LIST OF RFI Responses.pdf
PDF 600 KB Posted
- Solicitation number
- 36C24220B0038
About this file
This document contains a federal contract opportunity for relocating an MRI at the Brooklyn VA Medical Center in New York. The scope of work involves site preparation and construction of a new MRI suite, and must be completed within 250 calendar days of the notice to proceed. Bids are due by July 1, 2020 and the public bid opening will be held on that same date. The estimated value is between $1-5 million. This requirement is set aside 100% for Service-Disabled Veteran-Owned Small Businesses, which must be registered on vetbiz.gov and sam.gov. A mandatory site visit will be held on June 5, 2020, following all COVID-19 safety protocols. All requests for information must be submitted by June 19. No extensions will be granted for late RFIs. The awarded firm cannot be the one that designed the project, per FAR 36.209.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24220B0038 0002.docx | DOCX document | |
| FInal N-EAS190279.pdf | ||
| 36C24220B0038 0001.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01 Jul. 2020
Mr. Avin Kannadan, COR
U.S. Department of Veterans Affairs
Brooklyn Campus VA New York Harbor Healthcare System
800 Poly Pl.
Brooklyn, NY 11209-7104
Re:
Renovate MRI
Project #630A4-14-450 Responses to List of RFI’s
1) Please confirm lump sum bid price is required only on the SF 1442 para no. 17.
Yes, lump sum only.
2) Solicitation page no. 50 of 85 para 10 states ‘Documents are based on purchase and installation of a Philips Ingenia Ambition 1.5T MRI. Contractor to share their schedule of work with Philips to assist in coordination of delivery of Philips supplied products which shall be installed by the contractor’. ---- Please provide a list of Philips supplied products (along with detailed drawings) which are to be installed by the contractor. Does contractor have to do any start-up/commissioning of these products which are installed by the contractor? Also please provide the contact name and phone number at Philips or their project manager. lease confirm that all the furniture and equipment’s in the project rooms will be removed by VA. Philips coordination drawings will be attached to this document. Project Manager information is also on the drawings.
3) There We did not get the notification of this bid until March 18th, 2020, therefore we and our sub-contractors, vendors need some more time to review the bid documents. Can agency please extend the RFI due date by one more week and extend the bid due date by couple of weeks?Bid Opening has been moved to July 8.
4) Spec section 01 00 00 page 32, para 1.28 states for the work of storage space. --- Please advice if any work is required in this bid and if yes how much is the square footage?
Contractor may use up to 300 S.F. outside the work area for staging if needed. Contractor to secure area and return to existing conditions.
5) In division 2 there is no spec section for demolition work. Please provide the required specs.
Outside of Abatement, demolition scope is very limited and addressed within the contract documents.
6) Spec section 01 35 26 page 15, para 1.9B states to provide CSP with monthly site visit. Please confirm this is required and if it has to be by a third party?
You should always have a safety professional on site, which is usually your site superintendent, and not it does not have to be a third party.
7) There is an extensive spec section no. 01 91 00 for General Commissioning Requirement. Please advice if this is VA’s responsibility or contractor can performed this commissioning work with his own crew and sub-contractors.
Commissioning is required by the contractor.
8) There are no key notes on the Drawing 19-01-BK/15-SB-01 Framing plan/Concrete work. – So the scope of the work is not clear, Please confirm if all the work indicated under the ‘Legend’ is new work?
Yes, all symbols in the legend are related to new work. All items, with the exception of the existing steel columns/column footing to be VIF, within the bold “proposed slab on grade extents” on the framing plan for proposed S.O.G. on sheet 19-01-BK/15-SB101 pertain to the new structural work.
9) Please advice if the new concrete slab in the basement can be poured in one phase or two phases, also what is the access to get the concrete and gravel inside the basement floor.
The large slab on grade (S.O.G.1) may be constructed in 1 phase if desired as long as all contraction, construction and isolation joints can adequately be achieved. However, equipment pads (S1 & S2) and MRI slab (S.O.G.2 w/ haunches) should be poured as part of a separate phase. Regarding the access into the building, this should be coordinated with the facility manager and be part of the contractor’s means and methods for the project. MFS does not have detailed as-built/existing conditions information and recommends any questions regarding existing conditions be verified in field.
10) What is the floor to deck height inside the project area? n crew.
Existing documents provide a datum elevation for the top of the existing 6” conc slab at +7’-7 ½”. The top of the finished floor on the ground level is listed at +22’-7 ½”. GC to field verify.
11) Drawing 15-AD101 demo key note # 3 states ‘Survey the unfinished Floor area, clean up all the debries...’. please provide the detailed survey/condition of the existing unfinished floor area with elevations of the existing floor The area is relatively free of debris, however, GC to field verify existing conditions.
12) Will agency allow to use a gas operating equipment inside the project construction area?
Not allowed.
13) There is spec section 09 05 16 for Subsurface preparation of floor finishes. As this renovation work is in the basement area please advice if any moisture remediation coating is required on any surfaces?
At this point there is no expectation for the need of a moisture remediation coating. GC is responsible to verify existing conditions at the time of construction to make sure surfaces meet specification requirements to receive new product applications. Discrepancies are to be brought to the attention of the VA.
14) For the new MRI room construction drawings indicates copper RF shielding panels and copper shielding floors. --- Please provide specification for RF shielding panels and copper floors and confirm if this work is contractor’s responsibility.
Please see Philips’ Drawings (last 35 pages of the Project Manual). This includes RF Shielding specifications.
15) The existing unfinished floor area may have existing gravel or stone, please provide thickness of this existing gravel/stone layer also please provide details of this existing unfinished floor.
GC to field verify existing conditions.
16) In order to pour concrete for the new basement slab, concrete trucks, concrete pump trucks will use the space outside the building, please advice if any lanes will have to be closed and will agency provide traffic control during this work.
Partial lane closure is needed during this process. VA police will provide cones, but contractor should have a flagger or their super viewing the process for safety concerns.
17) Drawing 15-SB-101 indicates limits of new concrete slab, there are other unfinished areas which does not require the new slab, please provide a detailed drawing/section showing the joint details of the existing unfinished floor and the new slab new slab and joint details of new slab to existing slab areas.
All existing areas in the basement shall remain unfinished as they are currently. Structurally, the transition from new slab on grade to the existing unfinished gravel shall be separated by formwork to be provided by contractor and expansion joint shall be installed as indicated in the drawings.
18) Please provide detailed description of Philips supplied and installed equipment’s. Also, will Philips install set and deliver the MRI machine Ingenia Ambition 1.5T? Is there proper access to get this MRI equipment inside the basement? Does contractor need to make any openings in the wall?
Please see Philips’ Drawings. This document describes all the equipment and who supplies and who installs. Also, as in question 23, the louver will provide access for delivery of the MRI.
19) Drawing 15-PL001 has plumbing symbols & abbreviations which shows new sanitary drainage and waste drainage piping. Please provide a detailed/section drawing of the trench with details of bedding, backfill material, etc . Also cellar part plan 15-PL001 does not show these new sanitary and waste drainage piping or any key notes. What type of piping material is required for new sanitary and waste drainage, cast iron or PVC?
Detailed section will be provided showing trenching, bedding, and backfill material & specifications. There is no underground sanitary piping on Part Plan PL001, only risers. Cellar part Plan is on PL100 it shows the location of underground sanitary piping. Underground sanitary piping shall be cast iron hub and spigot compression joints.
20) Is any work of RF wave guides required? If yes who will supply and install RF wave guides for all the different trades penetrations?
Please see Philips’ Drawings, especially “Waveguide/Feedthrough Summary,” page 18 of their drawings.
21) Please provide the list of prebid/site visit attendees.
Attached.
22) The estimated amount of construction is between $1M-5M seems less or is it between $5M- $10M?
$1-5M
23) Will agency allow removal of any basement wall exterior louvers/windows if there are any to gain access for the new concrete slab work.
Yes, the removal of the exterior louvers is to be coordinated with the COR.
24) Drawing AS102 notes states removable ceiling area per Philip requirement. Refer to Philips drawings for accurate size. ---- There are no Philip drawings. Please provide.
See last portion of Project Manual.
25) Drawing AS103 finish schedule abbreviations states DP1 and DP2 decorative wall panels. But on the elevation drawings it only states decorative panels, please specify on elevation drawings which panels are DP1 and which are DP2.
Corridor CB-8 to receive DP-1; MRI Room B-652 to receive DP-2.
26) Drawing MH705 details 38 and 39 indicates structural steel dunnage. – Please clarify if this is required or not, contractor cannot determine this at this bidding stage.
Detail 39 is required for mounted equipment on roof housekeeping pad. Structural steel dunnage is not required.
27) The existing basement floor is exposed crushed stone. Can you please provide the existing elevation of this existing stone base in order for us to determine how much additional fill or removals that may be required for new slab? Please provide elevation of new slab on grade to be poured.
The new finish floor elevation shall match the adjoining Corridor finish floor elevation.
28) Will we be able to remove existing wall louver for concrete pumping and material delivery?
Yes, the wall louver shall be removed for site access (to be coordinated with VA COR).
29) Can you please provide the company and contact information for the HVAC control company that handles VA Brooklyn?
Robert E. Rousseau Senior Account Manager - NY Metro Area Honeywell Building Solutions 127 West 30th Street, Suite 912 New York, NY 10001 Direct: (516) 302-9497 Mobile: (917) 843-4945 www.buildingsolutions.honeywell.com Robert.Rousseau@Honeywell.com
30) Is there a specification available for the RF & Magnetic Shielded Enclosure for the MRI room?
Please see Philips’ Drawings.
31) On drawing sheet number AS600 equipment schedule item number F12 and F13 are noted to be furnished by VA and installed by Contractor. Please clarify that “Contractor” does not mean the general contractor and these items are installed by MRI machine supplier and is not part of our contract?
F12 has a typo. It should read, “Injector, MRI,” and is purchased by VA and installed by that vendor. F13 is a reference to the MRI equipment in its entirety, therefore the GC’s responsibilities are assigned in the Philip’s drawings.
32) On drawing 15-MH402 there is a piece of equipment AC-2SS/CU-1 ( split system air conditioner) for the MRI room. On drawing 15-M101 it indicates that the SACU unit is provided by Phillips.
The question I have is Phillips providing the Stulz unit AC-2SS which seems to part of the SACU?
This is a costly item so please clarify.
The SACU is provided by Phillips and installed by GC but is not a part of AC-2SS. Even though the dwg shows them together. The SACU is a duct control device that has nothing to do with AC-2SS. The Split system Stulz unit CU-1/AC-2SS is provided and installed by the contractor.
END OF RESPONSES