SANDIEGO(SAN)
MEDIUMAPPROACHLIGHTINGSYSTEM(MALS)

DIRECT BORE INSTALLATION

CONSTRUCTION SPECIFICATION

For

RUNWAY27
MEDIUMAPPROACHLIGHTINGSYSTEM

at

SAN DIEGO INTERNATIONAL AIRPORT

in

SAN DIEGO, CALIFORNIA

September 07, 2019

Preparedby:
FEDERALAVIATIONADMINISTRATION
AirTrafficOrganization
TechnicalOperationsUnit
WesternServiceArea
EngineeringServices
NavaidsEngineeringCenter–LosAngeles
SANDIEGO(SAN)
MEDIUMAPPROACHLIGHTINGSYSTEM–RUNWAY27

SAN DIEGO, CALIFORNIA

ii

TableofContents
DIVISION1SUMMARYOFWORK.....................................................................................................................1
SECTION01010.........................................................................................................................................................1
SUMMARYOFWORK..............................................................................................................................................1
PART1 GENERAL...........................................................................................................................................1
1.1ScopeofWork................................................................................................................................................1
1.2References.......................................................................................................................................................2
1.3Drawings..........................................................................................................................................................2
1.3.1ConstructionDrawingsProvided......................................................................................................2
1.3.2As‐BuiltDrawings....................................................................................................................................2
1.4Submittal.........................................................................................................................................................2
1.4.1Material........................................................................................................................................................2
1.4.2Schedule......................................................................................................................................................2
1.4.3ScheduleofValues..................................................................................................................................3
1.4.4SafetyPlan...................................................................................................................................................3
1.4.5WorkPlan....................................................................................................................................................3
1.4.6Testing...........................................................................................................................................................3
PART2 PRODUCTS........................................................................................................................................4
2.1GovernmentFurnishedMaterial...........................................................................................................4
2.1.1InventoryandInspectionofGFM......................................................................................................4
2.2contractorFurnishedMaterial...............................................................................................................4
2.3Material............................................................................................................................................................5
2.3.1ExternalHardware..................................................................................................................................5
2.3.2GalvanizedRigidMetalConduit(GRMC).......................................................................................5
2.3.3Anti‐oxidantCompound........................................................................................................................5
2.3.4AsbestosFreeMaterial..........................................................................................................................5
PART3 EXECUTION......................................................................................................................................5
3.1Schedule...........................................................................................................................................................5
3.1.1WorkSchedule...........................................................................................................................................5
3.1.2ConstructionSchedule...........................................................................................................................5
3.1.3WeeklyLookAheadWorkSchedule................................................................................................6
3.1.4DeviationfromWorkSchedule..........................................................................................................6
3.1.5DailyConstructionLog...........................................................................................................................6
3.2Pre‐ConstructionMeeting........................................................................................................................6
3.3Layout...............................................................................................................................................................6
3.4SpecialRequirements.................................................................................................................................7
3.4.1SpecialPrecautions..................................................................................................................................7
3.4.2SafetyRequirements...............................................................................................................................7
3.4.2.1RunwaySafetyArea.............................................................................................................................7
3.4.2.2ApproachSurface..................................................................................................................................7
3.4.2.3ConstructionVehicleTraffic............................................................................................................8
3.4.2.4UnauthorizedStructures...................................................................................................................8
3.4.2.5HazardMarking.....................................................................................................................................8
SANDIEGO(SAN)
MEDIUMAPPROACHLIGHTINGSYSTEM–RUNWAY27

SAN DIEGO, CALIFORNIA

iiii

3.4.2.6SafetyPlan...............................................................................................................................................8
3.4.3RadioCommunications..........................................................................................................................9
3.4.4WorkLimitations......................................................................................................................................9
3.4.4.1Trenches,Holes,andExcavations.................................................................................................9
3.4.4.2Displaced/RelocatedThreshold.....................................................................................................9
a)DisplacedThreshold....................................................................................................................................9
b)RelocatedThreshold....................................................................................................................................9
3.4.5WorkPlan.................................................................................................................................................10
3.5ProtectionofExistingUtilitiesandCables.....................................................................................10
3.6InstallationandWorkmanship...........................................................................................................10
3.7TemporaryFacilities................................................................................................................................11
3.7.1TemporaryWater..................................................................................................................................11
3.7.2TemporaryToiletsandSanitation.................................................................................................11
3.8SecurityRequirements...........................................................................................................................11
3.9Safety..............................................................................................................................................................12
3.10Sedimentation,Erosion,AndDustControl.................................................................................12
3.11DebrisControlAndClean‐Up............................................................................................................12
3.12Inspection&Acceptance.....................................................................................................................12
DIVISION2SITEWORK......................................................................................................................................14
SECTION02011......................................................................................................................................................14
DIRECTIONALBORING.......................................................................................................................................14
PART1–GENERAL..........................................................................................................................................14
1.1WorkIncluded............................................................................................................................................14
1.2Definitions....................................................................................................................................................14
1.3Submittals.....................................................................................................................................................14
1.4QualityAssurance.....................................................................................................................................15
1.4.1General.......................................................................................................................................................15
1.4.2ProductTesting......................................................................................................................................15
1.4.3JointTestingMethods..........................................................................................................................15
1.4.4FailedBorePath.....................................................................................................................................16
1.5SiteConditions...........................................................................................................................................16
PART2‐PRODUCTS........................................................................................................................................16
2.1General...........................................................................................................................................................16
2.2ConduitMaterials......................................................................................................................................16
2.3BoreHoleDiameter..................................................................................................................................17
2.4DrillingFluids.............................................................................................................................................17
2.5EquipmentRequirements.....................................................................................................................17
2.6Thrust/PullbackRequirements..........................................................................................................17
PART3‐EXECUTION......................................................................................................................................18
3.1SitePreparation.........................................................................................................................................18
3.2DamagedRestoration..............................................................................................................................18
3.3ProductLocatingandTracking...........................................................................................................18
3.4Execution......................................................................................................................................................20
3.5DocumentationRequirements............................................................................................................21
SANDIEGO(SAN)
MEDIUMAPPROACHLIGHTINGSYSTEM–RUNWAY27

SAN DIEGO, CALIFORNIA

DIVISION 1 SUMMARY OF WORK

SECTION 01010

SUMMARY OF WORK

PART 1 GENERAL

1.1 Scope of Work

Thescopeofworkunderthisspecificationprovidesforallworkrequiredfortheinstallationof
undergroundconduitinsupportoftherunway27MediumApproachLightingSystem(SAN‐MALS)
ReplacementProjectatSanDiegoInternationalAirport,inSanDiego,California.Thecontractoris
requiredtofurnishlabor,materials(exceptGovernmentFurnishedMaterials(GFM)),equipment,
constructionmethods,procedures,documents,incidentals,insurance,bonds,securitynotifications,
licenses,permitsnecessaryfortheinstallationofundergroundconduitusinganunderground
electronicsteerableboringsystem,alsocommonlycalledHorizontalDirectionDrilling(HDD).The
boringtoolshallbeelectronicallytrackableandsteerabletoavoidundergroundobstaclesand
existingutilities.Uponcompletionofboringandinstallationofconduit,thecontractorshallremove
allspoilsfromthestartingandterminationpits.Thepitsshallberestoredtotheiroriginal

conditions.

Work includes, but is not limited to the following:

A. Install conduits utlizing HDD under the airport access road and Taxiway B as shown on drawing

SAN‐D‐MALS27‐1X.Thelengthoftheboreisapproximately704feet.
B. Thedirectionalboreshallincludeinstallationofeleven(11)3”diameterHigh‐Density

Polyethylene (HDPE) conduits, schedule 80 or SDR11, installed nominally 7 feet below existing grade.

C. The directional boring run shall include a #6 bare copper tracer for future locating of the buried conduit.

D. HDPEconduitshallbesmoothinside,andsmoothoutside.
E. Endsofconduitsshallbekeptsealedatalltimestopreventintrusionofdirtand/orwater.
F. Install4’x4’handholes(GFM)atbothendsoftheboreinthelocationsshownondrawingSAN‐
D‐MALS27‐1X.Notethatonehandoleisair‐craftratedandoneistraffic‐rated.Extendconduits
intothehandholes[conduitbellendandhandholefinishwork(i.e.‐grounding,rack
installation,etc.)willbedonebyothers].
Installationoftheundergroundconduitmustbecompletedwithin14calendardaysfromthedateof
NoticetoProceed(NTP).
Thedimensions,measurements,andquantityofmaterialslistedinthisspecificationandonthe
constructiondrawingsareestimatedandarepresentedtogivethecontractoranideaofthetotal
scopeofwork.Thecontractorisstronglyencouragedtomakeasitevisittoverifytheexisting
conditions,quantitiesofmaterials,andamountofworkrequired.Thecontractoris
responsibleforassuringthatthebidreflectsallworkrequiredtoaccomplishthisproject.
CoordinatesitevisitwiththeFAAProjectEngineer,CharlesDodgeat(424)405‐7531.
SANDIEGO(SAN)
MEDIUMAPPROACHLIGHTINGSYSTEM–RUNWAY27

SAN DIEGO, CALIFORNIA

1.2 References

Airport Ground Vehicle Operations Guide available from:

www.faa.gov/runwaysafety/asw/downloads/AGVO-guide.doc

1.3 Drawings

Calloutsontheconstructiondrawingsindicateworktobedoneunderthiscontractunless
specificallynoted"installedbyothers"or"existing".Calloutsindicatingworktobedonedonot
alwaysincludetheword"install".

1.3.1 Construction Drawings Provided

Drawingsapplicabletothisprojectarelistedinthedrawingset.Thewrittenscale(e.g.1”=100’)is
onlyvalidforFAA“D‐size”drawings(22”x34”)andmaybeslightlyoffduetovariationsinprinting.
Onreducedsizedrawings,thebarscales(whereshown)andwrittendimensionsremainvalid.

1.3.2 As‐Built Drawings

ThecontractorshallprovidethreecompletesetsofAs‐BuiltdrawingstotheFAAContractingOfficer
Representative(COR)attheendoftheproject.Thefollowingcolorcodesshallbeused:
Red‐toindicatedneworchangedinformation
Green‐toindicateddeletions
Blue‐toindicatenotestothedraftsman
Anyadditionaldiagramsand/orschematicsthatwouldbehelpfulforthemaintenanceofthefacility
shouldalsobeincluded.

1.4 Submittal

1.4.1 Material

Thecontractorshallsubmitforapproval;catalogdata,cut‐sheets,samples,andanyotherrelevant
informationonthecontractorfurnishedmaterialtobeusedonthisproject.Twocopiesofthe
submittalpackageshallbegiventotheFAACORforapproval.Submittalsonmaterialsshallinclude,
butisnotlimitedto:
‐ DrillingFluid(s)
‐ DrillingAdditive(s)(i.e.–bentonite)
‐ Conduit(Sch80HDPE)
‐ Electricalfittingsandcomponents
‐ AdditionalitemsdeemednecessarybytheFAACOR

1.4.2 Schedule

Priortostart,thecontractorshallsubmitascheduleandworkplantotheFAACORforapproval.
Seesection3.1.2forthedatetocompletethisproject.Thescheduleshallshowstartdates,
duration,andfinishdatesforeachworkactivity.ActivitiesshallincludeforeachCLIN,butarenot
limitedto:
SANDIEGO(SAN)
MEDIUMAPPROACHLIGHTINGSYSTEM–RUNWAY27

SAN DIEGO, CALIFORNIA

Sitelayout
Installationofconduit
Installationofhandholes
Inspectionandcleanup
TheFAAreservestherighttomodifythecontractor’ssequenceofactivitiesintheinterestoffacility
operation,airportrunwayextensionworkandairportsafety.

1.4.3 Schedule of Values

As described in the CLINs. Below are some of the major work items associated with this solicitation.

Thecontractor’sproposalshallincludeascheduleofvalues,showingataminimum,abreakdownof
costforeachworkactivitylistedintheworkschedulebelow.Costforeachitemshouldincludeany
profitandoverhead.
Mobilization(submittals,insurance,bonding,badging,etc.)$
Installationofconduit$
Installationofhandholes$
Inspection(CAI)andcleanup$
Demobilization$

1.4.4 Safety Plan

The contractor shall submit a safety plan per paragraph 3.4.2.6 of this section.

1.4.5 Work Plan

The contractor shall submit a work plan per paragraph 3.4.5 of this section.

1.4.6 Testing

Thecontractorshallcomplete,athisownexpense,alltestingasrequiredbythesespecifications.
TheresultsshallbesubmittedonapprovedFAATRDRformstotheFAACOR.Requiredtesting
includes,butisnotlimitedto,thefollowing:

‐ Soil compaction testing at handhole locations (performed by an independent testing company).

SANDIEGO(SAN)
MEDIUMAPPROACHLIGHTINGSYSTEM–RUNWAY27

SAN DIEGO, CALIFORNIA

PART 2 PRODUCTS

Referencehereinorintheconstructiondrawingstoanyspecificcommercialproduct,process,or
service,anytradename,trademark,manufacturer,orotherwise,doesnotnecessarilyconstituteor
implyitsendorsement,recommendation,orfavoringbytheFederalAviationAdministration.The
contractormaysubmitarequestforsubstitutionofaproduct,process,orservicespecificallycalled
out.Suchrequestshallbethroughthesubmittalprocess.

2.1 Government Furnished Material

Government furnished material (GFM) for this project is listed as follows:

Quantity Item Description

14’x4’Aircraft‐RatedHandhole
14’x4’Traffic‐RatedHandhole
ContactCharlesDodgeat(424)405‐7531,FAAProjectEngineer(atleast72hoursinadvance)for
coordinationofpickup.Thecontractorisresponsiblefortheloading,transportation,unloading
andstorageofGFMmaterial.

2.1.1 Inventory and Inspection of GFM

ThecontractorshallsignacopyoftheGovernmentfurnishedmaterial(GFM)listacknowledging
receiptofthefurnishedmaterial,notinganydiscrepanciesifnecessary.Whenthecontractorsigns
forcustody,heacknowledgesreceiptingoodconditionandassumesresponsibilityforany
subsequentlossordamage.ThecontractorshallreturnallGFMthatisnotinstalledtothelocation
wherethematerialwaspickedup.

2.2 contractor Furnished Material

Thecontractorshallfurnishallmaterialthatisrequiredandnototherwiseindicatedtobe
Governmentfurnished.Materialsfurnishedbythecontractorshallbenew,thestandardproducts
ofmanufacturersregularlyengagedintheproductionofsuchmaterials,andofthemanufacturer’s
latestdesignsthatcomplywiththespecificationrequirements.
Thecontractorisresponsibleformakingtheirownarraignmentsformaterialdeliveryand
receiving.ThecontractorshallnothaveanymaterialdeliveredtoanyFAAoffices.Deliverytothe
Airportaddressshallonlybedonewiththepriorapprovaloftheairportmanagement.
Thelistofcontractorfurnishedmaterialincludes,butisnotlimitedto:

‐ Drilling fluid(s)/additive(s)

‐ HDPE conduit

‐ Electrical fittings and components, as required

SANDIEGO(SAN)
MEDIUMAPPROACHLIGHTINGSYSTEM–RUNWAY27

SAN DIEGO, CALIFORNIA

2.3 Material

2.3.1 External Hardware

N/A

2.3.2 Galvanized Rigid Metal Conduit (GRMC)

N/A

2.3.3 Anti‐oxidant Compound

N/A

2.3.4 Asbestos Free Material

Thecontractorshallnotuseanyasbestoscontainingmaterial(ACM)atanytimeduringthe
construction.Thecontractorshallverifythatallmaterial,includingthosesuppliedbythirdparties,
areasbestosfreematerials.Awrittencertificationlettershallbeprovidedbythecontractortothe
FAAcertifyingthatthefinishedworkisasbestosfree.

PART 3 EXECUTION

3.1 Schedule

3.1.1 Work Schedule

Allairfieldworkshallbeperformedduringthenighthoursof0000and0530,Tuesdaythrough
Saturdaywhenrunway27isclosedforroutinemaintenance.Noworkshallbeperformedoutside
thesehoursorscheduledonSundaysorlegalholidayswithoutpriorapprovalfromtheFAACOR.
AllworkscheduledtooccurinsidetheRSAmustbeapprovedbytheFAACORandSANAirport

Manager.

WorkonthisprojectmayonlyoccurduringwintermonthsfromSeptemberuntilthemiddleof
Aprilduetothepresenceofanendangeredbirdhabitatwithintheprojectarea.
ThecontractorshallfurnishtheFAACORwithemergency(24hour)contactphonenumbersforthe
contractor’ssuperintendentandanalternateindividual.Suchnumberswillbeusedifthe
contractorneedstobecontactedoutsideofnormalworkinghours.

3.1.2 Construction Schedule

Priortostart,thecontractorshallsubmitascheduleandworkplantotheFAACORforapproval.
Thescheduleshallshowstartdates,duration,andfinishdatesforeachworkactivity.Activities
shallincludeforeachCLIN,butarenotlimitedto:
Sitelayout
Installationofconduit
Installationofhandholes
SANDIEGO(SAN)
MEDIUMAPPROACHLIGHTINGSYSTEM–RUNWAY27

SAN DIEGO, CALIFORNIA

Inspection and cleanup

TheFAAreservestherighttomodifythecontractor’ssequenceofactivitiesintheinterestoffacility
operationandairportsafety.

3.1.3 Weekly Look Ahead Work Schedule

Onaweeklybasis,thecontractorshallsubmitascheduleshowingactivitiesdesiredtobe
performedduringtheupcomingweek.TheseworkactivitiesshallbeapprovedbytheFAACOR.

3.1.4 Deviation from Work Schedule

TheAirportManagerandtheFAACORreservetherighttosuspendorstopconstructionas
necessaryforthesafetyofaircraftorairportproperty.Inaddition,theFAAmayadjustthework
hourstosatisfythefacilityoperations.

3.1.5 Daily Construction Log

The contractor shall keep a Daily Construction Log. At a minimum, the daily log shall contain:

Itemsaccomplishedforthatday
Startandstoptimeofwork
Nameofworkers(includingsub‐contractors),andhourstheyworkedforthatday
Weather(includingsky,groundmoistureconditions,andtemperature)
Materialreceived
Documentalphotographsshowingtheprogressofwork,andasrequired.

The Daily Construction Logs shall be turned over to the FAA COR on a weekly basis.

3.2 Pre‐Construction Meeting

Priortothestartofanyworkandthecontractor'saccesstotheworksite,thecontractorshallbe
requiredtoattendapre‐constructionmeeting.Attendeesatthemeetingmayinclude,butarenot
limitedto,theFAAProjectEngineer,FAACOR,FAAContractingOfficer,theAirportManager,
AirportOperations,FAAmaintenance,andotherinterestedpartiesasdeterminedbytheFAA
ProjectEngineer.Topicsatthemeetingwillinclude;siteaccess,airportsecurity,worksafety,work
schedule,projectexpectations,workprocedures,emergencyplans,andotheritemsrelatingtothe
executionoftheproject.

3.3 Layout

Thecontractorshallverifythefieldmeasurementsandcoordinatesindicatedonthedrawingswith
theFAACORbeforestartinganylayout.Thecontractorshalllayouthisworkfrombaselinesand
benchmarksindicatedonthedrawingsandshallberesponsibleforallmeasurementsinconnection
therewith.Thecontractorshallfurnish,athisownexpense,allstakes,templates,platforms,
equipment,tools,materialsandlaborasmayberequiredinlayingoutanypartofthework.All
layoutworkshallbeaccomplishedbyaStateofCaliforniaProfessionalLandSurveyor.The
contractoristoproperlymaintainthespecifiedlayoutstoassureproperalignmentofthe

construction.

SANDIEGO(SAN)
MEDIUMAPPROACHLIGHTINGSYSTEM–RUNWAY27

SAN DIEGO, CALIFORNIA

3.4 Special Requirements

3.4.1 Special Precautions

Thecontractorshallconformtotherulesandregulationsoftheairportandshallcoordinateall
workwiththeFAACOR.
Note:UnscheduledinterruptionsoftheelectricalservicetoFAAfacilitiesmaycauseaircraft
accidentsandlossoflife.Workrequiringatemporaryorpermanentde‐energizationofequipment
shallbescheduledinwritingwiththeFAACORandtheonsiteFAAmaintenancepersonnel.Only
onsiteFAAmaintenancepersonnelareauthorizedtoenergize/de‐energizeequipment,orto
operateacircuitbreaker,switch,orfuseinanFAAfacility.

3.4.2 Safety Requirements

AviationSafetyisaprimaryconsiderationduringairportconstruction.Thecontractoris
completelyresponsibleforcomplyingwiththeAirport’ssafetyandoperationprocedures,as
dictatedbytheAirport.
Duringtheperformanceofthiscontract,theairportrunways,taxiways,andaircraftparkingaprons
shallremaininusebyaircrafttothemaximumextentpossible,CONSISTENTWITHCONTINUAL
SAFETY.Thecontractorshallnotallowemployees,subcontractors,suppliers,oranyother
unauthorizedpersontoenterorremaininanyairportareawhichwouldbehazardoustopersons
ortoaircraftoperations.
Employeesviolatinganyactiverunwaysafetyareas(incursions)willbepermanentlyremovedfrom
theentireproject.

3.4.2.1 Runway Safety Area

TheRunwaySafetyArea(RSA)forRunway27extendsto250feetoneachsideoftherunway
centerline.ThecontractorshallnotbeallowedintotheRunwaySafetyAreawithoutpriorapproval
fromtheFAACORandtheAirportManager.Ingeneral,noworkersorequipmentshallbeallowed
insidethesafetyareawhenaircraftareusingtherunway.Anyworktobedoneinsidethesafety
areashallbescheduledandcloselycoordinatedwiththeFAACORandtheAirportmanager.
InadditiontotherestrictionsofworkingintheRSA,theAirportManagerand/ortheFAACORmay
imposemorerestrictiverequirementsasneededtomaintainairportsafety.

3.4.2.2 Approach Surface

Novehiclesorequipmentshallbepermittedtopenetrateanapproachsurface(extendedalongthe
runwaycenterline)50:1forILSapproach,34:1approachsurfacesforprecisionapproachrunways
and20:1fornon‐precisionapproachrunways.Theapproachsurfacesbeginattherunway
thresholdcenterlineelevationandstarts200ft.downwindfromthethreshold(orfromthelocation
oftheDisplaced/Relocatedthreshold).Thedeparturesurfacebeginsattherunwaythreshold.The
approachsurfaceforRunway27is50:1.
SANDIEGO(SAN)
MEDIUMAPPROACHLIGHTINGSYSTEM–RUNWAY27

SAN DIEGO, CALIFORNIA

3.4.2.3 Construction Vehicle Traffic

Thecontractors'vehiclesandequipmentshallentertheworksiteandconstructionareasat
approvedlocations,andbywayofauthorizedroutes.Theuseofrunways,aprons,taxiways,ramps,
willnotbepermittedunlessspecificallyapprovedbytheFAACORandtheAirportManager.The
contractorshallinformallpersonnelthataircrafthavetheright‐of‐wayatalltimes.Thecontractor
shallberesponsibleformaintainingcontrolandsecurityateachentrypoint,asapproved.
Asaminimum,allvehiclesandmotorizedequipmentthatentertheAirportOperationsArea(AOA)
shallbemarkedperAC150/5210‐5B(orlatestversion).Ingeneral,allvehiclesandmotorized
equipmentinsidetheAOAshallbemarkedwithathreefootbythreefootflagwithinternational
orangeandwhite12inchsquaresdisplayedinfullviewabovethevehiclesfordaytime
constructionoranapprovedyellowflashingbeacon.Aflashingbeaconisrequiredforallnighttime

work.

Inaddition,nopersonnelwillbepermittedtodriveontheairsideoftheairportunlesshe/shehas
metwithAirportOperationsforreviewofAirportRulesandRegulationsandhasread,andcertified
thathe/shehasread,“AGuidetoGroundVehicleOperationsonanAirport”(DOT/FAA/AS‐90‐3).A
copyofthisdocumentisattachedattheendofthisspecification.

3.4.2.4 Unauthorized Structures

Thecontractorshallinstallnofencesorotherphysicalobstructionsonoraroundtheprojectwork
areawithouttheapprovalofFAACOR.

3.4.2.5 Hazard Marking

The contractor shall use barricades, flashers, flags, traffic cones, signs, etc., for the following:

‐ To prevent aircraft from taxiing onto a closed runway, taxiway or apron

‐ To outline construction/maintenance areas

‐ To identify isolated hazard areas such as open manholes, ditches, potholes, waste areas, etc.

‐ToidentifyFAAandAirportfacilities,cables,powerlines,andothersensitiveareas,in
ordertopreventdamage,interferenceandfacilityshutdown
Allhazardmarkingsshallbefurnishedandsetupbythecontractor.Barricadesinsidetherunway
safetyareashallbelightweightandfrangible.Fordaytimeuse,barricadesshouldbesupplemented
byflags;fornighttimeuse,theyshallhaveflashingyellowlights.Nighttimebarricadesshallnot
penetratetheapproachsurface.AllmarkingsshallbetotheapprovaloftheFAACOR.

3.4.2.6 Safety Plan

SANDIEGO(SAN)
MEDIUMAPPROACHLIGHTINGSYSTEM–RUNWAY27

SAN DIEGO, CALIFORNIA

Priortocommencementofwork,thecontractorshallsubmitasafetyplanforapprovalbytheFAA
COR.AnacceptablesafetyplanshalltakeintoaccountareasdiscussedinAppendix1ofAC
150/5370‐2FandtheAirport’srulesforconstructionactivityattheAirport.
Adraftsafetyplanwillbeprovideduponrequest.

3.4.3 Radio Communications

Thecontractor'ssuperintendent(orsomeoneappointedbythesuperintendent)shallberequiredto
monitoratransceiverradioatalltimeswhenthecontractorisoperatinginsidetherunwaysafety
area.Thetransceivershallbecontractorfurnishedwithafrequencyrangeof118‐136Mhzand
tunedtothelocalATCTTowerorGroundControl(CTAFwhentowerisclosed)frequency,UNICOM
frequency,orasrequired.Suchradiosshallbeusedsothatanyunusualoccurrenceofapproaching,
departing,taxiingaircraftcanbeacknowledgedbyallconcernedparties.Thecontractor'suseof
thetransceiverradioisbasicallyforlisteningpurposes,transmittingshouldbeinemergenciesonly.
AlsoeachcontractorvehiclewillhaveaSANapprovedgroundtogroundradio.Thisradiowillbe
fordirectcommunicationwiththeSANonsitesafetyofficerorhis/herdesignee.

3.4.4 Work Limitations

Thecontractor’sactivitiesshallbeplannedandscheduledtominimizedisruptionofnormal
aircraftactivities.Iftheclearancesandrestrictionsdescribedinthissectioncannotbemaintained
whileconstructionisunderway(forexample,whenperformingworkthatisrequiredinsidethe
runwaysafetyarea),actionshallbetakentocloserunways(ortaxiways,oraprons),
displace/relocatetherunwaythresholdtemporarily(see3.4.4.2),and/ortoperformworkatnight
orduringperiodsofminimalaircraftactivity,asapproved.

3.4.4.1 Trenches, Holes, and Excavations

Trenches,holes,andanyothertypeofexcavationwithintherunwaysafetyareaarenotallowed
withouteitherclosingtherunwayoradequatelydisplacing/relocatingtherunwaythresholdto
accommodatethework.Ifarunwayclosureordisplacement/relocationoftherunwaythreshold
becomesnecessary,thecontractorshallsubmitadetailedplanwhichmustbeapprovedbythe
AirportandtheFAA.Notrench,hole,orexcavationshallbeleftopenafterthecloseofanywork
period.Steelplatesshallbeprovidedandplacedoveranytrench,hole,orexcavationthatistobe
leftopenafterthecloseoftheworkperiod.Allsteelplatesshallbeaminimumof1”thick.

3.4.4.2 Displaced/Relocated Threshold

N/A

a) Displaced Threshold

N/A

b) Relocated Threshold

N/A

SANDIEGO(SAN)
MEDIUMAPPROACHLIGHTINGSYSTEM–RUNWAY27

SAN DIEGO, CALIFORNIA

3.4.5 Work Plan

Priortocommencementofwork,thecontractorshallsubmitaworkplanforapprovalbytheFAA
COR(see1.4).Anacceptableworkplanshalltakeintoaccountallareasdiscussedinthissection.

3.5 Protection of Existing Utilities and Cables

Theexistingutilitylines,utilitystructuresandallundergroundcables,asmaybeshownonthe
drawingsareapproximateandincomplete.Whereexcavationoccursinthevicinityofexisting
utilitiesorcables,thecontractorshalluseaprivateprofessionalcablelocatorasapprovedbythe
FAA,tolocatetheexistingutilitiesorcablespriortoanyexcavation.Thecontractorshall
immediatelyrepairtothesatisfactionoftheFAA,anydamagedonebythecontractororsuppliersto
utilitiesorcablewithintheworkarea.

3.6 Installation and Workmanship

Allworkshallbeperformedaccordingtotheintentofthecontract,andnormalandaccepted
industryandGovernmentstandards.
Allworkshallbeaccomplishedbyskilledworkersregularlyengagedinthistypeofwork.Where
requiredbylocalregulations,theworkersshallbeproperlylicensed.Electricalterminationsand
splicesshallbedonebyaqualifiedelectrician.
Thecontractorshallgiveconstantattentiontotheworktofacilitatetheprogressthereof,andshall
cooperatewiththeFAACORineverywaypossible.Thecontractorshallhaveacompetent
superintendentontheworksiteatalltimeswhoisfullycapableofreadingandthoroughly
understandingtheplansandspecificationsandshallreceiveandfulfillinstructionsfromtheFAA

COR.

Aninitialinspectionshallbeconductedwhenarepresentativesampleofworkhasbeencompleted.
ThisworkshallbeapprovedbytheFAACORorhisrepresentative,priortothecommencementof
additionalwork.
Allconduitsshallbecompletelycleanedpriortoinstallingcable.Aflexiblemandrelshallbeusedto
cleanoutmud,dirt,anddebrisfromtheraceways.
Undergroundconduitsshallbeinstalledsothatnowatercanbetrappedintheraceway(water
mustabletodrainoutofoneend).
Allfoundations,manholes,vaults,pullbox's,equipmentracks,buildings,roads,retainingwallsand
otherabovegroundstructuresshallbeinstalledsquare(perpendicularandparallel)totherunway
centerline,prevailingstructureorroadasindicatedonthedrawingsunlessspecificallyindicatedto
beotherwise.Elevatedconduitsandstructures(thoseextendingabovegrade)shallbeinstalled
levelandplumb.Unlessotherwiseindicated,maximumtoleranceforverticalplumbnessis1/8”
horizontalforeveryfourfeetvertical.Exposedracewaysshallbeinstalledparalleltooratright
angleswiththelinesofthefinishedstructure,unlessotherwiseindicated.
SANDIEGO(SAN)
MEDIUMAPPROACHLIGHTINGSYSTEM–RUNWAY27

SAN DIEGO, CALIFORNIA

Topsoffoundations,cans,pullbox’s,manholes,vaults,etc.,shallbeuniformwiththetopsof
concreteatthesurroundingstructures,naturalgradeorasindicatedonthedrawingsorasdirected
bytheFAACOR.Unlessotherwiseindicated,topoffoundations,cans,pullbox’s,manholes,etc.
shallbelevelwithamaximumtoleranceof1/16”perfoot.
RoadcurvesshallbeasindicatedonthedrawingsorasindicatedbytheFAACOR.Edgesofroads,
walkwaysandgraveledareasshallbeclean,sharp,andwelldefined.Installedsurfacematerialshall
notbeallowedtospilloutsidethedefinededges.
Installedfoundations,structures,walkways,androadsnotmeetingtheaboverequirementsshallbe
removed,disposedof,andre‐installedcorrectlyatthecontractor’sexpense.

3.7 Temporary Facilities

Thecontractorshallprovideandpayforalltemporaryservicesandfacilitiesasspecifiedbelowand
asnecessaryfortheproperandexpeditiousexecutionofthework.Thecontractorshallmake,or
havemade,allconnectionstoexistingservicesandsourcesofsupplyasnecessaryand/orindicated
andpayallchargesforsame.AllworkunderthisSectionshallcomplywithapplicablelaws,rules,
regulations,codes,ordinances,andordersofallFederal,State,andLocalauthoritieshaving
jurisdictionforthesafetyofpersons,materialsandproperty.Thecontractorshallremoveallsuch
temporaryinstallationsandconnectionswhennolongernecessaryfortheprojectwork.

3.7.1 Temporary Water

Thecontractorshallmakearrangementstofurnishapotablewatersupplyforworkersandproject
work,andpayforallwaterandservices.

3.7.2 Temporary Toilets and Sanitation

Thecontractorshallprovideampleandsuitableonsitesanitaryconvenienceswithproper
enclosuresfortheusebytheworkers,FAApersonnel,andFAAsupportpersonnel.Such
conveniencesshallbekeptclean,properlyventilatedandinstalledandmaintainedinconformity
withrequirementsofalllawsandordinancesgoverningsuchinstallations.Locationsshallbe
subjecttotheFAACOR'sapproval.Aftercompletionoftheworksuchconveniencesshallbe
removedfromthesite.

3.8 Security Requirements

ThecontractorshallcomplywithallsecurityrequirementsestablishedbytheAirport.Onlydirect
constructionsupportpersonnel,vehiclesand/orequipmentwillbeallowedtotheconstructionsite
andAOA.Allothervehicles(includingpersonalvehicles)willbeparkedoutsidetheAOA.
Duringconstructionoperations,thecontractorshalluseonlytheaccessgatesandhaulroadsthat
aredesignatedbytheFAACOR.Thegatemaybeusedonlyforauthorizedvehicletrafficflow.At
suchtimesasthisgateisnotguarded,itshallbeclosedandsecurelylocked.Thecontractorshallbe
helddulyresponsibletoupholdtheabovesecuritystipulationsatalltimesduringtheprogressof
theconstructionproject.Nodeviationsfromthesesecuritymeasuresshallbeallowedatanytime.
SANDIEGO(SAN)
MEDIUMAPPROACHLIGHTINGSYSTEM–RUNWAY27

SAN DIEGO, CALIFORNIA

3.9 Safety

AllworkshallbeaccomplishedinaccordancewithOSHARegulations(Standards–29CFR),Part
1926,SafetyandHealthRegulationsforConstruction.
ProtectiveEquipment,includingpersonalprotectiveequipmentforeyes,face,head,andprotective
clothingshallbeusedwhereveritisnecessarybyreasonsofhazardsorenvironment[1926.95].
Headprotectiveequipment(helmets)shallbeworninareaswherethereisapossible
dangerofheadinjuriesfromimpact,flyingorfallingobjects,orelectricalshockandburns

[1926.100].

Eye and face protection equipment shall be worn when machines or operations present potential eye or face injury [1926.102].

Specificworkandoperationsrequiringthemandatoryuseofpersonnelprotectiveequipmentshall
bedeterminedbytheFAACOR.

3.10 Sedimentation, Erosion, And Dust Control

Thecontractorshallsubmitaplanforsedimentation,erosion,anddustcontrol.Theplanshallshow
bestmanagementpracticessuchastheuseofsiltfencingand/orhaybalestofiltersedimentsfrom
runoffandtheapplicationofwaterasneededtocontroldust.

3.11 Debris Control And Clean‐Up

Theworksiteshallbekeptcleanandorderlyduringtheprogressofwork.Specialattentionshallbe
exercisedtopreventtheproductionofFOD(foreignobjectdebris)whichcouldcausedamageto
aircraftand/orairportequipment.PriortotheContractFinalInspection,thecontractorshallclean
allareasoftheconstructionsite.Thisshallincludebutisnotlimitedtothedress‐up,sweep‐up,and
re‐seedingofallareasdisturbedduringconstruction.ANEATFINALAPPEARANCEOFTHE
INSTALLEDFACILITIES(INTERIORANDEXTERNAL)SHALLBEEMPHASIZED!Allclean‐upwork
shallbetotheapprovaloftheFAACOR.
Uponcompletionofwork,thecontractorshallberequiredtoobtainaletterfromtheAirport
Managerindicatingthattheworkareahasbeenleftinanacceptablecondition.Acopyoftheletter
shallbegiventotheFAACOR.

3.12 Inspection & Acceptance

Thecontractorshallmaintainanadequateinspectionsystemandperformsuchinspectionsto
ensurethattheworkperformedunderthecontractconformstocontractrequirements.The
contractorshallmaintaincompleteinspectionrecordsandmakethemavailabletotheGovernment.
THEPRESENCEORABSENCEOFAGOVERNMENTINSPECTORDOESNOTRELIEVETHE
CONTRACTORFROMANYCONTRACTREQUIREMENT.
SANDIEGO(SAN)
MEDIUMAPPROACHLIGHTINGSYSTEM–RUNWAY27

SAN DIEGO, CALIFORNIA

The Government inspections and tests are for the sole benefit of the Government and do not‐

Relievethecontractorofresponsibilityforprovidingadequatequalitycontrolmeasures;
Relievethecontractorofresponsibilityfordamagetoorlossofthematerialbefore

acceptance;

Constitute or imply acceptance.

Thecontractorshall,withoutcharge,replaceorcorrectworkfoundbytheGovernmentnotto
conformtocontractrequirements.Thecontractorshallpromptlysegregateandremoverejected
materialfromthepremises.

END OF SECTION

SANDIEGO(SAN)
MEDIUMAPPROACHLIGHTINGSYSTEM–RUNWAY27

SAN DIEGO, CALIFORNIA

DIVISION 2 SITE WORK

SECTION 02011

DIRECTIONAL BORING

PART 1 – GENERAL

1.1 Work Included

TheworkunderthisSectionincludes,butisnotlimitedto,thefurnishingoflabor,materials,
equipment,constructionmethods,procedures&documents,andincidentalsnecessaryforthe
installationofundergroundconduitfordirectionalboring,alsocommonlycalledHorizontal
DirectionalDrilling(HDD).

1.2 Definitions

HDD–Isatrench‐lessmethodforinstallingaproductthatservesasaconduitforliquids&gasses,
orasaductforpipe,cable,orwirelineproducts.Itisamulti‐stageprocessconsistingofsite
preparationandrestoration,equipmentset‐up,anddrillingapilotborealongapredeterminedpath
andthenpullingtheproductbackthroughthedrilledspace.Whennecessary,enlargementofthe
pilotboreholemaybenecessarytoaccommodateaproductlargerthanthepilotboreholesize,
Thisprocessisreferredtoasbackreamingandisdoneatthesametimetheproductisbeingpulled
backthroughthepilotborehole.
Orientationandtrackingofthedrillbitasitisbeingpushedintothegroundbyahydraulicjackis
determinedbyanabovegroundradiodetectiondevicewhichpicksuparadiosignalgenerated
fromatransmitterlocatedwithinthedrillbithead.Thisthenelectronicallytranslatestheradio
signaltoprovideadepthandalignmentreading.Inordertominimizefrictionandpreventcollapse
oftheborehole,asoil‐stabilizingagent(drillingfluid)isintroducedintotheannularborespace
fromthetrailingendofthedrillbit.Therotationofthebitinthesoilwettedbythedrillingfluid
createsslurry.Theslurryactstostabilizethesurroundingsoilandpreventcollapseoftheborehole
aswellasprovideslubrication.

1.3 Submittals

Submittals shall include:

A. The Contractor shall select or design drilling fluids for the site‐specific soil and ground water

conditions.ThisshallbesubmittedtotheCORforapprovalpriortobeginninganydrilling
operations.Confinefreeflowing(escaping)slurryordrillingfluidsatthegroundsurface
duringpullbackordrilling.Accomplishthisbycreatingsumpareasforvacuumoperationsto
preventdamageorhazardousconditionstosurroundingareas.Removeallresidualslurry
fromthesurfaceandrestorethesitetopreconstructionconditions.

B. Submit for review complete working drawings describing the equipment, material, lay‐out

detailsandthesequenceofoperationstobeperformedduringtheboring.Indicatethetypeof
drillbitandback‐reamerproposedforthesitespecificsoilandalternativesifrockconditions
SANDIEGO(SAN)
MEDIUMAPPROACHLIGHTINGSYSTEM–RUNWAY27

SAN DIEGO, CALIFORNIA

are encountered. Include any proposed dewatering method to be used if necessary.

C. Submitforreviewthelayoutanddesignofaccesspitsand/orshafts.Submitacertificationthat
thestructuraldesignoftheshoringandbracingifapplicablemeetsthecontractsafety

requirements.

D. ReviewbyCORshallnotbeconstruedinanywayofrelievingcontractorofhiscontractual
responsibilitiestoensurethatboringiscarriedoutasefficientlyandassafelyaspossible.

E. As‐built plans and bore path report.

1.4 Quality Assurance

1.4.1 General

Thecontractorshallhaveacompetentrepresentativewhoisthoroughlyknowledgeableofthe
equipment,boringprocedures,andispresentatthejobsiteduringtheentireinstallation&
availabletoaddressimmediateconcernsandemergencysituations.contractorshallnotifytheCOR
48hoursinadvanceofstartingwork.DonotbegininstallationuntiltheCORispresentatthejob
siteandagreesthatproperpreparationshavebeenmade.

1.4.2 Product Testing

Whenthereisanyindicationthattheinstalledproducthassustainedjointdamageorhasbeen
severelydeformed,stopallworkandnotifytheCORtoinvestigatedamage.TheCORmayrequirea
pressuretestforanyjointdamageandreservestherighttobepresentduringthetest.Perform
pressuretestwithin24hoursunlessotherwiseapprovedbytheCOR.Furnishacopyofthetest
resultstotheCORforreviewandapproval.TheCORmayrequirenon‐compliantinstallationstobe
filledwithexcavatableflowablefill.

1.4.3 Joint Testing Methods

Testing may consist of one of the following methods:

(a) Follow the product manufacturer’s pressure testing recommendations.

(b)Ensurethatproductcarrierpipesinstalledwithoutacasingmeetthepressure
requirementsascalledforinthecontractplans.

(c) A water tight pipe and joint configuration where the product is installed beneath any

pavement(includingshoulders).TheCORwilldeterminewhenandwherewatertight
jointrequirementsaretobeappliedtotherunway/taxiway/roadwaysections.Whena
productislocatedelsewhere,thepipeandjointconfigurationmustmeetorexceedsoil
tightjointrequirements.Conducttestsforjointintegrityforonehour.Thetestforasoil
tightjointallowsupto0.1gallon[0.4liter]ofwaterleakageatasustainedpressureof2
psi[13.79kPa].Thewatertightjointcriteriaallownoleakageatallforasustained