This is a Questions and Answers document for the Fenix Watch federal contract solicitation. The document addresses delivery and pricing requirements that offerors must understand when preparing quotations.
The Government has not established a required delivery date, allowing offerors to propose their own delivery lead times within their quotations. Partial deliveries are acceptable, and items do not need to be shipped in one complete shipment. All quoted prices must be submitted on an FOB Destination basis with all shipping costs included in the price. These flexible delivery terms provide offerors with scheduling flexibility while ensuring the Government receives transparent, all-inclusive pricing for the Fenix Watch products.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF 30.pdf | ||
| SOW Watches Updated 10JUL26_Redacted.pdf | ||
| Name Brand Justification _Redacted.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions for Fenix Watch Solicitation
1. Could you please confirm whether the Government has established a required delivery date?
a. There is no required delivery date.
2. If no specific delivery date is required, may offerors state their proposed delivery lead time in the quotation?
a. You can include the delivery lead time in the quotation.
3. The required delivery date or number of calendar days after receipt of order;
a. No delivery date required.
4. Whether all items must be delivered in one complete shipment or whether partial deliveries are acceptable; and
a. Does not need to be shipped all at once.
5. Whether the quoted price should be FOB Destination with all shipping included.
a. Include all shipping.