This is a sources sought notice for professional architect/engineering design services to develop drawings, specifications, cost estimates and construction administration associated with extending chill water services at a VA medical center. Interested SDVOSB, VOSB and small businesses must indicate interest by August 7, 2020 via email and provide evidence of NAICS code 541330 verification as an SDVOSB/VOSB, a statement of intent to submit a proposal, and experience with retrofitting chill water systems, MEP upgrades, and utility upgrades in occupied medical buildings. Firms must also prove sufficient professional liability insurance and register in SAM. The notice is issued by the Department of Veterans Affairs Veterans Health Administration VISN 1 for the VA Medical Center Central Western Massachusetts located in Leeds, MA.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contract Opportunity Sources Sought Notice

PRODUCT SERVICE CODE

SUBJECT

CONTRACTING OFFICE'S

ZIP-CODE

SOLICITATION NUMBER

RESPONSE

DATE/TIME/ZONE

ARCHIVE

DAYS AFTER THE RESPONSE DATE

RECOVERY ACT FUNDS

SET-ASIDE

NAICS CODE

CONTRACTING OFFICE

ADDRESS

POINT OF CONTACT

(POC Information Automatically Filled from User Profile Unless Entered)

DESCRIPTION

See Attachment

AGENCY'S URL

URL DESCRIPTION

AGENCY CONTACT'S EMAIL

ADDRESS

EMAIL DESCRIPTION

ADDRESS

POSTAL CODE

COUNTRY

ADDITIONAL INFORMATION

GENERAL INFORMATION

PLACE OF PERFORMANCE

Required Field Contract Opportunity Sources Sought Notice

C1NZ

631-18-001 Extend Chill Water Through Bldgs 1 & 60 01053 36C24120R0137 08-07-2020

2:00PM

EASTERN TIME, NEW YORK, USA

N 541330 Department of Veterans Affairs

VAMC CENTRAL WESTERN MASSACHUSETTS (CWM)

Acquisitions-90 421 North Main Street Leeds MA 01053-9764 Heather Libiszewski-Gallien Heather.Libiszewski-Gallien@va.gov

VAMC CWM

North Main Street Leeds, MA 01053

USA

SOURCES SOUGHT: The VA Medical Center Central Western Massachusetts in Leeds, MA has a requirement for a Firm Fixed Price contract to provide professional Architect/Engineer (A/E) Design Services to develop complete drawings, specifications, cost estimates and construction period administration associated with extending chill water services.

The NAICS code is 541330 and the small business size standard is $16.5 million. Interested SDVOSB, VOSB and SB firms must indicate their interest to the Contracting Officer no later than August 7, 2020 via email to Heather.Libiszewski-Gallien@va.gov. The following information is requested in response to this notice:

(1) If an interested firm is an SDVOSB or VOSB, evidence of verification in Vet Biz as an SDVOSB or VOSB firm under NAICS code 541330;

(2) A positive statement of your intention to submit a proposal in response to a solicitation for this project;

(3) Evidence of your experience in A/E Services with retrofit and expansion of existing chill water systems;

(4) Evidence of your experience in A/E Services with MEP upgrades to existing HVAC systems;

(5) Evidence your firm has experience with a complete design of utility upgrades within an occupied medical building;

(6) Proof of professional liability insurance required to cover the amount of this project;

All information must be submitted in sufficient detail for a decision to be made on the availability of interested SDVOSB, VOSB or SB concerns. Failure to submit all information requested will result in a contractor not being considered as an interested SDVOSB, VOSB, or SB concern. If adequate interest is not received this action will not be set-aside. Interested firms may reply via e-mail to Heather.Libiszewski-Gallien@va.gov. Firms must be registered in the System for Award Management (SAM). Visit www.sam.gov to register in this database. SDVOSB or VOSB firms must be verified by the Center for Veteran Enterprises (CVE).

Scope of Work NRM Project No. 631-18-001 Extend Chill Water Through Buildings 1 & 60

1. OVERVIEW —

1.1 Government Agency Department and Address:

VA Central Western Massachusetts HealthCare System – VISN1 – Leeds

1.2 Project Title, Number and Location:

Project Title: Exterior Site Improvements Project Number: NRM No. 631-18-001

1.3 Scope of Work

Provide all professional architectural and engineering (A/E) services necessary to develop complete drawings, specifications, cost estimates, and construction period administration associated with extending chill water service on the Leeds campus in Northampton Massachusetts. Conduct preliminary project scope meetings and site survey investigations to develop the necessary elements for conceptual layout schemes with proposed alternatives consistent with the VA’s project team goals as prioritized during preliminary project meetings, field surveys and studies.

The intent of this project is to expand the chill water service and modernize the Chapel HVAC, but is not limited to:

· Upgrade the chill water distribution system in the Main Hospital, building 1, to extend chill water service to all floors and existing HVAC units.

· Extend the chill water system to the Chapel Building via building 1 or a separate line.

· Evaluate the Chapel HVAC deficiencies and design the partial or complete replacement of these systems.

· Evaluate Chiller Plant to determine the available capacity above and beyond the new loads from building 1 and 60, and accommodate the service to additional buildings.

The Leeds Campus Main Hospital building currently has chill water service, from the chill water plant commissioned in 2014, limited to the second floor east and west wings.

VA Chapel, building 60, was built around 1960. The existing heating and ventilating systems appear to be original and are essentially inoperative. The original controls are a mix of electronic and pneumatic, and are in serious disrepair. Perimeter steam radiation is functional and will be updated in a concurrent steam upgrade phase. The heating and ventilating systems are in need of evaluation and replacement with a new HVAC system.

Work will include, but not be limited to, mechanical, electrical, plumbing, civil, and environmental. There is minor structural, architectural, and possible asbestos and lead paint removal work expected. Include other specialty consultants such as those associated with the environmental permitting and others pertinent to the project requirements within the constraints of the construction budget consistent with the VA’s project team goals as prioritized during project meetings and field surveys.

The A/E shall obtain all environmental and other necessary permits that would be required prior to construction commencing – including but not limited to the Massachusetts Dept. of the Environmental Protection (MassDEP)

The A/E shall base their design to meet the following sustainable energy requirements:

· VA Sustainable Design Manual (May 2014 or later)

· Site Development Design Manual (Feb 2013 or later)

· NEPA Interim Guidance for Projects (Sept 2010 or later)

· VA Cultural Resource Management Checklist

2. DESCRIPTION OF WORK —

2.1 General: Conduct preliminary meetings and site survey investigations to define the necessary elements of the project scope of work fulfilling the goals of the VA’s project team (Engineering Svc), and presentation of preliminary layout plans with proposed alternatives to the User Group. Based on User Group meetings and site surveys, prepare a detailed project plan description report pertinent to the project requirements within the constraints of the construction budget consistent with the VA’s project team goals. Through the course of the design phase, it will be necessary to interface with Medical Center staff to ascertain the details of the scope through a series of meetings and periodic submissions of documents. All design submission requirements shall be in accordance to A/E Contract and conform to all VA criteria and standards.

The A/E shall use VA Program Guides, Design Manuals and Master Specifications in preparing the Construction Documents for the project. However, should the A/E determine that deviation from such standards and specifications is necessary or beneficial to the Government; s/he shall promptly submit a request in writing to the Contracting Officer for permission to make the deviation. The request shall include an explanation of the specific reasons for the desired change and benefits expected.

2.2 Implementation: Engage the services of all consultants in each discipline deemed to be necessary to fulfill the requirements of the project plan. Each discipline shall document and investigate the relevant existing conditions, review the building available information, and verify all essential elements pertinent to their discipline. Site investigations shall measure, photograph, video tape, and document the conditions of areas to be renovated and/or impacted.

The A/E shall visit the project site to investigate the information shown on the Government Furnished drawings, record (asbuilt) drawings and other planning documents which are part of this contract. This information is the best available, but the Government does not guarantee its accuracy or completeness. The A/E's investigation of field conditions shall be performed in a competent professional manner in accordance with the Architectural Design Manual PG18-10. It is the A/E's responsibility to research the existing Government documents, determine those that are applicable to the project and request copies from the Government; the Government will not perform a search of Government documents to determine the information that the A/E may need during design.

2.3 Project Development: The A/E shall provide all services required to prepare documents and reports for the subject project consistent with the VA’s project team goals as prioritized during preliminary project meetings, field surveys and studies. The A/E shall determine existing conditions, severity of deficiencies, if any previous deficiencies have been corrected and to identify any conditions which may have previously been unreported. Cost estimates shall be prepared to reflect the cost of replacing the component in a stand alone project (i.e., not as part of another project) and all cost for this replacement including but not limited to asbestos removal, required phasing, special field conditions and/or temporary equipment needed during the construction. The completed report shall then be submitted for approval to the Project Engineer.

2.4 Project Design: Based on the approved design development the A/E shall provide all services required to prepare plans, specifications, and other supporting documents necessary to correct the identified deficiencies in priority order. The approved cost estimate and available project funding will be used to determine the amount of deficiencies which will be correct under this project. A complete design including but not limited to determination and evaluation of existing conditions, necessary engineering calculation, necessary design work, independent fire safety/life safety review, IH Services, quantity and cost estimates, bid schedule, construction cost estimates, a proposed construction schedule, design analyses and calculations, a design documentation report, engineering considerations and options report shall be developed for this project.

2.5 Asbestos: The proper identification of Asbestos to determine construction costs associated with Comprehensive Strategy & Report phase of this project are considered part of this project. To extent possible existing Asbestos Assessment of the facility will be made available to the A/E. Additionally proper asbestos abatement design and IH monitoring services required during construction to correct the deficiencies selected for the construction design portion of this project shall also be provided by the A/E.

2.6 Lead: The proper identification of lead paint to determine construction costs associated with Comprehensive Strategy & Report phase of this project are considered part of this project. To extent possible existing Lead Paint Assessment of the facility will be made available to the A/E. Additionally proper lead paint abatement design required during construction to correct the deficiencies selected for the construction design portion of this project shall also be provided by the A/E.

3. GENERAL DESCRIPTION of SERVICES —

A/E shall provide the services indicated in this Overview, Supplement A, Supplement B and Volume C A/E Design Submission Instructions link: http://www.cfm.va.gov/til/ae/aesubmin.doc.

These services will be provided in distinct phases:

Conceptual – Preliminary User Group Meetings & Field Surveys 15% Submittal – Conceptual 35% Submittal – Schematics 65% Submittal – “DD” Design Development 90% Submittal – “CD” Construction Documents 100% Submittal – Bid [Final] Documents Construction Period Services Project Close Out Submittal – “As-Built” Construction Documents

3.1 Drawings: The drawings, specifications, and all other submittal items will be prepared using English units of measure.

3.1.1 General: The A/E shall prepare drawings in a manner that clearly and adequately delineates the work to be accomplished by the construction contractor. Design documents will be sufficiently detailed to permit construction contractors to submit responsive bids without visiting the project site. The cover sheet will be signed and stamped by principal of the firm who is a registered Architect or Professional Engineer. All drawings will be created using AutoCAD and National CAD standards. These CAD standards are available on the Internet at http://www.cfm.va.gov/til/projReq.asp and click on the VA National CAD Standard Application Guide link.

3.1.2 CAD Files: One CAD (*.DWG) file shall be used per drawing (sheet) applying the VA’s CAD layering and disk labeling protocols. All files shall be IBM compatible and furnished on high quality CD-R disks. Provide in accordance with Supplement “B” sets of drawings (AutoCAD). The computerized version, format and media of the computer disks and files shall be specified and verified by the VA Project Engineer at the time each submission is due (XRF, DXF and ZIP files are not acceptable). Provide durable high quality plastic storage boxes at each submission for long term archiving of the disks.

3.1.3 Format: All drawings and sketches will be provided in both hard copy and electronic file format. Full-sized drawings shall be developed 30”x42” sized sheets (30 inches by 42 inches at the trim line) and shall utilize the standard VA title block. Fonts shall be standard AutoCAD, and drawings must be fully compatible with AutoCAD 2014. Drawing file names must relate to the VA project name, discipline and subject as approved by the VA Project Engineer. Drawings shall utilize world coordinate system with standard cross hairs. Adobe Acrobat PDF files for each AutoCAD file shall be provided.

3.1.4 An independent fire safety and life safety review shall be accomplished at each design submission. Include the cost and coordination for a fire/safety review.

3.2 Specifications …

3.2.1 General: The A/E shall utilize the latest edition of VA Master Specifications as revised and provided by the facility supplemented by the VA Office of Construction and Facilities Management Master Specifications as needed. The VA retains no responsibility for the development or preparation of any specification. While it is recognized that certain Divisions and/or Sections will require significant input from the VA, the A/E retains overall responsibility for these Sections.

3.2.2 Electronic Files: All files shall be Microsoft compatible and furnished on high quality CD-R disks. Provide in accordance with Supplement “B” sets of specifications (MS Word). The computerized version, format and media of the computer disks and files shall be specified and verified by the VA Project Engineer at the time each submission is due (ZIP files are not acceptable). Provide durable high quality plastic storage boxes at each submission for long term archiving of the disks.

3.2.3 Outline Specifications: The A/E shall develop an outline specification listing the proposed guide specifications and the A/E prepared sections that will be used for the project. The outline specification will list the guide specification number and title for each proposed section. Sections shall be arranged within their respective divisions, in numerical order. New specification sections, developed by the A/E, will be numbered to fall in their respective division at a logical location.

3.2.4 Editing Specifications: The A/E must thoroughly edit and adapt the Specifications to satisfy the project requirements and provide a complete set of construction specifications. The A/E shall notify the VA in writing should there be instances where there are no appropriate Master Specifications available for use. At the VA’s direction the required specifications will be prepared by the A/E. These specifications shall list the essential features, functions, and other factors to clearly indicate the type and quantity of items/work required. All specifications will be prepared by listing parameters and requirements that can be met by several manufacturers.

3.2.5 Construction Contractor Submittal Register: The specifications require the construction contractor to submit shop drawings, samples, manufacturer’s data, certificates, test reports, and other items to the Government. The A/E shall prepare a complete listing of construction contractor submittal requirements on an Excel Spreadsheet. The spreadsheet shall have a separate line for each required submittal and separate columns for Division, Section, and type of submittal (catalog cut, sample, etc).

3.3 Quantity and Cost Estimates …

3.3.1 Format: The A/E shall prepare quantity computations, cost estimates, and construction cost estimates for this project. All construction cost estimates shall conform to the requirements contained in VA Manual for Preparation of Cost Estimates (latest edition). Manual is available on the internet at http://www.cfm.va.gov/cost/ .

3.3.2 Cost Estimate Submittal: Cost estimates shall be submitted in 2 hard copies and in electronic form. THE A/E IS RESPONSIBLE FOR ESTABLISHING INTERNAL CONTROLS FOR KEEPING THE PRJOJECT DESIGN WITHIN PROJECTED CONSTRUCTION FUNDING. THE A/E WILL BE REQUIRED TO REVISE DESIGN AND RESUBMIT COST ESTIMATES AS NECESSARY (AT NO COST TO THE VA) SHOULD COST ESTIMATES EXCEED CONSTRUCTION FUNDING.

3.3.3. Proposed Phasing and Construction Schedule: The A/E shall prepare a proposed schedule for construction that is consistent with the project construction cost estimate. During development of this schedule, due consideration will be given to standard construction practices, durations of tasks, the sequence of construction, procurement of materials, climatic conditions, etc. It is planned that areas in and adjacent to the proposed construction area shall be occupied during construction. The A/E shall develop a phasing plan that addresses this fact and assures smooth implementation of required construction.

3.4 Design Analysis (DA): The A/E shall develop a DA that addresses general project parameters, functional and technical requirements, design objectives, design assumptions and calculations applicable to the project’s design. Design/Construction Alternatives, existing physical limitation and their impact shall also be included in the DA.

3.5 Quality Control …

3.5.1. Quality Control Plan: The A/E shall prepare a Quality Control Plan (QCP) which includes the following as a minimum:

· Identification and discussion of all organizational and technical interfaces

· Design team members and their areas of responsibility

· Team members responsible for checking the design

· Team members responsible for checking the electronic files

· Team members responsible for reviewing and submitting the required VA Design Alerts and Quality Alerts

· Project Schedule showing key milestones and review periods

3.5.1.1. VA Design Alerts and VA Quality Alerts can be found on the internet at http://www.cfm.va.gov/TIL/ .

3.5.2. Quality Assurance: The A/E is responsible for developing and performing quality assurance reviews of all work to confirm that proper criteria, regulations, laws, codes, principles and professional procedures have been used. This includes work performed by subcontractors. The VA shall review all project submissions but this review is general in nature and should not be considered as part of the A/E’s Quality Control Plan and/or Quality Assurance.

3.5.3 Quality Certification: The A/E shall certify at each submission in writing that he/she has performed quality assurance reviews of that submission.

3.6 Site Visits, Meetings/Conferences, and Discussions …

3.6.1. Site Visits: The A/E shall perform design site visits as required to accomplish the scope of this project. The purpose of these visits is to further define project requirements, observe and evaluate existing field conditions, review any existing documentation, conduct required design meetings, and to gather supplemental site data necessary for performing the design. Reports summarizing the conditions observed, personnel contacted, and data gathered during the visits shall be prepared and included in the Design Development Documentation.

3.6.2. Design Review Conferences: Design review conferences shall conduct shortly following the issuance of each review Submission. Refer to Supplement B for the proposed schedule, but will typically take place two weeks after the submission date. Design review conferences for the Schematics, Design Development and Construction Document Development phase shall include the A/E Project Manager/Senior Designer. These conferences shall take place at the facilities where the work is being performed.

3.6.3 Site Visit and Meeting Minutes: The A/E shall take notes and prepare minutes for all site visits, meetings and conferences attended during design. Minutes will be prepared in typed form, signed by the A/E Project Manager, and furnished to project engineer within seven calendar days after the meeting/conference for concurrence and distribution to attendees. Copies of all meeting/conference minutes will be included in each Submission.

3.7 Responsibility after Design Completion: The A/E is required to support the VA should errors or omissions in the documents create problems in bidding or administering the contract for construction. As needed, the A/E will clarify the design intent and correct any errors or omissions in the original documents. The corrections shall be done in a timely manner at no additional cost to the Government. The A/E shall incorporate amendment changes on the original drawings and/or CAD drawings when requested to do so after the bidding process at no extra cost to the Government. In addition, the A/E shall incorporate amendment changes on the submittal registers and submit on a CD labeled with the project title, location, and construction contract number. Also, during the bidding period, the A/E is required to assist in answering all bidders’ inquiries pertaining to the design. If clarifications are required, the A/E will prepare the required amendment. The A/E, however, shall not receive or respond to any direct inquiries from contractors.

3.8 A/E Services during Construction – Construction Period Administration (CPA):

CPA Services shall include, but are not limited to, review and approval of construction submittals covering products that have been listed within the contract documents and contractor substitutions, manufacturer’s data/performance sheets, samples, shop drawings, schedules, phasing plans. Compatibility analyses of different materials and recommendations associated with acceptance or rejection of alternate materials and products. Responses to Request for Information (RFI); change order review and recommendations; preparation of cost estimates to Request for Proposal (RFP); cost/time/impact estimates and recommendations relevant to design omissions and construction plan deviations.

Site visits (6 minimum) as required and/or requested by the VA Project Engineer for inspection of ongoing construction including final tests and inspections; documentation of all necessary site visits to the VA Project Engineer within one (1) week after the visit; verification of as-built conditions from contractor supplied marked up prints, and preparation of as-built documents in accordance with Supplement “B” which the VA will retain permanently. IH services associated with any asbestos abatement identified in the project.

The Government may issue a change order for the A/E to provide additional services to such as review of value engineering change proposals, preparation of design modifications, or other similar services during construction.

4. INCORPORATED REFERENCES — The following documents form a part of this contract to the extent referenced are included in the A/E Scope of Work. Design requirements identified in these documents are part of the A/E Required Services. National Codes, Standards and other requirements referenced in these documents also become part of the A/E Required Services. Design Copies of these may be found on internet at http://www.cfm.va.gov/TIL/ .

Supplement “A” - Scope of Work (attached)
Supplement “B” - A/E Submissions of Design Review Materials (attached)
Supplement “C” - A/E Minimum Submission Requirements (attached)
Supplement “D” - A/E Asbestos Requirements (by reference)
Asbestos Abatement Design Manual (by reference)
Construction Standards (H-18-3); latest revision (by reference)
Master Specifications (PG-18-1); as revised by facility supplemented with PG-18-1 as needed (by reference)
DVA National CAD Standard Application Guide (by reference)
DVA National CAD Standards & Detail (PG-18-4); latest revision (by reference)
Volume 1 Architectural; latest revision
Volume 2 Site Engineering & Landscaping; latest revision
Volume 3 Mechanical Engineering; latest revision
Section 1 Plumbing & Sanitary
Section 2 HVAC
Section 3 Steam Generation & Distribution
Volume 4 Electrical; latest revision
DVA Special Design Criteria; HVAC, Mechanical, Plumbing, Electrical, Structural, et al (by reference)
National Standard Plumbing Code (NAPHCC) (by reference)
National Electrical Code; latest revision (by reference)
Handicapped Standards; latest revision (by reference)
Barrier Free Deisgn Guide (VA Pub) (by reference)
NFPA; latest revision (by reference)
Applicable VA Design Guides (by reference)
Applicable VA Design Alerts (by reference)
Applicable VA Design Manuals (by reference)
Applicable VA Quality Alerts (by reference)
Applicable VA Equipment Guide Lists (by referenced)
VA Equipment Reference Manual PG-18-6 (by referenced)
A/E Representations and Certifications (attached)
A/E General Provisions (attached)
A/E Special Provisions (attached)
A/E Contract Procedures (attached)
A/E Architectural Review Checklist (attached)
A/E HVAC Review Checklist (attached)
A/E Plumbing Review Checklist (attached)
A/E Electrical Review Checklist (attached)
A/E Coordination Drawing Checklist (attached)
Manual for Preparation of Cost Estimates (by reference)
Applicable VA Energy Conservation & Sustainability Program requirements (by reference)
Preparation and Issuance of Construction Solicitation Contract Documents Manual (by reference)
A/E Submission Instructions for Minor and NRM Construction Program (PG-18-15) (by reference)

5. DESIGN BUDGET —

5.1 A/E is responsible to develop a design that can be built within budget and function as intended without change orders. The design must be based on the reality of existing site conditions and not solely on “As-Built” drawings. The A/E as part of their site investigation is responsible for confirming all existing conditions that may affect the project construction.

5.2 Cost Estimating: A/E shall be responsible, as part of the Quality Assurance Plan, to develop procedures for tracking estimated construction costs throughout the project design. Cost estimates submitted as part of the submission requirements shall not be used as the sole method of meeting this requirement. The A/E shall notify the Project Engineer when estimated construction costs exceed the construction budget. The A/E shall be responsible for proposing alternates to bring the project cost estimate within the construction budget. A/E shall modify design elements as necessary to keep the project cost estimate within the construction funding level. These changes shall be made at no additional cost to the Government.

5.3 Construction Budget: Refer to Supplement A

5.4 Deduct Alternates: Shall be utilized in the best interest of the Government for market condition variations to maximize the use of available Government funds. The Government shall select the proposed alternates from the A/E recommendations. Deduct Alternates shall not be used to bring the projected project costs within construction funding. These alternates are designed to assure a contract award and are in addition to the requirement to have a project design and estimate at or below construction funding.

5.5 Add Alternates: Shall not be used.

6. DESIGN PHASES —

6.1 CONCEPTUAL with ALTERNATIVES: Refer to Supplement A and B. Working with the VA Medical Center’s project team (Project Engineer and User Group) the A/E shall propose conceptual needs and requirements with proposed alternatives for the planned scope of work. This task is an iterative process requiring multiple proposals and revisions developed during site meetings.

6.2 SCHEMATICS: Refer to Volume C A/E Design Submission Instructions see link under paragraph 3. A/E shall develop specific design needs and requirements with proposed alternatives. These documents are to be developed from the documents, meeting minutes and recommendations made during the conceptual phase. Any existing utilities and/or equipment which are to be incorporated into the project design shall be reviewed and evaluated to assure that they are indeed there and are in sufficient quantity and condition to do so. Documents for this task define project requirements based on the planned scope of work. All required functional requirements shall be identified and incorporated into the project. All Architectural and Engineering requirements shall be identified and incorporated into the project. A/E shall provide an evaluation of the coordination of the drawings between disciplines; identification of errors, omissions or conflicts found within or between drawings and specifications.

6.3 DESIGN DEVELOPMENT: Refer to Volume C A/E Design Submission Instructions see link under paragraph 3. Any existing utilities and/or equipment which are to be incorporated into the project design shall be further reviewed and evaluated to assure that they are indeed there and are in sufficient quantity and condition to do so. Documents for this task define project requirements based on the approved scope of work. These documents are to be developed from the documents, meeting minutes and recommendations made during the schematics phase. All required functional requirements shall be identified and incorporated into the project. All Architectural and Engineering requirements shall be identified and incorporated into the project. A/E shall provide an evaluation of the coordination of the drawings between disciplines; identification of errors, omissions or conflicts found within or between drawings and specifications. A/E shall provide an evaluation of schedule to meet operating plan, project phasing and market conditions which may affect bidding. It is expected that at the completion of this phase marks the completion of the data gathering portion of the project. The A/E shall have obtained all information required (including site visits) to proceed directly the preparation of Construction Documents.

6.4 CONSTRUCTION DOCUMENTS: Refer to Volume C A/E Design Submission Instructions see link under paragraph 3. The A/E shall develop complete drawings and specifications and other documents necessary for the bidding and construction of this project. These documents are to be developed from the documents, meeting minutes and recommendations made during the design development phase. A/E shall perform an evaluation of the coordination of the drawings between disciplines; identification of errors, omissions or conflicts found within or between drawings and specifications. A/E shall provide an evaluation of schedule to meet operating plan Invitation for Bids and Award dates, project phasing, and market conditions which may affect bidding.

6.5 Special Remarks: Cost estimates shall incorporate construction related issues which include but are not limited to materials, systems and construction techniques. Design documents review, analyses and recommendation of cost estimates covering labor, materials, equipment, general conditions and requirements developed for the project. Estimates shall allow for incorporation of review comments, which are within the SOW.

7. SUBMITTALS AND PERFORMANCE SCHEDULE —

7.1 Deliver Submission Documents to the VA Central Western Massachusetts Healthcare System Project Engineer. The performance period will be project specific and will be specified with each scope of work. Review of material with the VA will take place approximately 14 days after submission.

7.2 Submission Materials and Schedules: Refer to Supplement B. Reproduction, mailing and delivery time is inclusive to the stated durations.

7.3 Government Review and Comment Resolution: The VA will review all submittals identified under this contract for functional and aesthetic relationship. VA review of the A/E’s work shall not be construed by either party to relieve the A/E from any requirements of this scope of work. The A/E will be responsible for taking minutes from submission review meetings and submitting them to the project engineer for concurrence within 7 days of the meeting. Both parties will discuss these comments, if necessary, and attempt to resolve any unsettled issues that may arise from the review.

7.4 The A/E may choose to perform work, at its own risk, during the Government review and comment resolution period, however, comments resulting from that review must be incorporated into the design prior to the next submittal. In the event a subsequent design phase is not authorized, the A-E shall incorporate all available review comments into the design to complete the current phase.

7.5Construction Execution:
Construction Documents to Bidders Date: TBD
Bid Opening Date: TBD
Actual Construction Contract Award: TBD
Anticipated Construction Duration: TBD
Construction Completion Date: TBD

8. AUTHORIZED CHANGES — The A/E shall only accept instructions and/or directions from the assigned VAMC Project Engineer and/or Contracting Officer. Changes in the project scope of work or cost must be authorized by the VA Contracting Officer only.

9. Timely Response - As time is of the essence, particularly during the construction phase, the A/E shall promptly review and approve, disapprove or take other appropriate action upon all the VA requests. The A/E shall submit recommendations on all shop drawings and other submittals and other requests within fifteen (15) calendar days after receipt.

E N D

SUPPLEMENT “A”

General Scope of Work (SOW):

Provide all professional architectural and engineering (A/E) services necessary to develop complete drawings, specifications, cost estimates, project phasing site visits and construction period administration associated with renovating and modernizing Specialty Care Clinic Space on the Second Floor East Wings of Building 1 at the Central Western Massachusetts Veterans Affairs Medical Center, within the constraints of the construction budget consistent with the Veterans Affairs (VA’s) project team goals as prioritized during project meetings and field surveys. Conduct preliminary project scope meetings and site survey investigations to develop the necessary elements for conceptual layout schemes with proposed alternatives consistent with the VA’s project team goals as prioritized during preliminary project meetings, field surveys and studies.

Task Order: #631-18-001 Extend Chill Water Through Buildings 1 & 60

Task Order Construction Budget: To be provided to successful Offeror

Deduct Alternates} Shall be part of the design requirements to be utilized in case of market condition variations in order to maximize the use of available Government funds. The VA shall select the proposed alternates from the A/E recommendations. Deduct Alternates shall not be used to bring the projected project costs within construction funding; these alternates are designed to assure a contract award and to have a project design and estimate at or below construction funding.

General Statement of Task} Provide services for the preparation of drawings, specifications, estimates, phasing schedules, and construction administration including all applicable engineering and design details for architectural, interior finishes, mechanical (plumbing, fire protection and HVAC), electrical, structural, asbestos and lead paint abatement, and other specialty consultant elements required consistent with the VA’s project team goals as prioritized during preliminary project meetings and field surveys.

General Description of Requirements} Design shall comply with the latest editions of all applicable DVA guidelines (e.g., Construction Standards, Master Specifications, Standard Details, Special Design Criteria), NFPA, TJC, Federal and State codes pertinent to the project scope within the constraints of the construction budget.

Services shall also include, but are not limited to the following:

1) On site visits to define the details of the project scope of work meeting the goals of the Veterans Affairs' (VA) project team, and presentation of preliminary layout plans with proposed alternatives.

2) Engage the services of all consultants in each discipline deemed to be necessary to fulfill the requirements of the project plan. Site investigations shall measure, and record the conditions of the area to be renovated and/or impacted by the project. Each discipline shall document and investigate the relevant existing conditions found, review the availability of existing building information, and field verify all essential elements pertinent to their trade.

3) Based on meetings and site field surveys, prepare a proposed detailed project scope description report within the limits of the project construction budget consistent with the VA goals.

4) Representation during all design review and field survey meetings. Architect/Engineer (A/E) shall document the results of each meeting and provide the conclusions to the Contracting Officer and VA Project Engineer within one (1) week following each meeting.

5) Based on meetings and investigations prepare preliminary, schematic, working, and construction documents with the necessary engineering and design details for all architectural, mechanical (plumbing, fire protection and HVAC), electrical, structural, civil, and other specialty consultants elements within the limits of the project goals established.

6) Electronic drawings shall be developed utilizing AutoCAD 2014. Electronic drawing files shall be identified with the drawing number and drawing title.

7) Specifications shall be developed utilizing MS Word 2010. Electronic Specification files shall be identified with the specification number and specification section title.

8) Cost Estimates shall be developed utilizing MS Excel 2010.

9) All computer-generated files shall be IBM compatible and furnished on high quality CD-R disks. Provide in accordance with Supplement “B” sets of drawings (AutoCAD) and specifications (MS Word) and cost estimates (MS Excel). The computerized version, format and media of the computer disks and files shall be specified and verified by the VA Project Engineer at the time each submission is due (XRF and ZIP files are not acceptable). Provide durable high quality plastic storage boxes at each submission for long term archiving of the disks by the VA.

10) 90% Design Submission: The 90% design submission shall be a complete 100% design. All plans, sections, details, etc. shall be complete at this time. The A/E shall ensure that the 90% design submittal is in fact his/her 100% product, and that it represents a total biddable package. An incomplete 90% design submittal may be rejected by the VA; a rejection will require the A/E to resubmit a 90% design at no additional cost.

11) VA Design Review Comments: The A/E shall submit written responses to the VA's oral and written design review comments. These written responses shall be within seven (7) calendar days of the VA's comments; and these responses shall explain the action the A/E will take for each comment.

12) Verification and preparation of as-built drawings which the VA shall retain.

13) The design consultant must have a PDF writer program to electronically sign material submittals; all Material Submittal Forms will be processed via electronic format with digital signature which utilizes a PDF Writer Program such as Adobe Reader/Writer.

14) Site visits (15 design and 9 construction) as required and/or requested by the VA Contracting Officer and Project Engineer for review and inspection of progress including final tests and inspections.

15) Documentation of all site visits shall be submitted in writing to the VA Contracting Officer and Project Engineer within one (1) week after each visit.

SUPPLEMENT “B”

A/E SUBMISSIONS

OF DESIGN REVIEW MATERIAL

FIRST REVIEW (15% Conceptual – Preliminary User Group Meetings & Field Surveys) 3 Set of AutoCAD and PDF conceptual/preliminary drawings in electronic format in accordance with Supplement “A” 1 Set of full size conceptual/preliminary layout plans/details - 30 inches by 42 inches 3 Sets of reduced size conceptual/preliminary layout plans 3 Sets of Preliminary Investigation Report with Recommendations 3 Set of Preliminary Investigation Report with Recommendations in PDF electronic format in accordance with Supplement “A” 3 Sets of conceptual/preliminary estimates 3 Set of MS Excel conceptual estimates in electronic format in accordance with Supplement “A”

SECOND REVIEW (35% Submittal – Schematics) 3 Sets of AutoCAD & PDF schematic drawings with phasing plans in electronic format in accordance with Supplement “A” 1 Set of full size bound schematic layout plans/details with phasing plans– 30 inches by 42 inches 3 Sets of reduced size bound schematic layout plans/details with phasing plans 3 Sets of design analysis 3 Set of design analysis in electronic format in accordance with Supplement "A" 3 Sets of spiral bound draft specifications with Mylar front and back cover sheets 3 Set of MS Word draft specifications in electronic format in accordance with Supplement “A” 3 Sets of schematic estimates with proposed alternate 3 Set of MS Excel schematic estimates with proposed alternate in electronic format per Supplement “A”

THIRD REVIEW (65% Submittal – “DD” Design Development) 3 Sets of AutoCAD & PDF design drawings in electronic format in accordance with Supplement “A” 1 Set of full size bound design development layout plans/details with phasing plans– 30 inches by 42 inches 3 Sets of reduced size bound design development layout plans/details with phasing plans 3 Sets of design analysis 3 Set of design analysis in electronic format in accordance with Supplement "A" 3 Sets of spiral bound design development specifications with Mylar front and back cover sheets 3 Set of MS Word design development specifications in accordance with Supplement “A” 3 Sets of design development estimates 3 Set of MS Excel design development estimates in electronic format in accordance with Supplement “A”

FOURTH REVIEW (90% Submittal – “CD” Construction Documents) 3 Sets of AutoCAD & PDF construction drawings in electronic format in accordance with Supplement “A” 1 Set of full size bound construction documents plans/details with phasing plans– 30 inches by 42 inches 3 Sets of reduced size bound construction documents plans/details with phasing plans 3 Sets of design analysis 3 Set of design analysis in electronic format per Supplement "A" 3 Sets of spiral bound construction documents specifications with Mylar front and back cover sheets 3 Sets of MS Word construction documents specifications in accordance with Supplement “A” 3 Set of MS Excel construction documents estimates in electronic format in accordance with Supplement “A” 3 Sets of construction documents estimates

FIFTH REVIEW (100% Submittal – Bid [Final] Documents) 3 Sets of AutoCAD & PDF bid drawings in accordance with Supplement “A” 1 Set of approved full size bid documents Mylar drawings with Registered Architect (RA) and Professional Engineer (PE) stamps - 30 inches by 42 inches 3 Sets of approved reduced size bound bid plans/details with RA and PE stamps 0 Sets of full size Mylar bid plans/details with RA and PE stamps rolled in individual mailing tubes 3 Sets of MS Word final specification sections in accordance with Supplement “A” 3 Sets of MS Word final specification sections merged in accordance with Supplement “A” 3 Sets of final specifications boxed on single sided sheets 3 Sets of 3-ring bound final specifications paginated front to back with Mylar front/back cover 3 Sets of final estimates 3 Set of MS Excel final estimates in electronic format in accordance with Supplement “A” 3 Sets of final phasing schedules

SIXTH REVIEW (Project Close Out Submittal – “As-Built” Construction Documents) 3 Sets of AutoCAD & PDF As-Built drawings in accordance with Supplement “A” 1 Set of approved full size As-Built Mylar drawings with RA and PE stamps 3 Sets of approved reduced size As-Built plans/details with RA and PE stamps

ID
Milestone Task Description
Duration
Schedule

Date Actual Date

1
User Group Preliminary Mtg (Review Scope, Site Survey Investigation)
1 Day
NTP + 1
2
Preliminary Investigation of Existing Conditions
As Needed
3
Submit Conceptual Layout Schemes with Proposed Alternates
---
4
User Group Mtg (Review Proposed Schemes)
1 Day
NTP + 14
5
Prepare 35% Schematic Design Submissions
---
6
Survey Existing Conditions, Coordinate Design with Consultants & VA Comments
As Needed
7
Submit 35% Schematic Design Package
---
8
VA Engineering 35% Review
7 Days (Min)
9
User Group 35% Schematic Design Review Meeting
1 Day
NTP + 60
10
Prepare 65% “DD” Design Development Submissions
---
Confirm Existing Conditions, Coordinate Design with Consultants & VA Comments
As Needed
11
Submit 65% “DD” Design Development Package
---
VA Engineering 65% Review
14 Days (Min)
12
User Group 65% “DD” Review Meeting
1 Day
NTP + 105
13
Prepare 90% “CD” Construction Document Submissions
---
Coordinate Design with Consultants, Existing Conditions & VA Comments
As Needed
14
Submit 90% “CD” Construction Documents Package
---
VA Engineering 90% Review
14 Days (Min)
15
User Group 90% “CD” Review Meeting
1 Day
NTP + 135
16
Prepare 100% Bid Final Documents
---
Finalize Coordination with Consultants, Existing Conditions & VA Comments
As Needed
17
Submit 100% Bid Final Documents with PE Stamps
---
NTP + 150

ATTACHMENT

SPECIFICATION

CLARIFICATION

AND

REQUIREMENTS

Ver. 8 1/10/2019

SPECIFICATION REQUIREMENTS & CLARIFICATIONS

1. Ensure project number and title are referenced correctly in the specifications and on the drawings. (Match to project application)

2. General Conditions, 00 72 00, are no longer used in Government projects and have been replaced with General Requirements, 01 00 00. Ensure Project Specifications do not reference General Conditions 00 72 00 and incorporate General Requirements, 01 00 00.

Keyword search: “General Conditions”, “00 72 00”

3. Reports: Many times Project Specifications refer to additional reports such as a Geotechnical Report or an Asbestos/Lead Report, but the Project Specifications have not necessarily included the report. Ensure the applicable reports are included and incorporated in the specifications.

Keyword search: “Report”

4. Guarantee Period Services: Guarantee Period Services are not permitted by Contracting requirements. Do not include this section for any Construction Project. Ensure the section is not included in the project specifications. Ensure Guarantee Period Services are not referenced or specified in any specification section.

Keyword search: “Guaran”, “Guarantee”, “Guarantee Period Services”, “GPS”

5. Emergency Service: Emergency Service as written into TIL spec 28 05 00, 28 26 00, and 28 31 00 are similar to Guarantee Period Services or Emergency Repair Services and are not permitted by Contracting requirements. Ensure Emergency Service (i.e. Emergency Repair Services) are not referenced or specified in any specification section.

Keyword search: “Emergency Service”

6. Warranty of Construction: The Warranty of Construction language shall be included in the General Requirement 01 00 00. If it is not included add the following paragraph at the end of section 1:

1.xx Warranty of Construction

A. All work shall be warranted for a period of one year, as specified under Warranty of Construction FAR clause 52.246-21, to be free of any defect in equipment, material, or design furnished, or workmanship performed by the Contractor or any subcontractor or supplier at any tier.

B. Contractor shall also, as specified under Warranty in FAR clause 52.246-21, obtain all warranties that would be given in normal commercial practice executed, in writing, for the benefit of the Government.

C. This contract shall be subject to all parts of FAR clause 52.246-21 and it’s Alternate I.

7. Retained by VA: Ensure the VA is not responsible for hiring or retaining Industrial Hygienist, commissioning agents, inspection and testing firms, etc. Commissioning services is part of the A/E scope of work. The Contractor shall be responsible for retaining the inspection and testing firm, and an Industrial Hygienist if needed.

Keyword search: “By VA”, “Retained by VA”, “By others”, “By owner”

8. Completion Time: Ensure the Completion Time for the entire project is included within the Statement of Work. If there are any Deduct Alternates or Alternates that impact the Completion Time, it shall be provided with the description of the deduct items in the specifications.

9. Deduct Alternates: Ensure Deduct Alternates are not included in any project other than a Minor Construction Project unless stipulated in the A/E SOW of non-Minor projects. Minor project guidance requires that deduct alternates equivalent to 10% of the authorized construction budget be included in the design. If a deduct alternate requires a substitution, ensure the substitution is included in the specifications and detailed and quantified with the plans.

10. Regular Hours: Ensure regular working hours are clearly defined within the Project Specifications. (to include Off hours work and Phasing)

11. A/E Firm Reference: Ensure the project specifications do not include the name of the A/E firm, including in the header and footer.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .