SOW - Electrical Testing and Calibration.docx

DOCX document 59 KB Posted

Attached to
J059--FY27 Electrical Test and Calibrations
Solicitation number
36C24227Q0133
Issued by

About this file

This is a Statement of Work (SOW) for maintenance, inspection, testing, and calibration of the electrical power distribution system at Syracuse VA Medical Center in Syracuse, New York, with a performance period of March 1-31, 2027. The work encompasses a comprehensive three-year maintenance program for medium voltage primary switchgear, secondary unit substations, paralleling switchgear, low voltage switchgear, molded case circuit breakers, dry type transformers, low voltage busways, motor control centers, and switchboards. The scope is divided into nine sequential phases: infrared scanning, steady state testing, two single-end testing phases, night work with generator runs, building shutdowns, a chiller plant shutdown, a scheduled four-hour emergency power system test, and a final SCI building shutdown. Work during phases 1-4 occurs during regular business hours (Monday-Friday, 7:00 AM-3:30 PM), while phases 5-9 are evening and weekend operations scheduled to avoid more than five consecutive nights of work.

Contractor qualifications require International Electrical Testing Association (NETA) or NICET certification with minimum Level II certification for technicians and Level III for supervisors, at least two years of industry experience for Level II technicians and five years for Level III personnel, and five continuous years of demonstrable experience in maintenance and testing of electrical power distribution systems in healthcare, industrial, educational, and commercial facilities. All contractor personnel must complete OSHA 10-hour construction safety training and be trained in NFPA 70E electrical safety standards. Contractors must provide all necessary tools, equipment, and personal protective equipment with current calibration documentation. A complete written report including test data, equipment descriptions, deficiency lists, and recommended corrective actions must be submitted within seven calendar days of completion in both hard copy (two copies) and electronic format (two CDs/DVDs in Microsoft Word or PDF). The contractor must be present for and participate in the facility's required four-hour emergency power system test scheduled for a Friday between 6:00 PM-10:00 PM, documenting all operational aspects and deficiencies during the test.

View the file

Other files

File Type Posted
Equipment Photos.docx DOCX document
36C24227Q0133.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Maintenance, Inspection, and Testing of the Electrical Power Distribution System at the Syracuse VA Medical Center

Statement of Objectives/Summarized High Level Tasking Requirements

The Syracuse VA Medical Center (located at 800 Irving Ave, Syracuse, NY 13210) at has a need to perform required 3-year maintenance on its electrical equipment including but not limited to medium voltage primary switchgear, secondary unit substations, paralleling switchgear, low voltage switchgear, molded case circuit breakers, dry type transformers, low voltage busways, motor control center and switchboards.

THE UPSTATE NEW YORK HEALTHCARE SYSTEM SYRACUSE VAMC

1. Introduction:

A. This Statement of Work (SOW) describes the requirements for the maintenance, inspection, testing, and/or calibration of the Electrical Power Distribution System and all its components at the Syracuse VA Medical Center located at 800 Irving Ave Syracuse, NY 13210. These work items are referenced as “Maintenance and Testing” in this document, hereafter.

B. This SOW describes the requirements for the Qualified Electrical Contract Professionals – known as “Contractors” in this document, hereafter. Contractors who are contracted by the Syracuse VA Medical Center to perform maintenance and testing of the Electrical Power Distribution System, and all its components shall meet all requirements stated in Section 2 of this SOW.

C. This SOW describes the requirements to establish maintenance and testing reports.

2. Period of Performance

· 3/1/2027-3/31/2027

· All services shall be rendered in March of 2027 to ensure compliance

3. Scope of Work:

A. The testing must be completed in the following nine sequential phases: (see drawings for more details

1) Infrared Scan (see section 5 below)

2) Steady State. During this phase all gear will be double ended. Contractor to test all tie breakers and spare breakers.

3) Single End 1. During this phase all gear will be single ended to right side allowing testing of secondary substations on left sides of double ended switchgear. VA will only manipulate switchgear at 6AM on weekdays.

4) Single End 2. During this phase all gear will be single ended to left side allowing testing of secondary substations on right side of double ended switchgear. VA will only manipulate switchgear at 6AM on weekdays.

5) Night work/ generator runs. During this phase, generators will run which will allow IR scan of emergency side of transfer switches, IR scan of generator switchgears, Bldg 1 XF3 substation maintenance, and breaker testing of normal side transfer switch feeders. 10PM-6AM. Additionally, any testing work that must be done during nights without generator activity is also accomplished during this phase.

6) Building 1 Shutdown. One night for shutdown of building 1 switchgear “MSWGR” 8PM-6AM, or as needed.

7) Chiller Plant Shutdown. One night for shutdown of chiller plant switchgear “SWGR-CH” and secondary injection testing of HVGEDP 8PM-6AM and for secondary injection testing of emergency swbds EEQHVGE-DPA, and EEQ-GE-DP. Emergency and normal power shutdowns must occur separately, but not simultaneously on same evening. Note: That 2nd Floor MRI will need to be completely shut down for this duration. This will involve shutting off the City Water transferring to mitigate the loss of Glycol in the condenser outside. Once power is restored the valve can be reopened.

8) 4 Hour test. On a Friday between 6PM-10PM, the VA will conduct its required triennial 4-hour test. This test will consist of opening the two main 15KV breakers and operating the entire facility on generator power for 4 hours. See Section 7. Note: That 2nd Floor MRI will need to be completely shut down for this duration. This will involve shutting off the City Water transferring to mitigate the loss of Glycol in the condenser outside. Once power is restored the valve can be reopened. Note: When working on this gear doing Secondary injection there was an incident report dated 3-13-2024 solution was to disable the UV trip on the main and Tie beakers. Only perform secondary injection testing on three main breakers MB1, MB2 and MB3 and tie breakers T1 and T2 during MSWGR complete shutdown.

9) SCI Building shutdown. SCI building switchgear “HVSD” will be shut down on Saturday between 10PM-6AM immediately following the 4 Hr test, with power restored by 6AM the following morning.

B. Contractors shall report deficiencies that are deemed critical or catastrophic immediately to the Contracting Officer and COR for immediate actions.

C. All work items, definitions, and references shall comply with the latest edition of the NETA – Maintenance Testing Specifications (MTS) and with the VHA Directive, Electrical Power Distribution System.

D. All work performed shall be fully documented by the Contractor. Testing shall be performed in compliance with manufacturers’ recommendations and per the applicable procedures as outlined in the latest edition of the ANSI/NETA Standard for Maintenance Testing Specifications and/or as noted in this document. Contractor shall submit work plans and/or check lists of the testing to be performed prior to start of work. See Section 6 for equipment details.

F. Contractor shall affix label on all equipment tested documenting at a minimum the date of test, equipment tested, name of testing firm, and name or initials of testing technician.

G. Unless specified elsewhere in this document, any test labeled as “optional” by NETA is not required.

H. VA electricians must be present when contractor racks in or racks out circuit breakers. In addition, switchgear must be put in “manual” prior to any racking operation. Contractor must verify that all breakers and switchgear are returned to their normal operating state at the end of their work shift and that breakers are completely racked in.

I. No breakers shall be removed offsite without approval by COR.

J. All outages shall be scheduled in advance. Outages will be scheduled only at night and/or on weekends or unless as noted elsewhere in this document. Contractor shall verify all times of scheduled shutdowns and testing with the COR, who will verify all scheduled times in writing. Unless otherwise noted, regular working hours are defined as Monday-Friday between 7:00AM-3:30PM.

K. When cleaning gear, contractor shall use lint free rags to clean conductors, contact points between the circuit breakers and main buss bars, buss bars, and interior of the electrical equipment. Use a vacuum cleaner to remove large debris; compressed air is not to be used for this purpose. Lubricate all moving parts as recommended by the manufacturer with manufacturer’s approved lubricants. Visually inspect for sign(s) of overheating, misaligned contacts, damaged insulation, or loose lugs. Top of gear shall be cleaned of accumulated dust and dirt.

L. All oil filled transformers are annually inspected. Contractor is not required to do any oil sampling on these except document visual inspection for leaks and gauge readings. Note any out of Specifications shall be reported to COR and listed in final report.

4. Qualifications of Contractors:

A. Contractors shall be experienced Electrical Contractors, having properly trained and licensed permanent staff required to perform the proposed work. Electrical Contracting (i.e. the construction, repair, testing and maintenance of industrial and commercial electrical distribution systems) shall be the primary interest/specialty of the Contractor’s business.

B. Contractor personnel doing testing shall be certified by the International Electrical Testing Association (NETA) or NICET as Certified Technicians. All team members who will be working on this project shall provide proof of their certifications and roles described (e.g. supervision, laborer, assistant technician, IR Scanner, certified technician, etc...). At a minimum, contractor is expected to provide supervisors, technicians, and assistant technicians with certifications commensurate with their responsibilities on this project; which shall include one or more technicians with at least a current level II NETA or NICET electrical testing certification and supervisors with at least a level III NETA or NICET electrical testing certification.

C. In addition, contractor shall provide documentation of at least two years of demonstrable industry experience for all team members listed as level II technicians and at least five years of demonstrable industry experience for all team members listed as technician level III or higher involved in servicing, testing and calibrating any/all VA equipment specifically listed on this solicitation.

D. Contractors shall have technical training and demonstrable track records of working experience in maintenance, inspection, and testing of the Electrical Power Distribution Systems and related components in healthcare, industrial, educational, and commercial facilities for a minimum of five (5) continuous years. Electrical components on which the Contractors have experience shall include, but not be limited to, switchboards & switchgear (low and medium voltage); low voltage controls; motor control centers, wiring, transformers, meters, and other electrical appurtenances.

E. Contractors shall have safety trainings – either on-the-job or class-room type - in electrical safety outlined in the OSHA Standard 29 Code of Federal Regulations (CFR) 1910 Subpart S – Electrical, and the NFPA 70E – Standard for Electrical Safety in the Workplace. Training certification shall be provided indicating each technician is a Qualified Person as defined by NFPA 70E.

F. Every contractor worker on site must complete the Occupational Safety & Health Administration (OSHA) approved 10-hour construction safety training. Proof of OSHA 10 hr. training will be required. All contractors working on site must provide documentation of being trained in latest version of NFPA 70E.

G. Contractor shall provide a proposed schedule with their quote. The schedule shall be in the form of a progress chart of suitable scale to indicate the work scheduled for completion in March of 2027. Show individual phases and duration of each. The proposed schedule shall be reviewed by the COR and any requirements for adjusting the schedule shall be incorporated by the Contractor. Phases 5-9, evening phases, shall be scheduled so that no more than 5 nights are worked consecutively.

H. Contractors shall have ready access to the latest versions of the following references:

1) NFPA 70, National Electrical Code.

2) NFPA 70B, Recommended Practice for Electrical Equipment Maintenance.

3) NFPA 70E, Standard for Electrical Safety for the Workplace.

4) NFPA 110, Standard for Emergency and Standby Power System.

5) OSHA Standard 29 CFR 1910, Subparts I & S.

6) International Electrical Testing Association, Inc. (NETA) – Maintenance and Testing Specifications.

7) VHA Directive 1028, Electrical Power Distribution System (See attachments)

8) Operating /Maintenance manuals and specifications of the electrical equipment to be maintained and tested. Included but not limited to the documents listed below:

Secondary Unit Substations Square D

a. 80330-001-04PLC Automatic throw over System, Class 2700
b. IB HRB28361Masterpact NW Low Voltage Power/Insulated Case Circuit
Breaker Installation
c. 0613IB1204Masterpact NW Low Voltage Power/Insulated Case Circuit
User Guide
d. 48049-136-05Micrologic Electronic Trip Units, 2.0A thru 6.0A
e. 0613IB1202Maintenance and Field Testing Guide Masterpact NT/NW
f. 80298-002-07Power Zone 4 Low Voltage Metal Enclosure w/
Masterpact Circuit Breakers
g. 48049-027-02LE,LX & LXI Electronic Trip Circuit Breakers w/

Trip System , Series B

h. 48049-900-02Field Testing and Maintenance Guide Micrologic
i. 6040HVL Load Current Interrupting Switches, Class 6040
j. 43500-054-04R13 Phase Liquid Filled Primary/Secondary Unit Substation

type transformer, Class 7240

General Electric

a. DET-890 Application and Technical Guide General Electric AKD-20 Low Voltage Switchgear Entellisys Low Voltage Switchgear

b. DET-653E General Electric Entelliguard G Circuit Breaker Application Guide

c. DEH-41526 General Electric Entelliguard E Circuit Breaker

d. DEH-41427D General Electric AKD-20 Entellisys Low Voltage Switchgear

e. GET-8032C General Electric Spectra Series Switchboards

f. GET-7005K 1015 General Electric Spectra Series Busway

Medium Voltage Switchgear Square D

a. 6055-30 Masterclad Metal Clad Indoor Switchgear Series 5 w/ type VR Vacuum Circuit Breaker, Class 6055

b. 6055-31Type VR Vacuum Circuit Breakers
c. 63230-300-212B1Power Logic Circuit Monitor, CM400
d. 310000400.05984-A120 Compact PLC User Guide
e. 9424200772Basler Electric BE1-11 Protection System
f. 6320-216-208C1SEPAM Use Commissioning
g. 6320-216-219-C1SEPAM Series 40 Protective Relays

Other:

a. Siemens Type WL Circuit Breaker Selection and Application Guide

b. 80043-055-14 Square D Power Style QED-2 Switchboards

c. 0600IB1201 Square D Field testing and Maintenance Guide

d. 45123-961-01A Square D I-Line II Indoor Busway

e. 48049-207-05 Square D Micrologic 2,3,5 Electronic Trip Units

f. MN202002EN Cooper Substation Transformer

g. 8998CT9701 Square D Model 6 Motor Control Centers

E. Contractors shall have and provide all necessary tools, equipment, and Personal Protective Equipment (PPE) to perform the work safely, effectively, and timely. Tools, equipment, and PPE shall comply with the requirements of OSHA Standard 29 CFR 1910, Subpart I, and NFPA 70E. Prior to initiating work, Contractor shall provide documentation that all instruments, test equipment, tools and PPE have current calibration. Dated calibration labels shall be visible on all instruments, test equipment, tools and PPE as appropriate. 480V/100A disconnect switches exist in SL21 and NG13 for connection to test sets. If contractor requires a different source of power for any test equipment, details of power requirements must be submitted at the time of bid.

5.Close Out Documents:

A. A complete written report of the work performed shall be provided to the VA within 7 days of completion. Information shown in the report shall be as following:

1) Company’s name, addresses, telephone, & FAX numbers.

2) Name and signature of contractors who perform the maintenance and testing.

3) VA Project Number, name and number of VA COR.

4) Date and Time of work.

5) Copies of contractors’ valid licenses, professional and training certificates.

6) Descriptions and model number of specialized tools and equipment used, such as torque wrench or infra-red scanning camera. For certain tools Calibration Certifications will be required.

7) Location, Type, Name, and nameplate information of electrical equipment to be maintained and tested.

8) Descriptions of work items.

9) Test data.

10) Reference materials such as equipment manufacturer’s specifications, coordination study, etc.

11) Remarks on conditions of electrical equipment. List all deficiencies, if any.

12) Recommended corrective actions, if any.

B. Contractor shall submit (2) hard copies of the complete written report, and two (2) CD-ROM or DVD of the electronic version of the report in Microsoft Word or PDF format to the COR within seven (7) calendar days of test completion. All reference materials shall be included in the electronic version of the report, either through scanning or other means of electronic text import methods

5. Infra-Red Scanning/Thermography Survey (Phase 1)

Contractor shall use an infra-red scanning camera to detect hot spots in the Electrical Power Distribution System. Objective of this work is to detect any loose, broken, or corroded connections in the system. Problem connections shall be replaced with new connectors, and/or tightened with torque wrench to meet the equipment manufacturers’ specifications. This work should be done first before any of the hands-on testing is conducted. Provide a thermographic survey report as specified in ANSI/NETA MTS.

Note that since this work item must be done while the Electrical Power Distribution System is energized, appropriate safety precautions must be taken before, during and after scanning the system. Contractor shall advise the facility in advance where and if panel covers need to be removed. Emergency side of transfer switches, emergency paralleling switchgear, emergency busways and emergency generator breakers must be scanned during regularly scheduled generator tests or during phase 5. (Generator tests are conducted the first and second Wednesday of each month between 5:30-7:00AM.)

Scanning shall be performed on the electrical equipment listed in Section 6 and also the following panelboards, switchboards, enclosed breakers, busways, automatic transfer switches and dry type transformers listed below.

Designation
Location
Dwg.
15KV Swgr
SL21
E-101
15 KV Swgr batteries
SL21
E-101
E11C-A
11th Flr
E-106
XF1 Sub
CL15
E-101
XF2 Sub
CL15
E-101
XF3 Sub
Cl15
E-101
LC-DPA
CL02
E-105
LC-DPB
CL02
E-105
LC-DPF
CL02
E-105
LC-DPD
CL02
E-105
LC-DPE
CL02
E-105
MCC-1
BL20
E-105
ATS-20 Russ Electric
CL02
E-105
EEQ-LC-DPA1
CL02
E-107
EEQ-LC-DPA2
CL02
E-107
EEQ-LC-DPB
CL02
E-107
ECR-LC-DPA
CL02
E-106
ECR-LC-DPB
CL02
E-107
ELS-LC-DPA
CL02
E-107
ATS-15 Russ Electric
CL02
E-105
ATS-16 Russ Electric
CL02
E-105
ATS-17 ASCO
CL45
E-105
ATS-18 ASCO
CL45
E-105
ATS-19 Russ Electric
CL02
E-105
GE Spectra Busway
CL02 (LC-DPA)
E-105
GE Spectra Busway
CL02 (LC-DPB)
E-105
GE Spectra Busway
CL02 (LC-DPD)
E-105
GE Spectra Busway
CL02 (LC-DPE)
E-105
GE Spectra Busway
CL02 (LC-DPF)
E-105
GE Spectra Busway
Sub Basement MB1 to MSWGR
E-101
GE Spectra Busway
Sub Basement MB2 to MSWGR
E-101
GE Spectra Busway
Sub Basement MB3 to MSWGR
E-101
HVSD A, B
SL21
E-102
Fire Pump Xfmr
SL60
E-101
ATS-FP Joslyn Clark
SL58
E-101
Designation
Location
Dwg.
HV-LCA
CL45
E-104
HDP-1
SL61
E-104
ATS-6 Cummins
SL63
E-108
EQPDP-1
S510
E-109
ATS-2 Cummins
SL63
E-108
EQDP-1
SL63
E-109
EQDPL-1 Bkr
SL63
E-109
EQDPL-1
SL63
E-109
ATS-9 Cummins
SL63
E-108
EGE-DPHVC
NL31
E-103
ATS-14 Russ Electric
SL63
E-108
EEQ-HV-LCA
CL45
E-109
ATS-10 Cummins
SL63
E-108
PDP-1 Bkr
SL63
E-102
PDP-1
SL61
E-102
ATS-11 Cummins
SL63
E-108
ELSDP-1
SL63
E-109
ATS-5 Cummins
SL63
E-108
ECRDP-1
SL63
E-109
ECRPL-1 Bkr
SL63
E-109
ATS-7 Cummins
SL63
E-108
EQDP-2
SL63
E-109
EQDPL-2 Bkr
SL63
E-109
EQDPL-2
SL04
E-109
ATS-8 Cummins
SL62
E-108
ATS-3 Cummins
SL63
E-108
EQPDP-2
S510
E-109
ATS-1 Cummins
SL63
E-108
PDP-2 Bkr
SL63
E-102
PDP-2
SL04
E-102
ATS-4 Cummins
SL63
E-108
ECRDP-2
SL63
E-109
ECRDPL-2 Bkr
SL63
E-109
ECRDPL-2
SL04
E-109
EDP-1
S802 By C835
E-109
EDP-2 (Disc)
SL62
E-109
EDP-2
SL57
E-109
T-SWGR-CH-A Sub
NL31A
E-101
T-SWGR-CH-B Sub
NL31A
E-101
Swgr-CH
NG17
E-103
Designation
Location
Dwg.
Sq D I-Line Busway
NL31A
E-103
Sq D I-Line Busway
NL31A
E-103
HVGE-DP
NG17
E-103
ATS-12 Cummins
NG17
E-103
ATS-13 Cummins
NG17
E-103
EGE-DPHVB
NL31
E-103
EEQHVGE-DPA
NG17
E-103
EEQ-GE-DP
NG17
E-103
(*) EMDP-1
SL20
E-108
(*)EMDP-2E1 Sub
CL60
E-106
(*)EMDP-2E2 Sub
CL60
E-106
(*)EMDP-2 Swgr
CL60
E-106
(*)GE Spectra Busway
CL60 Emer. Bus
E-106
(*)GE Spectra Busway
CL60 Emer. Bus
E-106
(*)GE Spectra Busway
CL60 Emer Bus- Portable Gen
E-106
(*)Sq D I-Line Busway to ATS-17
Bsmnt (CL09-CL45)
E-106
(*)Sq D I-Line Busway to ATS-18
Bsmnt (CL09-CL45)
E-106

For Busways, check all connections for proper torque. Tighten where required. Clean exterior housing as needed. IR scan visible portions where busway enters equipment and at connection points. No other testing required.

(*) Items only energized when generators are running.

Dry Type Transformers

Transformers listed below shall be cleaned exteriorly and inspected for signs of overheating with infrared thermal detecting equipment. No other maintenance required.

Designation
Location
KVA
Dwg
T-EEQ-GE-DP
NG17
225
E-103
T-N-12
SL63
225
E-102
T-N-11
SL63
225
E-102
T-EQ-11
SL63
150
E-109
T-CR-12
SL63
112.5
E-109
2nd floor Iso
B224
30
T-EQ-12
SL63
225
E-109
T-CR-11
SL63
150
E-109
T1
Garage rm 110
45
E-103

6. Equipment and Testing Details

Please see Attachment titled “Equipment Photos” for photo references of equipment.

A. Dwg E-101 15Kv Metalclad Switchgear, Square D Masterclad, SO# 27553403 (1)-double ended 15KV incoming switchgear lineup with 11 vacuum breakers (incl mains and tie) with SEPAM 1000 digital relaying and metering. Note: Basler relays on main breakers are not to be serviced.

Contractor shall also replace the Power Logic PLC backup battery and switchgear PLC battery types ½ AA 3.6v Lithium.

Complete Shutdown on switchgear can occur during phase 9.

The left side of switchgear can be shut down one evening during phase 5 (if coordinated w/ Fire Pump Xfmr shutdown)

The right side of the switchgear can be shut down during phase 6

B. Direct-Current Systems: Batteries Nickel -Cadmium (Main Primary Switchgear) Provide service on swgr battery bank per NETA 7.18.1.2, including optional load test per 7.18.1.2.B.5

When Testing these Batteries they may not meet the 3 hr test. In this case if the batteries will support Primary Switch Gear for over 30 minutes the batteries will not require replacement. Batteries that have filed to hold a charge will be replaced and date stamped when changed as needed. Reason being is that the Charger is fed from Life Safety Circuit that become live once the generators start during an power outage and will not be required to support the load for more than 1 minute max duration. Therefore the 30 min requirement is more than adequate.

C. Dwg E102 General Electric Entellisys Low Voltage Draw out Switchgear, Designation MSWGR

Consisting of (18) tie and feeder type Entelliguard circuit breakers

Complete shutdown of switchgear will occur in phase 6.

Test breakers using secondary injection utilizing the appropriate General Electric test kit. Note that GE Entellisys might be considered proprietary by the manufacturer and that test kits and service might need to be supplied from an authorized ABB service technician.

D. GE Spectra Swbds, LC-DPA, LC-DPB, LC-DPD, LC-DPE, LC-DPF Test all circuit breakers via secondary injection utilizing the appropriate GE Spectra test kit. Circuit breakers are type micro Entelliguard, (62) total breakers to be tested.

E. Dwg E101

(3) 15KV 750KVA Cooper Substations w/ type Primary VFI Main and close coupled GE Entelliguard secondary MCB, Designation XF1/XF2/XF3 MB1/MB2/MB3

Note: When working on this gear doing Secondary injection there was an incident report dated 3-13-2024 solution was to disable the UV trip on the main and Tie beakers.

Test secondary main breakers using secondary injection utilizing the appropriate General Electric test kit. Note that GE Entellisys might be considered proprietary by the manufacturer and that test kits and service might need to be supplied from an authorized ABB service technician.

F. Low Voltage Motor Control Center, 3 vertical sections, Sq D Model 6

Motor Control Center will be shut down during phase 6

G. Grounding Systems (switchgear room- CL02) Test ground resistance in CL02. Inspect and tighten ground connections as necessary. Document results and include in final report to owner.

H. Grounding Systems (substation room- CL15) Test ground resistance in CL15. Inspect and tighten ground connections as necessary. Document results and include in final report to owner.

I. Dwg E102 (1)-Double ended 13.2KV/480V substation, Type Square D Power Zone, Order # 27553403 Designation HVSD

Substation consists of:

(2) HVL Primary switches, (2)-2000KVA oil filled transformers and (1) low voltage double ended drawout switchgear lineup with (28)- 480V Masterpact breakers w/ Micrologic trip units

· Test all Masterpacts using primary injection.

· Test and confirm that 1500 va UPS in section 5D below Tie breaker is operational. If not report to VA any issues.

Contractor shall replace batteries in each Micrologic trip unit: type ½ AA as well as replacing the battery backup for PLC: type ½ AA (Replace UPS batteries)

Complete shutdown on the switchgear will occur in phase 8 and phase 9.

Test ground resistance in SL21. Inspect and tighten ground connections as necessary. Document results and include in final report to owner.

J. Fire Pump Transformer Type Schneider Electric Ser # 27553403-491-01 225KVA Oil Filled, 13200 Pri, 480/277V Secondary Fire Pump transformer can be serviced during phase 5

K. GE Spectra Swbds, HV-LCA Test all circuit breakers via secondary injection utilizing the appropriate GE Spectra test kit. Circuit breakers are type micro Entelliguard, (10) total breakers to be tested. Board will be down during time which HVSD is shut down.

L. GE Spectra Swbds, EEQ-HV-LCA Test all circuit breakers via secondary injection utilizing the appropriate GE Spectra test kit. Circuit breakers are type micro Entelliguard, (6) total breakers to be tested

M. Dwg E103 (1)-Double ended 480V Drawout Switchgear, Type Square D Power Zone, Designation SWGR-CH

Consisting of (11) 480V Masterpact breakers w/ Micrologic trip units Contractor shall replace the batteries inside each Masterpact Micrologic trip unit, type ½ AA 3.6v Lithium.

Contractor shall test all Masterpacts using Secondary injection.
Entire switchgear lineup will be shut down during phase 7.

N. Dwg E101

(2) 15KV 2500KVA Cooper Substations w/ type VFI Main Designations T-SWGR-CH-A, B

(Qty 3) Type Sq D QED Powerstyle Swbds with a total of (34) Powerpact circuit breakers with Micrologic trip units. Designations HVGE-DP, EEQ-GE-DP, EEQHVGE-DPA

Powerpacts to be tested via secondary injection utilizing the appropriate SqD test kit.

O. Dwg E-108 Paralleling Switchgear type Cummins Power Generation, 480V, Designation EMDP-1 consisting of (23) drawout Sq D Masterpact breakers with Micrologic trip units, located in Room SL20.

Contractor shall replace batteries type 12v, 12ah sealed lead acid battery qty(2), replace the battery backup in the PLC type ½ AA 3.6v Lithium, and replace batteries inside each Micrologic trip unit type ½ AA 3.6v Lithium.

Contractor shall test all Masterpacts using Primary injection.

Due to critical nature of switchgear, the gear will never be shut down (but is normally de energized). The individual breakers can be tested one at a time per drawing E-104.

P. Dwg 106 208V Low Voltage Emergency Switchgear, GE Entellisys, Designation EMDP-2 One double ended switchgear lineup with Main, Tie and spare breakers.

Due to critical nature of switchgear, the gear will never be shut down (but is normally de energized). The individual breakers can be tested one at a time per drawing E-105.

Test breakers using secondary injection utilizing the appropriate General Electric test kit. Note that GE Entellisys might be considered proprietary by the manufacturer and that test kits and service might need to be supplied from an authorized ABB service technician.

Q. Dwg E106

(2) 1000 KVA Low Voltage Substations , Designations EMDP-2E1, E2 consisting of a 1600A GE Spectra Power Break II Primary MCB and an Olsun 1000 KVA 480-120/208V dry type transformer.

Test ckt bkr utilizing secondary injection utilizing appropriate GE test kit. Isolate and Clean both Dry-type transformers as scheduled with VA.

R. Qty (1) Portable Generator Connection Box

Consisting of a Siemens type WL Ckt Bkr. Test ckt bkr utilizing secondary injection utilizing appropriate Siemens test kit.

Clean inside of cabinet of any debris and test low voltage components installed (lighting, receptacles, heater) S. Grounding Systems (main switchgear room- SL21)

7. Additional requirements

A. The Contractor shall be present for and will participate in the 4-hour test of the Essential Electrical System (EES). This test shall fulfill the requirements of VHA Directive, Electrical Power Distribution System, NFPA 110 (e.g. Para. 8.4.9.) and The Joint Commission. This test will include simultaneous opening of each main breaker serving the facility and having emergency generators supply power to entire hospital for a minimum of 4-hours. During the test period, verify operation of all EES components including the transfer to emergency power and return to normal service. The contractor will document this test, record any deficiencies, note fuel consumption used during test, note transfer time to generator power, note approximate average load during test both in KW and % as indicated on generator control panel, document which generator(s) were running and include in the final project report. Any remaining contractor work requiring entire gear shutdowns should be accomplished during this scheduled test. Test is expected to be scheduled 6PM-10PM on a Friday

1 Syracuse VAMC Test and Calibrate 2027 528A7-27-101