a) As an alternative to filing a protest with the Contracting Officer, an interested party may file a protest by mail or electronically with: Executive Director, Office of Acquisition and Logistics, Risk Management and Compliance Service (003A2C), Department of Veterans Affairs, 810 Vermont Avenue NW, Washington, DC 20420 or Email: EDProtests@va.gov.

(b) The protest will not be considered if the interested party has a protest on the same or similar issue(s) pending with the Contracting Officer.

(End of Provision)

FAR Number
Title
Date
52.204-8
ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAY 2022) (JUL 2020) (DEVIATION)
MAY 2022

A.2 VAAR 852.219-77 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (SEP 2021) (DEVIATION)

(a) Pursuant to 38 U.S.C. 8127(k)(2), the offeror certifies that—

(1) If awarded a contract (see FAR 2.101 definition), it will comply with the limitations on subcontracting requirement as provided in the solicitation and the resultant contract, as follows:

(i) [] Services. In the case of a contract for services (except construction), the contractor will not pay more than 50% of the amount paid by the government to it to firms that are not VIP-listed SDVOSBs as set forth in 852.219-10 or VOSBs as set forth in 852.219-11. Any work that a similarly situated VIP-listed subcontractor further subcontracts will count towards the 50% subcontract amount that cannot be exceeded. Other direct costs may be excluded to the extent they are not the principal purpose of the acquisition and small business concerns do not provide the service as set forth in 13 CFR 125.6.

(ii) [X] General construction. In the case of a contract for general construction, the contractor will not pay more than 85% of the amount paid by the government to it to firms that are not VIP-listed SDVOSBs as set forth in 852.219-10 or VOSBs as set forth in 852.219-11. Any work that a similarly situated VIP-listed subcontractor further subcontracts will count towards the 85% subcontract amount that cannot be exceeded. Cost of materials are excluded and not considered to be subcontracted.

(iii) [] Special trade construction contractors. In the case of a contract for special trade contractors, the contractor will not pay more than 75% of the amount paid by the government to it to firms that are not VIP-listed SDVOSBs as set forth in 852.219-10 or VOSBs as set forth in 852.219-11. Any work that a similarly situated subcontractor further subcontracts will count towards the 75% subcontract amount that cannot be exceeded. Cost of materials are excluded and not considered to be subcontracted.

(2) The offeror acknowledges that this certification concerns a matter within the jurisdiction of an Agency of the United States. The offeror further acknowledges that this certification is subject to Title 18, United States Code, Section 1001, and, as such, a false, fictitious, or fraudulent certification may render the offeror subject to criminal, civil, or administrative penalties, including prosecution.

(3) If VA determines that an SDVOSB/VOSB awarded a contract pursuant to 38 U.S.C. 8127 did not act in good faith, such SDVOSB/VOSB shall be subject to any or all of the following:

(i) Referral to the VA Suspension and Debarment Committee;

(ii) A fine under section 16(g)(1) of the Small Business Act (15 U.S.C. 645(g)(1)); and

(iii) Prosecution for violating section 1001 of title 18.

(b) The offeror represents and understands that by submission of its offer and award of a contract it may be required to provide copies of documents or records to VA that VA may review to determine whether the offeror complied with the limitations on subcontracting requirement specified in the contract. The Contracting Officer may, at their discretion, require the Contractor to demonstrate its compliance with the limitations on subcontracting at any time during performance and upon completion of a contract if the information regarding such compliance is not already available to the Contracting Officer. Evidence of compliance includes, but is not limited to, invoices, copies of subcontracts, or a list of the value of tasks performed.

(c) The offeror further agrees to cooperate fully and make available any documents or records as may be required to enable VA to determine compliance with the limitations on subcontracting requirement. The offeror understands that failure to provide documents as requested by VA may result in remedial action as the Government deems appropriate.

(d) Offeror completed certification/fill-in required. The formal certification must be completed, signed, and returned with the offeror’s bid, quotation, or proposal. The Government will not consider offers for award from offerors that do not provide the certification, and all such responses will be deemed ineligible for evaluation and award.

Certification:

I hereby certify that if awarded the contract, [insert name of offeror] will comply with the limitations on subcontracting specified in this clause and in the resultant contract. I further certify that I am authorized to execute this certification on behalf of [insert name of offeror].

Printed Name of Signee:________________________________________ Printed Title of Signee:_________________________________________ Signature:___________________________________________________ Date:_____________________ Company Name and Address:________________________________________ (End of Clause)

A.3 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008)

The contracting officer reserves the right to designate representatives to act for him/her in furnishing technical guidance and advice or generally monitor the work to be performed under this contract. Such designation will be in writing and will define the scope and limitation of the designee's authority. A copy of the designation shall be furnished to the contractor.

(End of Clause)

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C24422B0011 X 09-06-2022 642-22-4-526-0143 642-22-130 00244 Department of Veterans Affairs Network Contracting Office 4 ATTN: Maureen Jackson BLDG 5, 3900 Woodland Avenue Philadelphia

PA

19104 See Block 7

Maureen Jackson 215-823-5800 642-22-130 - Building 2, 30 – Refrigerator Condensing Unit and Refrigerator Door Repairs

The scope of work consists of providing all labor, materials, and equipment to perform the tasks outlined in the Statement of Work to replace the refrigeration equipment in Building 2 at the VAMC Philadelphia, PA.

The contractor shall abide by all federal state, and local code/regulations/standards.

Magnitude of Construction: Between $250,000 and $500,000.

NAICS: 236220 - Commercial and Institutional Building Construction Size Standards: $39.5 Million This procurement is a 100% Service Disabled Veteran Owned Small Business (SDVOSB) set-aside acquisition.

Award will be made to the responsive, responsible bidder, whose bid, in conformance with the solicitation, results in the Lowest Price.

This solicitation will result in a firm-fixed price contract. Only one award will be made.

Bidders must be registered and certified in VETBIZOPS to be eligible for award, SEE http:/www.vip.vetbiz.gov/ Bidders must be registered in SAM to be eligible for award, SEE https://www.sam.gov/.

Bidders must be registered in the VETS-4212 Database, SEE https://www.dol.gov/vets/vets4212.htm.

Interested parties are encouraged to attend the pre-bid Conference/Site Visit, which will be held IAW FAR 52.236-27 Site Visit (FEB 1995).

Bids will be conducted at the Philadelphia Contracting Office located at 3900 Woodland Avenue Building 5, Philadelphia, PA 19104.

The Contractor shall be responsible for the correct title classification of workers and compliance with all applicable wage and hour laws.

Solicitation may be canceled and all offers rejected before award but after solicitation closing date when it is clearly in the best interest of the Government.

A Site Visit has been scheduled for September 8, 2022 at 11:00 AM, Participants will meet at Bldg 5 VAMC Philadelphia PA

X X 52.211-10 X 14:00

EDT

09-21-2022 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

00244 Department of Veterans Affairs Network Contracting Office 4

Austin Payment Center Department of Veterans Affairs PO Box 149971 Austin

TX

78714-9971

(877) 353-9791

(512) 460-5429

Table of Contents

A.1 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)1
A.2 VAAR 852.219-77 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (SEP 2021) (DEVIATION)1
A.3 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008)3
PART I - THE SCHEDULE4
SECTION A - SOLICITATION/CONTRACT FORM4
A.4 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)4
A.5 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK5
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS11
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS12
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)12
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)12
2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)12
2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)13
2.5 52.233-2 SERVICE OF PROTEST (SEP 2006)14
2.6 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)15
2.7 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)16
2.8 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)16
2.9 52.223-99 ENSURING ADEQUATE COVID-19 SAFETY PROTOCOLS FOR FEDERAL CONTRACTORS (OCT 2021) (DEVIATION)16
2.10 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (NOV 2021)17
2.11 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)21
2.12 52.223-21 FOAMS (JUN 2016)22
REPRESENTATIONS AND CERTIFICATIONS24
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAY 2022)24
3.2 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021)28
3.3 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)30
3.4 SUPPLEMENTAL INSURANCE REQUIREMENTS30
3.5 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018)32
3.6 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)33
3.7 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)34
3.8 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020)34
3.9 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)35
3.10 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)37
3.11 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)37
3.12 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)37
3.13 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)38
3.14 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)41
GENERAL CONDITIONS43
4.1 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (SEP 2021)43
4.2 52.223-20 AEROSOLS (JUN 2016)46
4.3 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2019) (DEVIATION)47
4.4 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)49
4.5 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)50
4.6 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)50
4.7 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS– CPM) (NOV 2018)50

DEPARTMENT OF VETERANS AFFAIRS

Philadelphia VA Medical Center 3900 Woodland Ave Philadelphia, PA 19104

Page 1 of Page 1 of

Page 1 of Page 1 of Page 1 of

STATEMENT OF WORK

642-22-130 - Building 2, 30 – Refrigerator Condensing Unit and Refrigerator Door Repairs

· Scope Summary: The selected contractor will provide all labor, material, and equipment necessary to replace the refrigeration equipment in Building 2 main kitchen room B2B123. Multiple walk-in cooler and freezers replacement. Also, the walk-in refrigerator door needs replaced in the Building 30 main kitchen room 1A110.

· Performance Period: This installation should take place within 150 days of award unless otherwise specified.

· Task and Requirements: The selected contractor will provide the necessary labor, equipment, and material to:

· Replace equipment inside the walk-in boxes and walk in freezers: condensers and evaporators. See equipment schedule below for breakout.

· Replace walk in box Door in CLC. Including all hardware closure, and Frame to insure proper seal and operation

· Recover remaining refrigerant from system

· Remove failing condensing unit and failing evaporator from system

· Install new condensing unit and evaporator assembly

· Install new Properly sized refrigerant piping to and from each individual condenser to evaporator assembly inside walk in refrigerators and freezers

· Disconnect and reconnect all mechanical and electrical connections to components of systems

· Pressure test refrigerant piping with nitrogen to ensure systems have no leaks in new piping

· Evacuate refrigerant piping to a minimum 500 microns

· Charge systems with new refrigerant

· Do a proper start-up to verify operating temperatures and pressures

· Brazing will be required for all connections

· Insulate all piping as required

· All required piping modifications for correct functionality of the system related to the above work

· Seal all penetrations properly including panels of interior boxes with silicone

· Schedule: The contractor shall perform all tasks during weekday hours Between 6:00am- 3:30 pm. Replacement of equipment to be coordinated with kitchen manager/COR.

· Place of Performance: All work will be performed at the Corporal Michael J. Crescenz VA Medical Center, 3900 Woodland Ave. (Bldg#2) and (Bldg. #30) Philadelphia, PA 19104.

· Site Security: The contractor will not have access to sensitive information, software, programs, computers, laptops, or cell phones during this service.

· Safety: Contractor crew shall be OSHA 10 certified and abide by all applicable safety regulations established by VA and federal policies.

1. Evaluation Factors: The proposals will be evaluated on the following criteria:

8. Price

· Quality Control: All work shall be accomplished in accordance with federal, state, local, and VA guidelines, codes, and regulations. Refer to the Technical Information Library for all technical requirements: https://www.cfm.va.gov/til/spec.asp

· Industrial Hygiene: Contractor is responsible for clean-up of the work site and the disposal of all waste and excess materials. Contractor shall not utilize VA waste containers to dispose of their waste and materials. All waste and excess materials shall be removed from the facility and disposed of properly by the contractor.

· Parking: Contractor will have parking access for one vehicle.

· Other Criteria: Any damage caused by the contractor to the facility including but not limited to walls, ceilings, surfaces, equipment, furniture, utility lines, etc. shall be repaired to match existing conditions. Contractor shall be responsible to make these repairs at their own expense.

· EQUIPMENT:

1) Walk in freezer 36x13x7’6 (1 condensing unit and 3 evaporators) Condensing unit 6HP, 208 3 PH Crankcase heater, Adjustable low-pressure control, fixed high pressure control Sealed liquid line drier, liquid line sight glass, liquid line and suction line base valves Painted steel cabinet, Removable & hinged e-box door with cabinet fasteners Evaporator 208V *Electric defrost

* Low profile, pre- assembled electronically commutated motors, L

* Features the intelliGen refrigeration controller is a factory-mounted electronic control that delivers reliable operation and system performance. Intelligen helps reduce product spoilage by maintaining better temperature control and provides energy savings through optimizing defrosts

2) 3x Walk in refrigerators (each system is one condensing unit and two evaporators) 60x15 Meat cooler 23x19 Veg cooler 14x30 Retherm box

Condensing unit 2.5HP 208V 3 PH Standard features Microchannel coil, Head pressure control valve150 psi standard Crankcase heater, Adjustable low-pressure control, Fixed high pressure control Sealed liquid line drier, liquid line sight glass, liquid line and suction line base valves Painted steel cabinet, Removable & hinged e-box door with captive fasteners Evaporator 115V *Air Defrost *Low-profile, pre- assembled electronically commuatated motors, L *Feature the Intelligen Refrigeration controller is a factory mounted electronic control that delivers reliable operation and system performance. Itelligen helps reduce product spoilage by maintaining better temperature control and provides energy savings through optimizing defrosts

3)Walk in Veg freezer 26x13(1 condensing unit and two evaporators)

Condensing unit 5HP, 208 3PH Crankcase heater, adjustable low-pressure switch, fixed high pressure control Sealed liquid line drier, liquid line sight glass, liquid line and suction line base valves Painted steel cabinet, Removable & hinged e-box door with captive fasteners Evaporator 208V *Electric defrost

* Low profile, pre- assembled, electronically commuted motors, L *Feature the Intelligen Refrigeration controller is a factory-mounted electronic control that delivers reliable operation and system performance. Itelligen helps reduce product spoilage by maintain better temperature control and provides energy savings through optimizing defrosts

3) Dairy cooler 16x20(1 condensing unit 2 evaporators Condensing unit 2 HP 208V 3PH Standard features Microchannel coil, head pressure control valve 150psi standard Crankcase heater, adjustable low-pressure control, fixed high pressure control Sealed liquid line drier, liquid line sight glass, liquid line and suction line base valves Painted steel cabinet, removable and hinged e-box door with captive fasteners Evaporator 115V *Air Defrost *Low profile, pre-assembled, electronically commuted motors, L *Features the Intelligen refrigeration controller is a factory-mounted electronic control that delivers reliable operation and system performance, Intelligen helps reduce product spoilage by maintaining better temperature control and provides energy savings through optimizing defrosts

5)CLC Dairy cooler26x13(1 condensing unit 2 evaporators) Condensing unit 2.5 HP 208V 3 PH Standard features Microchannel coil, head pressure control valve 150 psi standard Crankcase heater, adjustable low-pressure control, fixed high pressure control Sealed liquid line drier, liquid line sight glass, liquid line and suction line base valves Painted steel cabinet, removable & hinged e-box door with captive fasteners Evaporator115V *Air Defrost *Low profile, pre- assembled, electronically commutated motors, L

* Features the Intelligen refrigeration controller is a factory-mounted electronic control that delivers reliable operation and system performance. Intelligen helps reduce product spoilage by maintaining better temperature control and provides energy savings through optimizing defrosts

6) CLC cooler 13x10 Condensing unit 1HP 208V 3PH Standard features Microchannel coil, head pressure control valve 150psi standard Crankcase heater, adjustable low-pressure control, fixed high pressure control Sealed liquid line drier, liquid line sight glass, liquid line and suction line base valves Painted steel cabinet, removable & hinged e-box door with captive fasteners Evaporator 115V *Air Defrost *Low profile, pre-assembled, electronically commutated motors, L *Features the intelligen refrigeration controller is a factory-mounted electronic control that delivers reliable operation and system performance, intelligen helps reduce product spoilage by maintaining better temperature control and provides energy savings through optimizing defrosts.

7) CLC cooler 1A110C Walk in box Door TK-4278-F-L(must be confirmed) Door, Closer Hardware Heater 110V Size 48P

Page 1 of Page 1 of

INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

(End of Provision)

2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade
Goals for female participation for each trade
17.3 %
6.9 %

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Philadelphia County

(End of Provision)

2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

FAR Number
Title
Date
52.228-17
INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE)
FEB 2021

2.5 52.233-2 SERVICE OF PROTEST (SEP 2006)

Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:

Maureen Jackson

Hand-Carried Address:

3900 Woodland Ave Building 5

Philadelphia PA 19104 Mailing Address:

Same as above

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

2.6 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/

(End of Provision)

FAR Number
Title
Date
52.204-16
COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING
AUG 2020
52.214-3
AMENDMENTS TO INVITATIONS FOR BIDS
DEC 2016
52.214-5
SUBMISSION OF BIDS
DEC 2016
52.214-7
LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS
NOV 1999
52.214-19
CONTRACT AWARD—SEALED BIDDING—CONSTRUCTION
AUG 1996
52.214-35
SUBMISSION OF OFFERS IN U.S. CURRENCY
APR 1991
52.228-1
BID GUARANTEE
SEP 1996

2.7 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for— September 8, 2022 at 11:00 AM

(c) Participants will meet at— 3900 Woodland Ave, Bldg 5, Philadelphia PA (End of Provision)

FAR Number
Title
Date
52.204-7
SYSTEM FOR AWARD MANAGEMENT
OCT 2018
52.204-22
ALTERNATIVE LINE ITEM PROPOSAL
JAN 2017
52.214-4
FALSE STATEMENTS IN BIDS
APR 1984
52.214-6
EXPLANATION TO PROSPECTIVE BIDDERS
APR 1984
52.214-18
PREPARATION OF BIDS—CONSTRUCTION
APR 1984

2.8 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) Prime contractors are encouraged to assist service-disabled veteran-owned and veteran-owned small business potential subcontractors in obtaining bonding, when required. Mentor firms are encouraged to assist protégé firms under VA's Mentor-Protégé Program in obtaining acceptable bid, payment, and performance bonds, when required, as a prime contractor under a solicitation or contract and in obtaining any required bonds under subcontracts.

(End of Clause)

FAR Number
Title
Date
52.222-40
NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT
DEC 2010

2.9 52.223-99 ENSURING ADEQUATE COVID-19 SAFETY PROTOCOLS FOR FEDERAL CONTRACTORS (OCT 2021) (DEVIATION)

(a) Definition. As used in this clause— United States or its outlying areas means—

(1) The fifty States;

(2) The District of Columbia;

(3) The commonwealths of Puerto Rico and the Northern Mariana Islands;

(4) The territories of American Samoa, Guam, and the United States Virgin Islands; and

(5) The minor outlying islands of Baker Island, Howland Island, Jarvis Island, Johnston Atoll, Kingman Reef, Midway Islands, Navassa Island, Palmyra Atoll, and Wake Atoll.

(b) Authority. This clause implements Executive Order 14042, Ensuring Adequate COVID Safety Protocols for Federal Contractors, dated September 9, 2021 (published in the Federal Register on September 14, 2021, 86 FR 50985).

(c) Compliance. The Contractor shall comply with all guidance, including guidance conveyed through Frequently Asked Questions, as amended during the performance of this contract, for contractor or subcontractor workplace locations published by the Safer Federal Workforce Task Force (Task Force Guidance) at https:/www.saferfederalworkforce.gov/contractors/.

(d) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (d), in subcontracts at any tier that exceed the simplified acquisition threshold, as defined in Federal Acquisition Regulation 2.101 on the date of subcontract award, and are for services, including construction, performed in whole or in part within the United States or its outlying areas.

(End of Clause)

2.10 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (NOV 2021)

(a) Definitions. As used in this clause— Commercially available off-the-shelf (COTS) item—

(1) Means any item of supply (including construction material) that is—

(i) A commercial product (as defined in paragraph (1) of the definition of ‘‘commercial product’’ at Federal Acquisition Regulation (FAR) 2.101;

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

Component means any article, material, or supply incorporated directly into construction material.

Construction material means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means—

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the end product (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Domestic construction material means—

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both—

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if—

(A) The cost of its components mined, produced, or manufactured in the United States exceeds 55 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or

(B) The construction material is a COTS item; or

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of ‘‘cost of components’’.

Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

Foreign construction material means a construction material other than a domestic construction material.

Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

United States means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:

None

[Contracting Officer to list applicable excepted materials or indicate ‘‘none’’]

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that—

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute.

(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including—

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

FOREIGN AND DOMESTIC CONSTRUCTION MATERIALS PRICE COMPARISON

Construction Material Description
Unit of Measure
Quantity
Price (Dollars)*

Item 1:

Foreign Construction Material.

Domestic Construction Material.

Item 2:

Foreign Construction Material.

Domestic Construction Material.

[*Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).] [List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.] [Include other applicable supporting information.] (End of Clause)

2.11 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/

(End of Clause)

FAR Number
Title
Date
52.203-3
GRATUITIES
APR 1984
52.203-6
RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT
JUN 2020
52.203-8
CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR IMPROPER ACTIVITY
MAY 2014
52.203-12
LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS
JUN 2020
52.203-19
PROHIBITION ON REQUIRING CERTAIN INTERNAL CONFIDENTIALITY AGREEMENTS OR STATEMENTS
JAN 2017
52.204-10
REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS
JUN 2020
52.204-18
COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE
AUG 2020
52.204-23
PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES
NOV 2021
52.209-6
PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH CONTRACTORS DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT
NOV 2021
52.219-8
UTILIZATION OF SMALL BUSINESS CONCERNS
OCT 2018
52.222-3
CONVICT LABOR
JUN 2003
52.222-4
CONTRACT WORK HOURS AND SAFETY STANDARDS—OVERTIME COMPENSATION
MAY 2018
52.222-6
CONSTRUCTION WAGE RATE REQUIREMENTS
AUG 2018
52.222-7
WITHHOLDING OF FUNDS
MAY 2014
52.222-8
PAYROLLS AND BASIC RECORDS
JUL 2021
52.222-9
APPRENTICES AND TRAINEES
JUL 2005
52.222-10
COMPLIANCE WITH COPELAND ACT REQUIREMENTS
FEB 1988
52.222-11
SUBCONTRACTS (LABOR STANDARDS)
MAY 2014
52.222-12
CONTRACT TERMINATION—DEBARMENT
MAY 2014
52.222-13
COMPLIANCE WITH CONSTRUCTION WAGE RATE REQUIREMENTS AND RELATED REGULATIONS
MAY 2014
52.222-14
DISPUTES CONCERNING LABOR STANDARDS
FEB 1988
52.222-15
CERTIFICATION OF ELIGIBILITY
MAY 2014
52.222-21
PROHIBITION OF SEGREGATED FACILITIES
APR 2015
52.222-26
EQUAL OPPORTUNITY
SEP 2016
52.222-27
AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION
APR 2015
52.222-36
EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES
JUN 2020
52.222-37
EMPLOYMENT REPORTS ON VETERANS
JUN 2020
52.222-50
COMBATING TRAFFICKING IN PERSONS
NOV 2021
52.222-54
EMPLOYMENT ELIGIBILITY VERIFICATION
MAY 2022
52.222-55
MINIMUM WAGES FOR CONTRACTOR WORKERS UNDER EXECUTIVE ORDER 14026
JAN 2022
52.222-62
PAID SICK LEAVE UNDER EXECUTIVE ORDER 13706
JAN 2022
52.223-5
POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION
MAY 2011
52.223-6
DRUG-FREE WORKPLACE
MAY 2001
52.223-18
ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE DRIVING
JUN 2020

2.12 52.223-21 FOAMS (JUN 2016)

(a) Definitions. As used in this clause— Global warming potential means how much a given mass of a chemical contributes to global warming over a given time period compared to the same mass of carbon dioxide. Carbon dioxide's global warming potential is defined as 1.0.

High global warming potential hydrofluorocarbons means any hydrofluorocarbons in a particular end use for which EPA's Significant New Alternatives Policy (SNAP) program has identified other acceptable alternatives that have lower global warming potential. The SNAP list of alternatives is found at 40 CFR part 82, subpart G, with supplemental tables of alternatives available at http://www.epa.gov/snap/.

Hydrofluorocarbons means compounds that contain only hydrogen, fluorine, and carbon.

(b) Unless otherwise specified in the contract, the Contractor shall reduce its use, release, and emissions of…