This is a Performance Work Statement (PWS) for OEM-supported preventive and corrective maintenance services for five Bayer radiology injector systems at the White River Junction VA Medical Center in White River Junction, Vermont. The contract period consists of a one-year base period from December 5, 2026 to December 4, 2027, followed by two optional one-year renewal periods extending through December 4, 2029.

The contractor must maintain equipment uptime with unscheduled downtime not exceeding 8 hours per unit monthly, excluding scheduled preventive maintenance and federal holidays. Key service requirements include: performing one annual OEM-recommended preventive maintenance per unit with documentation provided within two business days; acknowledging routine service requests within 24 hours and providing onsite service within 48 hours (excluding weekends and federal holidays); and responding to emergency service requests with phone contact within 1 hour and onsite response within 2 hours during normal operating hours (Monday–Friday, 7:30 AM–4:30 PM local time). All parts must be OEM-supplied, and technicians must be OEM-trained Facility Service Engineers. The contractor shall provide PM reports and emergency service reports electronically to the Government Representative and equipment users, with copies of PM reports also sent to VHAWRJCE@VA.gov. Hardware and software updates must be coordinated outside normal hours at no additional charge unless detrimental to equipment uptime. Contractor personnel are required to check in/out with Clinical Engineering, wear visible identification, comply with VA policies regarding parking and weapons, and schedule routine service at least 48 hours in advance. The PWS includes a Performance Requirements Summary establishing specific performance standards, acceptable quality levels (ranging from 95–100%), surveillance methods, and remedies for nonconforming performance including corrective action requests (CDRs) and personnel removal for credential failures.

View the file

Other files

File Type Posted
SSJ Bayer Injector Maint - WRJ 11.04.2026.pdf PDF
36C24127Q0057.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Work Statement (PWS) Preventive & Corrective Maintenance of Bayer Radiology Injectors

White River Junction VA Medical Center

1. Scope

The contractor shall provide OEM-supported preventive and corrective maintenance, parts, and technical support for five Bayer radiology injector systems at the White River Junction VA Medical Center, 163 Veterans Dr, White River Junction, VT 05009.

2. Period of Performance

The period of performance consists of a one-year base period, plus two one-year option periods.

Base Year: 12/5/26 -12/4/27 Option Year 1: 12/5/27 – 12/4/28 Option Year 2: 12/5/28 – 12/4/29

3. Place and Hours of Performance

Services shall be performed at the White River Junction VA Medical Center. Normal hours are Monday–Friday, 07:30–16:30 local time, excluding Federal holidays.

4. Performance Requirements

• Unscheduled equipment downtime shall not exceed 8 hours per unit per month, excluding scheduled PM, holidays, and periods when the vendor is awaiting Government access.

• The Contractor shall perform one annual OEM-recommended preventive maintenance (PM) per unit, scheduled in coordination with the Government Representative, and shall provide complete PM documentation within two business days of completion.

• The Vendor shall acknowledge routine service requests within 24 hours and provide onsite service within 48 hours, excluding weekends and federal holidays, unless otherwise approved by the Government Representative.

• For emergency service requests (ESR), the Contractor shall provide phone response within 1 hour and on-site response within 2 hours during normal hours of coverage, excluding weekends and federal holidays, unless otherwise authorized by the Government Representative.

5. Parts and Qualified Personnel

All parts shall be OEM. Technicians must be OEM-trained and fully qualified Facility Service Engineers (FSEs).

6. Documentation and Deliverables

The contractor shall provide PM reports and ESRs for all service events. Reports shall be submitted electronically to the Government Representative and equipment user. PM reports may also be sent to VHAWRJCE@VA.gov.

PM checklists and procedure outlines shall be provided to the Government Representative.

7. Updates/Upgrades

Hardware and software updates shall be coordinated outside normal hours at no additional charge unless detrimental to equipment uptime, as determined by the Government Representative.

8. Government Furnished

No Government-furnished tools, equipment, manuals, or diagnostic software shall be provided.

9. Security and On-Site Protocols

Contractor personnel shall check in/out with Clinical Engineering, wear visible identification, and comply with VA parking, no-smoking, and no-weapons policies. Escort will be provided in sensitive areas. Routine service shall be scheduled at least 48 hours in advance.

10. Federal Holidays

New Year’s Day; Martin Luther King Jr. Day; Presidents’ Day; Memorial Day; Independence Day; Labor Day; Columbus Day; Veterans Day; Thanksgiving Day; Christmas Day.

11. Performance Requirements Summary (PRS)

The Performance Requirements Summary (PRS) serves as a performance management tool that defines the required service outcomes, performance standards, acceptable quality levels (AQLs), Government surveillance methods, and applicable remedies for nonconforming performance. The PRS establishes objective criteria for evaluating contractor performance and documenting compliance with the requirements of this Performance Work Statement (PWS).

Requirement Performance Standard

AQL Surveillance Method

Remedies

Downtime ≤ 8 hrs/month/unit

100% Downtime logs CDR, corrective action

PM Completion Annual OEM PM 100% PM report review

Rework, CDR

Routine Response

24h response / 48h onsite

95% Timestamp review

CDR

Emergency Response

1h phone / 2h onsite

95% Call log / ESR CO escalation

OEM Parts OEM parts only 100% Parts audit Replacement at no cost

Documentation ESR complete and timely

95% ESR review Resubmission

Qualified Personnel

OEM-trained FSEs

100% Credential check

Personnel removal

1. Scope
2. Period of Performance
3. Place and Hours of Performance
4. Performance Requirements
5. Parts and Qualified Personnel
6. Documentation and Deliverables
7. Updates/Upgrades
8. Government Furnished
9. Security and On‑Site Protocols
10. Federal Holidays
New Year’s Day; Martin Luther King Jr. Day; Presidents’ Day; Memorial Day; Independence Day; Labor Day; Columbus Day; Veterans Day; Thanksgiving Day; Christmas Day. 11. Performance Requirements Summary (PRS) The Performance Requirements Summary (PRS...

File details come from the government source that posted it. Updated .