36C24219Q0319-0002000.docx
DOCX document 36 KB Posted
- Solicitation number
- 36C24219Q0319
About this file
36C24219Q0319 0002 36C24219Q0319 0002.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24219Q0319-0003000.docx | DOCX document | |
| 36C24219Q0319-0001000.docx | DOCX document | |
| 36C24219Q0319-001.docx | DOCX document | |
| 36C24219Q0319-002.docx | DOCX document | |
| 36C24219Q0319-000.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION
OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADM
INISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and d ate specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 3
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO
MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 03-01-2019
NONE
Department of Veterans Affairs Network Contracting Office (NCO) 2 2875 Union Road Suite 3500 Cheektowaga NY 14227 Department of Veterans Affairs Network Contracting Office (NCO) 2 2875 Union Road Suite 3500 Cheektowaga NY 14227 To all Offerors/Bidders
36C24219Q0319 03-22-2019
X X
X See attached document.
Michael Spivack Contracting Officer )Sound too bad
This amendment is in three sections: the first section answers questions posed at the 02/26/2019 walkthrough for this solicitation, the second section makes changes to the combined synopsis/solicitation document as a result of questions posed in section one of this amendment, the third section makes changes to the Scope of Work document as a result of questions posed in section one of this amendment.
Section 1: Questions and responses from walkthrough Q: What are the water volumes for each of the cooling towers?
A: Numbers are approximate:
-850 ton- 2100 gal.
-500 ton- 1600 gal.
-500 ton- 1600 gal.
-335 ton- 1600 gal.
-335 ton- 1600 gal.
-inside sump for walk-ins- 200 gal.
Q: Are the Condenser and chilled water systems metered? Can you provide readings?
A: Yes, systems have water make-up meters on them.
Building 1- 500-ton condenser flow rate is 1215 GPM Building 28- 850-ton condenser flow rate is 2550 GPM Building 1 chilled water flow rate is 2400 GPM Building 20 chilled water flow rate is 1086 GPM Building 20 condenser flow rate is 1510 GPM
Q: Does the VA intend to lease or own the equipment?
A: The VA intends to lease the equipment.
Q: There are different levels of disinfection based on the level of CFUs, the SOW and pricing does not reflect this.
A: The price list shall be modified in section 2. of this modification to reflect the two different types of disinfection Q: What are the current boiler and chiller chemicals being used and what are the current chemical ranges?
A: BOILERS:
pH – 7.5-8.5 triact 1825 is chemical being used Nexguard 22310 – 200-300ppm Sulfite 1720 : 30-60ppm Boiler conductivity – 2000-2500uhmos Conductivity of feed water – 50-100uhmos Alkalinity – 300-900ppm Water hardness – not an issue Soft water make-up - summer: 5,000 gpd winter 10-13,000 gpd Steam poundage – summer:5,000lbs/hr winter: 20K-28K per hour
CHILLED WATER AND CONDENSER WATER
Chilled water- Sodium Hydroxide Solution
- Condenser water scale inhibitor- Phosphono, Butane tricarboxylic acid
- Condenser Water Biocide- Sodium Hypochlorite, Sodium Bromide
- Condenser water microbicide- Glutaraldehyde
- Condenser water (tower) disinfection- Sodium Hypochlorite
- Layup - Sodium Tolytriazole, Sodium Hydroxide
Q: How often do you sample water from the boiler system A: daily Q: Does the vendor need to create their own Maintenance Plan Program (MPP)?
A: No, the vendor can use the existing VA MPP. No need to create a new MPP.
Q: Who will be responsible for submitting required state reporting requirements?
A: VA is exempt from state reporting requirements.
Q: Who is responsible for EPA reporting?
A: The vendor is responsible for submitting required EPA reports.
Q: Does the VA want controllers that perform water testing to include biocide levels and have SIM card data collection?
A: Yes, the VA will change the system requirements to add these features, see section X on this modification.
Q: What biocide feed schedule are you requesting?
A: The VA is requesting that the vendor use a stabilized Bromide as the oxidizing biocide and Glutaraldehyde as the non-oxidizing biocide. There is no specific feed schedules requested. The only requirements are that 1. The schedules are in accordance with EPA and NY State regulations 2. That fungal/bacteria growth is within stated limits of this solicitation 3. There are 0 Legionella hits on an annual basis.
Q: What water sampling does the VA perform on the chilled water and condensing tower systems?
A: Daily biocide level readings and dip slides weekly Q: What are acceptable levels of bacteria and fungi in the chilled water and condensing tower systems?
A: Remediation required at 10,000 cfu/ml or greater Q: Can the start of season cleaning of the condensing towers be started before the start of the season?
A: Yes, the vendor can perform start the start of season cleaning before the cooling season has been announced by the COR.
Q: How much water does the closed loop system make up?
A: -Chiller plants (Bld.#1 & 20 combined): Condenser water usage including makeup and initial fill: approximately 16,000,000 gal/yr.
-Chilled water make up unknown for both systems Q: Is there a filtration system on the closed loop? IF, no does the VA want one added to each of the two systems?
A: No, the VA does not have a filtration system on either of the two closed loop systems.
Yes, the VA would like a bag filter system added to each of the two closed loop systems. This requirement is added to the SOW of this solicitation in section X of this modification.
Q: What is the flow rate for each of these closed systems?
A: Building 1 chilled water flow rate is 2400 GPM Building 20 chilled water flow rate is 1086 GPM Q: What are the guidelines for scale/corrosion for the chilled water and condensing tower systems?
A: Follow industry standards for galvanized towers and steal pipe.
Q: Can you subcontract the work to install the side stream filters on the chilled water systems?
A: Yes, as long as the requirements of VAAR clause 852.219-10 are met 13 CFR §125.6 (1) In the case of a contract for services (except construction), it will not pay more than 50% of the amount paid by the government to it to firms that are not similarly situated. Any work that a similarly situated subcontractor further subcontracts will count towards the 50% subcontract amount that cannot be exceeded.
Q: Are the closed loops currently adequately treated when the vendor takes over?
A: No, it is the vendors responsibility to do the initial treatment?
Q: What chemical do you want used for the initial treatment? Molybdenum or Nitrite?
A: The VA is currently using Sodium Hypochlorite, but has no preference between the two.
Section 2: Modifications to Combined Synopsis/Solicitation Document This amendment makes the following changes to the combined synopsis/solicitation document
1. The table: ANNUAL PRICING FOR WATER TREATMENT SERVICES found in section (v) of the combined synopsis/solicitation shall be replaced by the table below
| Line Item |
| DESCRIPTION |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| TOTAL PRICE |
| 1 |
| BASE PERIOD: WATER TREATMENT SYSTEMS, REQUIRED CHEMICALS AND SUPPORT SERVICES TO TREAT CHILLED WATER, COOLING TOWER AND BOILER SYSTEMS LOCATED AT THE BUFFALO VA MEDICAL CENTER (TOTAL OF LINE ITEMS 1.a THROUGH 1.f). PERIOD OF PERFORMANCE: 04/01/2019 TO 03/31/2020). |
| 1 |
| YR |
| 1.a |
| BASE PERIOD: INITIAL SET UP AND INSTALLATION OF WATER TREATMENT SYSTEMS – CHILLED WATER SYSTEMS |
| 4 |
| JB |
| 1.b |
| BASE PERIOD: INITIAL SET UP AND INSTALLATION OF WATER TREATMENT SYSTEMS– COOLING TOWER SYSTEMS |
| 6 |
| JB |
| 1.c |
| BASE PERIOD: INITIAL SET UP AND INSTALLATION OF WATER TREATMENT SYSTEMS– BOILER |
| 3 |
| JB |
| 1.d |
| BASE PERIOD: LEASING PAYMENTS, SERVICE SUPPORT AND CHEMICALS FOR WATER TREATMENT SYSTEMS – CHILLED WATER SYSTEMS |
| 12 |
| MO |
| 1.e |
| BASE PERIOD: LEASING PAYMENTS, SERVICE SUPPORT AND CHEMICALS FOR WATER TREATMENT SYSTEMS – COOLING TOWER SYSTEMS |
| 12 |
| MO |
| 1.f |
| BASE PERIOD: LEASING PAYMENTS, SERVICE SUPPORT AND CHEMICALS FOR WATER TREATMENT SYSTEMS – BOILER |
| 12 |
| MO |
| 2 |
| OPTION YEAR 1: WATER TREATMENT SYSTEMS, REQUIRED CHEMICALS AND SUPPORT SERVICES TO TREAT CHILLED WATER, COOLING TOWER AND BOILER SYSTEMS LOCATED AT THE BUFFALO VA MEDICAL CENTER (TOTAL OF LINE ITEMS 2.a THROUGH 2.c). PERIOD OF PERFORMANCE: (04/01/2020 TO 03/31/2021). |
| 1 |
| YR |
| 2.a |
| OPTION YEAR 1: LEASING PAYMENTS, SERVICE SUPPORT AND CHEMICALS FOR WATER TREATMENT SYSTEMS – CHILLED WATER SYSTEMS |
| 12 |
| MO |
| 2.b |
| OPTION YEAR 1: LEASING PAYMENTS, SERVICE SUPPORT AND CHEMICALS FOR WATER TREATMENT SYSTEMS – COOLING TOWER SYSTEMS |
| 12 |
| MO |
| 2.c |
| OPTION YEAR 1: LEASING PAYMENTS, SERVICE SUPPORT AND CHEMICALS FOR WATER TREATMENT SYSTEMS – BOILER |
| 12 |
| MO |
| 3 |
| OPTION YEAR 2: WATER TREATMENT SYSTEMS, REQUIRED CHEMICALS AND SUPPORT SERVICES TO TREAT CHILLED WATER, COOLING TOWER AND BOILER SYSTEMS LOCATED AT THE BUFFALO VA MEDICAL CENTER (TOTAL OF LINE ITEMS 3.a THROUGH 3.c). PERIOD OF PERFORMANCE: (04/01/2020 TO 03/31/2021). |
| 1 |
| YR |
| 3.a |
| OPTION YEAR 2: LEASING PAYMENTS, SERVICE SUPPORT AND CHEMICALS FOR WATER TREATMENT SYSTEMS – CHILLED WATER SYSTEMS |
| 12 |
| MO |
| 3.b |
| OPTION YEAR 2: LEASING PAYMENTS, SERVICE SUPPORT AND CHEMICALS FOR WATER TREATMENT SYSTEMS – COOLING TOWER SYSTEMS |
| 12 |
| MO |
| 3.c |
| OPTION YEAR 2: LEASING PAYMENTS, SERVICE SUPPORT AND CHEMICALS FOR WATER TREATMENT SYSTEMS – BOILER |
| 12 |
| MO |
| 4 |
| OPTION YEAR 3: WATER TREATMENT SYSTEMS, REQUIRED CHEMICALS AND SUPPORT SERVICES TO TREAT CHILLED WATER, COOLING TOWER AND BOILER SYSTEMS LOCATED AT THE BUFFALO VA MEDICAL CENTER CENTER (TOTAL OF LINE ITEMS 4.a THROUGH 4.c). PERIOD OF PERFORMANCE: (04/01/2021 TO 03/31/2022). |
| 1 |
| YR |
| 4.a |
| OPTION YEAR 3: LEASING PAYMENTS, SERVICE SUPPORT AND CHEMICALS FOR WATER TREATMENT SYSTEMS – CHILLED WATER SYSTEMS |
| 12 |
| MO |
| 4.b |
| OPTION YEAR 3: LEASING PAYMENTS, SERVICE SUPPORT AND CHEMICALS FOR WATER TREATMENT SYSTEMS – COOLING TOWER SYSTEMS |
| 12 |
| MO |
| 4.c |
| OPTION YEAR 3: LEASING PAYMENTS, SERVICE SUPPORT AND CHEMICALS FOR WATER TREATMENT SYSTEMS – BOILER |
| 12 |
| MO |
| 5 |
| OPTION YEAR 4: WATER TREATMENT SYSTEMS, REQUIRED CHEMICALS AND SUPPORT SERVICES TO TREAT CHILLED WATER, COOLING TOWER AND BOILER SYSTEMS LOCATED AT THE BUFFALO VA MEDICAL CENTER (TOTAL OF LINE ITEMS 5.a THROUGH 5.c). PERIOD OF PERFORMANCE: (04/01/2022 TO 03/31/2023). |
| 1 |
| JB |
| 5.a |
| OPTION YEAR 4: LEASING PAYMENTS, SERVICE SUPPORT AND CHEMICALS FOR WATER TREATMENT SYSTEMS – CHILLED WATER SYSTEMS |
| 12 |
| MO |
| 5.b |
| OPTION YEAR 4: LEASING PAYMENTS, SERVICE SUPPORT AND CHEMICALS FOR WATER TREATMENT SYSTEMS – COOLING TOWER SYSTEMS |
| 12 |
| MO |
| 5.c |
| OPTION YEAR 4: LEASING PAYMENTS, SERVICE SUPPORT AND CHEMICALS FOR WATER TREATMENT SYSTEMS – BOILER |
| 12 |
| MO |
TOTAL PRICE
2. This amendment adds the following requirement to the TECHNICAL EVALUATION section of part (ix) of the combined synopsis/solicitation.
i) Document Proposed a team, including all subcontractor personnel and resources, and the duties that will be performed by each of the pertinent individuals.
3. This amendment changes the solicitation closing date listed in section (xiv) to Friday, March 15th, 2019 at 12pm Section 3: Modifications to Scope of Work Document
1. This amendment replaces section A.3.2.2 SYSTEM REQUIREMENTS with
a) The vendor shall install and provide leased water treatment systems to include: chemical tanks with containment vessel for each tank, chemical injector pumps, chemical and conductivity monitors, injectors, check valves, isolation valves and all tubing or piping connecting the chemical feed to the buildings chilled water and condenser water to treat the systems listed in section A.3.2.1 b) in accordance with standards listed in ASHRAE Standard 188-2015 (Legionellosis: Risk Management for Building Water Systems). The water treatment systems shall also have the following capabilities:
i) Treat the water to prevent scale and corrosion.
ii) Controllers shall have SIM card data collection
iii) Controllers shall have the ability to test for reagents to include biocides used.
b) The vendor shall install bag side stream filters on both of the closed loop systems. The vendor shall not be responsible for providing support or consumables for these filters. The flow rate for each closed loop system is as follows:
i. Building 1 chilled water flow rate is 2400 GPM
ii. Building 20 chilled water flow rate is 1086 GPM
2. This amendment adds the following information to section A.3.2.3.1 CHEMICALS
The vendor shall use a stabilized bromide as the oxidizing biocide and Glutaraldehyde as the non-oxidizing biocide to treat the chilled water and condenser tower systems. There is no specific feed schedules requested. The only requirements are that 1. The schedules are in accordance with EPA and NY State regulations 2. That fungal/bacteria growth is maintained below 10,000 cfu/ml 3. There are 0 Legionella hits on an annual basis.
3. This amendment changes section A.3.2.4 DISINFECTION AND INSPECTION SERVICES (f) to The vendor shall respond to a high bacteria or fungi samples (above 10,000 cfu/ml) on the next work day to disinfect and remediate all impacted systems.
4. This amendment changes section A.3.2.4 DISINFECTION AND INSPECTION SERVICES (d) to Unscheduled disinfections of any of the systems covered under this procurement shall be included in the cost of this procurement.
All other terms and conditions remain the same.