36C24220B0008-001.docx

DOCX document Posted

Attached to
528A4-19-212 CANTEEN BURIED PIPING
Solicitation number
36C24220B0008
Issued by

About this file

36C24220B0008 36C24220B0008_2.docx

View the file

Other files

File Type Posted
36C24220B0008-0001000.docx DOCX document
36C24220B0008-005.docx DOCX document
36C24220B0008-006.docx DOCX document
36C24220B0008-007.docx DOCX document
36C24220B0008-003.pdf PDF
36C24220B0008-004.docx DOCX document
36C24220B0008-002.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C24220B0008

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C24220B0008 X 12-11-2019 528-20-1-4192-0006 528A4-19-212 Department of Veterans Affairs Network Contracting Office (NCO) 2 2875 Union Road Suite 3500 Cheektowaga

NY

14227 Tanya Baldwin, Contract Specialist Department of Veterans Affairs Network Contracting Office 2 2875 Union Road, Suite 3500 Cheektowaga NY 14224

BALDWIN, TANYA

716-862-7461 ext. 22443 Contractor shall provide all labor, equipment, materials and supervision necessary to perform all work required to correct a floor drain and grease trap in the VA canteen in accordance with (IAW) all drawings, specifications, and the scope of work. This project is located at the Batavia New York Veterans Hospital at 222 Richmond Avenue in Batavia NY.

Project magnitude: between $25,000 and $100,000. The NAICS code is 236220. Small Business size standard is $39.5.

In accordance with P.L. 109-461, this acquisition is 100% set aside for Service-Disabled Veteran Owned Small Business concerns. See VAAR 852.219-10, Notice of Total Service-Disabled Veteran Owned Small Business Set-Aside of this VERIFIED by the Department of Veterans Affairs Center for Verification and Evaluation (CVE) at time of submission of bid and at time of award. Failure to be both VERIFIED by CVE and VISIBLE in VetBiz prior to contract award will result in the bidder's proposal being deemed non-responsive. All offerors are urged to contact the CVE and submit the required documents to obtain CVE verification of their SDVOSB status if they have not already done so.

In accordance with FAR 52.204-7, System for Award Management (SAM), prospective contractors shall be registered in the SAM database prior to award of a contract or agreement.

Offerors shall submit Experience Modification Rate (EMR) with bid. This EMR shall be equal to or less than 1.0 or the SAM database prior to award of a contract or agreement.

See full solicitation text for information related to pre-bid site visit, requests for information, bidding materials, and public bid opening.

Note: In accordance with FAR 36.209 and VAAR 836.209, an A/E firm cannot be awarded any construction contract for which it provided design services unless approved by the head of the agency.

A site visit is scheduled for Friday, December 20, 2019 @ 11:00 AM (Eastern). Participants will meet at the Batavia VAMC, Building 2, Rm 106E.

X X 52.211-10 X 10 days after award

11:00 AM

01-09-2020 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

528-3600162-4192-854200-2543 23NRNR000

Canteen Buried Piping Construction Services Department of Veterans Affairs Network Contracting Office (NCO) 2 2875 Union Road Suite 3500 Cheektowaga

NY

14227 Tungsten Network http://www.tungsten-network.com/us/en /veterans-affairs

Edward Kostolansky

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS10
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS10
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS12
A.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)13
A.4 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)14
A.5 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)15
A.6 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)16
A.7 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)16
REPRESENTATIONS AND CERTIFICATIONS18
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (OCT 2018)18
3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (AUG 2019)21
GENERAL CONDITIONS23
4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014)23
4.2 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (JUL 2018)23
4.3 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984)24
4.4 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JUL 2013)24
4.5 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014)26
4.6 52.228-13 ALTERNATIVE PAYMENT PROTECTIONS (JULY 2000)29
4.7 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)29
4.8 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUL 2014)30
4.9 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2019) (DEVIATION)32
4.10 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018)34
4.11 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)35
4.12 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)36
4.13 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)37
4.14 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)37
4.15 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (APR 2019)37
4.16 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)38
4.17 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008)40
4.18 LIST OF ATTACHMENTS40

SCOPE OF WORK

Canteen Buried Piping

CONSTRUCTION SERVICES

Project # 528A4-19-212

Period of Performance: Two (2) months from NTP to completion General Information:

Project Description:

Project Overview The Batavia, New York Veterans Hospital is requesting construction services to correct a floor drain and grease trap in the VA Canteen. The Canteen is in room G25 (REFER TO DWG-1 through DWG-3) at the Batavia, New York Veterans Hospital is located at 222 Richmond Avenue in Batavia, N.Y. 14020.

General Description:

The Canteen Services are NOT part of the Veterans Administration Hospital as they lease space from the VA and provide services to our Veterans, Staff and Families including a convenience store, cafeteria and barber shop. This contract will entail working concurrently inside of the project area while the Canteen is open for business. The Canteen staff will allow us the room that we need to complete our scope of work. The objective as part of this scope is to have all this work completed concurrently with Canteen operations and to fully re-open the Canteen for business in 4 weeks.

The services that are required as part of this contract are as follows:

· Refer to drawing DWG-1, DWG-2 and the scope of work below

The Contractor Shall:

Grease Trap and Floor Drain Under Equipment Area 1

· Saw cut the floor to remove the old grease trap and relocate the floor drain as indicated on DWG-2. The saw cut dimensions are approximately 35 square feet and the depth of work is approximately 18 inches. This will include the saw cut for both the grease trap and floor drain in Area 1.

· Practice extra caution after saw cutting and digging down into the earth as it is not well documented as to what is under the floors.

· Remove the earth around the area where you will excavate and dispose of.

· When work is completed, fill in the void with pea gravel around work area in the floor.

· Pour Portland Cement with rebar as per the specifications to match the exiting depth of the floor. Dowel the rebar into the existing floor slab.

· Patch and repair floors to match existing 6x6 red clay floor tile and black grout.

· The intake and outlet of the grease traps are 3 inches in diameter. The intake is galvanized, and the outlet is cast iron.

· The intake elevation is 15.5” top of pipe to finished floor. The outlet elevation is 15.5” top of pipe to finished floor.

· Remove and replace the grease trap with a grease trap that is designed to handle 12 Gallons Per Minute and has the same inlet and outlet size.

· The grease trap shall be stainless steel and be accessible at the floor level with a diamond plate stainless steel cover.

· The grease trap shall have a capacity to hold 5 gallons of grease for every quarter (3 months).

· Provide submittals for approval when the project is awarded prior to proceeding with work.

· Saw cut the area to access the 3-inch floor drain. The floor drain shall be relocated approximately 6 feet in the direction indicated on DWG-2 (verify with VA COR). The reason for the floor drain relocation is that new coolers will be located where the current drain is presently located. Coordinate with VA COR prior to locating the floor drain.

· The existing floor drain to be removed is 2 inches in diameter and shall be replaced with a 3-inch floor drain.

· The existing 2” floor drain trap shall be replaced with 3” trap and all supporting piping shall be 3”. The pipe shall be schedule 40 cast steel service weight with push rubber connection.

· Provide a floor drain connected to the cast steel pipe with a brass strainer. Provide submittals for approval.

· The floor drain piping shall connect back into the inlet piping to the grease trap as indicated on DWG-2.

Floor Drain Area 2

· Saw cut the floor approximately 12 square feet and 18 inches deep to locate the damaged pipe under the slab. Refer to DWG-2.

· Practice extra caution after saw cutting and digging down into the earth as it is not well documented as to what is under the floors.

· Remove the earth around the area where you will excavate and dispose of.

· When work is completed, fill in the void with pea gravel around work area in the floor.

· Pour Portland Cement with rebar as per the specifications to match the floor depth. Dowel the rebar into the existing floor slab.

· Patch and repair floors to match existing 6x6 red clay floor tile and black grout.

· Locate the 3-inch schedule 40 cast steel drain pipe that is damaged, replace the damaged section. Provide shoring under the repaired and replaced section to prevent the pipe from dropping again. Have COR verify.

· Provide new cast steel pipe from the floor drain to the repaired section.

Special Condition Work Parameters

· Move all the kitchen equipment into a storage Conex as part of this contract. Contractor to visit site prior to bidding to see what equipment shall be moved by the contractor into a storage conex.

· Provide hard barrier containments with negative air HEPA filtration and manometers on the exterior of the containment area for duration of work. The containments shall be fire rated with a self -closing fire rated door. containments for all saw cutting work to mitigate dust.

· The containment shall be drywall that is primed and painted as this will appear to be a finished wall for the duration of work. The canteen will remain in operation.

· All personnel in containment for saw cutting shall be wearing respirators and all other OSHA required personal protective equipment during saw cutting. This is as per the most recent OSHA silica dust working standards.

· Saw cutter shall NOT be gas. The saw cutter shall be electric or battery operated. Provide generator to power saw cutter if necessary.

· The contractor shall provide a safety plan to the VA COR to submit to safety for approval prior to work.

· Provide negative air with HEPA filtration.

· Provide temporary heat detectors to maintain the fire protections system during construction. These heat detectors shall be connected to our Batavia Fire Alarm system.

· The concrete pour shall have supporting rebar doweled into the existing rebar.

· Provide submittals for approval on all materials.

VA COR and the Contracting Officer shall be the only point of contact for all work pertaining to this project.

Part I Construction

1. General:

Construction shall take place during normal working hours and after hours to meet the construction timeframe if necessary and through coordinating with the VA COR. During construction the boiler plant will be occupied by facility personal.

1.1 GENERAL INTENTION

A.Contractor shall repair work that is outlined under General Description at the VA Medical Center, Batavia NY. Furnish all necessary labor and materials.
B.Visits to the site will take place prior to bidding. Additional visits may be made only by appointment with the Contracting Officer or COR.
C.All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
D.Prior to commencing work, general contractor shall provide proof that a OSHA certified “competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present.
E.Training:
1.All employees of general contractor or subcontractors shall have the 10-hour OSHA certified Construction Safety course and /or other relevant competency training, as determined by VA CP with input from the ICRA team. The supervisor of the work shall have a 30-hour OSHA certificate.
2.Submit training records to the CO and COR of all such employees for approval before the start of work.

1.2 STATEMENT OF BID ITEM(S)

A. ITEM I, GENERAL CONSTRUCTION:

1.3 SCOPE OF WORK

A. GENERAL CONSTRUCTION

1. Provide all mobilization and demobilizations services. The mobilization work associated with the facilities mentioned shall be done in a safe and workmanlike manner and shall conform to all pertinent state and local laws and regulations.

2. It is the CONTRACTOR'S responsibility to develop a work plan detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the safety plan to be used during the work, and a schedule defining the duration of the work with milestone subtasks.

3. General Contractor to provide site supervision during all work.

4. Working Hours;

Normal daytime work hours are 0700 A.M EST to 04:00 P.M EST (whatever hours you choose) Monday through Friday. However, the Contractor permitted to work up until 06:00 P.M EST Monday through Friday and Saturday and Sunday from 8 until 4. Work that is extremely obtrusive including but not limited to saw cutting of the floors shall be scheduled for Saturday or off hours. Coordinate with VA COR.

If the contractor wishes to work during unscheduled times, he/she must get permission from the COR (Add COR POC and contact information). The hours exclude Federal Government holidays.

The Government observes the following holidays:

· New Year's Day January 1

· Birthday of Martin Luther King, Jr. Third Monday in January

· Washington’s Birthday Third Monday in February

· Memorial Day Last Monday in May

· Independence Day July 4

· Labor Day First Monday in September

· Columbus Day Second Monday in October

· Veterans Day November 11

· Thanksgiving Day Fourth Thursday in November

· Christmas Day December 25 If the Contractor anticipates that an interruption in the flow of work will occur (due to the weather, etc.), approval from the Contracting Officer Representative (COR) must be obtained prior to the interruption.

5. Warranty Period; There shall be a warranty period of one (1) year form completion and acceptance of work. This warranty shall include parts and workmanship.

1.4 CONSTRUCTION SAFETY

A. General:

1. Contractors are required to comply with the Occupational Safety and Health Act of 1970. This will include the safety and health standard found in CFR 1910 and 1926.

2. Questions regarding occupational safety and health issues can be addressed to the COR or Contracting Officer.

B. Tools/Equipment:

1. Under no circumstances are equipment, tools and other items of work to be left unattended for any reason. All tools, equipment and items of work must be under the immediate control of your employee.

C. Signs:

1. Signs must be placed at the entrance to work areas warning people of your work. Signs must be suitable for the condition of the work. Small pieces of paper with printing or writing are not acceptable.

D. Accidents and Injuries

1. Contractors must report all accidents and injuries to the COR.

REFER TO 010000 GENERAL REQUIREMENTS AND OTHER SPECIFICATIONS FOR WORK PERTAINING TO THIS PROJECT.

>>>END<<<

INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS

INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS

(a) Bidding materials consisting of Invitation for Bids, drawings, specifications and contract forms will be available on http://www.fedbizopps.gov in electronic format only. All interested parties (subs & primes) should register at http://www.fedbizopps.gov as an “Interested Vendor” so that others will know of your interest in participating in this procurement. A Bidder’s mailing list WILL NOT BE prepared by the Contract Specialist. SOLICITATION AMENDMENTS: Amendments to the solicitation will be posted at http://www.fedbizopps.gov. Paper copies of the amendments will NOT be individually mailed. By registering to “Receive Notification”, you will be notified by e-mail of any new amendments that have been issued and posted. No other notification of amendments will be provided. Offerors are reminded that they are responsible for obtaining and acknowledging all amendments to this solicitation prior to the time for receipt of offers.

(b) If bid exceeds $150,000 a bid bond must be submitted. A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $3,000,000. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for opening of bids, will require rejection of the bid in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then.

(c) If the contract will exceed $150,000 (see FAR 28.102-1 for lesser amount), the bidder to whom award is made will be required to furnish two bonds, a Payment Bond, SF 25A, and a Performance Bond, SF 25, each in the penal sum as noted in the General Conditions of the Specification. Copies of SFs 25 and 25A may be obtained upon application to the issuing office.

(d) If the bid/offer is between $30,000 - $150,000 The bidder/offeror to whom award is made will be required to furnish a Payment Bond, Standard Form 25A or alternative payment protection which conforms to the requirements set forth in FAR Clause 52.228-13, Alternative Payment Protections, as noted in the General Conditions of this Specification. Copies of the Standard Form of Payment Bond may be obtained upon application to the Issuing Office.

PROJECT BID ITEMS

A single award will be made on the Base Bid.

BASE BID: All work required in the construction documents (including but not limited to drawings, specifications, addenda, and contract documents).

Fill in price SF 1442 BOX 17, BASE BID (use ink) The construction magnitude is between $25,000 and $100,000.

BID SUBMISSION

The following documents are to be included in the bid submission:

(a) One (1) signed SF 1442 page 2, Offer page, with blocks 14-20c completed.

(b) Acknowledgment of all amendments must be accomplished either via entering data in block nineteen (19) of the SF1442 or completing blocks fifteen (15) a, b, and c of the amendment and attaching it to the SF 1442 Offer page.

(c) One (1) original completed/signed SF24 Bid Bond and Power Of Attorney as required.

(d) Safety or Environmental Violations and Experience Modification Rate:

1) All Bidders/Offerors shall submit the following information pertaining to their past Safety and Environmental record. The information shall contain, at a minimum, a certification that the bidder/offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years.

2) All Bidders/Offerors shall submit information regarding their current Experience Modification Rate (EMR) equal to or less than 1.0. This information will be obtained from the bidder’s/offeror’s insurance company and be furnished on the insurance carrier’s letterhead.

3) Self insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead may obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR will obtain their EMR rating from their state run worker’s compensation insurance rating bureau.

(e) Bidders are responsible for ensuring and verifying their bid and all required bid documents are received at the address designated in block eight (8) of the SF 1442 solicitation and by the date and time specified in block thirteen (13)a of the SF 1442 solicitation (subject to amendment).

DELIVERY OF BIDS

Bids in response to this solicitation are to be delivered to:

Department of Veterans Affairs Network Contracting Office 2 Attn: Tanya Baldwin 2875 Union Road, Suite 3500 Cheektowaga, NY 14227 The solicitation number and project title must be written on outside of the Delivery Package.

INSTRUCTIONS TO BIDDERS

A public bid opening will be held on Thursday, January 16, 2020 @ 11:00 AM (Eastern), at NCO 2, Appletree Business Park, 2875 Union Road, Suite 3500, Cheektowaga, NY 14227. Participants will be escorted to the conference room located inside the suite approximately five (5) minutes before official bid opening.

Bids received after this time will be rejected.

Any exception to the terms and conditions of this Invitation for Bid (IFB) will result in a nonresponsive bid.

Failure to provide a definitive price will result in a nonresponsive bid.

Receipt of bids must be in accordance with terms and conditions of this IFB.

Bidders must acknowledge (in writing only) amendments to this solicitation, otherwise a bid may be determined nonresponsive.

The winning bidder must be determined as "responsible" by the Contracting Officer in accordance with FAR Part 9, Contractor Qualifications.

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

GENERAL INTENTION

Contractor will provide services to include all tools, labor, materials, equipment, services, and supervision necessary to correct a floor drain and grease trap in the VA Canteen located at 222 Richard Avenue in Batavia, N.Y. 14020, Rm G25 for Project 528A4-19-212.

SITE VISIT

Bidders are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of performing these services. In no event shall failure to inspect the site constitute grounds for a claim after contract award.

There will only be one (1) organized site visit. It will be held on Friday, December 20, 2019 @ 11:00 AM (Eastern). Participants will meet at the Batavia VAMC, Building 2, Rm 106E.

Attendance is not mandatory; however, all bidders are strongly encouraged to attend.

REQUESTS FOR INFORMATION (RFI):

To obtain clarifications and/or additional information concerning the contract requirements or specifications, submit a written RFI via email to Tanya.Baldwin@va.gov.

RFIs will be responded to as necessary in amendment format which will be posted on https://beta.sam.gov/.

The deadline for submission of RFIs for this solicitation is Thursday, January 9, 2020 at 3:30 PM (Eastern). No questions will be answered after this date/time unless determined to be in the best interest of the Government as determined by the Contracting Officer. Telephone RFIs will not be accepted or returned.

BASIS FOR AWARD

Contract award will be made to the responsive, responsible bidder submitting the lowest price in accordance with FAR Part 14 – Sealed Bidding.

RESPONSIBILITY REQUIREMENTS

A Determination of Responsibility shall be accomplished for the apparent awardee prior to processing the award. The above information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases will be used to make the Determination of Responsibility. Failure to affirm being within the guidelines above or submit this information may result in a determination of “Non-Responsibility” for the bidder/offeror. NOTE: Any information received by the Government that would cause for a negative Determination of Responsibility may make the bidder/offeror ineligible for award.

This requirement is applicable to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors.

A.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision) A.4 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade
Goals for female participation for each trade
%
6.9 %

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is

(End of Provision) A.5 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

A.6 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for— December 20, 2019 at 11:00 A.M. EST

(c) Participants will meet at— Batavia VAMC, Bldg 2, Rm 106E (End of Provision)

A.7 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/

(End of Provision)

FAR Number
Title
Date
52.204-7
SYSTEM FOR AWARD MANAGEMENT
OCT 2018
52.204-16
COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING
JUL 2016
52.204-22
ALTERNATIVE LINE ITEM PROPOSAL
JAN 2017
52.214-3
AMENDMENTS TO INVITATIONS FOR BIDS
DEC 2016
52.214-4
FALSE STATEMENTS IN BIDS
APR 1984
52.214-5
SUBMISSION OF BIDS
DEC 2016
52.214-6
EXPLANATION TO PROSPECTIVE BIDDERS
APR 1984
52.214-7
LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS
NOV 1999
52.214-18
PREPARATION OF BIDS—CONSTRUCTION
APR 1984
52.214-19
CONTRACT AWARD—SEALED BIDDING—CONSTRUCTION
AUG 1996
52.214-34
SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE
APR 1991
52.214-35
SUBMISSION OF OFFERS IN U.S. CURRENCY
APR 1991

REPRESENTATIONS AND CERTIFICATIONS

3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (OCT 2018)

(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 236220.

(2) The small business size standard is $39.5 Million.

(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.

(2) If the provision at 52.204–7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:

[ ] (i) Paragraph (d) applies.

[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:

(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—

(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;

(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or

(C) The solicitation is for utility services for which rates are set by law or regulation.

(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.

(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements—Representation. This provision applies to all solicitations.

(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.

(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—

(A) Are not set aside for small business concerns;

(B) Exceed the simplified acquisition threshold; and

(C) Are for contracts that will be performed in the United States or its outlying areas.

(vi) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations—Representation.

(vii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.

(viii) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.

(ix) 52.214-14, Place of Performance—Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.

(x) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.

(xi) 52.219-1, Small Business Program Representations (Basic & Alternate I). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.

(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.

(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.

(xii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.

(xiii) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.

(xiv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.

(xv) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.

(xvi) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA-designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.

(xvii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA-designated items.

(xviii) 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals--Representation. This provision applies to solicitations that include the clause at 52.204-7.)

(xix) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.

(xx) 52.225-4, Buy American—Free Trade Agreements—Israeli Trade Act Certificate. (Basic, Alternates I, II, and III.) This provision applies to solicitations containing the clause at 52.225-3.

(A) If the acquisition value is less than $25,000, the basic provision applies.

(B) If the acquisition value is $25,000 or more but is less than $50,000, the provision with its Alternate I applies.

(C) If the acquisition value is $50,000 or more but is less than $80,317, the provision with its Alternate II applies.

(D) If the acquisition value is $80,317 or more but is less than $100,000, the provision with its Alternate III applies.

(xxi) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225-5.

(xxii) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan—Certification. This provision applies to all solicitations.

(xxiii) 52.225-25, Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran—Representation and Certifications. This provision applies to all solicitations.

(xxiv) 52.226-2, Historically Black College or University and Minority Institution Representation. This provision applies to solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions.

(A) Solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions; and

(B) For DoD, NASA, and Coast Guard acquisitions, solicitations that contain the clause at 52.219-23, Notice of Price Evaluation Adjustment for Small Disadvantaged Business Concerns.

(2) The following representations or certifications are applicable as indicated by the Contracting Officer:

[X](i) 52.204-17, Ownership or Control of Offeror.

[X](ii) 52.204-20, Predecessor of Offeror.

[](iii) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.

[](iv) 52.222-48, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment—Certification.

[](v) 52.222-52, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services—Certification.

[](vi) 52.223-9, with its Alternate I, Estimate of Percentage of Recovered Material Content for EPA-Designated Products (Alternate I only).

[](vii) 52.227-6, Royalty Information.

[](A) Basic.

[](B) Alternate I.

[](viii) 52.227-15, Representation of Limited Rights Data and Restricted Computer Software.

(d) The Offeror has completed the annual representations and certifications electronically in SAM accessed through https://www.sam.gov. After reviewing the SAM information, the Offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in paragraph (c) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer and are incorporated in this offer by reference (see FAR 4.1201); except for the changes identified below [offeror to insert changes, identifying change by clause number, title, date]. These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.

FAR Clause #
Title
Date
Change

Any changes provided by the offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications posted on SAM.

(End of Provision)

3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (AUG 2019)

(a) Definitions. As used in this provision— Covered telecommunications equipment or services, Critical technology, and Substantial or essential component have the meanings provided in clause 52.204–25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.

(b) Prohibition. Section 889(a)(1)(A) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L. 115–232) prohibits the head of an executive agency on or after August 13, 2019, from procuring or obtaining, or extending or renewing a contract to procure or obtain, any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. Contractors are not prohibited from providing—

(1) A service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or

(2) Telecommunications equipment that cannot route or redirect user data traffic or permit visibility into any user data or packets that such equipment transmits or otherwise handles.

(c) Representation. The Offeror represents that— It [ ] will, [ ] will not provide covered telecommunications equipment or services to the Government in the performance of any contract, subcontract or other contractual instrument resulting from this solicitation.

(d) Disclosures. If the Offeror has responded affirmatively to the representation in paragraph (c) of this provision, the Offeror shall provide the following information as part of the offer—

(1) All covered telecommunications equipment and services offered (include brand; model number, such as original equipment manufacturer (OEM) number, manufacturer part number, or wholesaler number; and item description, as applicable);

(2) Explanation of the proposed use of covered telecommunications equipment and services and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b) of this provision;

(3) For services, the entity providing the covered telecommunications services (include entity name, unique entity identifier, and Commercial and Government Entity (CAGE) code, if known); and

(4) For equipment, the entity that produced the covered telecommunications equipment (include entity name, unique entity identifier, CAGE code, and whether the entity was the OEM or a distributor, if known).

(End of Provision)

GENERAL CONDITIONS

4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) The Contractor's representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.

(End of Clause)

4.2 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (JUL 2018)

(a) Definitions. As used in this clause—Covered article means any hardware, software, or service that—

(1) Is developed or provided by a covered entity;

(2) Includes any hardware, software, or service developed or provided in whole or in part by a covered entity; or

(3) Contains components using any…

This is the start of the file's text. The full file is on GovTribe.