35851 Preliminary Bid Results.xlsx

XLSX spreadsheet 15 KB Posted

Attached to
ESB D1 US30 MP 48. 4 Stockpile Cleanup
Solicitation number
S-73000-00008553
Issued by
Columbia County, Oregon

About this file

The document provided is a Preliminary Bid Results spreadsheet for ITB No. S-73000-00008553/35851, a contract opportunity issued by the Oregon Department of Transportation (ODOT) to clean out a stockpile site near US30 MP 48.4, under the Lewis and Clark Bridge. The contract is for one (1) Emerging Small Business (ESB) certified contractor to perform this work. The bid closing date is November 13, 2023, at 12:00 pm. The bid tabulation shows the unit price and total price submitted by six different contractors for the single bid item.

The project description indicates that ODOT is seeking to clean out a stockpile site near US30 MP 48.4. The contract will be awarded to one ESB certified contractor. The bid prices range from $43,100 to $204,900 for the single bid item. This bid tabulation is not an indicator of award, but rather a compilation of the bids submitted for consideration.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Date Issued:
ITB No.S-73000-00008553/35851BIDDER
NAME:Mid Valley Excavation LLCNW Industrial Flooring, Inc dba NW Pure Construction IncSheets Trucking & Excavation LLCTrees Plus Northwest LLCNew-Gen Trucking & Excavation LLCGunter's Construction & Excavating Inc
Bid Closing:November 13, 2023 12:00pmCITY/STATE:Sublimity ORBoring ORWolf Creek OCSalem ORAurora ORColton OR
Description:CCB#:197179214573238173234684234444220093
This bid tabulation is not an indicator of award. It is only a tabulation of the bids submitted for consideration.
Bid Item #DescriptionEst
QTYUNITUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL

PRICE

1Stockpile site near US30 MP 48.4 under the Lewis and Clark Bridge1Project$ 43,100.00$ 43,100.00$ 48,900.00$ 48,900.00$ 54,745.00$ 54,745.00$ 141,250.00$ 141,250.00$ 199,479.00$ 199,479.00$ 204,900.00$ 204,900.00
TOTAL$ 43,100.00$ 48,900.00$ 54,745.00$ 141,250.00$ 199,479.00$ 204,900.00

File details come from the government source that posted it. Updated .