36C24418Q0003-00001000.docx

DOCX document 37 KB Posted

Attached to
Asbestos, Lead, and Mold Abatement
Solicitation number
36C24418Q0003
Issued by

About this file

36C24418Q0003 00001 36C24418Q0003 00001.docx

View the file

Other files

File Type Posted
36C24418Q0003-00002000.docx DOCX document
36C24418Q0003-003.pdf PDF
36C24418Q0003-001.docx DOCX document
36C24418Q0003-002.doc DOC document
36C24418Q0003-000.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2.

AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE

OF PAGES

10A. MODIFICATION OF

CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV.

11/2016) is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITE

M 10A.

15C. DATE

SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR

43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes r eference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

BY

Contractor

16C. DATE

SIGNED

14.

DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME

AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS

OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 00001 11-21-2017 None 00244 Department of Veterans Affairs Network Contracting Office 4 Services 1 1400 Black Horse Hill Road Coatesville PA 19320 00244 Department of Veterans Affairs Network Contracting Office 4 Services 1 1400 Black Horse Hill Road Coatesville PA 19320 To all Offerors/Bidders

36C24418Q0003 11-21-2017

X X X

11/29/2017, 1:00PM ET

X The purpose of this solicitation amendment is to change the contract line items from those stated in the base solicitation . Please disregard and omit the line item numbers (CLINs) of the base solicitation (i.e. 0001 - 4013).

Please complete the attached chart with proposed unit prices per item. The line items of the attached chart will be utilized as the CLINs in the contract award document.

The solicitation is being extended from November 27, 2017 to November 29, 2017 at 1:00PM.

All quotes must be submitted via email to Ms. Brittney Parker at Brittney.Parker@va.gov NLT the solicitation closing date and time specified.

Abatement Services – Unit cost will be used for the awarded contract document.

Base Year:

ABATEMENTS INCLUDING ALL DISPOSAL COSTS
UNIT
UNIT COST
Removal of Thermal System Insulation (TSI) (<6" O.D.) by full containment, negative pressure enclosure
Linear foot
Removal of Thermal System Insulation (TSI) (>6" O.D.) by full containment, negative pressure enclosure
Linear foot
Removal of Thermal System Insulation (TSI) (<6" O.D.) by glove bag technique. (EA = 3' glove bag units)
Each
Removal of Thermal System Insulation (TSI) (>6" O.D.) by glove bag technique. (EA = 3' glove bag units)
Each
Removal of Thermal System Insulation (TSI) fittings (2"-6" nominal) by full containment, negative pressure enclosure
number of fittings
Removal of miscellaneous material, i.e. Vinyl Asbestos Floor tile (VAT) with critical barrier enclosure under negative air
Square foot
Removal of miscellaneous material such as pipe enclosures (ceiling and walls) constructed of plaster, brow coat, wire lath and black iron
Square foot
Removal of surface material asbestos contaminated suspended ceiling panels and grid system
Square foot
Removal of miscellaneous material such as asbestos containing tile mastic by portable mechanized machine scraper (Unit = square foot)
Square foot
Chemical Removal
Each
Mobilization
Each
Permit Required Confined Space Requirements
Each
Large Dumpster
Each
Small Dumpster
Each

Option Year One:

ABATEMENTS INCLUDING ALL DISPOSAL COSTS
UNIT
UNIT COST
Removal of Thermal System Insulation (TSI) (<6" O.D.) by full containment, negative pressure enclosure
Linear foot
Removal of Thermal System Insulation (TSI) (>6" O.D.) by full containment, negative pressure enclosure
Linear foot
Removal of Thermal System Insulation (TSI) (<6" O.D.) by glove bag technique. (EA = 3' glove bag units)
Each
Removal of Thermal System Insulation (TSI) (>6" O.D.) by glove bag technique. (EA = 3' glove bag units)
Each
Removal of Thermal System Insulation (TSI) fittings (2"-6" nominal) by full containment, negative pressure enclosure
number of fittings
Removal of miscellaneous material, i.e. Vinyl Asbestos Floor tile (VAT) with critical barrier enclosure under negative air
Square foot
Removal of miscellaneous material such as pipe enclosures (ceiling and walls) constructed of plaster, brow coat, wire lath and black iron
Square foot
Removal of surface material asbestos contaminated suspended ceiling panels and grid system
Square foot
Removal of miscellaneous material such as asbestos containing tile mastic by portable mechanized machine scraper (Unit = square foot)
Square foot
Chemical Removal
Each
Mobilization
Each
Permit Required Confined Space Requirements
Each
Large Dumpster
Each
Small Dumpster
Each

Option Year Two:

ABATEMENTS INCLUDING ALL DISPOSAL COSTS
UNIT
UNIT COST
Removal of Thermal System Insulation (TSI) (<6" O.D.) by full containment, negative pressure enclosure
Linear foot
Removal of Thermal System Insulation (TSI) (>6" O.D.) by full containment, negative pressure enclosure
Linear foot
Removal of Thermal System Insulation (TSI) (<6" O.D.) by glove bag technique. (EA = 3' glove bag units)
Each
Removal of Thermal System Insulation (TSI) (>6" O.D.) by glove bag technique. (EA = 3' glove bag units)
Each
Removal of Thermal System Insulation (TSI) fittings (2"-6" nominal) by full containment, negative pressure enclosure
number of fittings
Removal of miscellaneous material, i.e. Vinyl Asbestos Floor tile (VAT) with critical barrier enclosure under negative air
Square foot
Removal of miscellaneous material such as pipe enclosures (ceiling and walls) constructed of plaster, brow coat, wire lath and black iron
Square foot
Removal of surface material asbestos contaminated suspended ceiling panels and grid system
Square foot
Removal of miscellaneous material such as asbestos containing tile mastic by portable mechanized machine scraper (Unit = square foot)
Square foot
Chemical Removal
Each
Mobilization
Each
Permit Required Confined Space Requirements
Each
Large Dumpster
Each
Small Dumpster
Each

Option Year Three:

ABATEMENTS INCLUDING ALL DISPOSAL COSTS
UNIT
UNIT COST
Removal of Thermal System Insulation (TSI) (<6" O.D.) by full containment, negative pressure enclosure
Linear foot
Removal of Thermal System Insulation (TSI) (>6" O.D.) by full containment, negative pressure enclosure
Linear foot
Removal of Thermal System Insulation (TSI) (<6" O.D.) by glove bag technique. (EA = 3' glove bag units)
Each
Removal of Thermal System Insulation (TSI) (>6" O.D.) by glove bag technique. (EA = 3' glove bag units)
Each
Removal of Thermal System Insulation (TSI) fittings (2"-6" nominal) by full containment, negative pressure enclosure
number of fittings
Removal of miscellaneous material, i.e. Vinyl Asbestos Floor tile (VAT) with critical barrier enclosure under negative air
Square foot
Removal of miscellaneous material such as pipe enclosures (ceiling and walls) constructed of plaster, brow coat, wire lath and black iron
Square foot
Removal of surface material asbestos contaminated suspended ceiling panels and grid system
Square foot
Removal of miscellaneous material such as asbestos containing tile mastic by portable mechanized machine scraper (Unit = square foot)
Square foot
Chemical Removal
Each
Mobilization
Each
Permit Required Confined Space Requirements
Each
Large Dumpster
Each
Small Dumpster
Each

Option Year Four:

ABATEMENTS INCLUDING ALL DISPOSAL COSTS
UNIT
UNIT COST
Removal of Thermal System Insulation (TSI) (<6" O.D.) by full containment, negative pressure enclosure
Linear foot
Removal of Thermal System Insulation (TSI) (>6" O.D.) by full containment, negative pressure enclosure
Linear foot
Removal of Thermal System Insulation (TSI) (<6" O.D.) by glove bag technique. (EA = 3' glove bag units)
Each
Removal of Thermal System Insulation (TSI) (>6" O.D.) by glove bag technique. (EA = 3' glove bag units)
Each
Removal of Thermal System Insulation (TSI) fittings (2"-6" nominal) by full containment, negative pressure enclosure
number of fittings
Removal of miscellaneous material, i.e. Vinyl Asbestos Floor tile (VAT) with critical barrier enclosure under negative air
Square foot
Removal of miscellaneous material such as pipe enclosures (ceiling and walls) constructed of plaster, brow coat, wire lath and black iron
Square foot
Removal of surface material asbestos contaminated suspended ceiling panels and grid system
Square foot
Removal of miscellaneous material such as asbestos containing tile mastic by portable mechanized machine scraper (Unit = square foot)
Square foot
Chemical Removal
Each
Mobilization
Each
Permit Required Confined Space Requirements
Each
Large Dumpster
Each
Small Dumpster
Each