This document is an exhibit titled "CALCULATION OF SELF-PERFORMED WORK" that is part of a response to RFP 36C24124R0065 for the Renovate and Upgrade Angio OR Suite project at the VA Medical Center in Providence, RI. The exhibit provides instructions and a format for the offeror to identify and calculate the cost of work they will self-perform on the project. It notes that self-performed work must meet a minimum of 25% of the total contract amount. The exhibit also states that an offeror demonstrating the capability to self-perform a major construction element may receive additional consideration in the evaluation. The related federal contract opportunity is for a firm-fixed-price construction project to renovate and upgrade the Angio OR Suite at the VA Medical Center in Providence, RI. The magnitude of the project is between $1-$5 million and is 100% set-aside for Service-Disabled Veteran-Owned Small Businesses.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT D: CALCULATION OF SELF-PERFORMED WORK

SUBMITTED IN RESPONSE TO RFP 36C24124R0065 – Renovate and Upgrade Angio

OR Suite, VA Medical Center, Providence, RI, Project Number 650-CSI-351

Use a format similar to the following to identify and calculate cost of the work to be self-performed.

Refer to the definitions pertaining to “Self-performance of work”, “On the Site” and “Total amount of work to be performed under the contract”.

Explain in detail how you will perform the minimum percentage required (25% GC) with your own resources. Note: An offeror who has the capability to perform both as a general contractor and self-perform a major element of construction, for example, prefabricated concrete, may be afforded additional consideration in the evaluation. You should address your general self-performance capability.

(Includes mobilization and utilization of owned or rented plant and equipment to be operated by the prime contractor’s own employees; only those materials which will be both purchased and installed by the prime’s own forces; labor associated with those aforementioned materials or equipment; only those supplies to directly support work performed by the contractor’s own employees; and the contractor’s own job overhead costs.)

Clearly describe the work to be self-performed:

Show Calculation of Self-Performed work:

B.1 Total Offer Price: $

B.2 If applying for consideration as a General Contractor (multi-discipline projects) work must be self-performed $

B.3 Subtract G&A, home office overhead, prime contractor’s markups for profit, bond, state use tax, etc.

B.4 Remainder is “Total amount of work to be performed under the Contract” = $

B.5 “Work to be self-performed”: = $ Amount shown on this line should match the amount shown for “Show Calculation of Self-Performed work”? (Includes mobilization and utilization of owned or rented plant and equipment to be operated by the prime contractor’s own employees; only those materials which will be both purchased and installed by the prime’s own forces; labor associated with those aforementioned materials or equipment; only those supplies to directly support work performed by the contractor’s own employees; and the contractor’s own job overhead costs.)

B.6 15 % Self-performed Work = Line B.5 / B.4 X 100% = %