5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
VA
1 3
0001 3-8-2023
None
00101
Department of Veterans Affairs
Veterans Benefits Administration
Acquisition Division
1800 G. Street N.W.
Washington DC 20006
00101
Department of Veterans Affairs
Veterans Benefits Administration
Acquisition Division
1800 G. Street N.W.
Washington DC 20006
To all Offerors/Bidders
36C10E23R0010
02-22-2023
X
X X
X 1
The purpose of this Amendment is to incorporate the Request For Information (RFI) that were submitted .
Refer to the attached questions and answers with their associated attachments.
The proposal due date remains unchanged and are due no later than 12:00pm EST on March 22, 2023
Solicitation 36C10E23R0010
St. Petersburg Cooling Tower
Questions and Answers – March 7, 2023
1. During the site visit. It was mentioned that the VBA's wanted to take possession of the old parts ( Motor & Fan ), Is this correct?
Yes
2. If so, will the VBA have something available to load the fan & motor on to next to site? To avoid remobilization of the Crane.
Yes, we have flat rolling carts for the equipment
3. During the site visit. It was mentioned that this would be weekend work, the SOW has it
Monday - Sunday 0600 to 1800. Can this be done during regular business hours, Monday - Friday from 0700 to 1800 to keep the cost down?
Yes this can be accomplished as stated in SOW
4. In the SOW, it is not mentioned to balance the New Fan and Motor. It is always our recommendation to have everything laser balance, to avoid having a new motor go bad that has not being balance correctly on site. Does the VBA want to have everything laser balanced? Or installed without being balanced?
We prefer the fan to be balanced as part of the installation using whatever the industry standard would be to balance a cooling tower fan.
5. Are you replacing just the motor and re-using the shaft, fan and bearing?
we are replacing the Motor, shaft, bearings and fan with new OEM parts.
6. Please clarify the project scope. During the walk thru Monday, it was discussed that only the fan motor was to be replaced. The solicitation states remove and replace, motor, shaft and fan.
Replace the motor, shaft, bearings and fan with new OEM Parts
7. Please advise if a motor manufactured by the Evapco cooling tower vendor is acceptable, w/out Evapco name brand
It does not have to be an Evapco name brand motor : Replacement parts catalog states the following” Totally enclosed ball bearing type motors with 1.15 service factor specifically designed for evaporative cooling applications. All motors equipped with double sealed non-relubricable bearings, double dip and bake windings and cast iron frames with corro-duty paint
8. Is it possible to obtain the list of attendees for the recently held site visit for this project?
Yes see attached
9. The contract has a value of $25,000, but the cost of the parts alone exceeds $27,000.
Additionally, does the estimated cost of labor need to be considered in determining whether the contract price will be increased to cover the additional cost of both parts and labor? In other words, will the overall cost of the contract be adjusted to reflect the combined cost of parts and labor, which exceeds the original contract value of $25,000?
Thank you.
Please provide a cost breakdown to support your proposal. Your cost breakdown will include all costs that result in your overall proposal price.
10. Are there any type of drawings or specs you can provide?
See attached
11. Can you provide the Site Visit attendees?
See attached