36A79720Q0010-002.pdf

PDF Posted

Attached to
6525--FEBRUARY 2020 CONSOLIDATION
Solicitation number
36A79720Q0010
Issued by

About this file

36A79720Q0010 February 2020 Consolidation Schedule Revised 3.18.20.pdf

View the file

Other files

File Type Posted
36A79720Q0010-003.xlsx XLSX spreadsheet
36A79720Q0010-001.pdf PDF
36A79720Q0010-000.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FEBRUARY 2020 NAC CONSOLIDATION SCHEDULE –

TEAM A

All modalities requiring installation Dates* Milestone – All Modalities

1/31/2020 Requirements/Requests due to the NAC

3/18/2020 Pre-Solicitation Notice posted to FBO

3/25/2020 Post requirements (RFQ) to FBO

4/8/2020 Deadline for Vendors to submit questions to NAC

4/22/2020 Deadline for NAC to respond to Vendor Questions

5/13/2020 Deadline for Vendor to submit quotes to NAC

5/27/2020 Deadline for Customers to receive vendor quotes via the shared drive

6/24/2020 (4 weeks) Deadline for Customer to submit Best Value Selections

7/22/2020 (4 weeks) Deadline for NAC to complete review of Selection Justifications

8/19/2020 (4 weeks) Goal to award all Delivery Orders *Dates are estimates and are subject to change