35921 Question and Answers.docx
DOCX document 28 KB Posted
- Attached to
- ESB - Crack Seal US 395 2024
- Solicitation number
- S-73000-00009785
- Issued by
- Harney County, Oregon
About this file
This is a Question and Answers document issued by the Oregon Department of Transportation (ODOT) in response to inquiries regarding mini-RFP No. S-73000-00009786 for the Statewide BUD Permit Expansion and Renewal project, dated April 11, 2024. The document clarifies two key procedural questions regarding Task 2 deliverables and timeline. ODOT confirmed that consultants are required to submit soil sampling to the Agency Project Manager within 8 weeks of completing Task 2, with this submission consisting of notification that sampling has been completed rather than a technical document. Additionally, ODOT defined the completion of Task 2 as DEQ's approval of the final work plan, rather than the consultant's submittal of the work plan to ODOT.
The Q&A document does not address pricing, contract terms, set-asides, or funding sources, as it serves solely to provide technical clarification on project deliverables and scheduling requirements for interested bidders on the referenced mini-RFP.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ESB_RFCQ_279C_Fnl~1.docx | DOCX document | |
| Exhibit 1 (Technical Specifications)~8.docx | DOCX document | |
| Addendum 1~13.docx | DOCX document | |
| ESB_RFCQ_Attachments_279C_Fnl~1.docx | DOCX document | |
| 00009785 Preliminary Results.xlsx | XLSX spreadsheet | |
| 00009785 Intent To Award.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question and Answers OregonBuys mini-RFP No. S-73000-00009786 (#35921) Project: Statewide BUD Permit Expansion and Renewal
April 11, 2024 In Section 3.0 of the mini-RFP, under the “Deliverables and Schedule” heading, the mini-RFP states “Consultant shall submit soil sampling to APM within 8 weeks of completing Task 2.”
· Question: Can ODOT clarify its expectations for what the consultant shall submit within 8 weeks of completing Task 2?
· Response: The expectation is the consultant would notify Agency Project Manager that the sampling has been completed (within the prescribed timeframe). This would not be a technical document, just notification.
· Question: Is the completion of Task 2 defined as the submittal of the final work plan to ODOT, or DEQ approval of the final work plan?
· Response: The completion of Task 2 is defined as DEQ’s approval of the final work plan.