This document is a contract amendment (Modification Number 0003) for a Department of Veterans Affairs solicitation (36C24224B0025) to replace patient room doors and sinks at the Syracuse VA Medical Center.
The key details are:
- The amendment revises the specifications, drawings, and RFI questions and answers for the project. It removes the previous specifications and drawings and incorporates the revised versions.
- The project involves replacing 12 patient room doors and sinks. The doors are to be extra heavy duty wood with a specific finish. The sinks are to be Corian Savannah material.
- Demolition and replacement work is to be done one room at a time, with a 1-hour infection control barrier required. New hollow metal door frames are to be provided.
- Temporary construction doors with anti-ligature hardware must be installed and kept locked at all times.
- No 2-hour fire-rated barriers are required, but modifications to existing plumbing and wall finishes as needed to accommodate the new sinks and doors are expected.
- Advance payment or payment for stored materials is not allowed.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
528A7-18-740 Replace 7C Patient Room Doors & Sinks RFIs - Pre-Bid
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 528A7-18-740 Department of Veterans Affairs Network Contracting Office 02 800 Irving Ave Syracuse
NY
13210 Department of Veterans Affairs Network Contracting Office 02 800 Irving Ave Syracuse
NY
13210 To all Offerors/Bidders
36C24224B0025
X X X
X Purpose of this amendment is to incorporate revised specification, drawings and RFI Q & As A.) Delete Specifications dated 3-1-23 and incorporate attached specifications entitled 7C Door-sinks - revised B.) Delete Drawings dated 3-1-23 and incorporate attached drawings entitled 7C Patient Room Doors and Sinks-revised C.) Incorporate Replace 7C Patient Room Doors and Sinks RFI Questions and Answers D.) Delete the 7C patient Room Door and Sinks Selected Design Options E.) All other terms and conditions remain unchanged
INCORPORATE REVISED SPECS AND DRAWINGS and INCORPORATE RFI Q and ANSWERS
1. Please clarify if we are to re-use/retrofit existing frame, or if existing frames are to be removed and new frames provided. Note R2 on AD-101 calls to remove frames, but no new frames listed in Door Schedule on A-501
VA Response: Doorframes are to be removed per note R2 on AD-101 and shall be replaced with new hollow metal frames. See revisions to door schedule detail 1/A-501.
Specification 08 11 13 Hollow Metal Doors and Doorframes has been added. Provide horizontal frame stiffeners and hinge frame reinforcement per Assa Abloy Pemko DSH1000SER double swing hinge anti-barricade hardware.
2. Please clarify existing wall type at each opening (steel studs & drywall, masonry block, drywall with tile etc.). This will impact demolition of existing frames if required, and new frame installation if required.
VA Response: Existing walls consist of metal studs and GWB; however, there may be some sections of masonry walls still remaining near columns.
3. Please review and clarify requirement for 2-hour fire-rated ICCRA barriers at each opening.
a. Are all the existing walls within each room 2-hour fire rated? If not, we will not be creating a true 2-hour enclosed work area.
VA Response: No, 2-hour fire rated barrier is not required.
b. The existing ceilings are all tamperproof / clipped, this restricts access above the ceiling to run a wall to the deck.
i. If the existing corridor walls are not 2-hour rated, we can’t build a “lid” back to the existing wall to create the 2-hour enclosure.
VA Response: 2-hour fire rated barrier is not required.
c. If 2-hour not required, please clarify ICRA requirements
VA Response: 2-hour fire rated barrier is not required.
d. Spec section 013526-1.12 Infection Control part B deems this project as Class II. Part C of this same section states barriers are only required for Class III & IV
VA Response: 2-hour fire rated barrier is not required. 1-hour barrier is required for patient safety within the Mental Health In-Patient Ward, and aids in meeting ICRA requirements. Barrier shall be constructed of heavy duty impact resistant GWB. As only one patient room can be worked on at a time, recommend Contractor constructs barrier in panel sections that can more easily be taken down and relocated to each patient room.
4. Please clarify hardware requirements on the temporary door given this area of the hospitals use.
VA Response: Temporary construction door shall be provided with Mental Health anti-ligature door hardware and must remain locked (storeroom function) at all times.
5. Drawings call for negative pressure at each area. Given this use of this area, are the windows able to be opened or how are we to exhaust the air?
VA Response: Windows are fixed and not available for use. Contractor shall provide new negative air machine free of dust and recirculate air within each room.
6. Please clarify note 18 on drawing AD-101 VA Response: Disregard note 18 on AD-101.
7. Drawings notes 19 & 20 on AD-101 state
a. Please clarify. Is this stating we need to fire caulk any and all existing penetrations through existing wall? If so, this isn’t quantifiable. Need some sort of quantifier.
VA Response: No, not required as limited work will be done that would require large sections of ceiling to be removed.
8. Drawing note 21 on AD-101 states:
a. Is this for every opening?
VA Response: Required for all patient room doors being replaced to ensure anti-ligature over the door alarms remain in working order during door replacements.
9. All existing bathroom walls contain tile, but are not identified as such on the drawings. These tiles will need to be cut/removed to install blocking as shown in detail 9 on P-100. Depending on stud layout & new sink layout, demolition may be beyond new sink enclosure location and new tiles will be required.
a. Can you please provide manufacturer & color of exiting tile & grout to match?
VA Response:
Floor tile: Daltile Keystones D050 Mottled Medium Brown 2x2 w/ 3” high base; MAPEI Ultralite Mortar: Color Unknown
Wall Wainscot: Meganite 683 Rushmore Granite solid surface material panels with 2mm deep beveled groove at 1 foot increments
b. Is this tile still readily available?
VA Response: Consult with local suppliers on availability.
10. The sink in room C274A is shown being relocated to opposite corner of room. All other sinks are being relocated relatively close to existing location. Please review and confirm this relocation.
VA Response: Sink shall be removed and replaced; use existing location for new sink in room C724A.
11. Please review and clarify these notes on PD-100 being this project is on the 7th floor a.
VA Response: Disregard. Intent is for plumbing lines to be modified as required within the new solid surface sink enclosures.
b.
VA Response: Disregard note. Intent is for plumbing lines to be modified as required within the new solid surface sink enclosures.
12. There is no wall demolition identified on architectural drawings at new sink locations. Is the intent for us to relocate all plumbing lines within new solid surface sink enclosures, or are we to open up walls and run new lines within walls?
a. If new drains are required to be ran to the floor below, please verify existing ceiling type below each bathroom.
VA Response: Intent is for plumbing lines to be modified as required within the new solid surface sink enclosures wherever possible.
13. Please review and clarify this note on P-101:
a. Per solid surface detail 7 on drawing P-100, the panels below the sink will be removable; is this acceptable for “access door”?
VA Response: Yes. Door shall not create ligature points and must be securely fastened.
14. Please clarify the requirements related to the SSHO (013526-1.7):
Please clarify and confirm the VA wants both a full time superintendent and a full time SSHO as spelled out in section 013526-1.7 C&D VA Response: Prime General Contractor’s superintendent may fulfill the SSHO role provided that the individual is competent and trained in all safety requirements for the project.
15. What kind of doors do you want?(Fire Rated, plated with steel, etc.). And what finish would you like on the door?
VA Response: Provide extra heavy duty wood doors per specification 08 14 00. Match existing wood veneer finish: Marshfield Door Systems Plain Sliced Red Oak Clear 0-95. Verify finish matches during submittal phase and prior to ordering.
16. The current hinges are on the floor and top of the frame. The hinges requested will be on one side of the door frame so it might require a new door frame. Would equivalent be one that can be mounted on the floor and top of frame with same safety features?
VA Response: Doorframes are to be removed per note R2 on AD-101 and shall be replaced with new hollow metal frames. See revisions to door schedule detail 1/A-501. Provide door hardware as specified.
17. Would any plumbing have to be moved?
VA Response: Intent is for plumbing lines to be modified as required within the new solid surface sink enclosures wherever possible.
18. What kind of door handle do you want? Would you like a double cylinder lock (Key port on both sides)?
VA Response: Provide single cylinder mortise locks SARGENT 8200 Series Mortise Lock with BHW Trim per specification 08 71 00. Provide the following functions:
· Key outside (corridor side) locks/unlocks door.
· Thumbturn inside (patient room side) locks/unlocks door.
· Key outside overrides thumbturn inside when thumbturn is held in a locked position.
· Handle inside always retracts latchbolt.
19. How many rooms would we be able to work on at a time?
VA Response: Per note 1 on drawing AD-101, only one room can be worked on at a time.
20. How big is the storage area provided?
VA Response: See room C703 Shaft on drawing GC-101. Room dimensions have been added. The room contains a disconnect that cannot be blocked at any time.
21. Would you like the sink and counter to be all one piece or two pieces that connect to one another?
VA Response: Provide sink integral to counter as one piece.
22. Would a deposit be granted during submittal period for all materials?
VA Response: Advance payment for materials is not allowed. Payment for stored materials is not allowed.
23. What size privacy window would you like? 18”by18” or 6”by24”
VA Response: Per drawing A-501 and specification 08 88 70, privacy window shall be 18” x 18”.
24. Was there any new information or photos or any additional info issued after the site visit?
VA Response: See SAM.gov for any solicitation amendments being posted.
25. I am seeing 12 Extra Heavy Gauge Cased open metal frames, 12 Extra Heavy Duty Wood door leafs (not the Acrovyn impact doors I was expecting) and 12 sets double acting door hardware.
VA Response: Quantities confirmed.
26. Can “Vistamatic” windows/ glazing be furnished this factory glazed into wood doors?
VA Response: Vistamatic privacy windows are currently installed in existing doors. New Vistamatic windows shall be provided with beads flush with door (no ligature points nor sharp edges allowed).
27. Requesting the Solid Surface material finishes for the sinks and sink bowls.
VA Response: Provide Corian Savannah for sink enclosure and integral sink basin.
28. If patching of existing walls is required following sink and doorframe removals, are there any special requirements for sheetrock?
VA Response: Provide 5/8” high impact resistant and mold resistant GWB. See revised specification 09 29 00 Gypsum Board. Patch, paint and repair to match existing adjacent finishes.
See attached document: 528A7-18-740 - Replace 7C Patient Room Doors and Sinks - Drawings REVISED.
See attached document: 528A7-18-740 Replace 7C Doors - Sinks - Specifications Revised.
image6.emf image7.emf image1.emf image2.emf image3.emf image4.emf image5.emf