About this file

36C10E18R0015 36C10E18R0015_1.docx

View the file

Other files

File Type Posted
36C10E18R0015-00002000.docx DOCX document
36C10E18R0015-00002001.doc DOC document
36C10E18R0015-00001001.pdf PDF
36C10E18R0015-00001000.docx DOCX document
36C10E18R0015-004.pdf PDF
36C10E18R0015-003.xlsx XLSX spreadsheet
36C10E18R0015-002.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT

NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE

DOCUMENTS (

Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV.

8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award notice to proceed. This performance period is mandatory negotiable (See _____________________________).

YES

NO

a Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ hour ) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that t ime. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b An offer guarantee is is not required.

c All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d Offers providing less than _______________________ calendar days for Government accepta nce after the date offers are due will not be considered and will be rejected.

36C10E18R0015 X 12-04-2017 3175-000096

VB3222

00101 Department of Veterans Affairs Veterans Benefits Administration Office of Acquisition 1800 G. Street N.W.

Washington DC 20006 Department of Veterans Affairs Veterans Benefits Administration E-mail Proposals to Heather Hampton, heather.hampton@va.gov

Heather Hampton 336-251-0500 Contractor shall provide all labor, material, equipment, transportation, and supervision for the construction of an office suite to be located on the 3rd floor, of the north wing, at teh St. Petersburg, FL VBA Regional Office.

The NAICS code for this procurement is 236220 and the size stand ard is $36.5 million.

Magnitude of Construction is b etween $100,000.00 and $250,000.00.

A site visit has been scheduled for Monday, December 11, 2017 @ 1:30 PM EST, at the St. Petersburg FL VBA RO, 9500 Bay Pines

Blvd., St. Petersburg, FL 33708; Room 204.

Please see Instructions to Offerors for additional details.

X X 52.211-10 X

NO

1:00 PM EST

01-08-2018 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT

WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract.

The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or pr int) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER

WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

See Schedule of Items for Pricing 00101 Department of Veterans Affairs Veterans Benefits Administration Office of Acquisition 1800 G. Street N.W.

Washington DC 20006 All invoices must be emailed to:

dennis.ecord@va.gov with a cc to Heather Hampton:

heather.hampton@va.gov

Heather Hampton

VA-VBA-2017-0E133C08

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.1 PRICE/COST SCHEDULE5
ITEM INFORMATION5
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS6
2.1 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)13
2.2 52.216-1 TYPE OF CONTRACT (APR 1984)14
2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)14
2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)14
2.5 52.233-2 SERVICE OF PROTEST (SEP 2006)15
2.6 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)16
2.7 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (JAN 2008)16
2.8 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (JAN 1998)17
2.9 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008)17
REPRESENTATIONS AND CERTIFICATIONS18
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2017)18
GENERAL CONDITIONS22
4.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)22
4.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)24
4.3 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JUL 2013)25
4.4 52.223-9 ESTIMATE OF PERCENTAGE OF RECOVERED MATERIAL CONTENT FOR EPA-DESIGNATED ITEMS (MAY 2008)26
4.5 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014)26
4.6 52.228-5 INSURANCE—WORK ON A GOVERNMENT INSTALLATION (JAN 1997)29
4.7 SUPPLEMENTAL INSURANCE REQUIREMENTS30
4.8 VAAR 852.203-70 COMMERCIAL ADVERTISING (JAN 2008)30
4.9 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2016)(DEVIATION)30
4.10 LIMITATIONS ON SUBCONTRACTING-- MONITORING AND COMPLIANCE (JUN 2011)31
4.11 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)32
4.12 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2012)32
4.13 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (JUL 2002)33
4.14 VAAR 852.236-74 INSPECTION OF CONSTRUCTION (JUL 2002)34
4.15 VAAR 852.236-76 CORRESPONDENCE (APR 1984)34
4.16 VAAR 852.236-77 REFERENCE TO "STANDARDS" (JUL 2002)34
4.17 VAAR 852.236-78 GOVERNMENT SUPERVISION (APR 1984)34
4.18 VAAR 852.236-79 DAILY REPORT OF WORKERS AND MATERIAL (APR 1984)34
4.19 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 1984)35
4.20 VAAR 852.236-82 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS) (APR 1984)35
4.21 VAAR 852.236-84 SCHEDULE OF WORK PROGRESS (NOV 1984)38
4.22 VAAR 852.236-85 SUPPLEMENTARY LABOR STANDARDS PROVISIONS (APR 1984)38
4.23 VAAR 852.236-86 WORKER'S COMPENSATION (JAN 2008)39
4.24 VAAR 852.236-87 ACCIDENT PREVENTION (SEP 1993)39
4.25 VAAR 852.236-88 CONTRACT CHANGES--SUPPLEMENT (JUL 2002)39
4.26 VAAR 852.236-89 BUY AMERICAN ACT (JAN 2008)41
4.27 VAAR 852.236-91 SPECIAL NOTES (JUL 2002)42
4.28 VAAR 852.246-74 SPECIAL WARRANTIES (JAN 2008)42
LIST OF ATTACHMENTS43

A.1 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM NUMBER
DESCRIPTION OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
0001
Contractor will provide all materials, labor, tools, equipment, transportation, qualified supervision, etc. necessary to construct an office suite on the 3rd floor, North Wing of the St Petersburg FL VA Regional Office. All work to be accomplished in strict accordance with the Statement of Work, and all other terms and conditions of the contract.
1.00
JB

GRAND TOTAL

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

INFORMATION FOR OFFERORS:

DESCRIPTION OF WORK: Contractor will provide all materials, labor, tools, equipment, transportation, qualified supervision, etc. necessary to construct an office suite on the 3d floor, North Wing of the St Petersburg FL VA Regional Office.

MAGNITUDE OF CONSTRUCTION: Between $100,000.00 and $250,000.00.

COMPLETION TIME: All work shall be completed within Ninety (90) calendar days from receipt of the Notice to Proceed.

PRE-PROPOSAL CONFERENCE: A pre-proposal conference has been scheduled for Monday, December 11, 2017, at 1:30 p.m., at the St. Petersburg FL VBA Regional Office, 9500 Bay Pines Blvd., St. Petersburg, FL 33708, Room 204.

A list of anticipated attendees must be emailed to heather.hampton@va.gov prior to the site visit. The list must contain attendees name, represented business, and contact information.

This will be the only opportunity for potential bidders to visit the site.

ALL POTENTIAL OFFERORS, SUBCONTRACTORS, AND SUPPLIERS ARE STRONGLY ENCOURAGED TO ATTEND THIS PRE-PROPOSAL CONFERENCE.

NOTE: QUESTIONS REGARDING THIS SOLICITATION MUST BE SUBMITTED VIA E-MAIL TO HEATHER.HAMPTON@VA.GOV ; NO TELEPHONE QUESTIONS WILL BE ACCEPTED. CUT OFF FOR QUESTIONS IS 1:00PM (EST), DECEMBER 18, 2017. The Government is not obligated to answer any questions submitted after the cut off, and late submission may result in the questions going unanswered.

PROPOSAL DUE DATE/TIME: Proposals are due electronically to heather.hampton@va.gov, by the date and time specified in block 13.a. of the SF1442.

SDVOSB SET-ASIDE AND REQUIRED REGISTRATION AT VETBIZ: This procurement is 100% set-aside for Service-Disabled, Veteran-Owned Small Business (SDVOSB). Offers are solicited only from SDVOSB concerns and offers received from concerns that are not SDVOSB concerns shall not be considered. See VAAR Clause 852.219-10. All SDVOSB must be certified by the Center for Veterans Enterprise (CVE) at www.vetbiz.gov, upon submission of proposals and at the time of award, to be eligible to participate.

BONDS: IAW FAR 52.228-15, unless the resulting contract price is $150,000 or less, the successful offeror shall furnish performance and payment bonds to the Contracting Officer as follows:

(1) Performance Bonds (Standard Form 25). The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.

(2) Payment Bonds (Standard Form 25-A). The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.

GENDER: Wherever masculine gender is used in the solicitation and contract documents, it shall be considered to include both masculine and feminine.

METRIC PRODUCTS: Products manufactured to metric dimensions will be considered on an equal basis with those manufactured using inch-pound units, providing they fall within the tolerances specified using conversion tables and contained in the latest revision of Federal Standard No. 376, and all other requirements of this document are met.

If a product is manufactured to metric dimensions and those dimensions exceed the tolerances specified in inch-pound units, a request should be made to the Contracting Officer, in writing, to determine if the product is acceptable. The Contracting Officer, in concert with the Contracting Officer’s Representative (COR), will accept or reject the product.

CONTRACTOR RESPONSIBILITY: Contractor shall be required to complete all contract work and schedule a final inspection within the specified contract performance period. Should the Contractor fail to complete the contract work (including scheduling of the final inspection), and it is determined by the Government to be a Contractor-caused delay, the Contractor shall be in default status. If the Government determines it to be in the best interest of the Government to allow the Contractor to continue to perform contract work, the Contractor shall provide equitable consideration to the Government for additional time granted for completion of contract work. Such agreement shall not be deemed a waiver of the Government’s right to terminate this contract in the event the Contractor fails to complete the contract work (including scheduling of the final inspection) on or before the completion date.

TRAINING: Effective July 1, 2005, all employees of the general contractor and subcontractors shall have the 10-hour OSHA certified construction safety course and/or other relevant competency training, as determined by the COR. The General Contractor’s competent person shall have completed the 30-hour OSHA certified construction safety course. Documentation of training shall be submitted to the Contracting Officer for review and approval prior to any work being performed. There shall be no exceptions to this requirement.

PREPARATION OF BIDS/OFFERS/PROPOSALS: Neither the VBA nor the VBA Southeast Acquisition Team will pay for any costs incurred in preparation and submission of bids or proposals.

PRIVACY AND CONFIDENTIALITY: Contractors to the Department of Veteran Affairs may be unintentionally exposed to sensitive information. Information may be overheard, seen on documents or electronic devices, or observed that could potentially violate the privacy and confidentiality of our veterans, employees, volunteers, and their families. Regulations such as, but not limited to the Health Insurance Portability and Accountability Act of 1996 (HIPAA), Freedom of Information Act (FOIA) and Privacy Act of 1974 have been enacted to protect sensitive information from being improperly disclosed. Information should not be divulged or released to anyone unless specifically authorized by this contract or its’ attached documents in accordance with the contracted services. Failure to comply with applicable statutes and regulation can result in the termination of this contract and civil and criminal penalties, including fines and imprisonment. All suspected or actual breeches of privacy and confidentiality should be reported immediately to the Contracting Officer, Contracting Officer’s Representative (COR) or the Facility Privacy Officer.

VETS 4212: As legislatively mandated under 38 U.S. Code, Section 4212, codified at 41 CFR Section 61-300, respectively, contractors and subcontractors who enter into, or modify a contract or subcontract with the federal government, and whose contract meets the criteria set forth in the above legislation/regulations, are required to report annually on their affirmative action efforts in employing veterans. Submission of the VETS 4212 reporting information can be done electronically at: https://vets4212.dol.gov/vets4212. Award cannot be made unless the awardee has filed their VETS 4212 report. Therefore, all offerors are encouraged to file every year.

SYSTEM FOR AWARD MANAGEMENT (SAM): Federal Acquisition Regulations require that federal contractors register in the System for Award Management (SAM) database at http://www.sam.gov and enter all mandatory information into the system. Award cannot be made until the contractor has registered. Offerors are encouraged to ensure that they are registered in SAM prior to submitting their offer.

CENTER FOR VETERANS ENTERPRISE: To be eligible to participate, contractor must be registered AND certified as an SDVOSB firm in the Center for Veterans Enterprise database (VetBiz).

CONTRACTOR NORMAL WORK HOURS: The contractor work hours are from 6:00 pm to 6:00 am, Monday through Friday, excluding federal holidays. The contractor may work on Saturday and/or Sunday's with prior coordination with the Contracting Officer Representative (COR). Federal holidays that fall on a non-work day –Saturday or Sunday-the holiday usually is observed on the Monday if holiday in on Sunday or on Friday if holiday is on Saturday. If the contractor desires to work an alternate schedule or on holidays a written request must be furnished to the COR. All federal holidays are observed as non work days. Federal holidays can be found on the following web site: https://www.opm.gov/policy-data-oversight/snow-dismissal-procedures/federal-holidays/#url=2017. These days will be identified during preconstruction.

PROPOSAL REQUIREMENTS AND EVALUATION CRITERIA:

This is a best value source selection conducted in accordance with Federal Acquisition Regulation (FAR) 15.3, Source Selection. Award will be made to a single Offeror who is deemed responsible in accordance with the Federal Acquisition Regulation (FAR), whose proposal conforms to the solicitation requirements, and whose proposal, judged by an overall assessment of the evaluation criteria, represents the Lowest Priced Technically Acceptable offer. In order to be determined technically acceptable, the Offeror must receive an adjectival rating of Acceptable for all non-priced factors. Evaluation factors that establish the requirements of technical acceptability are set forth below. Trade-offs between price and non-price factors are not permitted. Price will not be evaluated for any offeror who was found to be technically unacceptable. Unreasonably high, unbalanced, inaccurate or incomplete price proposals may be the grounds for eliminating a proposal from competition. The Government will evaluate proposed prices for reasonableness in accordance with FAR 15.404-1 (Proposal analysis techniques). Past performance shall be evaluated in accordance with FAR 15.305.

The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror's initial proposal should contain the offeror's best terms from a price and technical approach. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. The Government reserves the right to waive informalities and minor irregularities in offers received. If a minor clerical error has occurred, then the offeror may be given an opportunity to correct the minor error within the constraints of the "clarifications" process.

A. Technical Requirement – The technical approach, schedule, and key personnel standard will each receive one of the adjectival ratings defined below. The technical acceptability standard ratings will be used to determine an overall rating for the technical factor.

Project Approach Ratings Acceptable/Unacceptable Ratings

Rating
Description
Acceptable
Proposal clearly meets the minimum requirements of the solicitation.
Unacceptable
Proposal does not clearly meet the minimum requirements of the solicitation.

The Technical Proposal shall consist of the following:

1. Technical approach - Using the information submitted in response to the solicitation, the Government will evaluate the offeror’s ability to successfully perform the requirements of the project. To be evaluated as acceptable the offeror must provide a narrative that addresses their proposed approach for completion of the project, to include functions, responsibilities, authorities, and duties of proposed technical staff to determine if offeror has the ability to manage and perform the project without significant difficulty. Offeror should focus on methodology or approach taken to satisfy the requirements of the project.

2. Schedule - Ability to adhere to construction schedule for completion within 90 calendar days from Notice to Proceed as specified in the solicitation. Using the information submitted in response to the solicitation, the Government will evaluate the offerors’ scheduling methodology to determine if they have scheduling processes that ensure completion and control of the project from beginning to end. To be evaluated as acceptable the offeror must provide a sample schedule for this project that demonstrates an understanding of the limitations of the schedule as well as an understanding that an appropriate schedule will result in successful completion of the project for this evaluation factor. Offeror should annotate on the schedule key events and milestones like inspections and required reports due. The preferred but not mandatory schedule would be submitted in MS Project with earliest start/finish and latest start/finish dates annotated.

3. Key Personnel - Using the information submitted in response to the solicitation, the Government will evaluate the offerors’ proposed key personnel to determine if they have the technical expertise necessary to ensure completion of the project. To be evaluated as acceptable the offeror must provide a brief resume of the proposed key personnel for this project: Information at a minimum to include education, training, certification and licensing and any other related experience.

B. Past Performance Requirement – Past performance will be rated on an “acceptable” or “unacceptable” basis using the ratings in the below table.

Past Performance Relevancy Ratings

Rating
Description
Acceptable
Based on the offeror’s performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort, or the offeror’s performance record is unknown.
Unacceptable
Based on the offeror’s performance record, the Government has no reasonable expectation that the offeror will be able to successfully perform the required effort

The Offeror shall submit past performance information that is both recent (within the past three (3) years) and relevant (similar in size, scope, and complexity to the requirement being procured), if applicable.

Recent and relevant past performance shall be discussed for the prime contractor and/or any ‘team members” or “teaming partners” proposed to support this contract. The Offeror is provided an opportunity to submit a list of no more than three (3) of the Offeror’s most recent and relevant past performance information on projects: similar in size, scope, and complexity to the requirement being procured under this solicitation, performed for Government agencies and/or commercial customers within the last three (3) years from the solicitation release date.

The past performance submittals shall include (when applicable):

· Contract Number

· Contracting Officers (CO): Name, Phone number and Email address

· Contracting Officers Representatives (COR): Name, Phone number and Email address

· Non-Government Points of Contact (if applicable)

· Total Contract Value at time of award and final price after any/all modifications

· Initial Period of performance (POP) and final POP after any/all modifications

· Narrative describing the requirement and reason for any modifications which effected price or performance period.

The Government reserves the right to obtain past performance data from other sources than those identified by the Offeror in evaluating past performance. This includes, but not limited to, the Past Performance Information Retrieval System (PPIRS), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), or other databases; interviews with Program Managers, Contracting Officers, and the Defense Contract Management Agency. Offerors are reminded that both independent data and data provided by Offerors in their proposals may be used by the Government to evaluate the Offerors past performance. The Contracting Officer may also evaluate past performance based on direct knowledge of the Contractor’s performance on current or recent contracts. However, the burden of providing thorough, complete, and current past performance information as requested in this paragraph remains with the Offerors. All past performance received will be taken into account and could affect the overall rating. The overall past performance evaluation is a subjective decision based on the whole of all data received. In the case of an Offeror without a record of relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the Offeror may not be evaluated favorably or unfavorably on past performance (see FAR 15.305 (a)(2)(iv)). Therefore, the offeror shall be determined to have unknown past performance. In the context of acceptability/unacceptability, “unknown” shall be considered “acceptable.”

To be evaluated as acceptable the offeror must show that there is a reasonable expectation that they can successfully perform the required effort.

C. Price Proposal - Price will not be scored or rated. The techniques and procedures described under FAR Part 15.404-1 will be the primary means of assessing price to determine the proposed price to be reasonable and complete. Through these techniques, the Government will determine whether an Acceptable Offeror’s overall price is reasonable in accordance with FAR 15.404. Unbalanced Pricing may be evaluated in accordance with FAR 15.404-1(g), as applicable, to assess potential performance risk which could result in unreasonably high prices.

Definitions:

· Completeness/Accuracy: The Offeror’s proposal is in compliance with the Price Volume instructions in the RFP.

· Reasonableness: A price is reasonable if, in its nature and amount, it does not exceed that which would be incurred by a prudent person in the conduct of competitive business.

· Unbalanced: Unbalanced pricing exists when, despite an acceptable total evaluated Price, the price of one or more contract line items is significantly over or understated as indicated by the application of price analysis techniques.

The Price Proposal shall consist of the following:

0. Standard Form 1442- completed in its entirety to include the “Offeror” portion of the form. In accordance with FAR 4.102, an official having the authority to contractually bind your company must sign the SF 1442.

0. PRICE BREAKDOWN WORKSHEET - All Offerors must submit the Attached Price Breakdown Worksheet (or something similar) with their signed offer. Offerors shall provide a complete price breakdown in sufficient detail to permit a complete analysis of labor burden, materials, equipment, transportation, supervision, disposal costs and overhead and profit and shall cover all work involved in the contract.

PROPOSAL FORMAT

A. To assure timely and equitable evaluation of proposals, offerors must follow the instructions contained herein.

(1) Offerors are required to meet all solicitation requirements, including terms and conditions, representations and certifications, and technical requirements. Failure to meet a requirement may result in an offer being ineligible for award. Offerors must clearly identify any exception to the solicitation terms and conditions and provide complete accompanying rationale.

(2) Each volume of the proposal should be separately marked and labeled with the appropriate volume, i.e., Volume I, Volume II, Volume III, and Volume IV. A cover sheet should accompany each volume marked with the following: Volume number, title, solicitation number and the offeror's name. Printing shall be easily readable (12 point font, Times New Roman).

(3) The files are to be unlocked, while the file names shall be labeled “Company Name – Volume X – Document Title” for the first submission with X indicating the Volume number. File name of later submissions (if necessary), shall be “Company Name –Volume X – Revision X –Document Title’ with X indicating the number of the revision and Volume number.

(4) All electronic copies shall be submitted by email to the Contracting Officer at heather.hampton@va.gov . Once received, an e-mail will be sent to validate receipt of the proposal. If you do not receive an e-mail acknowledging the receipt of your proposal within one business day; please contact the Contracting Officer at heather.hampton@va.gov or 336-251-0950.

PROPOSAL CONTENT

General – All volumes shall be clear, concise, and include sufficient detail for effective evaluation and for substantiating the validity of stated claims. Legibility, clarity and coherence are very important. The proposal should not simply rephrase or restate the Government's requirements, but rather shall provide convincing rationale to address how the offeror intends to meet these requirements. Statements that the offeror understands, can, or will comply with the requirements as outlined in the specification and drawings (including referenced publications, technical data, etc.); and phrases such as “standard procedures will be employed” or “well known techniques will be used“, etc., will be deemed unacceptable. Offerors shall assume that the Government has no prior knowledge of their facilities and experience, and will base its evaluation on the information presented in the offeror's proposal. Elaborate brochures or documentation, binding, detailed art work, or other embellishments are unnecessary and are not desired.

A. Volume I – RFP Documents and General Information.

Documents shall contain the signed copy of all documents requiring signature of the offeror. This includes any/all amendments to this solicitation. Each offeror shall complete (fill-ins and signatures) and submit as stated below. An authorized official of the firm shall sign the offer and all certifications requiring signature. All proposals shall be valid for 120 calendar days.

B. Volume II – Technical Proposal to include:

Factor #1: Technical Approach - narrative that addresses proposed approach for completion of the project, to include functions, responsibilities, authorities, and duties of proposed technical staff to determine if offeror has the ability to manage and perform the project without significant difficulty.

Factor #2: Schedule - sample schedule for this project that demonstrates an understanding of the limitations of the schedule as well as an understanding that an appropriate schedule will result in successful completion of the project for this evaluation factor.

Factor #3: Key Personnel - brief resume of the proposed key personnel for this project: Information at a minimum to include education, training, certification, licensing, and any other related experience.

C. Volume III – Past Performance - past performance information on three (3) projects completed within the last three (3) years which are of similar size, scope, and complexity to the projects outlined in the solicitation.

D. Volume IV – Price: Price Breakdown Worksheet (or something similar) - provide a complete price breakdown in sufficient detail to permit a complete analysis of labor burden, materials, equipment, transportation, supervision, disposal costs and overhead and profit and shall cover all work involved in the contract.

BASIS FOR AWARD

This is a best value source selection conducted in accordance with Federal Acquisition Regulation (FAR) 15.3, Source Selection. Award will be made to a single Offeror who is deemed responsible in accordance with the Federal Acquisition Regulation (FAR), whose proposal conforms to the solicitation requirements, and whose proposal, judged by an overall assessment of the evaluation criteria, represents the Lowest Priced Technically Acceptable offer.

2.1 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/

(End of Provision)

FAR Number
Title
Date
52.204-7
SYSTEM FOR AWARD MANAGEMENT
OCT 2016
52.204-16
COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING
JUL 2016
52.204-22
ALTERNATIVE LINE ITEM PROPOSAL
JAN 2017
52.215-1
INSTRUCTIONS TO OFFERORS—COMPETITIVE ACQUISITION
JAN 2017
52.222-23
NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION
FEB 1999
52.222-60
PAYCHECK TRANSPARENCY (EXECUTIVE ORDER 13673)
OCT 2016
52.223-1
BIOBASED PRODUCT CERTIFICATION
MAY 2012
52.223-4
RECOVERED MATERIAL CERTIFICATION
MAY 2008
52.236-28
PREPARATION OF PROPOSALS—CONSTRUCTION
OCT 1997

2.2 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

(End of Provision)

2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

2.5 52.233-2 SERVICE OF PROTEST (SEP 2006)

Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from: Heather Hampton

Hand-Carried Address:

Department of Veterans Affairs Veterans Benefits Administration Office of Acquisitions 1800 G. Street N.W.

Washington DC 20006

Mailing Address:

Department of Veterans Affairs Veterans Benefits Administration Office of Acquisitions 1800 G. Street N.W.

Washington DC 20006

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of Provision)

2.6 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for— Monday, December 11, 2017 at 1:30 PM EST

(c) Participants will meet at— VBA Regional Office, 9500 Bay Pines Blvd., St. Petersburg, FL, Room 204 (End of Provision)

2.7 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (JAN 2008)

(a) Any protest filed by an interested party shall:

(1) Include the name, address, fax number, and telephone number of the protester;

(2) Identify the solicitation and/or contract number;

(3) Include an original signed by the protester or the protester's representative and at least one copy;

(4) Set forth a detailed statement of the legal and factual grounds of the protest, including a description of resulting prejudice to the protester, and provide copies of relevant documents;

(5) Specifically request a ruling of the individual upon whom the protest is served;

(6) State the form of relief requested; and

(7) Provide all information establishing the timeliness of the protest.

(b) Failure to comply with the above may result in dismissal of the protest without further consideration.

(c) Bidders/offerors and contracting officers are encouraged to use alternative dispute resolution (ADR) procedures to resolve protests at any stage in the protest process. If ADR is used, the Department of Veterans Affairs will not furnish any documentation in an ADR proceeding beyond what is allowed by the Federal Acquisition Regulation.

(End of Provision)

2.8 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (JAN 1998)

As an alternative to filing a protest with the contracting officer, an interested party may file a protest with the Deputy Assistant Secretary for Acquisition and Materiel Management, Acquisition Administration Team, Department of Veterans Affairs, 810 Vermont Avenue, NW., Washington, DC 20420, or for solicitations issued by the Office of Construction and Facilities Management, the Director, Office of Construction and Facilities Management, 810 Vermont Avenue, NW., Washington, DC 20420. The protest will not be considered if the interested party has a protest on the same or similar issues pending with the contracting officer.

PLEASE NOTE: The correct mailing information for filing alternate protests is as follows:

Deputy Assistant Secretary for Acquisition and Logistics,
Risk Management Team, Department of Veterans Affairs
810 Vermont Avenue, N.W.
Washington, DC 20420

Or for solicitations issued by the Office of Construction and Facilities Management:

Director, Office of Construction and Facilities Management
811 Vermont Avenue, N.W.
Washington, DC 20420

(End of Provision)

2.9 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008)

The contracting officer reserves the right to designate representatives to act for him/her in furnishing technical guidance and advice or generally monitor the work to be performed under this contract. Such designation will be in writing and will define the scope and limitation of the designee's authority. A copy of the designation shall be furnished to the contractor.

(End of Provision)

REPRESENTATIONS AND CERTIFICATIONS

3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2017)

(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 236220.

(2) The small business size standard is $36.5 Million.

(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.

(2) If the provision at 52.204-7 is not included in this solicitation, and the offeror is currently registered in the System for Award Management (SAM), and has completed the Representations and Certifications section of SAM electronically, the offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The offeror shall indicate which option applies by checking one of the following boxes:

[ ] (i) Paragraph (d) applies.

[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:

(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—

(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;

(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or

(C) The solicitation is for utility services for which rates are set by law or regulation.

(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.

(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements—Representation. This provision applies to all solicitations.

(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.

(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—

(A) Are not set aside for small business concerns;

(B) Exceed the simplified acquisition threshold; and

(C) Are for contracts that will be performed in the United States or its outlying areas.

(vi) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations—Representation.

(vii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.

(viii) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.

(ix) 52.214-14, Place of Performance—Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.

(x) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.

(xi) 52.219-1, Small Business Program Representations (Basic & Alternate I). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.

(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.

(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.

(xii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.

(xiii) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.

(xiv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.

(xv) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.

(xvi) 52.222-57, Representation Regarding Compliance with Labor Laws (Executive Order 13673). This provision applies to solicitations expected to exceed $50 million which are issued from October 25, 2016 through April 24, 2017, and solicitations expected to exceed $500,000, which are issued after April 24, 2017.

Note to paragraph (c)(1)(xvi): By a court order issued on October 24, 2016, 52.222-57 is enjoined indefinitely as of the date of the order. The enjoined paragraph will become effective immediately if the court terminates the injunction. At that time, DoD, GSA, and NASA will publish a document in the Federal Register advising the public of the termination of the injunction.

(xvii) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA-designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.

(xviii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA-designated items.

(xix) 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals--Representation. This provision applies to solicitations that include the clause at 52.204-7.)

(xx) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.

(xxi) 52.225-4, Buy American—Free Trade Agreements—Israeli Trade Act Certificate. (Basic, Alternates I, II, and III.) This provision applies to solicitations containing the clause at 52.225-3.

(A) If the acquisition value is less than $25,000, the basic provision applies.

(B) If the acquisition value is $25,000 or more but is less than $50,000, the provision with its Alternate I applies.

(C) If the acquisition value is $50,000 or more but is less than $77,533, the provision with its Alternate II applies.

(D) If the acquisition value is $77,533 or more but is less than $100,000, the provision with its Alternate III applies.

(xxii) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225-5.

(xxiii) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan—Certification. This provision applies to all solicitations.

(xxiv) 52.225-25, Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran—Representation and Certifications. This provision applies to all solicitations.

(xxv) 52.226-2, Historically Black College or University and Minority Institution Representation. This provision applies to solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions.

(A) Solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions; and

(B) For DoD, NASA, and Coast Guard acquisitions, solicitations that contain the clause at 52.219-23, Notice of Price Evaluation Adjustment for Small Disadvantaged Business Concerns.

(2) The following representations or certifications are applicable as indicated by the Contracting Officer:

[X](i) 52.204-17, Ownership or Control of Offeror.

[X](ii) 52.204-20, Predecessor of Offeror.

[](iii) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.

[](iv) 52.222-48, Exemption from…