Summary

This Request for Qualifications (RFQ) is issued by the Town of Cary Public Works Department in North Carolina seeking qualified licensed professional engineering firms to provide mechanical engineering design services for assessing and replacing heating, ventilation, and air conditioning (HVAC) equipment at multiple Town facilities. The project encompasses replacement of boiler and chiller equipment at four Town Hall buildings, a boiler at the Herbert C. Young Community Center, and a boiler and rooftop air handling unit at the Cary Senior Center. The equipment, primarily installed around 2005, has reached or exceeded its expected service life as documented in a 2020 Facility Condition Assessment. The RFQ was advertised on November 9, 2026, with written questions due by November 23, 2026, and proposals due December 7, 2026, at 2:00 PM ET. The Town anticipates an evaluation meeting at the end of December, potential interviews in mid-January, and a tentative selection announcement by the end of January. The selected firm will provide services across six project phases: pre-design and existing conditions assessment, preliminary design report (approximately 30% design), final design (60% and 100% milestones), bidding phase, construction administration, and closeout with asset integration. The contract term will extend through final project completion and closeout, with compensation structured according to design phases and total project cost.

Compensation for Basic Services is calculated as a percentage of the Total Project Cost allocated to each design phase, with hourly rates for Additional Services to be submitted separately. This procurement is conducted under North Carolina General Statute 143-64.31, commonly known as the Mini-Brooks Act, which mandates that selection be based solely on qualifications rather than price. Evaluation criteria include Corporate Background and Experience (15% weight), Project Understanding (20% weight), Project Approach (25% weight), and Team Firm Experience and Qualifications (40% weight), with scoring on a scale of 0 to 3 for each criterion. Proposals must not exceed 20 pages total (10 pages front and back) and must include a cover letter, corporate background with at least three references, project understanding and approach documentation, and detailed team qualifications with resumes. The selected firm must maintain professional liability insurance of $2,000,000 per claim, commercial general liability insurance of $1,000,000 per occurrence and $2,000,000 aggregate, and workers' compensation coverage as required by North Carolina law. Responses must be submitted electronically only through the North Carolina electronic Vendor Portal (eVP) as a single viewable and printable Adobe PDF file. No pre-bid conference is scheduled; all questions and clarifications must be submitted in writing to BoDean Norris, Capital Asset Coordinator, at bodean.norris@carync.gov.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

v.04.15.24

REQUEST FOR QUALIFICATIONS

RFQ # 354-PW27-22

Project Title: Town Facilities HVAC Equipment Replacement

Design Engineering Services

Issue Date: November 9th, 2026

Due Date: December 7th at 2:00pm ET

Issuing Department: Public Works

Direct all inquiries concerning this RFQ to:

BoDean Norris

Capital Asset Coordinator

Email: bodean.norris@carync.gov mailto:bodean.norris@carync.gov v.04.15.24

Table of Contents

1 INTRODUCTION

1.1 Purpose

1.2 Background

1.3 RFQ Timeline

1.4 Pre-Submittal Conference

1.5 Questions

1.6 Submittal Requirements and Contact Information

1.7 Rights to Submitted Material

1.8 Communications

1.9 Lobbying

1.10 Gifts and Favors

1.11 Proposer Expenses

1.12 Proposer Acceptance

2 QUALIFICATIONS PACKAGE

2.1 Request for Qualifications Required Document Format

2.2 Hourly Rates

2.3 Qualifications Package Documents

3 PROPOSAL EVALUATION

3.1 Evaluation Criteria

3.2 Final Selection

3.3 Notice to Proposers

4 SCOPE OF SERVICES

5 EXECUTION OF PROPOSAL

APPENDIX I

APPENDIX II

1 INTRODUCTION

1.1 Purpose

The Town of Cary is seeking one or more qualified firm(s) with which to contract for the following services:

The Town of Cary Public Works Department wants statements of qualifications from licensed professional engineering firms. The selected firm will provide mechanical engineering services for assessing and replacing heating, ventilation, and air conditioning (HVAC) equipment at several Town facilities.

The project covers the following equipment:

Facility Equipment

Town Hall Building A Boiler #1, Boiler #2, Chiller

Town Hall Building B Boiler #1, Boiler #2, Large Chiller, Small Chiller

Town Hall Building C Boiler #1, Boiler #2, Chiller

Town Hall Building D Mini Split #2, Data Aire unit

Herbert C. Young Community Center Boiler

Cary Senior Center Boiler, Rooftop Unit (AHU-8)

A detailed scope of services is provided in Section 4 of this solicitation.

Information related to this solicitation, including any addenda, will be posted to the North Carolina electronic Vendor Portal (eVP) at https://evp.nc.gov/solicitations/.

1.2 Background

In 2020, the Town of Cary performed a Facility Condition Assessment (FCA) of Town-owned facilities as part of its Capital Asset Management program. The assessment inspected the Town Hall campus buildings in January 2020 and the Herbert C. Young Community Center and Cary Senior Center in September and October 2020. The final capital expense matrices and system detail reports were delivered in September 2021.

For each major building system, the assessment recorded the equipment's age, observed condition, remaining useful life, and recommended renewal year. It also projected renewal costs over 20 years, starting from 2020 costs with a 5% annual inflation escalation. The Town is now loading these findings into its Capital Asset Management system to support long-range capital planning.

The assessment found that most of the primary heating and cooling equipment on the Town Hall campus was installed around 2005 and is past or at end of its expected service life now. The Cary Senior Center has HVAC unit and boiler listed for replacement not located on Town Hall campus.

1.3 RFQ Timeline

Provided below is a list of the anticipated schedule of events related to this solicitation.

The Town of Cary reserves the right to modify and/or adjust this schedule to meet the needs of the project. All times shown are Eastern Time (ET):

https://evp.nc.gov/solicitations/

RFQ Process Date and time

RFQ Advertisement Date November 9th 2026

Deadline for written questions November 23rd 2026

Town Response to Questions (anticipated)

November 30th 2026

Submittal Due Date and Time December 7th at 2:00pm ET

Evaluation Meeting (anticipated) End of December

Interviews (if required) Mid-January

Selection Announcement (tentative) End of January

No preproposal conference is planned for this solicitation. Refer to Section 1.5 for all questions and clarifications related to this RFQ.

1.4 Questions

Requests for clarification and questions to this RFQ must be received by the Town not later than the date shown above in Section 1.3, entitled “RFQ Timeline”, for the submittal of written inquires. The Town will not entertain any further questions after the due date.

All questions related to this solicitation must be submitted in writing (via email) to the following individual:

Contact Name Email Address

BoDean Norris bodean.norris@carync.gov

Indicate “RFQ #354-PW27-22 – Questions” in the subject of the email. Questions submitted via telephone will not be answered.

The Town shall issue addenda reflecting questions and answers to this RFQ, if any, which shall be posted to the NC eVP website. No information, instruction or advice provided orally or informally by any Town personnel, whether made in response to a question or otherwise in connection with this RFQ, shall be considered authoritative or binding.

Respondents shall be entitled to rely only on written material contained in an Addendum to this RFQ.

It is important that all Respondents submitting to this RFQ periodically check the NC eVP website for any Addenda. It is the Respondent’s responsibility to ensure that all addenda have been reviewed and, if required, signed and returned.

1.5 Submittal Requirements and Contact Information

Electronic responses ONLY will be accepted through the NC eVP website. Interested parties must be logged in to submit proposals electronically. Registration information is available at NC Electronic Vendor Portal (eVP). Proposals must be clearly marked with name of the submitting company, the RFQ number and RFQ title (Your Company Name 354-PW27-22 Town Facilities HVAC Equipment Replacement).

Proposers must submit one (1) electronic version, submitted as a viewable and printable Adobe Portable Document File (PDF), on or before the submittal due date and time mailto:bodean.norris@carync.gov https://evp.nc.gov/solicitations/ https://evp.nc.gov/ provided in Section 1.3. Submissions that do not comply with the stated submission method will be deemed non-responsive.

Cary reserves the right to reject any or all proposals for any reason and to waive any informality it deems in its best interest. Any requirements in the RFQ that cannot be met must be indicated in the proposal. Proposers must respond to the entire Request for Qualifications (RFQ). An incomplete proposal may be eliminated from consideration at the discretion of Cary.

It is the responsibility of the Firm to ensure that their response arrives at the designated location specified in this Section by the due date and time specified in Section 1.3 RFQ Timeline.

1.6 Rights to Submitted Material

All proposals and supporting materials, as well as correspondence relating to this RFQ, shall become the property of the Town. The content of all submittals will be held confidential until the selection of the firm is made. Proposals will be reviewed by the Evaluation Team, as well as other Town staff and members of the general public who submit public record requests. Any proprietary data must be clearly marked. In submitting a Proposal, each Prospective Proposer agrees that the Town may reveal any trade secret materials contained in such response to all Town staff and Town officials involved in the selection process and to any outside consultant or other third party who serves on the Evaluation Team or who is hired by the Town to assist in the selection process. Proposals marked entirely as “confidential”, “proprietary”, or “trade secret” will be considered non-responsive and will be removed from the evaluation process.

1.7 Communications

All communications of any nature regarding this RFQ with any Town staff, elected Town officials, evaluation committee members are strictly forbidden from the time the solicitation is publicly posted until award. Questions must be submitted in writing to the individual designated in Section 1.5 prior to the deadline provided in Section 1.3.

Violation of this provision may result in the Firm’s proposal being removed from consideration.

1.8 Lobbying

By responding to this solicitation, the Firm certifies that it has not and will not pay any person or firm to influence or attempt to influence an officer or employee of the Town or the State of North Carolina, or any elected official in connection with obtaining a contract as a result of this RFQ.

1.9 Gifts and Favors

Contractor shall become aware of and comply with laws related to gifts and favors, conflicts of interest and the like, including N.C.G.S. §14-234, N.C.G.S. §133-1, and N.C.G.S. §133-32

1.10 Proposer Expenses

The Town of Cary will not be responsible for any expenses incurred by any Firm in the development of a response to this Request for Qualifications or any other activities associated with this procurement including but not limited to any onsite (or otherwise) interviews and/or presentations, and/or supplemental information provided, submitted, or given to Town of Cary and/or its representatives. Further, the Town of Cary shall reserve the right to cancel the work described herein prior to issuance and acceptance of any contractual agreement/purchase order by the recommended Firm even if the awarding authority for each entity has formally accepted a recommendation.

1.11 Proposer Acceptance

Submission of any proposal indicates a Proposer’s acceptance of the conditions contained in this RFQ. The Town of Cary has the sole discretion and reserves the right to cancel this RFQ, and to reject any and all proposals, to waive any and all informalities and/or irregularities, if it is deemed to be in the Town’s best interests to do so. The Town of Cary reserves the right to accept or reject any or all of the items in the proposal, and to award the contract in whole or in part and/or negotiate any or all items with individual Firms if it is deemed in the Town of Cary’s best interest. Moreover, the Town of Cary reserves the right to make no selection if proposals are deemed not in the best interest of the Town of Cary.

REMAINDER OF PAGE INTENTIONALLY LEFT BLANK

2 QUALIFICATIONS PACKAGE

Responses must follow the format outlined below. The Town may reject as non-responsive at its sole discretion any submittal that does not provide complete and/or adequate responses or departs in any substantial way from the required format.

2.1 Request for Qualifications Required Document Format

Responses should be divided using tabs to separate each section, maximum of 10 pages total front and back (twenty pages total) and listed sequentially as follows:

Section 1: Cover Letter Provide an introduction letter summarizing the unique qualifications of your Firm to meet the needs of this project. This letter should be presented on the Firm’s official letterhead and signed by an authorized representative who has the authority to enter into a contract with the Town on behalf of the Firm. Include the name, title, address, telephone and email address of the individual who serves as the point of contact for this solicitation.

Section 2: Corporate Background and Experience Include background information on the Firm and provide detailed information regarding the Firm’s experience with similar projects. Provide a list of all similar contracts performed in the past 5 years, accompanied by at least Three references, including contact persons, firm, telephone number and email address.

Include the total amount invoiced for each listed project, the length of the project, and list of personnel involved in the project who are also proposed for the subject project named in this solicitation. Failure to provide a list of all similar contracts in the specified period may result in the rejection of the Firm’s proposal. The evaluation team reserves the right to contact any or all listed references, and to contact other public entities regarding past performance on similar projects.

Section 3: Project Understanding, Approach and Schedule Provide a comprehensive narrative, outline, and/or graph demonstrating the Firm's understanding and approach to accomplishing the tasks outlined in the Scope of Work section of this RFQ. A description of each task and deliverable and the schedule for accomplishing each shall be included.

Section 5: Team Firm, Experience and Certifications/Qualifications This section must include the proposed staffing, deployment and firm of personnel to be assigned to this project. The Proposer shall provide information as to the qualifications and experience of all executive, managerial, legal, and professional personnel to be assigned to this project, including resumes citing experience with similar projects and the responsibilities to be assigned to each person. A project-specific firm chart which clearly illustrates the roles, responsibilities, and the reporting relationships of each team member should be included.

2.2 Hourly Rates

This solicitation is being issued in accordance with NCGS 143-64.31, otherwise known as the Mini-Brooks Act, and therefore price cannot and will not be a determining factor in the selection of the successful contractor. One copy of the hourly rates for all proposed project personnel should be uploaded as a separate file using the same naming format described in Section 1.6.

2.3 Qualifications Package Documents

This RFQ is comprised of the base RFQ document, any attachments, and any addenda released before Contract award. All attachments and addenda released for this RFQ in advance of any Contract award are incorporated herein by reference.

REMAINDER OF PAGE LEFT BLANK INTENTIONALLY.

3 PROPOSAL EVALUATION

3.1 Evaluation Criteria

This is not a bid. There will not be a public opening. Proposals will be evaluated based solely on the following criteria:

Criteria

(a) Weight

(b) Score (0-3)

(a) x (b) Weighted

Score

Corporate Background and Experience 15

Project Understanding 20

Project Approach 25

Team Firm, Experience, and Qualifications 40

Final Score

Score Points 0- Missing or Does Not Meet Expectation 2- Meets Expectation 1- Partially Meets Expectation 3- Exceeds Expectation

3.2 Final Selection

Proposals will be reviewed after opening and will be ranked in order of choice, at which point contract negotiations will begin with the most qualified firm. If negotiations are unsuccessful, the Town will then pursue negotiations with the next most qualified firm.

The Town shall not be bound or in any way obligated until both parties have executed a contract. The Town also reserves the right to delay the award of a contract or to not award a contract.

The general conditions and specifications of the RFQ, including the Contractor’s fee proposal, and/or written correspondence applicable to the RFQ, may become part of the contract documents. Failure of the awarded Contractor to perform as represented may result in contract cancellation.

3.3 Notice to Proposers

It shall be the Proposer’s responsibility to read the Instructions, all relevant exhibits and attachments, and any other components made a part of this RFQ, and to comply with all requirements and specifications provided herein. Proposers are responsible for obtaining and complying with all Addenda and other changes that may be issued in connection with this RFQ.

4 SCOPE OF SERVICES

Awarded Contractor shall provide all services as set forth in this request for qualifications, and more particularly as described in this Section 4.

The Town of Cary Public Works Department wants statements of qualifications from licensed professional engineering firms. The selected firm (the “Professional”) will provide mechanical engineering services for assessing and replacing heating, ventilation, and air conditioning (HVAC) equipment at several Town facilities.

The project covers the following equipment:

Facility Equipment Town Hall Building A Boiler #1, Boiler #2, Chiller Town Hall Building B Boiler #1, Boiler #2, Large Chiller, Small

Chiller Town Hall Building C Boiler #1, Boiler #2, Chiller Town Hall Building D Mini Split #2, Data Aire unit Herbert C. Young Community Center Boiler Cary Senior Center Boiler, Rooftop Unit (AHU-8)

The goal of this project is to replace aging equipment so the HVAC systems at these Town facilities stay reliable, energy-efficient, and code-compliant, keeping building occupants, staff, and the public comfortable and safe.

4.1 Pre-design and Existing Conditions Assessment

The Professional will establish schedules and agendas for pre-design meetings, including a project kick-off meeting, with Cary project staff to understand and address needs and concerns for the replacement of the listed equipment. Before field work begins, the Professional will review the Town’s 2020 Facility Condition Assessment, available as-built drawings, maintenance records, and building automation system (BAS) trend data.

The Professional will perform a field assessment of each facility and its listed equipment.

Items to address in the assessment and pre-design meetings include:

• Condition, capacity, and remaining useful life of the existing equipment and the systems it serves, including pumps, piping, air handlers, controls, flues, and venting.

• Current and proposed code and regulatory requirements and Cary policies, including the North Carolina State Building, Mechanical, Fuel Gas, and Energy Conservation Codes and applicable ASHRAE standards (15, 62.1, and 90.1).

• Load verification and right-sizing of replacement equipment, including redundancy needs for the Town Hall chiller and boiler plants and for critical cooling serving the Town Hall Building D Data Aire unit.

• Electrical service capacity, structural support (including the Cary Senior Center rooftop unit AHU-8), and rigging and access routes for removal and setting of equipment.

• Integration of new equipment with the existing BAS and controls.

• Refrigerant recovery and disposal, removal and disposal of existing equipment, and identification of hazardous materials that may be disturbed, such as asbestos-containing insulation on boilers and piping.

• Construction phasing to maintain heating and cooling in occupied buildings, including seasonal work windows and temporary heating or cooling where needed.

4.2 Preliminary Design Report

The Professional will prepare a Preliminary Design Report (approximately 30% design) to clarify and document the results of the assessment and pre-design meetings, for project staff review and approval. This report will fully document and clarify all assumptions upon which the final design will be based. Project staff will have the opportunity to comment on this report and approve it prior to proceeding with final design.

The Preliminary Design Report will include:

• Replacement options for each facility, evaluated for energy efficiency, lifecycle cost, reliability, maintainability, and long-term operating needs, with a recommended option.

• A preliminary Total Project Cost Estimate as described in Section 4.2.3 of the attached agreement, to be used for budget purposes. It will be detailed enough that the costs of each facility and each major piece of equipment are identified, so the Town may consider phased or prioritized funding.

• A recommended construction phasing plan and schedule.

• A listing of all permits, approvals, inspections, third-party utility coordination (such as gas service changes), and regulatory requirements necessary for construction and operation.

• Identification of available utility incentives or rebates.

4.3 Final Design

Final design meetings shall be held between the Professional and Cary project staff. The Professional will provide recommendations for the required number of meetings to ensure the recommended schedule is followed and regular progress is reported. Information will be provided to Cary staff prior to each meeting for project staff to review and comment.

Plans, specifications, and an updated Total Project Cost Estimate shall be provided at the 60% and 100% design milestones. Complete plans and specifications shall also be provided prior to advertising for bids for Cary project staff review and approval to confirm that all requirements for bidding have been met. The Professional shall be responsible for providing suitable quantities of all review documents.

The Professional shall utilize the Town’s standard “front-end” construction documents, including general, supplementary, and special conditions, construction administration forms, bid proposals, and owner-contractor agreements.

Construction documents shall include:

• Mechanical, electrical, plumbing, controls, and any structural design required for the replacement work.

• Demolition, refrigerant handling, and disposal requirements.

• Phasing and temporary heating and cooling requirements.

• Testing, adjusting, and balancing (TAB), equipment startup, and commissioning requirements.

• Requirements for owner training, operation and maintenance (O&M) manuals, warranties, and equipment data submittals in a format compatible with the Town’s asset management system, AssetOptics.

The Professional shall be responsible for providing all information, documents, and design revisions necessary to obtain all permits and approvals associated with the project, and shall coordinate with utility providers (power, gas, etc.) on any service changes required.

A final estimate for the construction price of the improvements shall be provided to the Town prior to bidding the project.

Funding will be approved through Final Design. Additional services that should be addressed in the RFQ response are as follows:

4.4 Bidding

Upon completion and approval of the final plans and specifications, and once all necessary permits and approvals have been obtained, the project shall be publicly bid in accordance with North Carolina public bidding statutes. The Professional shall supply bid documents to bidders, maintain a plan-holders list, conduct a pre-bid conference and site walkthrough of each facility, answer contractor and supplier questions, and issue any necessary addenda. The bid opening shall be held at a Cary-owned facility as arranged by Cary. A certified bid tabulation and final recommendation for award shall be provided by the Professional. The Professional is required to check bidder qualifications prior to issuance of the award recommendation.

4.5 Construction Administration

The Professional shall provide construction administration services including submittal review, design clarifications, responses to requests for information (RFIs), field orders, negotiation and preparation of change orders, and construction schedule monitoring and evaluation. The Professional shall attend regular on-site progress meetings with the contractor(s) and Cary project staff to discuss project status and schedule adherence, and shall coordinate with building occupants and facility staff to minimize disruption during equipment outages and changeovers.

The Professional shall maintain submittal, RFI, supplemental information, and change item logs, tracking the progress and resolution of each, and shall:

a) maintain a submittal log; review and stamp each submittal and return it to the contractor;

b) maintain an RFI log; review and respond to each RFI;

c) verify all quantities and review and coordinate all payment applications with the contractor(s);

d) sign off on payment applications and forward copies to the Town for approval and payment processing in accordance with the contract requirements;

e) review and negotiate change orders with the contractor(s) on behalf of the Town, and receive the Town’s approval prior to notifying the contractor(s);

f) maintain one set of red-line drawings during construction noting all revisions and changes to the design drawings;

g) observe equipment startup, TAB, and commissioning, and review the associated reports;

h) notify the contractor of any observed safety problems or OSHA violations and issue “stop work” orders until the problem or violation has been corrected.

4.6 Closeout and Asset Integration

The Professional shall be responsible for the final punch list and follow-up to confirm that the work is completed according to codes, plans, and specifications. The Professional shall review the contractor’s close-out documents, including O&M manuals, warranties, TAB reports, and training records, and shall provide record drawings. The Professional shall also deliver equipment and asset data (make, model, serial number, capacity, installation date, warranty, and location) in a format suitable for loading into AssetOptics.

The Town will select a firm based on qualifications, as North Carolina’s Mini-Brooks Act requires (G.S. 143-64.31).

5 EXECUTION OF PROPOSAL

By submitting this proposal, the potential contractor certifies the following:

• This proposal is signed by an authorized representative of the Firm.

• The potential contractor has read and understands the conditions set forth in this RFQ to include any addenda and all attached exhibits and agrees to them with no exceptions.

Signature:

Printed Name:

Title:

Date:

APPENDIX I

References

Offeror must supply at least (3) three Governmental Agency or Private Company references for which (TYPE) services have been performed during the past (5) five years. Offerors are cautioned to provide accurate reference information. References will be checked during evaluation period.

OFFEROR:

CITY, STATE, ZIP:

Reference #1

Agency or Firm Name:

Business Address

City: State: Zip Code:

Phone Number: ( ) Fax Number: ( )

Email Address:

Reference #2

Business Address

City: State: Zip Code:

Reference #3

Business Address

City: State: Zip Code:

Reference #4

Agency or Firm Name:

Business Address

City: State: Zip Code:

Reference #5

Business Address

City: State: Zip Code:

APPENDIX II

Hourly Rate Schedule

Awarded Contractor shall perform the services to be performed as set forth in this RFQ and more particularly described in Section 5 utilizing the following hourly rate schedule below.

Position Title Hourly Rate

Firm Name:

Authorized Signature: Date

Signed by:

[Type or Print Name]

Title of Signer:

AGREEMENT FOR PROFESSIONAL SERVICES

By and Between

THE TOWN OF CARY, as OWNER, and dated as of

TABLE OF CONTENTS

1. Scope of Services

2. Definitions

3. Responsibilities of the DESIGNER

3.1 Standard of Care

3.2 DESIGNER’s Consultants

4. Basic Services

4.1 Commencement of Basic Services

4.2 Total Project Cost Estimates and Total Project Cost

4.3 Basic Services

4.4 Contractor Documentation

5. Additional Services

6. Duration of DESIGNER’s Services

6.1 Scheduling of Services

6.2 Adjustments to the Schedule

7. DESIGNER’s Compensation

7.1 Compensation For Basic Services

7.2 Compensation For Additional Services

7.3 Reimbursable Expenses

7.4 Accounting Records

7.5 Total Fixed Fee

8. Responsibilities of the OWNER

8.1 Cooperation and Coordination

8.2 Surveys and Testing

8.3 Permits and Approvals

9. Insurance

9.1 General Requirements

9.2 Limits of Coverage

9.3 OWNER’s Insurance Option

10. Damages and Remedies

10.1 Services, Reimbursement and Deductions

10.2 Indemnities

10.3 Non-Exclusivity of OWNER’s Remedies

10.4 Remedies Not Waived

10.5 Waiver of Damages

11. Amendments to the Agreement

11.1 Changes in Basic Services

11.2 OWNER Changes

12. Termination and Suspension

12.1 Termination for Convenience of the OWNER

12.2 Other Termination

12.3 Compensation After Termination

12.4 Survival

12.5 Suspension

13. Ownership of Documents

13.1 OWNER’s Ownership of Documents

13.2 Termination

13.3 Other Projects

13.4 Incorporation of Provision in all Contracts

14. Additional Provisions

14.1 Confidentiality

14.2 Dissemination of Information

14.3 Limitation and Assignment

14.4 Governing Law

14.5 Dispute Resolution

14.6 Extent of Agreement

14.7 Severability

14.8 Resolving Discrepancies

14.9 Conduct

14.10 Gifts and Favors

14.11 Data, Designs, Drawings, Memoranda, Etc.: Protocol

14.12 Compliance

14.13 Public Records

14.14 Notice

14.15 No Third Party Beneficiaries

14.16 Independent Contractor

14.17 Nondiscrimination

14.18 Pre-Audit Requirement

14.19 Performance of Government Functions

14.20 Principles of Interpretation and Definitions

14.21 Further Assurances

14.22 No Waiver of Qualified Immunity

14.23 Federal Funds

14.24 Emergencies

14.25 Electronic Signatures

14.26 List of Attachments

ATTACHMENTS

Attachment A -- Description of the Project

Attachment B -- Key Milestone Listing

Attachment C -- Consultants and Key Personnel

Attachment D -- Basic Services

Attachment E -- Additional Services

Attachment F -- Additional Services Hourly Rates Schedule

Attachment G -- Format of Total Project Cost Estimates

Attachment H -- Insurance Certificate v.9.26.22

AGREEMENT FOR PROFESSIONAL SERVICES

This Agreement, made by and between the Town of Cary (hereinafter, the "OWNER") and

, a professional [engineering] firm with a partner or principal registered in

North Carolina as a licensed architect and with offices in North Carolina (hereinafter, the

"DESIGNER").

WITNESSETH

That the OWNER and DESIGNER, for the consideration herein named, do hereby agree as follows:

ARTICLE 1

SCOPE OF SERVICES

1.1 This Agreement is for professional [engineering] services to be rendered by DESIGNER to OWNER with respect to the project known as Town Facilities HVAC Renewal, located in the Town of Cary, North Carolina, and generally consisting of engineering, design, construction drawings and specifications. The DESIGNER is responsible for performing certain portions of the project, as more particularly described in Section 2.37 and

Attachment A.

1.2 By its execution of this Agreement, the DESIGNER represents and agrees that it is qualified and fully capable to perform and provide the professional [engineering] services and other services required or necessary under this Agreement in a fully competent, professional and timely manner.

1.3 The services to be performed under this Agreement consist of Basic Services (hereinafter defined) and such Additional Services (hereinafter defined) as may be designated in Article

5 of this Agreement or as may from time-to-time be agreed upon by the OWNER and

DESIGNER by Written Amendment. All services performed by the DESIGNER not identified as Additional Services in Attachment E or in a Written Amendment shall be deemed to be Basic Services that are to be provided without additional compensation.

1.4 The Compensation for Basic Services shall be paid in accordance with Section 7.1.

Compensation for Additional Services shall be as described for such services in Section 7.2 and Attachment G, or as set forth in a Written Amendment regarding such services.

1.5 The Town’s Request for Qualifications, entitled

and dated , and the DESIGNER’s Proposal dated are hereby incorporated into the description of Basic Services by reference. Discrepancies between this Agreement, the

Request for Qualifications, and the DESIGNER’s Proposal shall be resolved as provided in Section 14.8.

1.6 Time is of the essence as to this Agreement.

ARTICLE 2

DEFINITIONS

2.1 Addenda. Written or graphic instruments issued prior to the opening of Bids which clarify, correct, or change the Bidding Requirements or the Construction Contract Documents.

2.2 Additional Services. Those services that may be provided by the DESIGNER in connection with the Project for additional compensation, as described in Article 5, Attachment E and

Attachment G.

2.3 Agreement. This agreement between the OWNER and DESIGNER concerning the

DESIGNER’s Services to be provided to the OWNER. The Agreement establishes the rights and obligations of the OWNER and DESIGNER in connection with the Project. The

Agreement includes all Attachments hereto, the Request for Proposals and the subsequent

Proposal submitted by the DESIGNER, and any Written Amendments.

2.4 Application for Payment. The form that is to be used by a Contractor during the course of the Work in requesting progress or final payments and which is to be accompanied by such supporting documentation as is required by the Construction Contract Documents.

2.5 Basic Services. Those professional services required to be provided by the DESIGNER in connection with the Project that are described in Attachment D and designated therein as services that are to be provided by DESIGNER under this Agreement.

2.6 Bid. The offer or proposal of a bidder submitted on the prescribed form setting forth the prices for the Work to be performed.

2.7 Bidding and Construction Contract Award Phase. See Attachment D for this definition.

2.8 Bidding Documents. The Bidding Requirements and the proposed Construction Contract

Documents (including all Addenda issued prior to receipt of Bids).

2.9 Bidding Requirements. The Advertisement or Invitation to Bid, Instructions to Bidders, Bid security form, if any, and the Bid form with any Addenda.

2.10 Certificate of Final Completion. Certificate issued by the OWNER when the Work has been completed in accordance with the Construction Contract Documents and the OWNER has received all documents and items necessary for closeout of the Work.

2.11 Change Order. A document recommended by the DESIGNER that is signed by a Contractor and OWNER and authorizes an addition, deletion, or revision in the Work or an adjustment in a Construction Contract Price or Construction Contract Time, issued on or after the effective date of the Construction Contract.

2.12 Claim. A demand or assertion by OWNER or a Contractor seeking an adjustment of a

Construction Contract Price or Construction Contract Times, or both, or other relief with respect to the terms of the Contract. A demand for money or services by a third party is not a Claim.

2.13 Compensation for Additional Services. All compensation due DESIGNER from OWNER for Additional Services, to be calculated and paid in accordance with Section 7.2 and

Attachment G.

2.14 Compensation for Basic Services. All compensation due DESIGNER from OWNER for all services under this Agreement except for Compensation for Additional Services and

Reimbursable Expenses, if any.

2.15 Construction Administration Phase. See Attachment D for this definition.

2.16 Construction Contract. The written instrument that is evidence of an agreement between the

OWNER and a Contractor covering the Work.

2.17 Construction Contract Documents. The documents that establish the rights and obligations of the OWNER and Contractor and include the Construction Contract, the Bidding

Requirements, the Bidding Documents, the Addenda (that pertain to the Construction

Contract Documents), the Contractor’s Bid (including documentation accompanying the Bid and any post Bid documentation submitted prior to the Notice of Award) when attached as an exhibit to the Construction Contract, the Notice to Proceed, the Bonds, the General

Conditions, the Supplementary Conditions and any Special Conditions, the Specifications and the Drawings as the same are more specifically identified in the Construction Contract, together with all Written Amendments, Change Orders, Work Change Directives, Field

Orders, and DESIGNER’s written interpretations and clarifications issued on or after the

Effective Date of the Construction Contract. Approved Shop Drawings and the reports and drawings of subsurface and physical conditions are not Construction Contract Documents.

Only printed or hard copies of the items listed in this paragraph are Construction Contract

Documents. Files in electronic media format of text, data, graphics, and the like that may be furnished by OWNER to Contractor are not Construction Contract Documents.

2.18 Construction Contract Documents Phase. See Attachment D for this definition.

2.19 Construction Contract Price. The moneys payable by OWNER to a Contractor for completion of the Work in accordance with Construction Contract Documents.

2.20 Construction Contract Times. The number of days or the dates stated in the Construction

Contract Documents to: (i) achieve Milestones, if any, (ii) achieve Substantial Completion;

and (iii) complete the Work so that it is ready for final payment as evidenced by

DESIGNER’s written recommendation of final payment.

2.21 Contractor. An individual or entity engaged directly by the OWNER pursuant to a

Construction Contract. The term “Contractor” includes the terms “Subcontractor” and

“Supplier” and the Contractor’s, Subcontractor’s and Supplier’s successors, assigns, employees, agents, consultants and other representatives and anyone for whose acts a

Contractor, Subcontractor or Supplier is legally liable.

2.22 Design Development Phase. See Attachment D for this definition.

2.23 DESIGNER. The individual or entity named as such in the Agreement. The term

“DESIGNER” means the DESIGNER and the DESIGNER’s Consultants and their successors, assigns, employees, agents, consultants and other representatives and anyone for whose acts the DESIGNER is legally liable.

2.24 DESIGNER’s Consultants. Any individuals or entities having a contract with DESIGNER to furnish services as DESIGNER’s independent professional associate or consultant with respect to the Project. See Section 3.2.1 and Attachment C for specific provisions regarding and identification of DESIGNER’s Consultants.

2.25 DESIGNER’s Services. The professional services and other services required or necessary under this Agreement, consisting of Basic Services and such Additional Services as are agreed upon by the OWNER and DESIGNER by Written Amendment or otherwise in accordance with this Agreement.

2.26 Drawings. That part of the Construction Contract Documents prepared or approved by

DESIGNER which graphically shows the scope, extent, and character of the Work to be performed by Contractor. Shop Drawings and other Contractor submittals are not Drawings hereunder.

2.27 Effective Date of the Agreement. The date of delivery to the DESIGNER from the OWNER of a fully executed original of this Agreement. The DESIGNER is to submit its executed counterpart of this Agreement to the OWNER, and this Agreement will be fully executed upon the OWNER’s counterpart being executed by the Town Manager or the Mayor (or another individual executing the counterpart on behalf of the OWNER after having been duly appointed to do so by the OWNER).

2.28 Field Order. A written order issued by DESIGNER that requires minor changes in the Work but that does not involve a change in the Construction Contract Price or the Construction

Contract Times.

2.29 General Conditions. That part of the Construction Contract Documents that supplements a Construction Contract and that describes the rights, responsibilities and relationships of the OWNER, DESIGNER and Contractor.

2.30 Key Milestone Listing. The list of the sequence and timing of the design and construction activities. See Section 6.1 and Attachment B.

2.31 Laws and Regulations. Any and all applicable laws, rules, regulations, ordinances, codes, and orders of any and all governmental bodies, agencies, authorities, and courts having jurisdiction over the Project.

2.32 Milestone Dates. The dates set forth in the Key Milestone Listing.

2.33 OWNER. The Town of Cary, a municipal corporation in North Carolina, and its successors and assigns, and the party for whom the DESIGNER’s Services are to be performed. The term “OWNER” means the OWNER and the OWNER’s Representative.

2.34 OWNER’s Representative. The OWNER’s Representative is BoDean Norris, Project

Manager . The Owner’s Representative may be an employee, agent or other representative of the Owner, and may be an individual or any one of several identified individuals, or a committee or entity, in which case the committee or entity shall select one or more individuals to speak and act on its behalf and on behalf of the Owner. The OWNER’s

Representative shall have the express authority to bind the OWNER with respect to all matters requiring the OWNER’s approval or authorization. Except as otherwise specifically stated, the DESIGNER does not have such authority.

2.35 Post-Construction Phase. See Attachment D for this definition.

2.36 Preliminary or Schematic Design Phase. See Attachment D for this definition.

2.37 Project. The following phases of the Project that is to be undertaken in connection with this

Agreement that are designated in Attachment D as phases in which the DESIGNER is to provide services to the OWNER: the Schematic Design Phase, the Design Development

Phase, the Construction Contract Document Phase, the Bidding and Construction Contract

Award Phase, the Construction Administration Phase and the Post-Construction Phase. The

Project may be enlarged to include Additional Services through Written Amendments or as otherwise allowed herein.

2.38 Project Manual. The bound documentary information prepared for bidding and constructing the Work and includes the Advertisement for Bids, Instructions to Bidders, Bid Forms, Agreements, Bonds, General Conditions, Supplementary Conditions, Special Conditions, Specifications, and Appendices.

2.39 Reimbursable Expenses. If there are expenses that are to be separately reimbursable by

OWNER to DESIGNER under this Agreement, they will be specified as such in Section

7.3 hereof. Unless expenses are specifically designated or described herein as separately reimbursable, expenses of DESIGNER in performing DESIGNER’s Services hereunder shall be deemed compensated by the Compensation for Basic Services and/or the

Compensation for Additional Services (if any).

2.40 Request for Qualifications. The invitation for a professional services firm, typically with a partner or principal registered in North Carolina as a licensed architect, engineer or landscape architect and with offices in North Carolina, to bid on the right to supply

DESIGNER services to the Town of Cary. The specific Request for Proposals made in connection with the making of this Agreement is specified in Section 1.5 hereof.

2.41 Samples. Physical examples of materials, equipment, or workmanship that are representative of some portion of the Work and which establish the standards by which such portion of the

Work will be judged.

2.42 Shop Drawings. All drawings, diagrams, illustrations, schedules, and other data or information which are specifically prepared or assembled by or for a Contractor and submitted by Contractor to illustrate some portion of the Work.

2.43 Site. The lands or areas that will be indicated in the Construction Contract Documents as being furnished by OWNER, upon which the Work is to be performed, including rights-of-way and easements for access thereto, and such other lands furnished by OWNER that are designated for the use of Contractor. The Site may not be specifically identified until after the Effective Date of this Agreement, but shall be specified in the Construction Contract

Documents, and reference herein to the “Site” shall mean such areas once determined and specified.

2.44 Specifications. That part of the Construction Contract Documents consisting of written technical descriptions of materials, equipment, systems, standards, and workmanship as applied to the Work and certain administrative details applicable thereto. Specifications include all Sections included under the Technical specifications of the Project Manual.

2.45 Subcontractor. An individual or entity having a direct contract with Contractor or with any other Subcontractor for the performance of a part of the Work on the Project.

2.46 Substantial Completion. The time at which the Work (or a specified part thereof) has progressed to the point where, in the opinion of the DESIGNER and with the approval of the

OWNER the Work (or a specified part thereof) is sufficiently complete, in accordance with the Construction Contract Documents, so that the Work (or a specified part thereof) can be utilized for the purposes for which it is intended. The OWNER’s receipt of all certificates of occupancy applicable to the Project is a condition precedent to the Work being deemed

“Substantially Complete.” The terms “substantially complete” and “substantially completed” as applied to all or part of the Work refer to Substantial Completion thereof.

2.47 Supplementary Conditions. That part of the Construction Contract Documents that amends or supplements the General Conditions.

2.47 Special Conditions. That part of the Construction Contract Documents that amends or supplements the Supplementary Conditions.

2.48 Supplier. A manufacturer, fabricator, supplier, distributor, materialman, or vendor having a direct contract with a Contractor or Subcontractor to furnish materials or equipment to be incorporated in the Work by a Contractor or Subcontractor.

2.49 Total Project Cost; Total Project Cost Estimate. The “Total Project Cost Estimate” is an estimate of the total cost of the Project developed in accordance with Section 4.2 and

Attachment H. The “Total Project Cost” is the Total Project Cost Estimate that is approved by the OWNER in accordance with Section 4.2.

2.50 Utilities Infrastructure. All underground or above-ground pipelines, conduits, ducts, cables, wires, manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any encasements containing such facilities, including those that convey electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or other control systems.

2.51 Work. The entire completed construction or the various separately identifiable parts thereof required to be provided to the OWNER under the Construction Contract Documents by parties other than the DESIGNER. The Work includes and is the result of performing or providing all labor, services, and documentation necessary or appropriate to produce such construction, and furnishing, installing, and incorporating all necessary or appropriate materials and equipment into such construction, all as more specifically described in the

Construction Contract Documents.

2.52 Written Amendment. A written statement modifying the Agreement, signed by OWNER and DESIGNER on or after the Effective Date of the Agreement.

ARTICLE 3

RESPONSIBILITIES OF THE DESIGNER

3.1 Standard of Care

3.1.1 The DESIGNER shall exercise reasonable care and diligence in performing the

DESIGNER’s Services under this Agreement in accordance with generally accepted standards of [engineering] practice throughout the United States and in accordance with all

Laws and Regulations. The DESIGNER shall serve as a representative of the OWNER in accordance with the terms and conditions of this Agreement to guard the OWNER against defects and deficiencies in the Work.

3.1.2 The DESIGNER shall be responsible for all errors or omissions in the Drawings, Specifications, and other documents prepared by the DESIGNER. It shall be the responsibility of the DESIGNER throughout the period of performance under this

Agreement to use reasonable professional care and judgment to guard the OWNER against defects and deficiencies in the Work.

3.1.3 The DESIGNER shall assure that all Drawings, Specifications and other documents prepared by the DESIGNER or the DESIGNER’s Consultants hereunder are in accordance with all Laws and Regulations and that all necessary or appropriate applications for approvals are submitted to federal, state and local governments or agencies in a timely manner so as not to delay the design or construction activities of the Project.

3.1.4 The DESIGNER shall correct at no additional cost to the OWNER any and all errors, omissions, discrepancies, ambiguities, mistakes or conflicts in the Drawings, Specifications and other documents prepared by the DESIGNER or DESIGNER’s

Consultants.

3.1.5 In addition to any other damages that might be due to OWNER hereunder in connection with the breach of this Agreement by DESIGNER, DESIGNER shall reimburse

OWNER, as described in Article 10 hereof, for costs, damages and expenses that are the result of errors, omissions or delays of the DESIGNER or the DESIGNER’s Consultants.

3.1.6 The DESIGNER shall perform the DESIGNER’s Services in a timely manner in accordance with all schedules for the Project and the Construction Contract Documents.

3.1.7 If the DESGINER’s key project personnel are listed in Attachment C to this agreement no changes in the DESIGNER’s key personnel indicated shall be permitted except with the prior written consent of the OWNER.

3.2 DESIGNER’s Consultants.

3.2.1 The DESIGNER’s Consultants for the project, along with their key project personnel, are listed in Attachment C to this Agreement. No changes in the consultants or key personnel indicated shall be permitted except with the prior written consent of the

OWNER, which consent shall not be unreasonably withheld.

3.2.2 All of the DESIGNER’s contracts with the DESIGNER’s Consultants shall be in writing and shall expressly provide that if this Agreement is terminated for any reason, the

OWNER may, at its sole option, take the assignment of the DESIGNER’s Consultants’ contracts with the DESIGNER, that such assignment shall automatically take place upon notification in writing by the OWNER to the DESIGNER’s Consultants and the

DESIGNER’s Consultants shall continue to be bound by their contract after such assignment. A copy of each contract between the DESIGNER and a DESIGNER’s

Consultant shall be furnished to the OWNER within seven (7) days of its execution.

ARTICLE 4

BASIC SERVICES

4.1 Commencement of Basic Services. The DESIGNER’s Basic Services shall commence upon the occurrence of the Effective Date of the Agreement and DESIGNER’s receipt of a

Notice to Proceed from OWNER.

4.2 Total Project Cost Estimates and Total Project Cost.

4.2.1 At the times designated herein, the DESIGNER shall develop a Total Project Cost

Estimate, including the DESIGNER’s fees, costs of the construction, costs of equipment, furnishings, furniture and signage, permit fees and appropriate contingencies. These costs shall be prepared and submitted to the OWNER, with supporting documents listing quantities, unit price, labor rates, man-hour estimates, overhead and profit.

4.2.2 The Total Project Cost Estimates shall be prepared by a qualified cost estimating consultant to the DESIGNER that is acceptable to the OWNER.

4.2.3 The Total Project Cost Estimates shall be prepared/revised at three points in the performance of the DESIGNER’s services: (1) at completion 30% of the Preliminary or

Schematic Design Phase; (2) at 60% completion of the Design Development Phase; and (3) at completion of 100% of the Construction Contract Documents Phase.

4.2.4 When the first…