36C24226Q0127 0001 Q and A.pdf
PDF 89 KB Posted
- Attached to
- C221--561A4-23-103 Water Piping Survey
- Solicitation number
- 36C24226Q0127
About this file
This document is a Questions and Answers (Q&A) amendment for Project 561A4-23-103, a Water Piping Survey associated with solicitation 36C24226Q0127. The amendment clarifies the project scope in response to a contractor's inquiry about the water line survey. Specifically, the statement of work focuses on surveying water lines internal to patient buildings, not exterior site water lines.
The document confirms that SF330s (likely Standard Form 330 for architect-engineer qualifications) remain due on December 15, 2025, at 12:00pm EST, and all other original submission terms and conditions remain unchanged. The amendment is labeled as Amendment 0001 to the original solicitation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24226Q0127 0001_1.docx | DOCX document | |
| PG 18-15.pdf | ||
| 36C24226Q0127.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project 561A4-23-103 Water Piping Survey
This document is associated with 36C24226Q0127 Amendment 0001 and is to provide an answer to a previously submitted question.
Question: After reviewing the details provided for this project, we were wondering if the scope of the project is to survey water lines internal to buildings, or is it related to exterior site water lines?
Answer: The statement of work is focused on surveying the water lines internal to the buildings, specifically patient buildings.
SF330s remain due on December 15, 2025, at 12:00pm EST.
All other terms and conditions of the original submission remain unchanged.
File details come from the government source that posted it. Updated .