36C24220B0020-0004001.docx
DOCX document Posted
- Solicitation number
- 36C24220B0020
About this file
This pre-solicitation notice describes a federal contract opportunity for fuel line and tank replacement at the Canandaigua VA Medical Center in New York. The project involves removing existing fuel tanks and installing a new tank, piping from the new tanks to Building 12, new pumps, and temporary fuel storage. It is a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses with a NAICS code of 238220 and a small business size standard of $36.5 million. The cost range is $1-5 million. The solicitation will post on February 13, 2020. A site visit is scheduled and noted in the solicitation. Bids are due with a 20% bid bond by the response date listed in the solicitation. Performance and payment bonds will be required.
36C24220B0020 0004 S06 - Fuel Line and Tank Replacement RFI's Adendum 4.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24220B0020-0004000.docx | DOCX document | |
| 36C24220B0020-0003000.docx | DOCX document | |
| 36C24220B0020-0002001.pdf | ||
| 36C24220B0020-0002000.docx | DOCX document | |
| 36C24220B0020-0001000.docx | DOCX document | |
| 36C24220B0020-004.docx | DOCX document | |
| 36C24220B0020-006.pdf | ||
| 36C24220B0020-005.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C24220B0020 VA Canandaigua Fuel Line and Tank Replacement - Pre-Bid RFI’s
1. What volume of fuel should we assume will be in the (2) 75,000 gallon AST’s when the work commences? The Contract documents appear to specify that the contractor is responsible to transfer the fuel into the (3) proposed frac tanks. If there is remaining fuel in the AST’s what are we responsible to do with it?
Answer: Tank #1 has approximately 50,000 gallons and Tank #2 has approximately 5,000 gallons. The contractor is responsible for disposing of remaining fuel after filling frac tanks.
2. Please provide a unit of measurement for the volume of tank bottom sludge we are to assume will be in the (2) 75,000 gallon AST’s.
Answer: The sludge is estimated to be 2 feet in depth at the bottom of each tank.
3. Please provide a detail or dimensions for the existing AST concrete foundations & dike walls below grade so we understand what we are responsible to remove and dispose of.
Answer: Encorus does not have reference drawings that show the existing tank foundations or containment walls. The walls are approximately 56” high and 11” wide.
4. Please advise what the intent is for the (2) frac tanks shown on the drawings that are not being temporarily connected to the existing heating system.
Answer: The intent is to maintain an emergency ten day supply of fuel oil on site to satisfy VA requirements. If the emergency supply is needed, the VA will hire a truck to transfer fuel between frac tanks. There is not enough room available next to the boiler plant to place all three frac tanks next to each other.
5. Are permits required for this project? If so, what permits are required and is the Contractor responsible for the permit fees per note #19 on drawing C-001.
Answer: Encorus is not aware of any permits required for this project.
6. The specification appears to specify that the contractor is responsible for dewatering, rock removal, etc. Were there any borings performed and / or is there a geotechnical report available that will inform us as to the existing conditions below grade? Note #5 on drawings S-001 mentions a geotechnical report.
Answer: Encorus performed a geotechnical engineering investigation. The report is attached.
7. Is the contractor to assume that excavated materials can be re-used where there are not specific details provided for backfill and / or base material?
Answer: It can be used for common fill, but not for granular fill. Refer to geotechnical report.
8. Is the contractor to assume that we are responsible to haul & dispose of excess excavated material? If so, are we to assume this material is not impacted or petroleum contaminated?
Answer: Yes, contractor is responsible to haul and dispose of excess excavated material. It can be assumed that the material will not be contaminated. Contaminated soil was remediated in the summer of 2019.
9. Is a Storm Water Pollution Prevention Plan (SWPP) required for this project? If so, who is responsible for the plans and coordination with the State?
Answer: Not required. Total disturbance is less than an acre.
10. Drawing CS501 detail #2 Typical Utility Trench specifies exist 4” min base, 2” min paving or match existing for asphalt pavement restoration on the site. If the existing pavement is thicker than 2” will the contractor be paid to remove and replace the additional asphalt? We have worked on other VA and federal projects where the existing paving is in excess of 14” thick.
Answer: Contractor is responsible for removal and replacement to match existing asphalt pavement. No unusually thick pavement was observed during the removal of the underground piping and soil remediation.
11. Detail #4 on S-001 reads all metal removed from existing equipment during this project is to remain the property of the VA. Does this mean that all scrap metal from demolition and construction activities remains on site? Including the AST scrap metal?
Answer: This note is corrected to read that all metal removed from existing equipment during the project (to include the AST) is to be removed in accordance with regulations by the contractor.
12. We do not see anywhere on the drawings that depicts the location of the underground supply & return piping from the existing AST’s to the building. Please provide a location. Please also confirm if this piping needs to be removed or if it can be abandoned in place.
Answer: All underground piping was removed in 2019 except for what is depicted on CD101 adjacent to and underneath the tank containment area.
13. The Contract documents do not appear to provide for spill containment with regard to the proposed new 50,000 gallon AST. WE Believe NYSDEC requires 120% containment for AST’s over 10,000 gallon. Please advise.
Answer: 120% containment is not required. The VA, not the NYSDEC, is the Authority Having Jurisdiction. The double wall tank with leak detection monitors provides the secondary containment for the tank. The solenoid valve, PCV-101, on the fill line provides the overfill protection. The normally closed solenoid valve on the outlet piping, V-112, provides protection from syphoning through the outlet piping.
14. Please confirm the existing 75,000 gallon AST’s as well as the existing 1,000 gallon AST contain #2 fuel oil or diesel fuel and do not contain #6 oil. The contract documents do not appear to specify the type fuel in the existing tanks.
Answer: Both tanks contain #2 fuel oil. The 75,000 gallon tanks originally were designed for #6 oil which may show up on some old reference drawings, but they currently contain #2 fuel oil.
15. Drawing CS102 detail(s) #2 depict existing utilities & piping as well as proposed structure elevation profiles. Based on these details irs the only existing utilities and / or structures that may be a conflict with the proposed construction are a 2” storm pipe and an electrical conduit. Please advise what the electrical conduit is, and the amperage & voltage contained inside the conduit.
Answer: The underground electric is power to the existing sanitary pump station. Wire size is not known.
16. Drawing CU101 depicts an existing 15” storm pipe, approximately 40’-0 north of the proposed 9” thick concrete drive slab that does not appear to be represented on the existing utility profile details. Please advise if this storm pipe is in conflict with the proposed construction.
Answer: The 15" storm pipe is a typo that should say 12". The profile correctly depicts this 12" storm pipe.
17. The pipe conduit calls for sch. 10 stainless steel. Is it carbon or stainless for the piping itself? Or is it our choice?
Answer: The 2" schedule 40S service pipe is stainless steel per drawing MP501 details 3 & 4 and specification 231000, section 2.7. The single wall pipe in the boiler plant can be either carbon steel or stainless steel per the specification.
18. Drawings MP102 and 3/MP102 indicate the requirement for field installed 1” mineral wool insulation on the tank. Specification section 230711 2.2 “Mineral Wool or Refractory Fiber” states “NOT USED”. Please provide a specification for the mineral wool that is to be used and please confirm no insulation facing and jacket is required to cover the mineral wool insulation that will be exposed to the elements.
Answer: The intent was to cover 1" mineral wool insulation with a thin gauge, painted steel weatherproof jacket. The specification should for the mineral wool insulation is ASTM C553 (Blanket, Flexible) Type I, Class B-3, Density 16 kg/m3 (1 pcf), k = 0.045 (0.31) /at 24 degrees C (75 degrees F), for use at temperatures up to 204 degrees C (400 degrees F).
19. Please confirm the Government will be responsible for furnishing ALL fuel oil on this Project (i.e. the fuel oil to fill the three temporary 16K frac tanks and the fuel oil to fill the new 50,000 gallon tank). Please confirm the Contractor is to not carry monies for fuel oil in their bid.
Answer: Correct, all additional fuel oil will be purchased by the VA.
20. For pricing purposes, how many gallons of fuel, sludge, and oily wastewater removal and disposal should the Contractor figure when cleaning the existing tanks prior to demolition? This cost would include pumping, handling, transportation, and disposals of remaining fuel, sludge and oil wastewater generated during cleaning and demolition of the existing above ground storage tanks. Generally the Government requests unit prices for these efforts.
Answer: 2 feed of sludge is to be assumed at the bottom of each tank.
21. Please confirm the Contractor is required to provide delegated design/calculations as outlined in Section 232111 1.4-C.11 & part 2.29.
Answer: Yes, design of pipe supports is delegated to the Contractor.
22. In review of the tunnel profile and tunnel site plan on CS102, does the Contractor need to assume an engineered shoring system adjacent to the Masonry Building No. 12 and the existing 8,000 gallon tank during construction of the tunnel?
Answer: Yes, assume an engineered shoring system is required adjacent to the building and tank.
23. 2/CS102 indicates existing 2” storm and existing UG electrical in the route of the tunnel. Does the Contractor need to assume these utilities need to be relocated?
Answer: Yes, utilities that will interfere with the trench need to be relocated.
24. Damp proofing and Waterproofing is not included in Division 07 of the specifications. Please confirm this is not required for the new tunnel.
Answer: Waterproofing is required. An updated specification 23 10 00 Facility Fuel Systems REV1 is attached.
25. Can one (1) larger frac tank be utilized in lieu of three (3) 16K gallon frac tanks?
Answer: No, there is not enough room next to the boiler plant for a larger frac tank.
26. Does the Contractor need to assume pumping/polishing fuel from frac tanks into the new 50,000 gallon tank at the end of the project?
Answer: Yes.
27. Who is responsible for monitoring and maintaining the fuel oil level in the frac tanks?
Answer: VA personnel will be responsible for monitoring the temporary fuel supply levels.
28. Specifications indicate the SSHO have to be a separate qualified individual from the Prime Contractor’s Superintendent and QC-M. Please confirm this project requires three (3) full-time on-site personnel during construction – SSHO, QC-M and Project Superintendent. This is overkill for a Project this size with limited definable features of work. We request the Project Superintendent be able to serve as all three (3) roles.
Answer: Personnel filling these roles must meet all criteria as outlined in the specifications and must be present on the site during all work. The Project Superintendent can be the same as the SSHO or the QC-M can be the same as the SSHO. The QC-M is to be an independent person from the Project Superintendent. If dual-hatting of these positions is utilized, the Project Superintendent, QC-M, and SSHO cannot hold other duties on the project unless approved by the COR.
29. Please confirm the Government will handle all Special Inspections as outlined in SECTION 014535. The specification indicates the special inspector will be a representative of the designer of record.
Answer: The contractor will hire and independent third-party agency to perform special inspections as well as hire the SIOR in accordance with the specifications. Please note that the Statement of Special Inspections (014535.1) has been updated and is attached to this amendment.
30. The drawings and specs do not detail the requirements for the Erosion Control Plan required to be submitted and approved by the VA. Please provide details on required E&S controls.
Answer: This information is included in 015719 as part of the environmental protection plan.
31. Will the project require the contractor to apply and procure a Stormwater Pollution Prevention Plan (SWPPP) or similar permit from New York State or any local AHJ?
Answer: Less than 1 acre will be disturbed. SWPPP not required.
32. If a SWPPP is required will the government provide the calculations and drawings required for applying for the permit?
Answer: SWPPP not required.
33. Should the contractor budget an amount for the removal and replacement of unsuitable soils that might be uncovered during the project?
Answer: No, all soil contamination is assumed to be remediated.
34. Does the Contractor need to assume excavation, handling on-site stockpiling (including stockpile management) of contaminated material, transportation, and disposal of petroleum contaminated soil encountered during removal of the existing storage tanks? If so, how many tons? This would include backfilling the excavation with an equal quantity of approved material.
Answer: No, all soil contamination is assumed to be remediated.
35. Please refer to section 010000 General Requirements, Article 1.15 Warranty Management, Para B, Performance Bond- Must the Performance Bond period be extended beyond the project completion date to the termination of the one year standard warranty and the date of any extended warranty? Can a maintenance bond be substituted in lieu of a Performance Bond for the period after project completion to the date of any extended warranty?
Answer: The Performance Bond must remain effective throughout the construction period.
36. There is an asbestos abatement section in the specifications, but nothing on the drawings. Can you please provide background on what environmental considerations were assessed? Did we do any hazardous materials assessments? If so, does a report exist for this?
Answer: The tanks were checked for lead based paint utilizing 3M Lead Check swabs. The results were negative for lead. As the pipes are buried for the project, there is a potential for asbestos containing insulation. If the contractor does find insulation or other questionable material, they are to stop and notify the COR. The contractor is then to complete bulk sample testing as applicable according to Code Rule 56 through the use of NYS certified inspector. The COR is to be notified when testing occurs for observation. The testing results would then be submitted to the government for review prior to proceeding. The contractor is to assume that no more than 8 bulk samples tests are required. An updated drawing is attached to reference potential asbestos abatement requirements.
37. Question: Spec Section 23 09 11 pages 11, 12, 13, and 14 are a Past Performance Questionnaire (titled “Attachment E”). We did not expect this document nor would we expect to find it within the Instrumentation and Control Specification. Was “Attachment E” included in the Spec by accident? If it was your intention to include it, please give directions on what we are supposed to do with “Attachment E”?
Answer: Remove pages 11-14 of specification section 23 09 11.
Due to COVID-19 concerns and direction from the NYS Governor for social distancing, we are taking all necessary precautions to ensure everyone’s safety. The requirement for solicitation submission of bids criteria has changed. In accordance with FAR 14.202-8, send all submission documents via email to Mark.simonson@va.gov by 2:00PM EST Thursday, April 23, 2020.
All Contractors providing an electronic bid submission must still meet all requirements listed under “Bid Submission” in the original IFB announcement. The previously scheduled bid opening for Thursday April 9, 2020 at the Bath VA Medical Center, 76 Veterans Avenue, B-29A conference Room, Bath NY 14810 has been rescheduled to a teleconference reading of the bids. Contractors can call 1-800-767-1750 at 1:55 PM EST and enter participant code 38459# to join.
After all bids have been read, the apparent low bidder shall submit the signed original copy of the bid and all required documents, including bonds via mail to: Mark Simonson, VA Medical Center, 76 Veterans Avenue, Bath, NY 14810.
Files should be in Adobe* PDF (Portable Document Format) Files: Size: Maximum size of the e-mail message shall not exceed five (5) megabytes. If the size limits are exceeded, the VA may not receive the file and/or you may not be considered. Only one email is permitted. This email should contain at least three separate attachments:
| • | One (1) signed SF1442 with amendments acknowledged. |
| • | One (1) complete signed Performance and Payment Bonds. |
| • | One (1) safety or environmental violations and experience modification rate. |
014535.1 - Statement of Special Inspections.REV1.pdf
FUEL LINE AND TANK REPLACEMENT
CANANDAIGUA VAMC | CANANDAIGUA, NY
CONSTRUCTION DOCUMENTS
4/03/2020
Project:
Location:
Project #:
Date:
C
IV
Yes
Project:
Location:
Project #:
Date: 4/3/2020
Statement of Special Inspections Page 1 of 2
Fuel Line and Tank Replacement
Canandaigua, NY
585A5‐19‐505
Horizontal LFRS Elements Notes
Lateral Force Resisting System (LFRS) 2015 IBC 1704.3.2 and 1704.3.3
Following is a listing of critical main wind/seismic force resisting systems for this structure. Carefully inspect these elements as part of the roles and responsiblities of the Special Inspector (reference the Schedule of Special Inspections for inspection checklists).
Vertical LFRS Elements Notes
Tank support foundations See sheet SB102
Professional Registration Number: Contractor to provide prior to construction start
Consulting Firm Name (if any): Contractor to provide prior to construction start
SIOR Office AND Mobile Phone Number: Contractor to provide prior to construction start
Special Inspector of Record (SIOR) A Special Inspector of Record (SIOR) IS required (per UFGS 01 45 35, Section 1.3.8)
SIOR Name (Registered Professional): Contractor to provide prior to construction start
Project Risk Category:
Project Design Wind Speed (mph):
Number of Stories:
Structure Height Above Grade (ft):
Hazardous Occupancy or attached to such? Group H Occupancies (2015 IBC, Section 415)
Fuel Line and Tank Replacement
Canandaigua, NY
585A5‐19‐505
4/3/2020
STATEMENT OF SPECIAL INSPECTIONS
Project Seismic Design Category:
CANANDAIGUA VAMC | CANANDAIGUA, NY
CONSTRUCTION DOCUMENTS
4/03/2020
1.
2.
3.
4.
5.
6.
6.
1. Record observations of Final Walk Down Inspection
2. Document that Inspections were performed in accordance with the Schedule of Special Inspections
3. Document that all Designated Seismic Systems are installed according to construction/manufacturer document requirements, and that Compliance Certificates have been collected (UFC 03 301 01, 2‐13.2.2.1).
Statement of Special Inspections Page 2 of 2
Final Walk Down Inspection and Report
(UFC 3 301 01 SECTION 2‐2.4.3)
Designated Seismic Systems shall receive a final walk‐down inspection by the Registered Design Professional in Responsible
Charge
Final Walk Down Report, Prepared by the Registered Design Professional in Responsible Charge, Must Include:
If additional space is required, append an additional sheet listing the remaining DSS
OTHER Designated Seismic Systems (DSS) Requiring a Certificate of Compliance
DSS Gas lines and associated fittings, anchorage, & flexible Connections
If additional space is required, append an additional sheet listing the remaining DSS
MECHANICAL/PLUMBING Designated Seismic Systems (DSS) Requiring a Certificate of Compliance
Designated Seismic Systems (DSS) (2015 IBC 1705.13.3.4) (ASCE 7‐10, 13.2.2, C13.2.2) (UFC 3‐310‐04, 2‐11.2 & 2‐13.2.2)
Non‐structural 'Designated Seismic Systems' (DSS) must remain operable and contain hazardous substances following a design
ELECTRICAL Designated Seismic Systems (DSS) Requiring a Certificate of Compliance
DSS Emergency or Standby Power System image4.emf
DWG-19175-CD101.REV1 CIVIL DEMOLITION PLAN.pdf
HP
S
HPS
HPS
W
UGE
UG
E
ST
STSTSTSTSTSTSTST
SA
SASA
SASA
AW
AW
AH
PS
AH
PS
AHPS
SA SA
EX
2"
TO
RM
EX 12" STORM
EX SAN
8"
AN
EX 12" STORM
EX 8" WATER
EX 15" STORM
EX 8" W
ATER
EX SAN
EX 16" STORMEX SAN
6"
GP
X
XXXXXX
X X X X X X
EDGE OF GRAVEL
BOLLARDS
FENCE
DEMOLISH 4" CURB
DEMOLISH 4' HIGH CONCRETE CONTAINMENT AND LINER
DEMOLISH 6' HIGH CHAIN LINK FENCE WITH RAZOR WIRE
DEMOLISH UNDERGROUND FUEL LINE - APPROX 50'
DEMOLISH CONCRETE MANHOLE - GROUTED SHUT
DEMOLISH 4" CURB
.7'
4.6'
.7'
.0'
77.0'
.6'
8.3'
.1'
DEMOLISH METAL
STAIRS AND WALK
TO TOP OF TANK
89.0'
DEMOLISH CONCRETE PAD
AND FOUNDATION
DEMOLISH CONCRETE PAD
DEMOLISH ABOVE GROUND FUEL TANK
(TYP)
G
AL
T
K
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
D
F
A
B
D
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORDCONSULTANT
321 4 5 6 7 8 9 10
Project Director
Revisions: Date:
CIVIL DEMOLITION PLAN 100% CONSTRUCTION
DOCUMENT
NON-SPRINKLERED
CANANDAIGUA VAMC
400 FORT HILL AVE
CANANDAIGUA, NY 14424
2019-10-21
CD101
SITE
585A5-19-505
SBV VAR
REV 0 100% CONSTRUCTION DOCUMENT 2019-10-21
"Unauthorized alteration or addition to any plans, specifications or reports bearing a Licensed Professional Engineer's seal is a violation of Section 7209, subdivision 2, of the New York State Education Law".
SCALE: 1" = 10'
CIVIL DEMOLITION PLAN1
KEYPLAN
B10
B16
B12 B11
B13
N
GENERAL NOTES
1. SEE C-001 FOR C-SERIES NOTES AND LEGENDS.
2. CONTRACTOR SHALL REMOVE AND DISPOSE OF REMAINING FUEL OIL
AND SLUDGE BEFORE DEMOLITION OF TANKS AND CONTAINMENT.
3. DEMOLITION SHALL BE IN ACCORDANCE WITH ALL REGULATIONS
REQUIRED FOR TANK REMOVAL.
KEYED NOTES
1. DEMOLITION INCLUDES TANK MOUNTED LIGHTS ON EACH TANK.
2. FUEL TANKS ARE TWO (2) VERTICAL 75,000 GALLON TANKS CONTAINING
#2 FUEL OIL
3. POSSIBLE ASBESTOS-CONTAINING MATERIALS (ACM) IN UNDERGROUND
PIPE INSULATION. ANY REMOVAL OF ACM MUST BE PERFORMED BY A
LICENSED ASBESTOS ABATEMENT CONTRACTOR.
N
REV 1 ADDED KEYED NOTE 3 FOR ACM 2020-04-02
4/2/2020
Sheets and Views
DWG-19175-CD101.REVX CIVIL DEMOLITION PLAN
2020-04-02T11:38:17-0700
Digitally verifiable PDF exported from www.docusign.com image1.emf
Geotechnical Report 13019 Report, 7.8.19.pdf image2.emf
231000 Facility Fuel Systems.REV1.pdf
FUEL LINE AND TANK REPLACEMENT CONSTRUCTION DOCUMENTS
CANANDAIGUA VAMC | CANANDAIGUA, NY 4/3/2020
23 10 00 - 1
SECTION 23 10 00
FACILITY FUEL OIL SYSTEMS
PART 1 - GENERAL
1.1 DESCRIPTION
A. Diesel fuel oil and unheated burner fuel oil tanks, piping, and accessories located outside, underground or aboveground as shown on contract drawings. Refer to contract drawings for type of fuel and for tank capacities.
B. Tank fluid level monitoring and alarm systems.
C. Leak detection system for tanks and underground piping.
D. Fuel oil quality maintenance system (water and particulate removal).
E. A complete listing of common acronyms and abbreviations are included in
Section 23 05 10, COMMON WORK RESULTS FOR BOILER PLANT AND STEAM
GENERATION.
1.2 RELATED WORK
A. Section 01 00 00, GENERAL REQUIREMENTS.
B. Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
C. Deleted.
D. Section 01 91 00, GENERAL COMMISSIONING REQUIREMENTS.
E. Section 03 30 00, CAST-IN-PLACE CONCRETE.
F. Section 05 50 00, METAL FABRICATIONS.
G. Section 09 91 00, PAINTING.
H. Deleted.
I. Section 23 05 10, COMMON WORK RESULTS FOR BOILER PLANT AND STEAM
GENERATION.
J. Deleted.
K. Section 23 07 11, HVAC AND BOILER PLANT INSULATION.
L. Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.
M. Section 23 09 11, INSTRUMENTATION AND CONTROL FOR BOILER PLANT.
N. Section 23 21 11, BOILER PLANT PIPING SYSTEMS.
O. Section 23 50 11, BOILER PLANT MECHANICAL EQUIPMENT.
P. Section 26 05 41, UNDERGROUND ELECTRICAL CONSTRUCTION.
Q. Deleted
R. Section 31 20 00, EARTHWORK.
1.3 APPLICABLE PUBLICATIONS
A. The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the
23 10 00 - 2 basic designation only. Where conflicts occur these specifications and the VHA standard will govern.
B. American Petroleum Institute (API):
RP 1631-2001............Interior Lining and Periodic Inspection of
Underground Storage Tanks
C. American Society of Mechanical Engineers (ASME):
B16.5-2013..............Pipe Flanges and Flanged Fittings: NPS 1/2 through NPS 24 Metric/Inch Standard.
B16.9-2012..............Factory Made Wrought Buttwelding Fittings
B16.11-2011.............Forged Fittings, Socket-Welding and Threaded
B31.1-2014..............Power Piping
D. American Society for Testing and Materials (ASTM):
A36/A36M-2014...........Standard Specification for Carbon Structural
Steel
A53/A53M-2012...........Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and
Seamless
A105/A105M-2014.........Standard Specification for Carbon Steel
Forgings for Piping Applications
A106/A106M-2015.........Standard Specification for Seamless Carbon
Steel Pipe for High-Temperature Service
A126-04(R2014)..........Standard Specification for Gray Iron Castings for Valves, Flanges, and Pipe Fittings
A234/A234M-2015.........Standard Specification for Piping Fittings of
Wrought Carbon Steel and Alloy Steel for
Moderate and High Temperature Service
B62-2015................Standard Specification for Composition Bronze or Ounce Metal Castings
D2996-2015..............Standard Specification for Filament-Wound
“Fiberglass” (Glass-Fiber-Reinforced
Thermosetting-Resin) Pipe
E. Federal Specifications (Fed. Spec.):
A-A-60005-1998..........Frames, Covers, Grating, Steps, Sump and Catch
Basin, Manhole
F. NACE International (NACE):
SP0169-2013.............Control of External Corrosion on Underground or
Submerged Metallic Piping Systems
23 10 00 - 3
3/SSPC–SP6..............Commercial Blast Cleaning
4/SSPC-SP7..............Brush-off Blast Cleaning
G. National Electrical Manufacturers Association (NEMA):
250-2014................Enclosures for Electrical Equipment (1000 Volts
Maximum)
H. National Fire Protection Association (NFPA):
30-2015.................Flammable and Combustible Liquids Code
31-2016.................Standard for the Installation of Oil-Burning
Equipment
70-2014.................National Electrical Code (NEC)
I. Steel Tank Institute (STI):
F001-2014...............Flameshield® Standard for Fire Tested Tanks
F841-2006...............Standard for Dual Wall Underground Steel
Storage Tanks
F894-2015...............ACT-100® Specification for External Corrosion
Protection of FRP Composite Steel Underground
F941-2015...............Fireguard: Specification for Fireguard
Protected Aboveground Storage Tanks
F961-2015...............ACT-100U Specification for External Corrosion
Protection of Composite Steel Underground
P3-2015.................Specification and Manual for External Corrosion
Protection of Underground Steel Storage Tanks
R891-2006...............Recommended Practice for Hold Down Strap
Isolation
J. Underwriters Laboratories Inc. (UL):
58-1996 (R1998).........Standard for Steel Underground Tanks for
Flammable and Combustible Liquids
142-2006 (R2014)........Standard for Steel Aboveground Tanks for
971-2008................Standard for Nonmetallic Underground Piping for
Flammable Liquids
1316-2008...............Glass-Fiber-Reinforced Plastic Underground
Storage Tanks for Petroleum Products, Alcohols, and Alcohol-Gasoline Mixtures
23 10 00 - 4
1746-2007 (R2014).......Standard for External Corrosion Protection
Systems for Steel Underground Storage Tanks
2085-2003...............Standard for Protected Aboveground Tanks for
1.4 SUBMITTALS
A. Submittals, including number of required copies, shall be submitted in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND
SAMPLES.
B. Information and material submitted under this section shall be marked
“SUBMITTED UNDER SECTION 23 10 00, FACILITY FUEL OIL SYSTEMS”, with applicable paragraph identification.
C. Manufacturer's Literature and Data including: Full item description and optional features and accessories. Include dimensions, weights, materials, applications, standard compliance, model numbers, size, and capacity.
D. Deleted.
E. Aboveground Steel Tanks, Including Vault-type Tanks:
1. Drawings of tanks, supports, ladders, platforms, heating coils, tank manholes, emergency relief vents and all accessories. Include overall dimensions and dimensional locations and sizes of pipe connections, and access openings.
2. Recommended tank support locations.
3. Weight of entire tank assembly, empty and flooded.
4. Design and construction of primary tanks, insulation, secondary containment, supports, pipe connections, platforms.
5. Application and performance data on coatings from manufacturer of coatings.
6. Data certifying tanks are designed for surcharge loads of platforms shown.
7. Certification of compliance with specified standards.
8. Certification that steel tank manufacturer participates in Steel Tank Institute (STI) Quality Assurance Program.
9. Design, construction, performance, dimensions of emergency relief vents.
10. Deleted.
F. Fuel Piping:
1. ASTM and UL compliance.
23 10 00 - 5
2. Grade, class or type, schedule number.
3. Manufacturer.
G. Pipe Fittings, Unions, Flanges:
1. ASTM and UL compliance.
2. ASTM standards number.
3. Catalog cuts.
4. Pressure and temperature rating.
H. Foot Valves, Check Valves, Overfill Prevention Valves:
1. Catalog cuts showing design and construction.
2. Pressure and temperature ratings.
3. Pressure loss and flow rate data.
4. Materials of construction.
5. Accessories.
I. Secondary Containment System for Fuel Piping:
1. Sizes, materials, construction of containment system including end seals, sumps, coatings and pipe supports.
2. Layout of system.
3. Installation instructions.
4. Design of cathodic protection system (steel casing).
J. Leak Detection System:
1. Drawings, description and performance data on sensors, control units.
2. Description of operation.
3. Layout of system.
4. Installation and operating instructions.
5. Data on interconnecting wiring systems to be furnished.
K. Tank Fluid Level Monitoring Instrumentation System:
1. Drawings showing instruments and in-tank sensing units, with dimensions.
2. Design and construction of all elements of system.
3. Installation instructions.
L. Tank and Piping Accessories: Design, construction, and dimensions of vent caps, fill boxes, fill caps, spill containers and other accessories.
1. Deleted.
23 10 00 - 6
M. Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replacement parts, and troubleshooting guide:
1. Include complete list indicating all components of the systems.
2. Include complete diagrams of the internal wiring for each item of equipment.
3. Diagrams shall have their terminals identified to facilitate installation, operation and maintenance.
N. Completed System Readiness Checklist provided by the Commissioning
Agent and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.
O. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.
1.5 QUALITY ASSURANCE
A. Approval by Contracting Officer is required of products or services of proposed manufacturers, suppliers and installers, and will be based on
Contractor’s certification that:
1. Manufacturers regularly and currently manufacture tanks, tank and piping accessories, tank fluid level monitoring and leak detection systems, and fuel quality management systems.
2. Manufacturers of steel tanks participate in the Quality Assurance
Program of the Steel Tank Institute (STI).
3. The design and size of each item of equipment provided for this project is of current production and has been in satisfactory operation on at least three installations for approximately three years. Current models of fluid level and leak detection systems with less than three years’ service experience are acceptable if similar previous models from the same manufacturer have at least three years’ service experience.
B. Apply and install materials, equipment and specialties in accordance with manufacturer’s written instructions. Conflicts between the manufacturer’s instructions and the contract drawings and specifications shall be referred to the COR for resolution. Provide copies of installation instructions to the COR two weeks prior to commencing installation of any item.
23 10 00 - 7
C. All equipment shall be free from defects that would adversely affect the performance, maintainability and appearance of individual components or overall assembly.
D. Tanks, Secondary Containment Systems for Piping, Plastic Piping and
Containment Systems, Tank Level Monitoring Systems, Leak Detection
Systems, Fuel Quality Management Systems, Cathodic Protection Systems:
Authorized manufacturer’s representatives shall provide onsite training of installers and supervision of the installation and testing of the equipment and systems to assure conformance to written instructions of manufacturers.
E. Tank and piping installation contractor shall be certified as acceptable by local and state pollution control authorities.
F. Entire installation shall conform to requirements of local and state pollution control authorities.
G. Pipe Welding: Conform to requirements of ASME B31.1. Welders shall show evidence of qualification. Welders shall utilize a stamp to identify their work. Unqualified personnel will be rejected.
H. Deleted.
I. Where specified codes or standards conflict, consult the COR.
J. Label of Conformance (definition): Labels of accredited testing laboratories showing conformance to the standards specified.
K. Equipment and materials installed shall be compatible in all respects with other items being furnished and with existing items so that the result will be a safe, complete and fully operational system which conforms to contract requirements and in which no item is subject to conditions beyond its design capabilities.
1.6 AS-BUILT DOCUMENTATION
A. Submit manufacturer’s literature and data updated to include submittal review comments and any equipment substitutions.
B. Submit operation and maintenance data updated to include submittal review comments, VA approved substitutions and construction revisions shall be in electronic version on CD or DVD inserted into a three-ring binder. All aspects of system operation and maintenance procedures, including applicable piping isometrics, wiring diagrams of all circuits, a written description of system design, control logic, and sequence of operation shall be included in the operation and maintenance manual. The operations and maintenance manual shall include
23 10 00 - 8 troubleshooting techniques and procedures for emergency situations.
Notes on all special systems or devices shall be included. A List of recommended spare parts (manufacturer, model number, and quantity) shall be furnished. Information explaining any special knowledge or tools the owner will be required to employ shall be inserted into the
As-Built documentation.
C. The installing contractor shall maintain as-built drawings of each completed phase for verification; and, shall provide the complete set at the time of final systems certification testing. Should the installing contractor engage the testing company to provide as-built or any portion thereof, it shall not be deemed a conflict of interest or breach of the ‘third party testing company’ requirement. Provide record drawings as follows:
2. As-built drawings are to be provided, with a copy of them on AutoCAD provided on CD or DVD. The CAD drawings shall use multiple line layers with a separate individual layer for each system.
3. Deleted.
D. The as-built drawings shall indicate the location and type of all lockout/tagout points for all energy sources for all equipment and pumps to include breaker location and numbers, valve tag numbers, etc.
Coordinate lockout/tagout procedures and practices with local VA requirements.
E. Certification documentation shall be provided to COR 21 working days prior to submitting the request for final inspection. The documentation shall include all test results, the names of individuals performing work for the testing agency on this project, detailed procedures followed for all tests, and provide documentation/certification that all results of tests were within limits specified. Test results shall contain written sequence of test procedure with written test results annotated at each step along with the expected outcome or setpoint. The results shall include all readings, including but not limited to data on device (make, model and performance characteristics), normal pressures, switch ranges, trip points, amp readings, and calibration data to include equipment serial numbers or individual identifications, etc.
23 10 00 - 9
1.7 PERMITS
A. Contractor shall obtain and complete all tank permit and registration forms required by governmental authorities.
PART 2 - PRODUCTS
2.1 UNDERGROUND STEEL TANKS: NOT USED
2.2 ABOVEGROUND STEEL TANKS
A. Type: Factory-fabricated all welded double wall with stainless steel inner and carbon steel outer, horizontal cylindrical configuration, atmospheric pressure, internal and external corrosion protection as specified. In addition to specified requirements, tanks shall be fabricated in accordance with Steel Tank Institute (STI) design standards by manufacturer that participates in STI Quality Assurance
Program.
B. Construction:
1. ASTM A36/A36M steel outer, 304 stainless steel inner, conform to UL
142. Inner and outer tanks of double wall tanks shall both conform.
Provide label of conformance.
2. Conform to NFPA 30 or NFPA 31 as applicable.
3. Double-wall, insulated, conforming to STI F001 “Flameshield” construction. Provide label of conformance.
4. Deleted
5. Deleted
6. Deleted
7. Design for surcharge load produced by tank-mounted platforms and platform loadings shown. Design tanks for saddle supports furnished by tank manufacturer.
8. Leaks and abrasions are prohibited. Maximum permissible out-of-roundness of cylindrical shells is one percent of the diameter.
9. Provide lifting lugs for rigging tanks.
10. Make provisions for leak detectors to be installed at lowest part of interstitial space between walls of double-wall tanks.
C. Platforms, Stairs, Ladders and Handrails: Provide welded steel assemblies as shown, conforming to OSHA requirements. Provide welded steel tank attachments designed to support platform framing, stairs, ladders and live and dead loadings. Clean and coat all surfaces as
23 10 00 - 10 specified for tank and steel dike exterior. Galvanizing is an acceptable alternative.
D. Factory Cleaning: Clean interior and exterior of tanks and steel dikes (if furnished). Remove mill scale, dirt, rust, oil, welding debris, loose coatings and coatings incompatible with fuel stored or protective coating. Sandblast exterior in accordance with NACE 3.
E. Factory Coating: Provide tanks and steel dikes (if furnished) with exterior coat of rust resistant metal primer, specified under Section
09 91 00, PAINTING. Coat interior from bottom of tank to 1 m (3 feet) above bottom in compliance with API RP 1631.
F. Field Painting: Clean and coat all surfaces as specified in Section 09
91 00, PAINTING.
G. Pipe Connections to Tanks:
1. Conform to UL 142.
2. Pipe sizes 50 mm (2 inches) and smaller, threaded. Pipe sizes 65 mm
(2-1/2 inches) and larger, flanged, 1034 kPa (150 psig) ASME rating.
3. Welded joints required on steel piping located inside tanks.
4. Provide and coordinate tank connection quantities, sizes and types with requirements of tank level gauge unit; sounding rod; vent, fill, supply and return pipes; and other pipes as shown.
5. On double-wall tanks, provide valved drain of interstitial space.
H. Tank Manholes: Provide quantity shown. Bolted cover type, gasketed.
I. Internal Ladder: Provide as shown with 50 mm x 6 mm (2 inch x 1/4 inch) sides and 20 mm (3/4 inch) diameter rungs at 300 mm (12 inches) on center. Provide slide supports to allow for tank movement.
J. Wear (Striker) Plates: Provide 300 mm (12 inch) square, 6 mm (1/4 inch) thick steel plates welded to tank bottom directly under the sounding opening, the fuel return discharge, and the fill discharge.
K. Lifting Lugs: Provide for rigging tanks.
L. Emergency Relief Vents for Fire Exposure: Venting capacity shall conform to NFPA 30 or NFPA 31 as applicable. Standard product of a manufacturer, designed to automatically open at tank pressure of 17 kPa
(2.5 psig) gauge. Aluminum or cast-iron construction with Teflon seating surface. Provide separate vents for primary and secondary tanks.
M. Provide fittings for grounding per NFPA 70.
N. Deleted
23 10 00 - 11
2.3 ABOVEGROUND CONCRETE-INSULATED STEEL VAULT TANKS: NOT USED
2.4 UNDERGROUND FIBERGLASS REINFORCED PLASTIC TANKS: NOT USED
2.5 SOIL SEPARATOR MAT: NOT USED
2.6 TANK AND PIPING ACCESSORIES
A. Vent Caps: Galvanized cast iron or cast aluminum with brass or bronze screens, arranged to permit full venting and to prevent entry of foreign material into the vent line. Same pipe size as vent pipe.
B. Fill Boxes:
1. Spill-container type enclosing a fill cap assembly with camlock hose connector with closure coordinated with fittings used by fuel supplier.
2. Watertight assembly, free standing remote location type, quick-opening corrosion-resistant watertight sealable cover, with minimum
10 gallon capacity.
3. Fill cap shall be tight-fill design with provision for padlock on the top of the cap. Fill cap shall screw onto threaded adapter that can be removed without removing fill box. Entire assembly shall seal tight with no leakage during filling and when cap is in place.
4. Provide special tools necessary for opening fill boxes and fill caps.
5. Protect spill container from traffic by ramped, drain-slotted cast iron body ring and cover. Design shall prevent transmission of traffic loads to the underground tank. Spill-container type not required at locations designated only for sounding tanks.
D. Refer to Section 05 50 00, METAL FABRICATIONS, for access platforms shown for aboveground tanks.
E. Support horizontal portion of pipes located inside tank every 2100 mm (7 feet) maximum.
F. Furnish gauging chart, liters versus mm and gallons versus inches depth.
G. Furnish sounding rod for each tank size. Mark rods in increments representing five percent of tank capacity. Provide length of rod suitable for tank burial depth (if applicable). Rods shall be graduated in gallons.
H. Fill Point Identification:
23 10 00 - 12
2. Fill Caps above Grade: Aluminum, brass or bronze plate, clamped to fill pipe, with stamped or engraved letters 20 mm (3/4 inch) high.
3. Legend: "BURNER FUEL OIL FILL" "DIESEL FUEL FILL” or "SOUNDING" as appropriate.
2.7 PIPING, VALVES, FITTINGS
A. Fuel supply and return, tank fill, vents, sounding, and pump out.
B. Steel Pipe and Fittings:
1. Piping: Stainless Steel or Carbon Steel as specified on contract drawings, seamless or electric resistance welded (ERW), ASTM
A53/A53M Grade B Schedule 40, or 304L or 316 Schedule 40S.
Aboveground piping shall be painted. Refer to Section 09 91 00, PAINTING.
2. Joints: Socket or butt-welded. Threaded joints are prohibited except at valves, unions and tank connections.
3. Fittings:
a. Butt-welded joints: Steel, ASTM A234/A234M, Grade B, ASME B16.9, or 304L Stainless Steel, same schedule as adjoining pipe.
b. Socket-welded joints: Forged steel, ASME B16.11, 13,790 kPa (2000 psig) class.
4. Unions: Malleable iron, 2070 kPa (300 psig) class or 304L Stainless
Steel.
5. Companion flanges: Flanges and bolting, ASME B16.5.
6. Welding flanges: Weld neck, ASME B16.5, forged steel ASTM A105/A105M, 1034 kPa (150 psig) or 304/L Stainless Steel Forged.
D. Check Valves - Fuel Pump Suction.
1. Pipe Sizes 50 mm (2 inches) and under: Rated for 1375 kPa (200 psig) water-oil-gas, swing-type, threaded ends, ASTM B62 bronze body.
Provide union adjacent to valve.
2. Pipe Sizes 65 mm (2-1/2 inches) and above: Rated for 1380 kPa (200 psig) water-oil-gas, swing-type, 861 kPa (125 pounds) ASME flanged ends, ASTM A126 class B cast iron body.
E. Foot Valves - Fuel Pump Suction: Double poppet, lapped-in metal-to-metal seats, double-guided stems, 20 mesh inlet screen, same size as fuel suction piping. Foot valve shall be removable to above grade through the tank manhole enclosure or through extractor fitting.
23 10 00 - 13
F. Extractor Fittings: Arranged to permit removal of foot valves, overfill prevention valves, and other devices that are located below grade.
Access point shall be through a cast iron fill box-type manhole located at grade. Provide extractor wrench.
G. Overfill Prevention Valve: On aboveground tanks, or tanks pressure-filled, provide solenoid operated valve located in the fill line, rated for fill flow and pressure, which stops flow completely at 95 percent of tank capacity.
2.8 SECONDARY CONTAINMENT FOR UNDERGROUND FUEL PIPING SYSTEMS
A. Enclose the fuel supply, return and fill pipes in factory-engineered and fabricated secondary containment conduit systems. The systems shall be complete with end seals, with 25 mm (1 inches) minimum continuous annular space, 40 mm (1-1/2 inches) between carrier pipes, which shall contain all leakage and which has provisions for leak detection system as specified.
B. Stainless Steel Conduit:
1. Stainless steel pipe, ASTM 304L or 316, Schedule 10S. All welded construction.
2. Deleted
3. Deleted
4. Deleted
D. Pipe Supports: Provide supports within conduit for fuel carrier pipes spaced 2100 mm (7 feet) apart except 3000 mm (10 feet) apart for carrier pipe size 50 mm (2 inches) through 100 mm (4 inches). Support design shall permit differential movement of pipes, allow drainage of leakage to sumps, and maintain alignment of carrier pipes.
E. Conduit End Seals: Same material as conduit; leak tight.
F. Leak Detector Sensor Locations: On each piping system, provide sumps at the low points with water-tight openings above grade for access to leak detector sensors. Design sumps to intercept all potential leakage.
Space leak detection sumps per contract drawings.
2.9 LEAK DETECTION SYSTEMS
A. Automatic digital continuous monitoring systems responsive to the presence of water and hydrocarbons in the interstitial space of the double-wall tanks, in the tank manhole access enclosures, and in the secondary containment of fuel piping systems. System shall distinguish
23 10 00 - 14 between hydrocarbon and water and identify location of leak as to individual tank and piping system. System may be combined with tank fluid level monitor and alarm system specified in paragraph, TANK FLUID
LEVEL MONITOR AND ALARM SYSTEM.
B. Functions and Arrangement:
1. Single control station to monitor all sensing probes.
2. Visual indicator to monitor and identify leaks as water or hydrocarbon and location.
3. Indicators showing system status including faults and alarms.
4. On board printer that provides complete reports of all system functions upon command.
5. Panel circuit test button.
6. 95 dB audible alarm with silencing control to sound when leak is detected.
7. Eight-hour memory backup system with battery.
8. NEMA 250 Type 4 cabinet.
9. UL or other accredited testing laboratory listing.
10. RS232 Modbus communications with boiler plant computer workstation to indicate system in service and alarm conditions.
C. Sensors:
1. Designed for required locations including: Insertion between walls of double-wall tanks, in sumps in double-wall piping systems and in tank manhole enclosures. Sensing points shall be at lowest point of each tank or sump. Intrinsically safe design.
2. Sensing units shall detect presence of water and a minimum 3.2 mm
(1/8 inch) thick layer of hydrocarbon on surface of water and minimum 50 mm (2 inch) thickness of hydrocarbon in area that has no water present.
3. Sensors shall be arranged to allow replacement of individual sensors without disturbing other portions of leak detection system or fuel storage and piping system. Underground sensors shall be accessed through caps as grade.
4. Materials of construction shall be non-corroding.
5. Transmit status signal to control unit.
D. Components:
2. Sensor housings from tank and piping shall be stainless steel.
23 10 00 - 15
3. Underground wiring between probes and control unit: Place in water-tight corrosion-resistant conduit system conforming to Section 26 05
41, UNDERGROUND ELECTRICAL CONSTRUCTION.
2.10 TANK FLUID LEVEL MONITOR AND ALARM SYSTEMS
A. Digital systems for central monitoring of fuel and water levels in all fuel oil storage tanks in the project. High and low level visual and audible alarms. Volumetric tank-tightness testing. Complete with all transducing, transmitting, and receiving devices. On board printer to provide complete report of all system functions upon command. System may be combined with leak detection system specified in paragraph, LEAK
DETECTION SYSTEMS.
B. Fluid Level Monitor:
1. Digital continuous readout, showing tank oil and water levels in gallons, smallest reading one gallon. Provide identification of product measured, measuring units, and the tank number.
2. Tank and fuel characteristics contained in preprogrammed non-volatile field-replaceable databases. Protected power supply.
C. High and Low Fluid Level Alarm System:
1. Automatic continuous on-line monitoring of all tanks.
2. Visual and audible indicators combined with fluid level monitor.
Identify the tank that is in alarm condition.
3. Manual alarm test and silencing controls.
4. Low level alarm actuation adjustable 0-25 percent of tank capacity.
High level alarm actuation adjustable 75-100 percent of tank capacity.
D. Locate all indicators, selector switches, alarms on face of wall-mounted NEMA 250, Type 4 panel.
E. Remote Alarm Annunciator:
1. Visual and audible high-level alarms adjacent to tank fill box locations. Locate in NEMA 250 Type 4X weatherproof exterior wall or pole-mounted panels.
2. Alarm shall include flashing red light with 180-degree visibility for each tank and 95 dB horn or 100 mm (4 inch) diameter bell.
Provide alarm silence control.
3. Provide identification sign: "WHEN ALARM SOUNDS - FUEL TANK FILLED
TO CAPACITY - DO NOT OVERFILL".
23 10 00 - 16
F. Modbus communication to boiler plant computer workstation to indicate tank fluid level and alarm conditions. Telephone modem communication capability.
G. System Performance: Accuracy plus or minus 2.5 mm (0.10 inch) of fluid height in inventory mode and 0.25 mm (0.01 inch) in leak detection mode. Automatic compensation for fluid temperature changes. Volumetric tank tightness sensitivity of 0.4 lph (0.1 gph).
H. Sensors:
1. Provide sensor types such as magnetostrictive, capacitance, float, hydrostatic and other types as necessary…
This is the start of the file's text. The full file is on GovTribe.