This is a Performance Work Statement (PWS) for Health Services Portfolio Technical Management and Strategic Solutioning Support (HTMS) under VA contract VA-27-0007804, issued by the Department of Veterans Affairs Office of Information & Technology Product Delivery Service. The contractor shall provide IT program management, technical management, and strategic solutioning support across the Health Services Portfolio at portfolio, product line, and product levels. Key service areas include project management, portfolio and product technical management, engineering and technical support, human-centered design, and innovation stakeholder engagement. The statement of work encompasses support for eleven product lines including Clinical Imaging, Clinical Services, Community Care, Discovery/Education/Affiliate Networks, Healthcare Environment and Logistics Management, Health Informatics, Patient Care Services, Scheduling and Telehealth, VHA Finance, VHA Front Office, and Electronic Health Record Modernization.

The performance period is 12 months from award with three optional 12-month extensions and one optional task, for a maximum 63-month duration. Work shall be performed at contractor facilities or remotely during core business hours (8 a.m. to 5 p.m. EST), with an estimated 75 trips to various locations including Washington DC, Austin TX, Eatontown NJ, Tampa FL, Denver CO, and New Orleans LA. The effort is priced on a firm-fixed-price basis with cost-reimbursable covering travel only. Deliverables include a Contractor Project Management Plan, bi-weekly progress and work plan reports, organizational strategic analysis and action plan, weekly intake and budget execution reports, risk management documentation, configuration and change management plans, communications plan updates, training plan, and various technical specifications and design documents. The contractor must comply with extensive VA, federal, and cybersecurity requirements including HIPAA, FISMA, zero trust architecture, Federal Identity and Credential Access Management, and generative AI governance standards.

View the file

Other files

File Type Posted
36C10B27Q0135.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Health Services Portfolio Technical Management and Strategic Solutioning Support, VA-27-0007804

PERFORMANCE WORK STATEMENT (PWS)

DEPARTMENT OF VETERANS AFFAIRS

Office of Information & Technology (OIT) Product Delivery Service

Health Services Portfolio Technical Management and Strategic Solutioning Support (HTMS)

Date: November 23, 2026

VA-27-0007804

PWS Version Number: 1.1

Contents

1.0BACKGROUND5
1.1VISION-DRIVEN EXECUTION5
1.2HSP PRODUCT LINES6
2.0APPLICABLE DOCUMENTS7
3.0SCOPE OF WORK11
3.1ORDER TYPE11
4.0PERFORMANCE DETAILS12
4.1PERFORMANCE PERIOD12
4.2PLACE OF PERFORMANCE12
4.3TRAVEL12
5.0SPECIFIC TASKS AND DELIVERABLES13
5.1PROJECT MANAGEMENT13
5.1.1CONTRACTOR PROJECT MANAGEMENT PLAN13
5.1.2REPORTING REQUIREMENTS14
5.1.3WORK PLAN15
5.1.4PRIVACY & HIPAA TRAINING16
5.1.5TOOLS TRAINING17
5.1.6TECHNICAL KICKOFF MEETING17
5.1.7CONTRACTOR RESOURCE INTAKE MANAGEMENT17
5.1.8ON-BOARDING SUPPORT18
5.1.9OFF-BOARDING SUPPORT19
5.1.10PROCESS IMPROVEMENT19
5.2HEALTH SERVICES PORTFOLIO AND PRODUCT TECHNICAL MANAGEMENT AND SUPPORT20
5.2.1TRAVEL ADMINISTRATION20
5.2.2PORTFOLIO REQUIREMENT AND PRODUCT INTAKE21
5.2.3STRATEGIC PLANNING AND ANALYSIS21
5.2.4MEETING MANAGEMENT22
5.2.5CAPITAL PLANNING AND INVESTMENT CONTROL (CPIC)23
5.2.6FINANCIAL INFORMATION INTEGRATOR REPORTING25
5.2.7ACQUISITION SUPPORT25
5.2.8DOCUMENT AND DATA MANAGEMENT26
5.2.8.1DOCUMENT AND DATA DEVELOPMENT26
5.2.8.2DOCUMENT AND DATA QUALITY27
5.2.8.3DOCUMENT AND DATA REPOSITORIES28
5.2.8.4DOCUMENT AND REPOSITORY REVIEWS29
5.2.8.5PROJECT DELIVERABLE TRACKING AND REVIEW MANAGEMENT29
5.2.9SPM CHANGE MANAGEMENT29
5.2.9.1ORGANIZATIONAL CHANGE MANAGEMENT (OCM)30
5.2.9.2PROGRAM CHANGE MANAGEMENT30
5.2.9.3CONFIGURATION MANAGEMENT31
5.2.9.4COMMUNICATION MANAGEMENT32
5.2.9.5COMMUNICATIONS PLAN32
5.2.9.6DATA CALL MANAGEMENT33
5.2.9.7ACTION ITEM MANAGEMENT34
5.2.9.8RISK MANAGEMENT PLANNING, TRACKING AND ANALYSIS34
5.2.9.9VIP SUPPORT35
5.2.9.10TRAINING SUPPORT36
5.3ENGINEERING AND TECHNICAL SUPPORT36
5.3.1AGILE REQUIREMENTS ELABORATION37
5.3.2REQUIREMENTS ANALYSIS AND MANAGEMENT39
5.3.3ARCHITECTURE AND DESIGN SUPPORT41
5.3.3.1 Portfolio Artificial Intelligence43
5.3.3.2 AI‑Enabled DevSecOpsLifecycle Support43
5.3.3.3 AI Workforce and Change Management Support43
5.3.3.4 AI Governance Support44
5.3.3.5 AI Security, Privacy, and Compliance Management44
5.3.4 SECURITY MANAGEMENT45
5.3.7 RELEASE MANAGEMENT SUPPORT47
5.3.8 SYSTEMS ADMINISTRATION SUPPORT50
5.3.9 TECHNICAL WRITING50
5.4 HUMAN CENTERED DESIGN (HCD) TECHNICAL SUPPORT (FIRM FIXED PRICE – QUARTERLY OPTIONAL TASK)50
5.4.1 DISCOVER - RESEARCH, INSIGHTS, AND SYNTHESIS50
5.4.2 DESIGN – CONDUCT COLLABORATIVE DESIGN ACTIVITIES AND MANAGE/CREATE DESIGN SOLUTIONS51
5.4.3 DETAILED DESIGN52
5.5 INNOVATION STAKEHOLDER ENGAGEMENT52
5.5.1 VOICE OF THE CUSTOMER52
5.5.2 BUSINESS PROCESS REENGINEERING/TRANSFORMATION53
5.5.3 EMERGING BUSINESS PRACTICES – TECHNOLOGY SUPPORT53
5.6 OPTION PERIOD ONE53
5.7 OPTION PERIOD TWO54
5.8 OPTION PERIOD THREE54
5.9 OPTION PERIOD FOUR54
5.10 TRANSITION AND ORIENTATION SUPPORT (OPTIONAL TASK) (FFP)54
6.0GENERAL REQUIREMENTS55
6.1ENTERPRISE AND IT FRAMEWORK55
6.1.1VA TECHNICAL REFERENCE MODEL55
6.1.2ZERO TRUST – VA CRITICAL SECURITY CONTROLS55
6.1.3FEDERAL IDENTITY, CREDENTIAL, AND ACCESS MANAGEMENT (FICAM)56
6.1.4INTERNET PROTOCOL VERSION 6 (IPv6)57
6.1.5TRUSTED INTERNET CONNECTION (TIC)58
6.1.6STANDARD COMPUTER CONFIGURATION58
6.1.7VETERAN FOCUSED INTEGRATION PROCESS (VIP) AND PRODUCT LINE MANAGEMENT (PLM)58
6.1.8PROCESS ASSET LIBRARY (PAL)59
6.1.9AUTHORITATIVE DATA SOURCES59
6.1.10ENTERPRISE SOCIAL SECURITY NUMBER (ESSN) REDUCTION60
6.1.11SOFTWARE AND LICENSING REQUIREMENTS61
6.1.12GENERATIVE ARTIFICIAL INTELLIGENCE REQUIREMENTS61
6.1.12.1AI SYSTEM/LLM DEVELOPMENT AND OPERATION DOCUMENTATION REQUIREMENTS63
6.1.12.2MONITORING, REPORTING, AND CORRECTIVE ACTION64
6.1.12.3AI MODEL UPDATES AND CHANGE DISCLOSURES65
6.1.13POSITION/TASK RISK DESIGNATION LEVEL(S)65
6.1.14CONTRACTOR PERSONNEL SECURITY REQUIREMENTS66
6.2METHOD AND DISTRIBUTION OF DELIVERABLES68
6.3PERFORMANCE METRICS68
6.4FACILITY/RESOURCE PROVISIONS69
6.5GOVERNMENT FURNISHED PROPERTYi71
ADDENDUM A – ADDITIONAL VA REQUIREMENTS, CONSOLIDATED72
ADDENDUM B – VA CYBERSECURITY AND PRIVACY LANGUAGE FOR INCLUSION IN ACQUISITIONS79

BACKGROUND

The Department of Veterans Affairs (VA), Office of Information & Technology (OIT), Product Delivery Service (PDS) strives to provide benefits and services to Veterans of the United States. In meeting these goals OIT strives to provide high quality, effective and efficient Information Technology (IT) services to those responsible for providing care to the Veterans at the point-of-care as well as throughout points of the Veterans’ health care in an effective, timely and compassionate manner. VA depends on Information Management/Information Technology (IM/IT) systems to meet mission goals.

VA OIT PDS, Health Services Portfolio (HSP) delivers world-class, Veteran-centric capabilities that provide secure, seamless delivery of services to Veterans and their families. HSP consists of a variety of products, programs, and projects that deliver Veteran-centric technology solutions that are available, adaptable, secure, and cost-effective. The technology HSP delivers is mission-critical capability used every day by clinicians, care coordinators, administrators, and Veterans themselves to support clinical decision-making at the point of care. In addition, these capabilities enable timely scheduling and access, coordinate care with community providers, manage financial integrity, and ensure the secure exchange of health information. The performance, reliability, and continuous modernization of these systems directly affect Veteran health outcomes, patient safety, and VA's ability to fulfill its enduring promise to those who have served.

VISION-DRIVEN EXECUTION

The HSP uses vision driven execution to enhance the digital experience for Veterans clinicians, care coordinators, administrators and VA business partners by executing a clear vision, roadmap, resource plans, and metrics of success. The Portfolio’s vision is to pursue excellence in how HSP envisions, plans, prioritizes, resources, and executes IT services and support. The Portfolio has the following goals:

· Strategy: Develop a clear vision and roadmap with prioritized strategic outcomes. Maintain continuous strategy-to-execution alignment. Align investment decisions with strategic goals and utilize an agile approach to allocate resources.

· Modern Architecture: Shrink monolithic and stove-piped products to develop and grow portfolio-wide health data and services that support Veteran health and claims processes.

· Efficiency: Reduce duplicative efforts and develop cross-cutting services and authoritative data to enable faster progress toward achieving strategic goals.

· Collaboration: Continuously improve customer and end-user experiences. Promote collaboration and cross-functional teams.

· Agility: Use an agile, iterative approach to data-driven informed decision-making.

HSP PRODUCT LINES

HSP delivers its mission through Product Lines (PLs), each providing technology solutions that are available, adaptable, secure, and cost-effective. The continual sustainment, management, modernization, enhancement, and integration of these products is essential to achieving a unified and seamless healthcare system for Veterans; eliminating the friction of fragmented technical architectures and delivering a cohesive care experience across every point of the Veteran health journey. This work demands rigor, innovation, and an unwavering focus on the Veteran at every stage of the product lifecycle.

HSP includes, but is not limited to, the following PLs. As HSP continues to evolve, PLs and products may be added or removed from the HSP throughout the life of this effort. This effort encompasses IT program management, technical management, and strategic solutioning support across the following HSP PLs, which together constitute the digital infrastructure of VA healthcare delivery:

· Clinical Imaging: Secure capture, storage, management, and retrieval of diagnostic imaging and clinical documentation essential to care delivery.

· Clinical Services: Frontline clinical tools and workflows that support care delivery at the point of contact, empowering clinicians with the information and capabilities needed to make informed, timely decisions.

· Community Care (CC): Technology solutions that facilitate Veteran access to care through community providers, extending VA's reach beyond its direct care network.

· Discovery, Education and Affiliate Networks (DEAN): Platforms and tools supporting VA's academic affiliations, research mission, and Veteran-focused education and training programs.

· Healthcare Environment and Logistics Management (HELM): Systems that support the safe, efficient management of VA facility environments and supply chains.

· Health Informatics: Data, analytics, and informatics capabilities that enable evidence-based clinical and operational decision-making across the enterprise.

· Patient Care Services: Coordinated, patient-centered care management solutions that support continuity of care across VA facilities and care settings.

· Scheduling and Telehealth: Modern appointment management and virtual care capabilities that expand Veteran access to healthcare regardless of geography or mobility constraints.

· Veterans Health Administration (VHA) Finance: Financial management systems that ensure the fiscal integrity and accountability of VA healthcare operations.

· VHA Front Office: Enterprise support capabilities for VHA leadership, strategic operations, and executive decision-making.

· Electronic Health Record Modernization (EHRM): The EHRM Product Line is considered part of the Health Services Portfolio and operates independently from the Office of Electronic Health Record Modernization.

Delivery Model and Management Structure: Under the Product Line Management (PLM) model, VA product teams are directly led by dedicated product managers and operations managers who own prioritization, execution, and accountability at the product level. Consolidated management services at both the portfolio and product line levels are critical to ensuring cohesive integration, consistent governance, and aligned delivery across the full HSP. Contractor support must fit seamlessly within this structure — functioning not as an external vendor executing isolated tasks, but as an embedded, collaborative partner accountable to mission outcomes and the Veterans those outcomes serve.

Product backlogs serve as the primary mechanism for defining, prioritizing, and tracking planned development and sustainment work across HSP product lines. These backlogs are living instruments that reflect VA's dynamic operational environment and must be managed with transparency, discipline, and a relentless focus on delivering measurable value to Veterans and the care teams who serve them.

APPLICABLE DOCUMENTS

In the performance of the tasks associated with this Performance Work Statement, the Contractor shall comply with the following:

1. “Federal Information Security Modernization Act of 2014”

2. Federal Information Processing Standards (FIPS) Publication 140-3, “Security Requirements for Cryptographic Modules”, March 22, 2019

3. FIPS Pub 199. “Standards for Security Categorization of Federal Information and Information Systems,” February 2004

4. FIPS Pub 200, “Minimum Security Requirements for Federal Information and Information Systems,” March 2006

5. FIPS Pub 201-3, “Personal Identity Verification of Federal Employees and Contractors,” January 2022

6. 10 U.S.C. § 2224, "Defense Information Assurance Program", as amended

7. 5 U.S.C. § 552a, as amended, “The Privacy Act of 1974”

8. Public Law 109-461 (P.L. 109-461), Veterans Benefits, Health Care, and Information Technology Act of 2006, as amended, Title IX, Information Security Matters

9. 42 U.S.C. § 2000d “Title VI of the Civil Rights Act of 1964”, as amended

10. VA Directive 0710, “Personnel Vetting Program,” September 8, 2025, https://www.va.gov/vapubs/index.cfm

11. VA Handbook 0710, “Personnel Vetting Program,” September 8, 2025, https://www.va.gov/vapubs/index.cfm

12. VA Directive 6102, “Internet/Intranet Services,” August 5, 2019

13. 36 C.F.R. Part 1194 “Information and Communication Technology Standards and Guidelines,” as amended

14. Office of Management and Budget (OMB) Circular A-130, “Managing Federal Information as a Strategic Resource,” July 28, 2016

15. 32 C.F.R. Part 199, “Civilian Health and Medical Program of the Uniformed Services (CHAMPUS)”, as amended

16. NIST SP 800-66 Rev. 2, “Implementing the Health Insurance Portability and Accountability Act (HIPAA) Security Rule: A Cybersecurity Resource Guide,” February 2024

17. 45 C.F.R Parts 160 and 164, Subparts A and E, the Standards for Privacy of Individually Identifiable Health Information (“Privacy Rule”); and 45 C.F.R. Parts 160 and 164, Subparts A and C, the Security Standard (“Security Rule”); as amended

18. Sections 504 and 508 of the Rehabilitation Act (29 U.S.C. § 794d), as amended

19. Homeland Security Presidential Directive (12) (HSPD-12), August 27, 2004

20. VA Directive 6500, “VA Cybersecurity Program,” September 22, 2026

21. VA Handbook 6500, “Risk Management Framework for VA Information Systems VA Information Security Program,” February 24, 2021 (see VA Notice 25-01, dated October 15, 2024, “Update to VA Handbook 6500 Risk Management Framework for VA Information Systems VA Information Security Program”, VA Notice 25-16, dated September 15, 2025, “Amending VA Handbook 6500 to Replace Enterprise Mission Assurance Support Services Tool With Office of Information Technology Governance Risk Compliance Tool, and VA Notice 25-17, dated September 22, 2025, “Rescission Of Office Of Information Security (OIS) Deputy Assistant Secretary (DAS) Memorandum – Requirements of Proper Plan of Action and Milestones (POA&M) Completion)

22. VA Handbook 6500.2, “Management of Breaches Involving Sensitive Personal Information (SPI),” June 30, 2023

23. VA Handbook 6500.6, “Acquisition Cybersecurity,” October 2, 2026

24. VA Handbook 6500.8, “Information System Contingency Planning,” March 25, 2025

25. VA Handbook 6500.10, “Mobile Device Security Policy,” August 24, 2026

26. VA Handbook 6500.11, “VA Firewall Configuration,” August 22, 2017

27. OIT Process Asset Library (PAL), OIT Process Asset Library.

28. One-VA Technical Reference Model (TRM) (reference at https://www.va.gov/trm/TRMHomePage.aspx)

29. VA Directive 6508, “Implementation of Privacy Threshold Analysis and Privacy Impact Assessment,” October 15, 2014

30. VA Directive 6510, “VA Identity, Credential and Access Management,” September 3, 2024

31. VA Handbook 6510, “VA Identity, Credential and Access Management,” September 27, 2024

32. VA Directive and Handbook 6513, “Secure External Connections,” October 12, 2017

33. VA Directive 6300, “Records and Information Management,” September 21, 2018

34. VA Handbook, 6300.1, “Records Management Procedures,“ March 24, 2010

35. NIST SP 800-37 Rev 2, “Risk Management Framework for Information Systems and Organizations: A System Life Cycle Approach for Security and Privacy,” December 2018

36. NIST SP 800-53 Rev. 5.2.0 “Security and Privacy Controls for Information Systems and Organizations,” August 27, 2025

37. VA Directive 0735, “Homeland Security Presidential Directive 12 (HSPD-12), Personal Identity Verification, Credential Management Program,” September 19, 2025

38. VA Handbook 0735, “Homeland Security Presidential Directive 12 (HSPD-12), Personal Identity Verification, Credential Management Program,” September 18, 2025

39. OMB Memorandum 05-24, “Implementation of Homeland Security Presidential Directive (HSPD) 12 – Policy for a Common Identification Standard for Federal Employees and Contractors,” August 5, 2005

40. OMB Memorandum M-19-17, “Enabling Mission Delivery Through Improved Identity, Credential, and Access Management,” May 21, 2019

41. OMB Memorandum, “Guidance for Homeland Security Presidential Directive (HSPD) 12 Implementation,” May 23, 2008

42. Federal Identity, Credential, and Access Management (FICAM) Architecture, June 30, 2023 (FICAM Architecture (idmanagement.gov))

43. NIST SP 800-116 Rev 1, “Guidelines for the Use of Personal Identity Verification (PIV) Credentials in Facility Access,“ June 2018

44. NIST SP 800-63 Rev 4, 800-63A-4, 800-63B-4, 800-63C-4, “Digital Identity Guidelines,” August 1, 2025

45. NIST SP 800-157, “Guidelines for Derived PIV Credentials,” December 2014

46. VA Memorandum “Personal Identity Verification (PIV) Logical Access Policy Clarification,” July 17, 2019, https://www.voa.va.gov/DocumentView.aspx?DocumentID=4896

47. Trusted Internet Connections (TIC) 3.0 Core Guidance Documents, https://www.cisa.gov/publication/tic-30-core-guidance-documents

48. OMB Memorandum M-19-26, “Update to the Trusted Internet Connections (TIC) Initiative,” September 12, 2019

49. OMB Memorandum M-08-23, “Securing the Federal Government’s Domain Name System Infrastructure,” August 22, 2008

50. Sections 524 and 525 of the Energy Independence and Security Act of 2007, (P.L. 110–140), December 19, 2007

51. Section 104 of the Energy Policy Act of 2005, (P.L. 109–58), August 8, 2005

52. Executive Order 13221, “Energy-Efficient Standby Power Devices,” August 2, 2001

53. Executive Order 14148, “Initial Rescissions of Harmful Executive Orders and Actions,” dated January 20, 2025

54. VA Directive 0057, “VA Environmental Management Program,” October 25, 2022

55. OIS VAIQ #7424808 Memorandum, “Remote Access,” January 15, 2014, https://www.voa.va.gov/DocumentListPublic.aspx?NodeId=28

56. Clinger-Cohen Act of 1996, 40 U.S.C. §11101 and §11103

57. “Veteran Focused Integration Process (VIP) Guide 4.0,” March 2021, https://www.voa.va.gov/DocumentView.aspx?DocumentID=4371

58. VA Memorandum “Proper Use of Email and Other Messaging Services,” January 2, 2018, https://www.voa.va.gov/DocumentListPublic.aspx?NodeId=28

59. “Product Line Management Transformation Playbook” version 3.1, August 2023, https://www.voa.va.gov/DocumentView.aspx?DocumentID=4946

60. NIST SP 500-267B Revision 1, “USGv6 Profile,” November 2020

61. OMB Memorandum M-21-07, “Completing the Transition to Internet Protocol Version 6 (IPv6),” November 19, 2020

62. Social Security Number (SSN) Fraud Prevention Act of 2017

63. Section 240 of the Consolidated Appropriations Act (CAA) 2018, March 23, 2018

64. C.F.R Title 15 Part 7, “Securing the Information and Communications Technology and Services (ICTS) Supply Chain”, as amended

65. Executive Order 14028, “Executive Order on Improving the Nation's Cybersecurity,” May 12, 2021, https://bidenwhitehouse.archives.gov/briefing-room/presidential-actions/2025/01/16/executive-order-on-strengthening-and-promoting-innovation-in-the-nations-cybersecurity/

66. OMB Memorandum M-22-09, “Moving the U.S. Government Toward Zero Trust Cybersecurity Principles”, January 26, 2022, https://www.whitehouse.gov/wp-content/uploads/2022/01/M-22-09.pdf.

67. NIST SP 800-52 Revision 2, “Guidelines for the Selection, Configuration, and Use of Transport Layer Security (TLS) Implementations

68. OMB M-26-05, “Adopting a Risk-based Approach to Software and Hardware Security,” January 23, 2026

69. OMB M-21-31, “Improving the Federal Government’s Investigative and Remediation Capabilities Related to Cybersecurity Incidents,” August 27, 2021

70. NIST SP 800-88 Revision 2 “Guidelines for Media Sanitization,” September 26, 2025

71. CISA BOD 23-01: Improving Asset Visibility and Vulnerability Detection on Federal Networks. Cybersecurity & Infrastructure Security Agency (CISA), BOD 23-01: Improving Asset Visibility and Vulnerability Detection on Federal Networks | CISA

72. CISA BOD 26-04: Prioritizing Security Updates Based on Risk, June 10, 2026

73. VA Directive 6550, Pre-Procurement Assessment and Implementation of Medical Devices/Systems, June 03, 2019

74. VA Memorandum, “VA Security Controls,” January 17, 2025, https://www.voa.va.gov/DocumentView.aspx?DocumentID=5010

75. E.O. 13960, “Promoting the Use of Trustworthy Artificial Intelligence in the Federal Government,” December 3, 2020

76. E.O. 14319, “Preventing Woke AI in the Federal Government,” July 23, 2025

77. OMB Memorandum M-25-21, “Accelerating Federal Use of AI through Innovation, Governance, and Public Trust,” April 3, 2025

78. OMB Memorandum M-25-22, “Driving Efficient Acquisition of Artificial Intelligence in Government,” April 3, 2025

79. OMB Memorandum M-26-04, “Increasing Public Trust in Artificial Intelligence (AI) Through Unbiased AI Principles,” December 11, 2025

80. OMB Memorandum M-26-10, “Reinforcing Transparency, Accountability, and Oversight of Federal Technology”, March 31, 2026

81. Federal Travel Regulation (FTR) (www.gsa.gov/federaltravelregulation)

82. VA AI Policy - AI-Policy.aspx

84. VA Enterprise Cloud (VAEC) Technical Reference Guide, Version 2.0 November 2022.

85. VA Cloud-First Policy, January 16, 2018.

86. Use of Cloud-Based Native Technologies and Approaches, October 29, 2019.

87. Architecture Standard Operating Framework (ASOF)

88. Key Performance Indicators (KPIs) for DevSecOps Support

89. FY27 Sustainment Data

90. Product Line Architecture (PLA) - VA Enterprise Architecture

91. Health Services Product List

92. DevSecOps Tools and the Delivery Process

93. Health Financial Product Line ASOF

94. Health Services Portfolio Current Product Listing

95. Health Services Data Call Process

SCOPE OF WORK

The Contractor shall provide IT program management, technical management, and strategic solutioning support for the Health Portfolio. The Contractor shall perform and execute the tasks at various levels of support to include Portfolio, Product Lines, Special Initiatives and Product level. Major work areas include IT product line management, product management, technical management, financial management, requirements management, implementation management, release management, schedule support, strategic analysis, capital planning and investment support, engineering and technical support, communications, and administrative support. The Contractor shall comply with all applicable VA, Veterans Health Administration (VHA), and other Government mandates, as necessary.

ORDER TYPE

The effort shall be proposed on a Cost-Reimbursable (CR) (for travel only) and Firm-Fixed-Price basis.

PERFORMANCE DETAILS

PERFORMANCE PERIOD

The Period of Performance (PoP) shall be 12 months from date of award, with three (3) 12-month option periods and one (1) Optional Task. The overall PoP shall not exceed 63 months. Any work at the Government site shall not take place on Federal holidays or weekends unless directed by the Contracting Officer (CO).

There are 11 Federal holidays set by law (USC Title 5 Section 6103) that VA follows:

Under current definitions, five are set by date:

New Year's DayJanuary 1
JuneteenthJune 19
Independence DayJuly 4
Veterans DayNovember 11
Christmas DayDecember 25

If any of the above falls on a Saturday, then Friday shall be observed as a holiday. Similarly, if one falls on a Sunday, then Monday shall be observed as a holiday.

The other six are set by a day of the week and month:

Martin Luther King's BirthdayThird Monday in January
Washington's BirthdayThird Monday in February
Memorial DayLast Monday in May
Labor DayFirst Monday in September
Columbus DaySecond Monday in October
ThanksgivingFourth Thursday in November

PLACE OF PERFORMANCE

Tasks under this PWS shall be performed at Contractor facilities or remotely. The Contractor shall identify its place of performance in their proposal submission. It is expected that this work will be primarily conducted during core business hours which are defined as 8 a.m. to 5 p.m. Eastern Standard Time (EST).

TRAVEL

The Government encourages the Contractor to maximize its use of teleconferencing and video conferencing for meetings.

The Government anticipates travel under this effort to perform the tasks associated with the effort, as well as to attend program-related meetings or conferences throughout the PoP. Include all estimated travel costs in your firm-fixed price line items. These costs will not be directly reimbursed by the Government.

The total estimated number of trips in support of program related meetings for this effort is 75 trips. Anticipated locations include, but are not limited to, the following, with each trip estimated at an average duration of four days:

1. Washington, DC

2. Austin, TX

3. Eatontown, NJ

4. Tampa, FL

5. Denver, CO

6. New Orleans, LA

Travel shall be in accordance with the Federal Travel Regulations (FTR) and requires advanced concurrence by the COR. Contractor travel within the local commuting area will not be reimbursed.

SPECIFIC TASKS AND DELIVERABLES

The Contractor shall perform the following:

PROJECT MANAGEMENT

CONTRACTOR PROJECT MANAGEMENT PLAN

The Contractor shall prepare and deliver a Contractor Project Management Plan (CPMP) that outlines the Contractor’s approach, timeline and tools to be used in execution of the TO. The CPMP shall describe the Contractor’s plans to support the OIT Health portfolio, program and projects. The CPMP shall detail how the resources shall support the maintenance and updating of all management artifacts. The CPMP shall incorporate the tasks described in this PWS. The CPMP shall take the form of both a narrative and graphic format that displays the schedule, milestones, risks and resource support. The CPMP shall also include how the Contractor shall coordinate and execute planned, routine, and special data collection reporting requests. The Contractor shall identify an individual as the primary contact point for all programmatic issues/concerns/status. The initial baseline CPMP shall be concurred upon and updated in accordance with Section B of the TO. The Contractor shall update and maintain the VA Program Manager (PgM) approved CPMP monthly or as changes occur throughout the period of performance. The Contractor shall maintain a staffing plan of resource assignments for all Projects, Programs and the Portfolio to be included in the CPMP.

The CPMP shall also include a staff roster identifying the following:

1. Employee Name

2. Personnel PIV Expiration

3. Personnel clearance level and adjudication date

4. Role

5. Project affiliation

6. Personnel duty location address, alternate email, phone number

The Contractor shall include a plan, within the CPMP, of their project management processes for the following project management disciplines:

1. Schedule Management

2. Financial management

3. Quality Management

4. Resource Management

5. Communication Management

6. Risk management

7. Internal Controls

Deliverable:

A. Contractor Project Management Plan

REPORTING REQUIREMENTS

The Contractor shall provide the COR with bi-weekly Progress Reports in electronic form in Microsoft Word and Project formats. The report shall include detailed instructions/explanations for each required data element, to ensure that data is accurate and consistent. These reports shall reflect data as of the last day of the preceding week.

The bi-weekly Progress Reports shall cover all work completed during the reporting period and work planned for the subsequent reporting period. The report shall also identify any problems that arose and a description of how the problems were resolved. If problems have not been completely resolved, the Contractor shall provide an explanation including their plan and timeframe for resolving the issue. The report shall also include an itemized list of all Information and Communication Technology (ICT) deliverables and their current Section 508 conformance status. The Contractor shall monitor performance against the CPMP and report any deviations. It is expected that the Contractor will keep in communication with VA accordingly so that issues that arise are transparent to both parties to prevent escalation of outstanding issues.

Deliverable:

A. Bi-Weekly Progress Report

WORK PLAN

The purpose of the Bi-Weekly (every two weeks) Work Plan is to provide a means to allow VA to effectively manage this TO as well as reprioritize activities on a bi-weekly basis. The Contractor shall provide a Bi-Weekly Work Plan, which includes information on all work-in-progress (WIP) activities and task backlog currently ongoing as part of this TO. Specifically, the Bi-Weekly Work Plan shall include the following data elements, for each activity ongoing under this PWS:

1. Project and specific activities.

2. Overview and description of the activity.

3. Overall high-level assessment of progress of the activity.

4. All WIP and completed for the activity during the period.

5. Backlog tasks aligned and prioritized to the domain roadmap.

6. Build domain roadmap.

7. Identification of any contract related issues uncovered during the previous period and especially highlight those areas with a high probability of impacting schedule, cost, or performance goals and their likely impact on schedule, cost, or performance goals.

8. Explanations for any unresolved issues, including possible solutions and any actions required of the Government and/or Contractor to resolve or mitigate any identified issue, including a plan and timeframe for resolution.

9. Status on previously identified issues and actions taken to mitigate the situation and/or progress made in rectifying the situation.

10. Work planned for the subsequent period.

11. Current activity schedule overlaid on original activity schedule showing any delays or advancement in schedule.

12. Current expenditures overlaid over the original budget showing any deviations in the actual expenditures versus the original budget and versus the current budget.

13. Workforce staffing data showing all Contractor personnel performing on the effort during the previous period. After the initial labor baseline is provided, each Bi-Weekly Work Plan Report shall identify any changes in staffing identifying each person who was added to the activity, removed, and/or moved from one program/project to another from the task order, including applicable PWS paragraph(s). This should also include any planned travel for the activity.

14. Original schedule of deliverables and the corresponding deliverables made during the previous period.

15. Bi-Weekly-On-Boarding Status Reports in electronic form. This data shall include but is not limited to status of personnel during on-boarding activities including anticipated personnel, training status, and Security Clearance status.

16. Strategic Planning-Analysis Activity Summary.

Additionally, the Contractor shall conduct a bi-weekly meeting to present the Bi-Weekly Work Plan. These reports shall not be the only means of communication between the Contractor, COR and the PgM/Project Manager (PM) to advise of performance/schedule issues and to develop strategies for addressing the issues. The Contractor shall continuously monitor performance and report any deviation from the previous Work Plan to the COR and PgM/PM during routine, regular communications. The Contractor shall respond to all COR queries related to project milestones and schedule within four business hours of receipt of written request.

Deliverable: Bi-Weekly Work Plan

PRIVACY & HIPAA TRAINING

The Contractor shall submit all on-boarding paperwork and documentation as required by all applicable VA onboarding requirements, including but not limited to VA Directive 0710, as well as documentation specifically requested by the COR, to ensure the timely on-boarding of contractor staff. Additionally, the Contractor shall submit Talent Management System (TMS) training certificates of completion for VA Privacy and Information Security Awareness and Rules of Behavior and Health Insurance Portability and Accountability Act (HIPAA) training and provide signed copies of the Contractor Rules of Behavior in accordance with Section 9, Training, from Appendix C of the VA Handbook 6500.6, “Contract Security”.

Deliverable:

A. VA Privacy and Information Security Awareness and Rules of Behavior Training Certificate/VA HIPAA certificate of completion/ Signed Contractor Rules of Behavior

TOOLS TRAINING

The Contractor shall be required to complete all necessary training courses to obtain access to and utilize appropriate tools, upon concurrence by the COR.

Examples of these tools include but are not limited to Slack, Jira, Selenium, Jenkins, GitHub, Prometheus, Docker, Kubernetes, and Confluence. Contractors who have completed these VA training courses within 24 months of their onboarding date and have furnished certificates will not be required to re-take the training course.

Deliverable:

A. VA Training Certificates

TECHNICAL KICKOFF MEETING

A technical kickoff meeting shall be held within 10 days after TO award. The Contractor shall coordinate the date, time, and location (can be virtual) with the Contracting Officer (CO), as the Post-Award Conference Chairperson, the VA PgM, as the Co-Chairperson, the Contract Specialist (CS), and the COR. The Contractor shall provide a draft agenda to the CO and VA PgM at least five calendar days prior to the meeting. Upon Government approval of a final agenda, the Contractor shall distribute to all meeting attendees. During the kickoff-meeting, the Contractor shall present, for review and approval by the Government, the details of the intended approach, work plan, and project schedule for each effort via a Microsoft Office PowerPoint presentation. At the conclusion of the meeting, the Contractor shall update the presentation with a final slide entitled “Summary Report” which shall include notes on any major issues, agreements, or disagreements discussed during the kickoff meeting and the following statement, “As the Post-Award Conference Chairperson, I have reviewed the entirety of this presentation and assert that it is an accurate representation and summary of the discussions held during the Technical Kickoff Meeting for the “Health Services Portfolio Technical Management and Strategic Solutioning Support.” The Contractor shall submit the final updated presentation to the CO for review and signature within three calendar days after the meeting. The Contractor shall also work with the CS, the Government’s designated note taker, to prepare and distribute the meeting minutes of the kickoff meeting to the CO, COR and all attendees within three calendar days after the meeting. The Contractor shall obtain concurrence from the CS on the content of the meeting minutes prior to distribution of the document.

CONTRACTOR RESOURCE INTAKE MANAGEMENT

The Contractor shall create a Health Services Technical Management and Strategic Solutioning Support Awareness Slide Deck to share with Health Services Portfolio staff detailing the available capabilities and support within this TO. The Contractor shall present this content to Health Services Portfolio staff as needed. The Slide Deck and presentation shall include the Contractor’s overall support approach, outline types of support provided by this TO and how capacities are being leveraged across the Health Portfolio.

The Contractor shall create and maintain a Health Services Technical Management and Strategic Solutioning Support resource request, intake and disposition process. The Contractor shall document the request, intake and disposition process within an Intake Analysis and Process Guide which will include process flows and guides depicting processes and sub-process. The Contractor shall maintain an intake repository providing status updates on demand.

Deliverables:

A. Technical Management and Strategic Solutioning Support Awareness Slide Deck B. Intake Analysis and Process Guide

ON-BOARDING SUPPORT

The Contractor shall assist with the onboarding process for VA access and for individual system/environment access for all Contractor staff supporting the Health Portfolio. This includes but is not limited to the Technical Management and Strategic Solutioning Support, DevSecOps, Development, and Operations and Maintenance (O&M) Contractors. The Contractor shall:

1. Collect signed rules of behavior documents, non-us citizen forms, signed non-disclosure agreements, training certificates, applications for access to VA information systems, Personal Identity Verification (PIV) card requests and other related information, for assigned Product Teams, and provide secure storage for the documents and files, in accordance with VA guidance.

2. Provide the documents, files and information to the VA PM, COR or IT staff for review/approval/signature, when requested, to support VA’s on-boarding process for granting access to VA systems.

3. Prepare and submit access requests, including TMS applications, PIV card applications, and current VA approved Contractor request forms. After receipt of a favorable Special Agreement Check (SAC) determination, and COR approval, the Contractor shall create Helpdesk tickets to request VA user accounts (for e-mail and remote access).

4. Monitor the submission of the artifacts and follow up to ensure that all artifacts submitted are complete and correct. The Contractor shall track VA system access requests, for assigned Product Team’s, to completion.

5. Specifically, track and report on the status of Health Portfolio onboarding of personnel as follows:

a. Upon COR approval, contact VA's Security Investigations Center (SIC) requesting the SAC and OPM background investigation status documentation by e-mail and-or by telephone.

b. Upon COR approval, request VA access for the subject using the intranet-based Computer Access Request site that resides inside of the VA network. Provide all information to complete the on-line version of a Computer Access Request Form and upload the required certificates as PDF files: Contractor Rules of Behavior, Non-Disclosure Agreement, Training Certificates, and the proof of SAC approval (the SAC approval can be an e-mail from the SIC or a report from the SIC). Notify the COR that the form is ready for approval, signature, and submission.

c. Coordinate with the TMS point of contact so that all Contractor personnel are listed under the proper supervisor (COR) and that contract start-end dates are accurate in TMS.

d. Provide a Bi-Weekly Resource Management Report in the form of a spreadsheet that lists all personnel currently and formerly assigned across all Health Portfolio Teams (VA and Contractors). The spreadsheet shall contain, at a minimum, name, city nearest to work location, telephone, alternate e-mail, GFE asset information, background investigation initiation and completion dates, a log of Electronic Permission Access System (ePAS) requests, and role. This spreadsheet shall reside on a VA SharePoint site in a location specified by the COR.

The Contractor shall provide a summary of the On-boarding Support activities performed in the monthly updates to the CPMP.

Deliverable:

A. Bi-Weekly Resource Management Report

OFF-BOARDING SUPPORT

The Contractor shall assist with the off-boarding process for VA access, including individual system/environment access, for all Contractor staff, Health Services Portfolio Technical Management and Strategic Solutioning Support, Development, and O&M Contractors. The Contractor shall prepare all forms necessary for termination of access to VA information systems, in accordance with VA guidance. The Contractor shall assist in confirming whether the GFE equipment, associated documentation, and PIV card has been returned to the proper receiving authorities in accordance with VA policy. All findings shall be documented in the Bi-Weekly Resource Management Report under paragraph 5.1.8 of this PWS.

PROCESS IMPROVEMENT

The Contractor shall support the Health Services Portfolio in continuous process improvement and innovation throughout the lifecycle of this TO. The Contractor shall provide a minimum of three (3) process improvement recommendations quarterly as an addendum to the CPMP to improve overall operational performance at the Health Services Portfolio, Product Line and Product levels. These improvements shall consider implementing new VA approved tools and processes to optimize operations and execution throughout the Portfolio. The Contractor shall collect feedback from VA staff within the Health Services Portfolio and externally, to identify opportunities to leverage existing and create new processes that would mature Health Services operations and execution. The Contractor shall link process improvement and innovation suggestions to organizational goals when applicable and provide executable recommendations, as the process improvement opportunities arise.

HEALTH SERVICES PORTFOLIO AND PRODUCT TECHNICAL MANAGEMENT AND SUPPORT

The Contractor shall provide strategic and programmatic support for the Health Services Portfolio at the Portfolio, Product Line and Product level. The Contractor shall directly support VA cross functional teams and provide daily active collaboration and feedback for the Health Portfolio’s goals, scope, requirements, costs, schedule, and risks. The Contractor shall provide synergy across the task order providing consistent support through each of the support layers within the Health Services Portfolio. The cross functional teams must have awareness of the work being completed throughout the Portfolio and implement solutions in a consistent, cohesive manner in alignment with Health Services Portfolio goals. The Contractor shall follow VA’s approved methodologies to support the Health Services Portfolio to include, but not limited to, Product Line Management, SAFe Agile, DevSecOps, and VIP while supporting the cross functional teams. The Contractor shall ensure efficiencies are leveraged across product lines and throughout the Health Services Portfolio while providing the support specified within this PWS.

TRAVEL ADMINISTRATION

The Contractor, with COR concurrence, shall assist with setting up travel requests for VA travel to meetings and assist with tracking them through the VA approval process for the travel associated with this TO as well as assist in preparing travel requests in support of the product line and product teams. The Contractor shall not approve or submit/prepare on their own any Government travel requests.

For tracking purposes only, the Contractor shall capture and maintain a list of Government travelers, location, duration, purpose, and justification for the travel event. The Contractor shall provide support for the preparation and submission of travel requests, coordination with VA Travel facilitators/approvers and travelers, and track the approval process on a VA SharePoint, electronic spreadsheet, or other VA-approved form of tracking. For high dollar value trips/large number of attendees, the Contractor may need to prepare the Conference Cost Estimate form (VA Form 10008a), Concurrence and Summary Sheet (VA Form 4265), Strategic Communication Review (VA Form 0907), Conference Responsibility Designations (VA Form 10008e), and Conference Request Memorandum.

PORTFOLIO REQUIREMENT AND PRODUCT INTAKE

The Contractor shall support the Health Services Portfolio through the OIT intake process for new VHA requests. The Contractor shall support existing intake processes and ensure key stakeholders are engaged through all phases of intake. The Contractor shall manage the product alignment process and ensure integration with the ultimate executing Product Line throughout the intake process. The Contractor shall manage intake and provide a Weekly Intake Report. The Weekly Intake Report shall include all current products that are in the requirement intake process and document any products that are currently being transitioned to/from each Product Line within Health.

Deliverable:

A. Weekly Intake Report

STRATEGIC PLANNING AND ANALYSIS

The Contractor shall create and review strategies to develop and document alternatives to address technical and schedule challenges that will enhance the Portfolio for the current and future state. The Contractor shall conduct research regarding various aspects of proposed strategies and alternatives and provide summaries of findings.

Where applicable, the Contractor shall identify and apply a variety of process analysis approaches to determine the impact of complex issues. When alternative strategies and approaches are required, the Contractor shall provide a composite list of all alternatives considered, and a detailed summary of cost, schedule, and performance risks and benefits of each. Following VA PMs approval of selected strategies, the Contractor shall document and analyze outcomes.

The Contractor shall provide strategic planning and analysis support, including the following:

1. Assist in the development and update of mission and vision statements while providing recommendations to build operational plans and specify measurable outcomes through a consolidated strategic planning process.

2. Make recommendations to and assist in the monitoring of program goals, objectives, and plans.

3. Apply sound business principles and performance metrics. Provide metrics analysis and insight into operating performance and then make recommendations for improvements.

4. Conduct complex management studies and reviews including analysis of organizational structure, policy, processes, and operations.

5. Analyze programs, functional areas, and organizations to determine whether the management systems currently being utilized are efficiently accomplishing the objectives sought and whether they provide controls necessary for sound management.

6. Perform analysis of proposed strategies and alternatives, and reporting impacts to the Health Portfolio due to business case savings analysis, new projects, new scope, organization changes, business changes, pricing adjustments and unplanned events.

7. Prepare and manage an Organizational Strategic Analysis and Action Plan (OSAAP)

The Contractor shall conduct quarterly in-person summits where it shall cultivate ideas for improvements; formalize industry sessions with subcontractors and potential industry partners to maximize Health Information Technology (HIT) expertise; prepare an annual report summarizing HSP’s strategic accomplishments; biannual congressional updates; and establish portfolio collaboration committees focused on portfolio-wide strategies, such as Artificial Intelligence.

The Contractor shall incorporate initiatives from the Strategic Plan, Annual Business Plan (ABP), and OSAAP to a backlog for traceability and flow-down to the PL and product teams. This supports full portfolio alignment at all levels. The Contractor shall use the HSP Communications Plan to communicate modernization initiatives to applicable stakeholders. The Contractor shall document and maintain portfolio and PL backlog plans in Jira, including associated operational tasks.

Deliverable:

A. Organizational Strategic Analysis and Action Plan

MEETING MANAGEMENT

The Contractor shall coordinate with Government leadership to plan, facilitate and document a variety of portfolio, product line and product level meetings. The Contractor shall identify organizational and industry standards regarding purpose and goal of each meeting and/or review when appropriate and shall coordinate with Government leadership to document goals. The Contractor shall create detailed agendas, identify attendees, identify cadence, and define meeting outcomes. The Contractor shall coordinate with proposed meeting participants to compare calendars and identify mutually acceptable meeting dates, times, and locations (virtual or in person). The Contractor shall post meetings on participant calendars using automated tools or compatible products such as MS Outlook, MS Teams, and the VA’s teleconferencing system and reserve meeting/conference facilities within Government facilities and required equipment. Following respective manager concurrence, the Contractor shall disseminate this information to meeting participants and shall manage meeting logistics. The Contractor shall be responsible for coordinating data collection prior to meeting and presenting data when applicable. Government leadership will host and chair reviews as appropriate. The Contractor shall facilitate meetings using tools such as MS Teams, MS Teams Live Meetings and Mural, as well as present slides and meeting content. The Contractor shall provide minutes from all briefings and meetings no later than two business days after briefing/meeting completion. In addition to documenting meeting attendees, topics of discussions, and related responses or decisions for the discussions, the Contractor shall create, organize, and distribute Action Items using capabilities within MS Teams. The Contractor shall support the following activities as outlined below:

1. Maturity Level Reviews

2. Program Increment (PI) Planning

3. Retrospectives

4. Requirements reviews

5. Design reviews

6. Test readiness reviews

7. Reviews required as part of the approved VA OIT project management methodology

8. Critical Decision Reviews/Presentations

9. Program/Project Management reviews

10. Technical Reviews

11. Daily scrums

12. Integrated Product Teams (IPT) meetings

13. IPT workgroups

14. Strategy reviews and working groups

15. Management status reviews

16. Other Health related meetings as needed

CAPITAL PLANNING AND INVESTMENT CONTROL (CPIC)

The Contractor shall collaborate and coordinate with the Health Portfolio Team and their designees to ensure the integration of project and program budgets with program and project management reports to support timely and accurate financial management and reporting activities.

The Contractor shall prepare, and review planning and expenditures data related to Operational Management Review (OMR), Internal Process Review (IPR), Program Management Review (PMR), VIP and Enterprise Project Structure and all other reporting requests to ensure accuracy. The Contractor shall:

1. Provide day-to-day tracking of execution year funding.

2. Assist in the development and updating of budget execution artifacts.

3. Coordinate with the VA Management…