Q_A Patient Internet Services Connectivity.docx
DOCX document 16 KB Posted
- Attached to
- Patient Internet Services Connectivity
- Solicitation number
- 36C10B24Q0340
About this file
This document contains a set of Questions and Answers related to a Patient Internet Services Connectivity requirement for the Department of Veterans Affairs (VA), Veterans Health Administration (VHA) Chalmers P. Wylie Veterans Affairs Ambulatory Care Center (VA ACC).
The key details are: the VA ACC has a requirement for internet service and maintenance for patients and family members, with a North American Industry Classification System (NAICS) code of 517112 Wireless Telecommunications Carriers (except Satellite). This is a Request for Information (RFI) only, not a formal solicitation. The Government is seeking information on vendor capabilities to provide the required services, including details on existing infrastructure, desired features, and performance requirements. Interested parties are instructed to submit a Vendor Capabilities Statement limited to five pages by the response deadline of April 24, 2024. The Government does not intend to pay for the information submitted in response to this RFI.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Q_A Patient Internet Services Connectivity UPDATED ANSWERS 5-10-24.docx | DOCX document | |
| Q_A Patient Internet Services Connectivity UPDATED ANSWERS.docx | DOCX document | |
| P01 Chalmers P Wylie VAACC WiFi SOW 02132024 DRAFT SS.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Patient Internet Services Connectivity Notice ID: 36C10B24Q0340
Questions and Answers
1. Can we have the diagrams for all locations as mentioned in the SOW?
As builts don’t exist. Floor plans can be provided.
2. How many floors at each location?
CBOCs are single floor. Main facility is 4 floors.
3. How much square footage of space needs to be covered?
100% coverage is required, exact square footage can be extracted from floor plans. Access points already exist per installation of previous contractor.
4. How many users at each location?
No more than 200 at CBOCs, and 750-1000 users in main facility.
5. How many Access Points (APs) per floor?
135 access points main facility (1st fl = 48, 2nd fl = 48, 3rd fl = 25, 4th fl = 10, ENG BLDG = 4) CBOCs Grove City = 8, Marion = 5, Zanesville = 7, Newark = 9, and Airport = 5
6. Must this be competing Wi-Fi networks? This could be handled doing an SSID and bring the guest network to a firewall and segment the network.
Yes, they must be competing networks.
7. Would you be open to using or upgrading current infrastructure to accomplish the same requirements using just one wireless network with multiple SSID’s and multiple security methods?
No maintain separation of networks.
8. The description of security services to be considered include live internet linked to the AT&T Business Network contract. Is it the government's intent that the services be tied directly to AT&T Business to the exclusion of other providers of similar services?
This is a service only solicitation. Infrastructure is currently in place and operational. Current Guest Wi-Fi service is provided by Spectrum. New provider may require new switches, access points and data runs.
9. The government makes several reference to CISCO networks. Because these statements are attributable to a specific manufacturer, is it the government's expectation that offeror solutions be based on the CISCO Systems suite of products or is the government open to other Brand Names?
Current Guest Wi-Fi utilizes Aruba networking products. New provider may require new switches, access points and data runs.
10. The Timetable of Deliverables states that equipment will be installed and fully functional 21 days from contract award, however the paragraph preceding the table reads "Installation and full operational capability is to be completed within 120 days of award." Is the government making a distinction between "full operational capability" and "...installed and fully functional", and if so, what is the distinction and how does it impact the timetable?
Timetable given as guide for installation of new service and infrastructure. Infrastructure currently in place and operational. There shall be minimal interruption to service and less than 5 days per switch. We require notification 48 hours prior to anticipated service interruption and duration.
11. The Timetable of Deliverables provides for a Mandatory Site Visit. Item 4 of the performance assumptions state "A spectrum analysis may be required before design, placement and implementation of Internet access can begin.", and item 2 of the Performance Requirements states "Perform spectrum analysis of the campus (as needed/required)". Is it the government's intent to afford all potential offerors the opportunity to conduct spectrum analysis during the site visit or some other time prior to the offerors engaging in system design?
If offeror wishes to conduct a spectrum analysis it can be scheduled.