This file is a detailed cost estimate template for a construction project at the Department of Veterans Affairs OIG Space in Manhattan, New York. The project involves flooring replacement (2,241.49 square feet of LVT flooring in Interface Textured Wood Grains - Antique Dark Oak), cove base replacement (666.90 linear feet of Roppe Pinnacle 194 Burnt Umber 4-inch cove base), and wall painting (4,587 square feet in Sherwin-Williams Shoji White SW 7042 and 998 square feet in Benjamin Moore Slate Blue 1648, both semi-gloss finishes). The estimate template includes line items for general conditions, demolition, flooring installation, cove base installation, painting, and closeout activities. Cost categories encompass direct construction costs, bonds and insurance (2.0% of direct cost), contractor overhead and profit (10.0%), and escalation/procurement risk (3.0%), with all current values shown as $0.00 pending contractor completion.
The corresponding federal contract opportunity (Solicitation 36C24227Q0135) is a sources sought notice for construction services under FAR Part 36 with an estimated magnitude between $100,000 and $250,000. This is a 100% Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside requiring all interested firms to be registered in SAM.gov and verified in the SBA VetCert database at time of submission. The applicable NAICS code is 236220 (Commercial and Institutional Building Construction) with a small business size standard of $45 million. The anticipated contract award date is on or before February 12, 2027, and the work location is the Margaret Cochran Corbin VA Campus at 423 E 23rd Street, New York, NY 10010.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24227Q0135.docx | DOCX document | |
| SOW.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Summary
| Column2 | Column1 | |
| Project | VA OIG Space Flooring, Cove Base Replacement, and Wall Painting | |
| Location | Manhattan, New York VA | |
| Prepared Date | ||
| Basis | SOW quantities; contractor shall field verify all dimensions | |
| Cost Summary | Amount | Basis / Formula |
| General Conditions | $0.00 | Cost Detail by category |
| Demolition | $0.00 | Cost Detail by category |
| Flooring | $0.00 | Cost Detail by category |
| Cove Base | $0.00 | Cost Detail by category |
| Painting | $0.00 | Cost Detail by category |
| Closeout | $0.00 | Cost Detail by category |
| Direct Construction Cost | $0.00 | Sum of all direct work |
| Bonds / Insurance (2.0%) | $0.00 | Direct Cost x 2.0% |
| Contractor Overhead & Profit (10.0%) | $0.00 | (Direct + Bonds/Insurance) x 10.0% |
| Escalation / Procurement Risk (3.0%) | $0.00 | (Direct + Bonds + O&P) x 3.0% |
| Contingency / Rounding to Approved Total | Balancing amount to establish final total | |
| GRAND TOTAL | $0.00 | Target total requested by VA |
| Key Quantities | Qty | Unit |
| Flooring Replacement | 2,241.49 | SF |
| Cove Base Replacement | 666.90 | LF |
| Total Wall Paint Area | 5,585.00 | SF |
| Shoji White SW 7042 | 4,587.00 | SF |
| Benjamin Moore Slate Blue 1648 | 998.00 | SF |
Cost Detail
| WBS | Category | Requirement / Work Task | Detailed Basis | Qty | Unit | Material/Equipment Unit Cost | Labor Hours | Labor Rate | Material/Equipment Cost | Labor Cost | Subtotal |
| 01.01 | General Conditions | Mobilization, field verification, preconstruction | Site verification, logistics, safety plan, submittals | 1.00 | LS | $0.00 | |||||
| 01.02 | General Conditions | Project management & superintendent | Scheduling, coordination, QA/QC oversight | 1.00 | LS | $0.00 | |||||
| 01.03 | General Conditions | Site protection, containment, daily cleanup | Dust protection, occupant protection, safe access/egress | 1.00 | LS | $0.00 | |||||
| 02.01 | Demolition | Remove existing flooring | Remove existing flooring in included OIG spaces - 2,241.49 SF | 2,241.49 | SF | $0.00 | |||||
| 02.02 | Demolition | Remove existing cove base | Remove existing 4-inch cove base - 666.9 LF | 666.90 | LF | $0.00 | |||||
| 02.03 | Demolition | Surface prep, debris handling and disposal | Hauling, disposal, substrate cleanup, minor scrape/grind | 1.00 | LS | $0.00 | |||||
| 03.01 | Flooring | Furnish LVT flooring | Interface Textured Wood Grains - Level Set A00416 Antique Dark Oak | 2,241.49 | SF | $0.00 | |||||
| 03.02 | Flooring | Install LVT flooring | Adhesive, layout, cutting, installation, transitions and terminations | 2,241.49 | SF | $0.00 | |||||
| 04.01 | Cove Base | Furnish 4-inch cove base | Roppe Pinnacle 194 Burnt Umber - 666.9 LF | 666.90 | LF | $0.00 | |||||
| 04.02 | Cove Base | Install 4-inch cove base | Adhesive, corners, clean lines, secure installation | 666.90 | LF | $0.00 | |||||
| 05.01 | Painting | Paint standard Shoji White walls | Sherwin-Williams Shoji White SW 7042 semi-gloss - 4,587 SF | 4,587.00 | SF | $0.00 | |||||
| 05.02 | Painting | Paint Slate Blue accent walls | Benjamin Moore 1648 Slate Blue semi-gloss - 998 SF | 998.00 | SF | $0.00 | |||||
| 05.03 | Painting | Wall prep, primer, patching and touch-up | Wall patching, primer where required, minor surface repairs - 5,585 SF | 5,585.00 | SF | $0.00 | |||||
| 06.01 | Closeout | Final cleaning, punch list, warranty, O&M | Final cleanup, deficiency correction, care/maintenance and warranty package | 1.00 | LS | $0.00 | |||||
| DIRECT CONSTRUCTION COST | $0.00 | $0.00 | $0.00 |
Labor Rates
| Trade / Role | Estimated Market Labor Rate | Unit | Used In Estimate | Notes |
| Project Manager | $/HR | General conditions | Manhattan commercial construction coordination | |
| Superintendent / Foreman | $/HR | Mobilization / field oversight | Field supervision, site access, safety | |
| Flooring Installer | $/HR | LVT installation | Commercial LVT installation labor | |
| Commercial Painter | $/HR | Wall painting and prep | Painting, patching, primer and finish coats | |
| Construction Laborer | $/HR | Demolition / disposal | Flooring/cove base removal, debris handling | |
| Closeout / Punchlist Labor | $/HR | Final cleanup and deficiencies | Finish correction and turnover support |
Equipment Basis
| Material / Allowance | Basis | Qty | Unit | Unit Cost | Extended Cost |
| LVT flooring | Interface Textured Wood Grains - Level Set A00416 Antique Dark Oak | 2,241.49 | SF | $0.00 | |
| LVT install materials/allowance | Adhesives, minor transitions and consumables | 2,241.49 | SF | $0.00 | |
| Roppe cove base | Roppe Pinnacle 194 Burnt Umber, 4-inch high | 666.90 | LF | $0.00 | |
| Cove base adhesive/consumables | Included as unit allowance | 666.90 | LF | $0.00 | |
| Shoji White paint material | Sherwin-Williams Shoji White SW 7042 semi-gloss | 4,587.00 | SF | $0.00 | |
| Slate Blue paint material | Benjamin Moore 1648 Slate Blue semi-gloss | 998.00 | SF | $0.00 | |
| Primer/patching material | Primer, spackle, sandpaper, sundries | 5,585.00 | SF | $0.00 |