About this file

This document outlines a federal contract opportunity for architectural and engineering services to develop a facility master plan for the Butler VA Medical Center located in Butler, Pennsylvania. Interested firms must submit a Standard Form 330 by May 28, 2020 responding to capabilities in areas such as professional qualifications of staff, experience completing similar master plan projects for VA facilities, past performance, capacity to complete the project on schedule, and location of the design office. The contract will be set aside for Service-Disabled Veteran-Owned Small Businesses and awarded on a firm-fixed price basis. The selected contractor will collect data, conduct analyses, and develop a basis of study, schematic study, draft master plan and construction phasing plan, study review, and final study by phases concluding by March 15, 2021. Deliverables include plans, drawings, cost estimates, and promotional materials.

36C24420R0060 Attachment C--Sample Contents Master Plan.pdf

View the file

Other files for this federal contract opportunity

Other files attached to C214--Facility Master Plan A&E, newest first.
File Type Posted
36C24420R0060-004.docx DOCX document
36C24420R0060-005.pdf PDF
36C24420R0060-006.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Exhibit C – Sample Master Plan Contents

1. Facility Overview

a. Summary of Facility Goals

b. Strategy to achieve Facility goals

c. Open issues

2. Facility Analysis:

a. Site Analysis showing:

i. Constructed features

ii. Site restraints (easements, zoning, height, etc.)

iii. Vehicular and pedestrian circulation plus traffic

iv. Parking demand (VA provided tool)

v. Physical security

vi. Major utility routing

vii. Environmental issues

viii. Historic issues

ix. Elevation and contours

x. Flood zones

b. Market Level Services Delivery Plan

i. Existing and proposed services

ii. Delivery Models

iii. Service Gap Analysis

c. Space use analysis and projections (Validate/update and complete)

i. Based on 10 year Space Calculator projections and/or other criteria with VA concurrence

ii. Organized by project and building

iii. Space Gap Analysis (projected space minus space per the facility's Capital Asset Inventory) with explanation of limitations of analysis

(a) Identification of gaps

(b) Closing of gaps

d. Facility condition analysis

(a) Summary of changes to FCA

(b) Best use designation of each facility

3. Campus Development:

a. Campus zoning site plans showing:

i. Areas of planned development – describe type and scope

ii. Areas reserved for future needs

iii. Parking areas

iv. Easements Infrastructure development (where information is available)

v. Area considered to be excess after all potential VA needs are considered – Identify on plan and in table giving description

vi. Conceptual building stacking plans showing:

(a) Areas of all departments and section diagrams for existing which are to be renovated or expanded and new buildings

(b) Recommendation on whether future development should have interstitial floors. Include related project identifiers and phasing verbiage

(c) Identification of historic preservation issues (information to be provided by VA)

4. Project Development:

a. For proposed facility projects (for each project) (MS Project):

i. Project listing and classification

ii. Identifier

iii. Description

iv. Project goal

v. Functions included

vi. Space requirements, departmental level

vii. Major, Minor, NRM, or Lease

viii. Total estimated cost

ix. Conceptual plans including adjacencies

x. Conceptual stacking diagrams

xi. Phasing issues

xii. Development Sequence

(a) Graphic and narrative information

(b) Recommended sequence of project

(c) Fiscal Year funding requirements

(d) Illustrations showing end state development with keyed identification of department/service locations

b. Capital (funds) requirements plan – time phased

c. Anticipated project outcomes – detail of how project will:

i. Increase operational efficiency, lower cost of operations

ii. Provide enhanced Veteran centric care

iii. Improve patient safety

iv. Close existing

(a) Utilization gaps

(b) Space Gaps

(c) Reduce Facility Condition Assessment items

5. Appendices of Supporting Documents:

a. Supporting Documents include:

i. Summaries of interviews

ii. Meeting minutes

iii. Documents and files provided by VA

iv. Documents and files provided by Vendors

v. Documents and reference material accessed during Task Order work

vi. Annotated Facility Condition Analysis

vii. Annotated Capital Assets Inventory

viii. Other Deliverables referenced in this TO

ix. Provided in native electronic format.

File details come from the government source that posted it. Updated .