S10.xls

XLS spreadsheet 49 KB Posted

Attached to
Y1DA--STATION-CONST TBD OIG RENOVATION
Solicitation number
36C24227Q0135
Issued by

About this file

This file is a detailed cost estimate template for a construction project at the Department of Veterans Affairs OIG Space in Manhattan, New York. The project involves flooring replacement (2,241.49 square feet of LVT flooring in Interface Textured Wood Grains - Antique Dark Oak), cove base replacement (666.90 linear feet of Roppe Pinnacle 194 Burnt Umber 4-inch cove base), and wall painting (4,587 square feet in Sherwin-Williams Shoji White SW 7042 and 998 square feet in Benjamin Moore Slate Blue 1648, both semi-gloss finishes). The estimate template includes line items for general conditions, demolition, flooring installation, cove base installation, painting, and closeout activities. Cost categories encompass direct construction costs, bonds and insurance (2.0% of direct cost), contractor overhead and profit (10.0%), and escalation/procurement risk (3.0%), with all current values shown as $0.00 pending contractor completion.

The corresponding federal contract opportunity (Solicitation 36C24227Q0135) is a sources sought notice for construction services under FAR Part 36 with an estimated magnitude between $100,000 and $250,000. This is a 100% Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside requiring all interested firms to be registered in SAM.gov and verified in the SBA VetCert database at time of submission. The applicable NAICS code is 236220 (Commercial and Institutional Building Construction) with a small business size standard of $45 million. The anticipated contract award date is on or before February 12, 2027, and the work location is the Margaret Cochran Corbin VA Campus at 423 E 23rd Street, New York, NY 10010.

View the file

Other files

File Type Posted
36C24227Q0135.docx DOCX document
SOW.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Summary

Column2Column1
ProjectVA OIG Space Flooring, Cove Base Replacement, and Wall Painting
LocationManhattan, New York VA
Prepared Date
BasisSOW quantities; contractor shall field verify all dimensions
Cost SummaryAmountBasis / Formula
General Conditions$0.00Cost Detail by category
Demolition$0.00Cost Detail by category
Flooring$0.00Cost Detail by category
Cove Base$0.00Cost Detail by category
Painting$0.00Cost Detail by category
Closeout$0.00Cost Detail by category
Direct Construction Cost$0.00Sum of all direct work
Bonds / Insurance (2.0%)$0.00Direct Cost x 2.0%
Contractor Overhead & Profit (10.0%)$0.00(Direct + Bonds/Insurance) x 10.0%
Escalation / Procurement Risk (3.0%)$0.00(Direct + Bonds + O&P) x 3.0%
Contingency / Rounding to Approved TotalBalancing amount to establish final total
GRAND TOTAL$0.00Target total requested by VA
Key QuantitiesQtyUnit
Flooring Replacement2,241.49SF
Cove Base Replacement666.90LF
Total Wall Paint Area5,585.00SF
Shoji White SW 70424,587.00SF
Benjamin Moore Slate Blue 1648998.00SF

Cost Detail

WBSCategoryRequirement / Work TaskDetailed BasisQtyUnitMaterial/Equipment Unit CostLabor HoursLabor RateMaterial/Equipment CostLabor CostSubtotal
01.01General ConditionsMobilization, field verification, preconstructionSite verification, logistics, safety plan, submittals1.00LS$0.00
01.02General ConditionsProject management & superintendentScheduling, coordination, QA/QC oversight1.00LS$0.00
01.03General ConditionsSite protection, containment, daily cleanupDust protection, occupant protection, safe access/egress1.00LS$0.00
02.01DemolitionRemove existing flooringRemove existing flooring in included OIG spaces - 2,241.49 SF2,241.49SF$0.00
02.02DemolitionRemove existing cove baseRemove existing 4-inch cove base - 666.9 LF666.90LF$0.00
02.03DemolitionSurface prep, debris handling and disposalHauling, disposal, substrate cleanup, minor scrape/grind1.00LS$0.00
03.01FlooringFurnish LVT flooringInterface Textured Wood Grains - Level Set A00416 Antique Dark Oak2,241.49SF$0.00
03.02FlooringInstall LVT flooringAdhesive, layout, cutting, installation, transitions and terminations2,241.49SF$0.00
04.01Cove BaseFurnish 4-inch cove baseRoppe Pinnacle 194 Burnt Umber - 666.9 LF666.90LF$0.00
04.02Cove BaseInstall 4-inch cove baseAdhesive, corners, clean lines, secure installation666.90LF$0.00
05.01PaintingPaint standard Shoji White wallsSherwin-Williams Shoji White SW 7042 semi-gloss - 4,587 SF4,587.00SF$0.00
05.02PaintingPaint Slate Blue accent wallsBenjamin Moore 1648 Slate Blue semi-gloss - 998 SF998.00SF$0.00
05.03PaintingWall prep, primer, patching and touch-upWall patching, primer where required, minor surface repairs - 5,585 SF5,585.00SF$0.00
06.01CloseoutFinal cleaning, punch list, warranty, O&MFinal cleanup, deficiency correction, care/maintenance and warranty package1.00LS$0.00
DIRECT CONSTRUCTION COST$0.00$0.00$0.00

Labor Rates

Trade / RoleEstimated Market Labor RateUnitUsed In EstimateNotes
Project Manager$/HRGeneral conditionsManhattan commercial construction coordination
Superintendent / Foreman$/HRMobilization / field oversightField supervision, site access, safety
Flooring Installer$/HRLVT installationCommercial LVT installation labor
Commercial Painter$/HRWall painting and prepPainting, patching, primer and finish coats
Construction Laborer$/HRDemolition / disposalFlooring/cove base removal, debris handling
Closeout / Punchlist Labor$/HRFinal cleanup and deficienciesFinish correction and turnover support

Equipment Basis

Material / AllowanceBasisQtyUnitUnit CostExtended Cost
LVT flooringInterface Textured Wood Grains - Level Set A00416 Antique Dark Oak2,241.49SF$0.00
LVT install materials/allowanceAdhesives, minor transitions and consumables2,241.49SF$0.00
Roppe cove baseRoppe Pinnacle 194 Burnt Umber, 4-inch high666.90LF$0.00
Cove base adhesive/consumablesIncluded as unit allowance666.90LF$0.00
Shoji White paint materialSherwin-Williams Shoji White SW 7042 semi-gloss4,587.00SF$0.00
Slate Blue paint materialBenjamin Moore 1648 Slate Blue semi-gloss998.00SF$0.00
Primer/patching materialPrimer, spackle, sandpaper, sundries5,585.00SF$0.00