B8 MOLD & ASBESTOS REMEDIATION & DRAINAGE REPAIRS Canandaigua, NY VA Medical Center
Solicitation number
36C24218B0070
Issued by

About this file

36C24218B0070 S02 SOW B8 mold asbestos 100.docx

View the file

Other files

File Type Posted
36C24218C0044-000.docx DOCX document
36C24218B0070-001.docx DOCX document
36C24218B0070-005.pdf PDF
36C24218B0070-006.pdf PDF
36C24218B0070-003.docx DOCX document
36C24218B0070-007.pdf PDF
36C24218B0070-004.txt TXT text file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Number: 528A5-18-509 B8, Mold & Asbestos Remediation & Drainage Repairs

B8 Mold & Asbestos Remediation & Drainage Repairs

PROJECT SCOPE

GENERAL PROJECT WORK SCOPE DESCRIPTION

Existing Conditions:

The Canandaigua VAMC is located at 400 Fort Hill Avenue, Canandaigua, NY 14424. The layout is a campus with more than 30 buildings located on over 150 acres. Normal working hours are Monday – Friday 8:00am – 4:30pm. Building 8 houses numerous functions including, but not limited to audiology, chaplain services, patient work spaces, and patient care areas on the first (A) and second (B) floor. This remediation effort will take place in portions of the audiology and patient computer lab on the ground (G) floor. Work will also take place on the exterior of the building to fix water drainage issues.

Scope of Work:

The scope of this project is to remediate all mold and asbestos in rooms 9A (Audiology) and 10 (Patient Computer Lab) and to install drainage tile and waterproofing to prevent further water infiltration.

It is highly recommended that the contractor attend the pre-bid site visit outlined in the solicitation. The facility is occupied by personnel including patients on 8B (second floor). Special precautions are to be taken to ensure that air and waste materials are handled and disposed of properly and in accordance with regulations. If debris is removed through the tunnel, the contractor shall ensure the tunnel is cleaned of tracked, dust, etc. All items remaining in the room when it is turned over to the contractor are to be removed and disposed of in accordance with regulations. Special care will be taken to not damage the white fence surrounding the courtyard. Off-hour work may be required in order to minimize impact to services provided in the facility.

The contractor will provide all necessary labor, materials, and supervision to execute the work detailed in the construction documents. The contractor will be required to submit a proposed mold and asbestos remediation plan to the VA prior to work start. This plan will include copies of necessary certifications and an outline of procedures that will be followed including personal protective equipment that will be worn. Refer to specifications and submittal section of this project scope for additional submittal information. The work must be accomplished by a team that includes a certified mold remediation specialist and a certified asbestos remediation specialist and must be in accordance with the specifications and all regulations. Placement of the shower and decontamination unit will be in coordination with the COR. Once abatement is complete, 1 hour fire rated construction barriers must be installed for the project duration.

Negative air pressure is to remain in place until post remediation mold and asbestos results for the area are returned negative, the room is deemed clear and the contractor has gained approval from the COR. The contractor is to place a manometer in both rooms to ensure negative pressure is maintained throughout the project. The location of the manometer will be decided in coordination with the COR. The VA will procure a third party sampling and testing company to monitor both the mold and asbestos remediation.

The contractor is to clean, charge, and return to service all HVAC units, condensers, etc. found in the space and that service the space.

Lead based paint is not anticipated on the project; however the contractor is required to perform an inspection of any area that shall be disturbed for lead based paint. Asbestos floor tile, with mastic is present and is to be abated under this project. Any additional issues identified are to be brought to the CORs attention before proceeding.

Liquid membrane waterproofing will be applied to the subsurface exterior walls as shown on the drawings. A new drain line is to be installed from the drainage point shown on the drawings to a connection point at the main sanitary drain line.

Full depth excavation will occur to the bottom of the footer in designated areas. 4” perforated pipe drainage tile will be installed. The tile will be tied into the existing drainage system as shown in the drawings.

Work done under this project must comply with the provided infection control risk assessment (ICRA) including negative air pressure through the use of a HEPA filter and complete isolation of the area including sealing of the area with duct tape. All work area exits are to be HEPA vacuumed and damp mopped with a detergent solution at the end of each daily work shift. The work space is to remain locked and secured at all times.

Work includes, but is not limited to:

Demolition

· Remove all carpeting from rooms 9A and 10 (approximately 600 SF)

· Removal all asbestos tile and mastic from rooms 9A and 10 (approximately 600 SF)

· Remove all cove base from room 9A and 10 (approximately 130 LF)

· Remove sheetrock, paint, plaster, etc. in areas shown in the drawings. Remove from floor to ceiling (approximately 8’) and beyond if required

· Remove all ceiling tile (approximately 600 SF)

· Notify the COR if mold extends beyond the remediation areas shown in the drawings

· Remove existing countertop

Reconstruction

· Replace carpeting (approximately 600 SF) as shown in schedule of finishes

· Install new cove base (approximately 130 LF) as indicated in schedule of finishes

· Patch, paint and refinish walls, doorframes, and window frames to match existing

· Paint all walls, door, and other surfaces (including those not remediated/repaired)

· Replace all ceiling tile with the VA standard.

Waterproofing

· Liquid membrane waterproofing shall be applied on the exposed subsurface exterior walls.

· Elastomeric waterproofing material shall be used

· Material shall be installed by a certified applicator

· Material must be applied within manufacturer’s specifications

· Material must be guaranteed by the manufacturer in writing

· Material must be proven in subsurface applications to completely stop water intrusion in similar regions to this VA

Drainage Repairs

· A 12” trench will be excavated around the building as shown in the drawings (approximately 60 LF).

· Full depth excavation will occur to the bottom of the footing in these designated areas. The contractor is responsible for disposing of all materials removed during excavation. Disposal of these materials will meet all regulatory requirements.

· A 6’ tall chain link fence shall be erected around the trenched area prior to work start. OSHA requirements are to be strictly adhered to and construction signs will be posted while trenching operations are on-going. The area is to be secured from access at all times. Keys to the area will be provided to the COR in accordance with the specifications.

· The drainage tile will be piped into a new storm drain run that runs to the main as is shown on the drawings.

· Flat-style geotextile fabric will be installed at the bottom of the trenched area following compaction testing. Fabric sides will be overlapped at least 4” throughout. This geotextile will be sufficient in size to fully wrap around the backfilled material and pipe once it is placed.

· Drainage tile will be placed as is shown on the drawings.

· The top of the drainage tile will be >1’ below the bottom of the basement floor slab throughout.

· Sock-style geotextile fabric shall encase the drainage tile in accordance with the specifications.

· The drainage tile shall be sufficient in strength such that it does not decompress or become damaged when the area is backfilled.

· The excavated area will be backfilled with stone in two 6” layers to within 1’ of the surface with 1” washed gravel fill.

· The last foot from rock to surface will be topsoil.

· The contractor shall run a camera through the line at project completion to visually show the VA that the pipe is completely open. The contractor shall commission the line to show that it functions.

· The last foot from gravel to surface (above the flat-style geotextile fabric) will be filled with topsoil.

· The surface will be returned to the condition it was in prior to turn over for the project. This will include returning and/or replacing all plants, flowers, wood chippings, etc., in kind.

HVAC condensate line

· Condensate lines are to be reworked such that they are tied into the drainage system. No leaking is to occur following this rework.

Code requirements:

The installed system must, at a minimum, be in accordance with all applicable codes including Veterans Affairs standards which can be found at https://www.cfm.va.gov/til/. This will include, but not be limited to: Department of Veterans Affairs Design Manuals, VA Publications, and Construction Standards, National Fire Protection Code (NFPA), Life Safety Code, Underwriters Laboratory (UL), International Building Code IBC, National Electric Code (NEC), the VA Information Security Handbook 6500.6, Occupational Health and Safety (OSHA), and Environmental Protection Agency (EPA) requirements (to include Mold Remediation in Schools and Commercial Buildings). All work will be completed by certified individuals. All abatement will be in compliance with NYSCR 56.

Specifications: Please see attached.

General Requirements:

A. The contractor shall review the contract documents for conflicts. Where conflicts exist work shall not proceed until the COR has been notified and has given direction.

B. Where incidental work is required to accomplish work shown on the drawings, this work is implied and shall be included as part of the base bid.

C. Prior to any work commencing in an area, the contractor shall notify the COR of his intention to work in the area and shall schedule a walkthrough with the COR to determine existing conditions.

D. After the work, the existing work areas shall be returned to their original state before final approval shall be given. After the completion of construction, the contractor shall completely clean all surfaces of construction debris. All surfaces shall be wiped clean of dust, including fixtures, window sills, door frames, etc.

E. The contractor shall ensure that all utility lines are marked prior to external work commencing. This work cannot be done through 811 as they do not do markings on federal property, but must be done by an independent marking agency secured by the contractor.

F. The contractor shall provide a minimum of two (2) hardcopies of operating and service manuals for each device/material installed as part of the project.

G. The contractor shall receive all deliveries of materials, equipment, tools, or other goods off of station, and bring them to the job site. The Canandaigua VA shall not accept deliveries for project purposes.

H. The contractor shall prepare and submit an excel spreadsheet listing all submittals required. The worksheet shall be submitted by the contractor and reviewed and re-submitted as necessary.

I. The contractor shall not proceed with any on-site work until the completion of the submittal process or approval to proceed from the CO and COR without completion of the submittal process. Not less than 14 calendar days shall be planned for COR review of each submittal. Re-submittals shall be provided as required by the COR, and shall be treated as a new, separate submittal.

J. Any non-lead time materials will only be paid for when installed.

K. Any items identified as punch list items will be fixed prior to project closeout.

L. Special care will be taken to secure tools and construction equipment during construction as this facility has patients living in it and have patients who utilize the courtyard gardens.

M. Work cleanliness must be adhered to throughout the project.

N. Sounds and vibrations must be kept to a minimum to avoid patient disruption. The COR reserves the right to stop work if sound and vibrations are impacting patient living.

O. The contractor shall warranty all work including the remediation, waterproofing and corrected drainage for 1 year from the date of acceptance. Warranty shall include any labor or parts necessary to ensure complete functionality of the new drainage system up to and including complete rework of installed system and re-repair of areas.

P. This work scope is based on the initial investigation. Additional removal may be necessary if mold has propagated in the time from the initial study to the time of the remediation.

Submittals:

Submittals are required for all items outlined in the specification and include, but are not limited to the submittals as shown in the attached submittal log.

Project Duration:

The total project duration for this project is not to exceed 90 days. This includes all processes starting with submission and approval of all submittals and ending with final punch list completion.