This document contains a questions and answers file and a federal contract opportunity notice for the Demolish Water Tower Design Build project at the Butler VA Health Care System. The project involves selecting a prime contractor through a two-phase design-build solicitation to provide design and demolition services. Only SDVOSB firms will be allowed to participate in Phase One and submit proposals by February 18, 2021 for evaluation of experience, qualifications and past performance. If selected, firms will then submit Phase Two offers for evaluation of technical approach and price. The contract will be awarded in summer 2021 and have a 200-day period of performance from notice to proceed. Services include demolishing a 250,000 gallon water tower and removing its foundation, with daily work hours from 7:30am to 4:00pm and possibly extending to 5:00am to 8:00pm on a case-by-case basis. The site is located off 325 New Castle Road near the main gate, which handles temporary contract badging.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q1. The project is described as a Design Build. There is no actual construction…correct? It is just the demolition of the existing old water tower. Please confirm.
A1. The requirements for the project are in the Statement of Work attached to the Request for proposal.
Q2. It looks like all of the drawings and specifications for the demolition have been completed by Tolman Engineering. Therefore, all of the A/E services outlined in the solicitation documents are already prepared with the exceptions of actual onsite work plans and safety procedures. Is this correct?
A2. No, The Drawings and specification’s need reviewed and updated by and accepted by a licensed AE. And approved by VA.
Q3. Just for curiosity, why are you approaching this project with the 2 Phased Approach Selection Procedure?
I am asking because the project Is not overly large or complex to do a pre-proposal vendor evaluation.
A3. Refer to 1.3 Phase I – Volume I will be evaluated for experience, technical qualifications and past performance only. Offeror shall Each section – Exhibits included must therefore be labeled with the offeror's organization, business address, and VA Project Number. Offerors shall affix their names and return addresses on their envelope/packaging.
Q4. When are the Phase 1 submittals are due?
A4. Phase I offers (original and three spiral bound hard copies, (Total 4 sets) and one (1) CD/DVD – NO USB FORMATTING) are now due on February 18, 2021 by 3 PM E.D.T. a commercial service verified delivery receipt is required.
Q5. When do you anticipate the demo of this tank to occur to the nearest month?
A5. Contract award is anticipated to be awarded summer of 2021, Contractor design build team will determine demolition date in accordance with the SOW.
Q6. How many gallons is the existing tank?
A6. 250,000
Q7 How deep will the foundation need to be removed?
A7. Foundation’s completely removed, Contractor to verify actual depth or elevation through their AE.
Q8. Will a new tank be built to replace this tank?
A8. No
Q9. Will the crew be required to have background checks? If so is there a specific form required to obtain these?
A9. No
Q10. Will the crew need to go through a badging process to work on the site? If so what are the hours of the badging office? Where is the gate located in relation to the tank site?
AMENDMENT A0003 Project 529-14-101 Demo Water Tower Questions and Answers
A10. The crew will be issued temporary contract badges, for the duration of the job. The main gate is off of 325 New Castle Road.
Q11. Where is the gate located in relation to the tank site?
A11. The gate is located off of 325 New Castle Road
Q12. Do you have current pictures of the surrounding area? We are curious what is around the site for overhead power lines?
A12. No Power lines in the near vicinity.
Q13. Could the work hours be extended to 5 am to 8 pm?
A13. Possibly on a case by case basis, but the normal daily work hours are 0730 to 1600
AMENDMENT A0003 Project 529-14-101 Demo Water Tower Questions and Answers