338-024 WOPS Macatawa Bay Servery_ (1)

320 KB Posted

Attached to
Middle School Cafeteria Renovation
Solicitation number
RFP - WOP - 240000001328
Issued by
Ottawa County, Michigan

About this file

This document is an Advertisement for Bids for the Macatawa Bay Servery & Cafeteria Renovations project for West Ottawa Public Schools in Holland, Michigan. Sealed bids are being accepted until March 5, 2024 at 1:00 PM for the renovation work. A pre-bid meeting will be held on February 26, 2024 at 9:00 AM at the Macatawa Bay Middle School. Bids must include a 5% bid bond/security, a sworn and notarized familial disclosure, and an Iran Disclosure Act. The project is not subject to prevailing wage requirements. Bidding documents can be obtained from the GMB Architecture + Engineering website or the West Michigan Builders Exchange.

The bid requires a base bid amount and provides for allowances, cost of bonds, and optional alternates. Bidders must have at least 10 years of experience, be licensed and insured in Michigan, and have the financial resources to complete the work. The project schedule calls for construction to begin on June 8, 2024 and reach substantial completion by August 16, 2024. Close out documents, including warranties and as-builts, will be required prior to final payment.

Text of this file

00 11 13 ADVERTISEMENT FOR BIDS

BID PROPOSAL

Sealed bids, in triplicate, for West Ottawa Public Schools, Macatawa Bay Servery & Cafeteria Renovations, will be received at West Ottawa Public Schools Administration Office, 1138 136 th Ave., Holland, MI 49424 on March 5, 2024 by 1:00 P.M. Any bids received after this date and time will not be accepted or considered. All bids will be opened and read publicly. FAXED OR EMAILED BIDS WILL NOT BE ACCEPTED.

This project is not a prevailing wage project.

All bids must be accompanied by the following:

1. 5% Bid Bond/ Security

2. Sworn and Notarized Familial Disclosure

3. Iran Disclosure Act

SITE INSPECTION

A Pre-Bid Meeting will be held on Monday, February 26 @ 9:00 A.M. This meeting will take place at Macatawa Bay

Middle School located at 3700 140th Ave, Holland, MI 49424. This pre-bid walk thru is highly recommended. There will be no other time available to view the site.

BID DOCUMENTS

Bidding documents may be viewed and/or requested via the following:

GMBs Website www.gmb.com under “Bid Sets”.

Bidders may download drawings and specifications from the Plan Command Site.

Please note that contractors are responsible to review information on all drawings and specifications.

GMB Architecture + Engineering

85 East Eighth St., Suite 200

Holland, MI 49423

Ph: (616) 796-0200

West Michigan Builders Exchange

678 Front St. NW, Grand Rapids, MI 49504

(616) 949-8650

Please note that contractors are responsible to review information on all drawings and specifications.

http://www.gmb.com/

BIDDER QUALIFICATIONS

Bidders submitting a proposal for this project shall have the following qualifications:

1. At least (10) years’ experience under the current company’s name.

2. Licensed and insured to perform work in the State of Michigan.

3. Shall have financial resources to complete work under this scope

BID SECURITY

All bids are required to have a bid security or bid bond in the amount of 5% of the bid being submitted. This shall secure the Owner from loss or damage by reason in the occurrence a bid is withdrawn or failure of the successful bidder to enter into Contract with the Owner if the bid is accepted by the Owner.

The Successful bidder will be asked to secure a Performance, Labor, and Material bond for all work under contract.

Please keep this cost separate on the bid form provided. All bonds shall be from a surety company with an ‘A’ rating.

00 41 00 BID FORM

SUBMIT IN TRIPLICATE

BID TO: West Ottawa Public Schools

1138 136 th Ave.

Holland, MI 49424

ATTENTION: Mr. Jeff Malloch, Assistant Superintendent of Business Services

BID FROM: _______________________________________________________

PROJECT: Macatawa Bay Servery & Cafeteria Renovations

The undersigned has familiarized themselves with the local conditions with the cost of the work by having examined the site conditions, and Bidding Documents prepared by GMB Architecture & Engineering (85 East Eighth St. (Suite

200), Holland, MI 49423), and hereby proposes to furnish all labor, materials, taxes, equipment, and services needed for the completion of the work category submitted. All Addendums that have been issued for this project have been recognized and included. The cost for performing work is:

Bid Category Number: _________________

Bid Category Description: ____________________________________________________________

Base Bid Amount: ____________________________________________________________ Dollars

ALLOWANCES: Base Bid includes all allowance cost(s) set forth in Section 01.2100 of the General Requirements and identified in the Instruction to Bidders.

TAXES: Base Bid includes all applicable taxes, including Michigan Sales Tax.

COST OF BONDS: Bond Cost for Performance, Labor, and Material Bond Cost. This cost must be included in the

Base Bid. Please list the cost of the bond below.

Macatawa Bay Servery & Cafeteria Renovations:

PLM Bond Amount ____________________________________________________________ Dollars

ACKNOWLEDGEMENT OF ADDENDA

The following addenda have been received and acknowledged with their execution included in the base bid cost:

Addendum No. _____ Dated __________ Addendum No. _____ Dated __________

Addendum No. _____ Dated __________ Addendum No. _____ Dated __________

ALTERNATES (MANDATORY TO PROVIDE PRICING AS NEEDED WITH BASE BID)

The following alternates are an add to the Base Bid cost:

Alternate #1: None

Cost: Add/ Delete $___________________________________

VOLUNTARY ALTERNATES

The following is a list of Voluntary Alternates. The owner reserves the right to accept or reject any voluntary alternates.

1. ______________________________________________________________________________

Cost: Add/ Delete $___________________________________

2. ______________________________________________________________________________

Cost: Add/ Delete $___________________________________

3. ______________________________________________________________________________

Cost: Add/ Delete $___________________________________

UNIT PRICE

1. Unit Price No. 1: None

BID BOND

Accompanying this bid as required by the Instructions to Bidders, is a bid security in the form of (Certified Check, Cashier’s Check, or Bid Bond) in the amount of:

Bid Bond Amount ____________________________________________________________ Dollars

CONSTRUCTION SCHEDULE

The undersigned acknowledges the construction schedule set forth in the bid documents and that it must be met.

ADDITIONAL WORK

1. There will be a fee of 10% applied to the total cost of materials purchased and work completed by a contractor's own forces. This includes both overhead and profit.

2. There will be a fee of 5% applied to the total cost of work completed by a subcontractor. This includes both overhead and profit.

CREDIT FOR WORK DELETED FROM CONTRACT

All work deleted from this contract by the Owner should be credited 100% back to the Owner.

AGREEMENT

In submitting this bid, it is understood that the Owner reserves the right to accept or reject any/all bids for any reason.

This bid is valid 60 days from the date of the opening.

Firm: _______________________________________________________________

Date: __________________

By: _____________________________________________________

Signature: ________________________________________________________

Title: ______________________________

Phone: (_______) _____________________

Email: ______________________________________________________

FAMILIAL DISCLOSURE STATEMENT

In accordance with Section 1267 of the Revised School Code this bid must be accompanied by a sworn and notarized statement disclosing the familial relationship between the owner or any employee of the Bidder and any member of West Ottawa Public Schools Board of Education or Superintendent of West Ottawa Public Schools.

(_____) No, there is no relationship between the owner or any employee of the Bidder and any member of West Ottawa Public Schools Board of Education or Superintendent of West

Ottawa Public Schools.

(_____) Yes, there is a relationship between the owner or any employee of the Bidder and any member of West Ottawa Public Schools Board of Education or Superintendent of West

Ottawa Public Schools. Please list the relationship below.

BIDDER BOARD OF EDUCATION MEMBER OR SUPERINTENDENT

Subscribed and sworn this _______________________ day of ___________________________________, 2024.

In the County of ______________________________ In the State of ___________________________________.

By ___________________________________________________________________________

Notary Public Signature

My Commission Expires on: ________________________________ Seal or Stamp:

AFFIDAVIT OF COMPLIANCE IRAN ECONOMICS SANCTIONS ACT

Michigan Public Act No. 517 of 2012

The undersigned, the owner, or authorized officer of the below-named company (the “Contractor”), pursuant to the compliance certification requirement provided in West Ottawa Public Schools Request for Proposal (the “RFP”), hereby certifies, represents, and warrants that the Contractor (which includes its officers, directors and employees) is not an “Iran Linked Business” within the meaning of the Iran Economic Sanctions Act, Michigan Public Act No. 517 of

2012 (the “Act”), and that in the event the Contractor is awarded a contract by the West Ottawa Public Schools as a result of the aforementioned RFP, the Contractor is not and will not become an “Iran Linked Business” at any time during the course of performing any services under the Contract.

The Contractor further acknowledges that any person who is found to have submitted a false certification is responsible for a civil penalty of not more than $250,000.00 or two (2) times the amount of the contract or proposed contract for which the false certification was made, whichever is greater, the cost of the School District’s investigation, and reasonable attorney fees, in addition to the fine. Moreover, any person who submitted a false certification shall be ineligible to bid on a request for proposal for three (3) years from the date that it is determined that the person has submitted the false certification.

Contractor: _____________________________________________________

By: _______________________________________________ Title: ____________________________________

Date: __________________________________________________________

This instrument was acknowledged before me on the __________________ day of _____________________, 2024

In the County of ______________________________ In the State of ___________________________________.

By ___________________________________________________________________________

Notary Public Signature

My Commission Expires on: ________________________________ Seal or Stamp:

REQUEST FOR INFORMATION (RFI) DURING BIDDING PHASE

Please fill out the RFI form provided on page 9 in the front ends of this project.

All Pre-Bid RFI’s due: February 29, 2024 by 4:00 P.M.

Please email the completed RFI form to both:

amanda@wahlfieldconstruction.com f3@wahlfieldconstruction.com

The CM will review the RFI before submitting to the AE firm.

Any questions not submitted following this process prior to the deadline will not be answered.

REQUEST FOR INFORMATION (RFI) FORM

Project: Macatawa Bay Servery & Cafeteria Renovations RFI No: _______ Date: ___________

Project Location: 3700 140th Ave, Holland, MI 49424

Action Requested:

Attn: Fritz Wahlfield III, Fritz Wahlfield Construction (CM) ______ Clarification

______ Direction

From: _________________________________________________ ______ Approval

Contact: _______________________________________________ ______ Alternate Proposal

Phone No: _____________________________________________ ______ Other

Reference Drawing No: __________________________ Detail No: ___________ Spec. Section: ___________

Information Needed / Clarification: _______________________________________________________________

CM Recommendation: _________________________________________________________________________

By: _______________________________ Date: ________________

AE Recommendation: __________________________________________________________________________

By: _______________________________ Date: ________________

BID CATEGORIES INDEX

1. Steel / Metals

2. General Trades

3. LPDA

4. Flooring

5. Painting

6. Fire Protection

7. Mechanical

8. Electrical

9. Food Service Equipment

BID CATEGORY NO. 01 - STEEL / METALS

INCLUDE:

1. Complete Steel / Metals and related work as shown on the drawings and as specified in the following sections:

SPECIFICATION MANUAL AND FRONT ENDS

00.4100 BID FORM

01.0000 GENERAL REQUIREMENTS

01.0001 ELECTRONIC MODEL/DRAWING FILE EXCHANGE AGREEMENT

01.1000.0 SUMMARY

01.1000.1 ABBREVIATIONS

01.1010.1 WORK COVERED BY CONTRACT DOCUMENTS

01.1010.2 SCHEDULING

01.1010.3 CONTRACTOR USE OF PREMISES

01.1010.4 SUBSTANTIAL COMPLETION

01.2100 ALLOWANCES

01.2200 UNIT PRICES

01.2300 ALTERNATES

01.3000 ADMINISTRATIVE REQUIREMENTS

01.3000.1 SUBMITTALS

01.3113 INSURANCE REQUIREMENTS

01.4000 QUALITY REQUIREMENTS

01.4100 REGULATORY REQUIREMENTS

01.5000 TEMPORARY FACILITIES AND CONTROLS

01.5100 TEMPORARY UTILITIES

01.7700 CLOSE OUT PROCEDURES

02.4119 SELECTIVE DEMOLITION

05.1200 STRUCTURAL STEEL FRAMING

2. CONSTRUCTION DRAWINGS: CONTRACTOR IS RESPONSIBLE FOR REVIEWING ALL

CONSTRUCTION DRAWING PAGES AND BECOMING FAMILIAR WITH THE COMPLETE SET TO

SATISFY THE SCOPE OF WORK RELATED TO THE BID CATEGORY.

a. DRAWING INDEX CAN BE FOUND ON THE TITLE PAGE.

3. Furnish and install Structural Steel Framing as shown.

4. All onsite welding must be completed by certified welders.

5. Provide Fire Watch for work completed above.

6. Dust control measures for all work in this Bid Category.

7. Daily clean-up at work areas.

8. Contractor to meet Project Schedule, this includes weekend work or daily overtime.

a. Project Manager/Project Foreman required to attend the following meetings:

i. Pre-Construction Kick Off

ii. Bi-Weekly Progress Meeting

iii. Any meetings required by the Local Ordinance, Architect, and/ or Civil Engineer

9. All work must be done in accordance with MIOSHA Regulations.

10. Warranties as specified.

11. Architectural Elevation 100’-0” = match existing finished floor.

12. Submit shop drawings to scale so they can be accurately commented on/coordinated with other trades.

13. When shop drawings are returned from the Architect to Contractor marked “Rejected” or “Revise and

Resubmit”, contractor shall reissue the second time with the revisions clouded.

BID CATEGORY NO. 02 - GENERAL TRADES

1. Complete General Trades work as shown on the drawings and as specified in the following sections:

SPECIFICATION MANUAL AND FRONT ENDS

00.4100 BID FORM

01.0000 GENERAL REQUIREMENTS

01.0001 ELECTRONIC MODEL/DRAWING FILE EXCHANGE AGREEMENT

01.1000.0 SUMMARY

01.1000.1 ABBREVIATIONS

01.1010.1 WORK COVERED BY CONTRACT DOCUMENTS

01.1010.2 SCHEDULING

01.1010.3 CONTRACTOR USE OF PREMISES

01.1010.4 SUBSTANTIAL COMPLETION

01.2100 ALLOWANCES

01.2200 UNIT PRICES

01.2300 ALTERNATES

01.3000 ADMINISTRATIVE REQUIREMENTS

01.3000.1 SUBMITTALS

01.3113 INSURANCE REQUIREMENTS

01.4000 QUALITY REQUIREMENTS

01.4100 REGULATORY REQUIREMENTS

01.5000 TEMPORARY FACILITIES AND CONTROLS

01.5100 TEMPORARY UTILITIES

01.7700 CLOSE OUT PROCEDURES

02.4119 SELECTIVE DEMOLITION

03.3000 CAST-IN-PLACE CONCRETE

06.1000 ROUGH CARPENTRY

07.8413 FIRESTOPPING

07.9200 JOINT SEALANTS

2. CONSTRUCTION DRAWINGS: CONTRACTOR IS RESPONSIBLE FOR REVIEWING ALL

CONSTRUCTION DRAWING PAGES AND BECOMING FAMILIAR WITH THE COMPLETE SET TO

SATISFY THE SCOPE OF WORK RELATED TO THE BID CATEGORY.

a. DRAWING INDEX CAN BE FOUND ON THE TITLE PAGE.

3. Schedule, take delivery, inventory, and store and install all items noted as “Install Only” above. Provide a list of material received each day to the Construction Manager’s Superintendent. All items not noted are to be furnished and installed.

4. Selective Demolition as shown on page A1.1H notes 1-5 and 7-9 and as shown on page A1.3H note 5.

5. Furnish & install concrete floor patching for areas noted 3 on page A1.1H. Patch to be finished to accept new floor covering.

6. Furnish & install 1,400 square feet of floor protection.

a. 1 layer 6 mil plastic

b. 1 layer fiber board

7. Furnish and erect all blocking shown on drawings or as specified in Miscellaneous Carpentry. Include all blocking not shown but incidental to your scope of work.

a. Top of wall blocking.

b. Casework and furnishings blocking as required.

c. Any door or window bucks as needed/shown.

8. All lumber to be treated as specified.

9. Furnish and install all interior signage as specified and shown or as required by code.

10. Furnish and Install all joint sealants for the work under this scope.

11. Dust control measures for all work in this Bid Category.

12. Daily clean-up at work areas.

13. Contractor to meet Project Schedule, this includes weekend work or daily overtime.

a. Project Manager/Project Foreman required to attend the following meetings:

i. Pre-Construction Kick Off

ii. Bi-Weekly Progress Meeting

iii. Any meetings required by the Local Ordinance, Architect, and/ or Civil Engineer

14. All work must be done in accordance with MIOSHA Regulations.

a. Provide lifting plan for any crane work.

15. Warranties as specified.

16. Submit shop drawings to scale so they can be accurately commented on/coordinated with other trades.

17. When shop drawings are returned from the Architect to Contractor marked “Rejected” or “Revise and

BID CATEGORY NO. 03 - LPDA

1. Complete LPDA work as shown on the drawings and as specified in the following sections:

SPECIFICATION MANUAL AND FRONT ENDS

00.4100 BID FORM

01.0000 GENERAL REQUIREMENTS

01.0001 ELECTRONIC MODEL/DRAWING FILE EXCHANGE AGREEMENT

01.1000.0 SUMMARY

01.1000.1 ABBREVIATIONS

01.1010.1 WORK COVERED BY CONTRACT DOCUMENTS

01.1010.2 SCHEDULING

01.1010.3 CONTRACTOR USE OF PREMISES

01.1010.4 SUBSTANTIAL COMPLETION

01.2100 ALLOWANCES

01.2200 UNIT PRICES

01.2300 ALTERNATES

01.3000 ADMINISTRATIVE REQUIREMENTS

01.3000.1 SUBMITTALS

01.3113 INSURANCE REQUIREMENTS

01.4000 QUALITY REQUIREMENTS

01.4100 REGULATORY REQUIREMENTS

01.5000 TEMPORARY FACILITIES AND CONTROLS

01.5100 TEMPORARY UTILITIES

01.7700 CLOSE OUT PROCEDURES

02.4119 SELECTIVE DEMOLITION

07.8413 FIRESTOPPING

07.9200 JOINT SEALANTS

09.2216 NON-STRUCTURAL METAL FRAMING

09.2900 GYPSUM BOARD

09.5100 ACOUSTICAL CEILINGS

2. CONSTRUCTION DRAWINGS: CONTRACTOR IS RESPONSIBLE FOR REVIEWING ALL

CONSTRUCTION DRAWING PAGES AND BECOMING FAMILIAR WITH THE COMPLETE SET TO

SATISFY THE SCOPE OF WORK RELATED TO THE BID CATEGORY.

a. DRAWING INDEX CAN BE FOUND ON THE TITLE PAGE.

3. Furnish and install all new metal studs as shown.

a. This includes cold form metal framing and non structural metal framing.

4. Furnish and install all gypsum board as shown.

a. All gypsum board must be finished as specified for painting.

5. Furnish and install new acoustical ceilings as shown on the drawings.

6. Furnish and install new drywall bulkheads as shown.

7. Furnish and install sound batt insulation in all interior partitions as needed.

8. Furnish and install firestopping at all rated assemblies as shown on the drawing.

9. Coordinate layout and elevations with the Construction Manager prior to install.

10. Dust control measures for all work in this Bid Category.

11. Daily clean-up at work areas.

12. Contractor to meet Project Schedule, this includes weekend work or daily overtime.

a. Project Manager/Project Foreman required to attend the following meetings:

i. Pre-Construction Kick Off

ii. Bi-Weekly Progress Meeting

iii. Any meetings required by the Local Ordinance, Architect, and/or Civil Engineer

13. All work must be done in accordance with MIOSHA Regulations.

14. Warranties as specified.

15. Submit shop drawings to scale so they can be accurately commented on/coordinated with other trades.

16. When shop drawings are returned from the Architect to Contractor marked “Rejected” or “Revise and

BID CATEGORY NO. 04 - FLOORING

1. Complete Flooring work as shown on the drawings and as specified in the following sections:

SPECIFICATION MANUAL AND FRONT ENDS

00.4100 BID FORM

01.0000 GENERAL REQUIREMENTS

01.0001 ELECTRONIC MODEL/DRAWING FILE EXCHANGE AGREEMENT

01.1000.0 SUMMARY

01.1000.1 ABBREVIATIONS

01.1010.1 WORK COVERED BY CONTRACT DOCUMENTS

01.1010.2 SCHEDULING

01.1010.3 CONTRACTOR USE OF PREMISES

01.1010.4 SUBSTANTIAL COMPLETION

01.2100 ALLOWANCES

01.2200 UNIT PRICES

01.2300 ALTERNATES

01.3000 ADMINISTRATIVE REQUIREMENTS

01.3000.1 SUBMITTALS

01.3113 INSURANCE REQUIREMENTS

01.4000 QUALITY REQUIREMENTS

01.4100 REGULATORY REQUIREMENTS

01.5000 TEMPORARY FACILITIES AND CONTROLS

01.5100 TEMPORARY UTILITIES

01.7700 CLOSE OUT PROCEDURES

02.4119 SELECTIVE DEMOLITION

07.9200 JOINT SEALANTS

09.6516 RESILIENT SHEET FLOORING

2. CONSTRUCTION DRAWINGS: CONTRACTOR IS RESPONSIBLE FOR REVIEWING ALL

CONSTRUCTION DRAWING PAGES AND BECOMING FAMILIAR WITH THE COMPLETE SET TO

SATISFY THE SCOPE OF WORK RELATED TO THE BID CATEGORY.

a. DRAWING INDEX CAN BE FOUND ON TITLE PAGE.

3. Selective Demolition as shown on page A1.1H note 10.

4. Furnish and install new flooring as shown on the drawings.

a. This includes resilient sheet flooring and integral cove base.

b. Any transitions, reducers, etc. as required.

5. Minor floor prep as needed.

6. Coordinate layout and elevations with the Construction Manager prior to install.

7. Dust control measures for all work in this Bid Category.

8. Daily clean-up at work areas.

9. Contractor to meet Project Schedule, this includes weekend work or daily overtime.

a. Project Manager/Project Foreman required to attend the following meetings:

i. Pre-Construction Kick Off

ii. Bi-Weekly Progress Meeting

iii. Any meetings required by the Local Ordinance, Architect, and/or Civil Engineer

10. All work must be done in accordance with MIOSHA Regulations.

11. Warranties as specified.

12. Submit shop drawings to scale so they can be accurately commented on/coordinated with other trades.

13. When shop drawings are returned from the Architect to Contractor marked “Rejected” or “Revise and

BID CATEGORY NO. 05 - PAINTING

1. Complete Painting work as shown on the drawings and as specified in the following sections:

SPECIFICATION MANUAL AND FRONT ENDS

00.4100 BID FORM

01.0000 GENERAL REQUIREMENTS

01.0001 ELECTRONIC MODEL/DRAWING FILE EXCHANGE AGREEMENT

01.1000.0 SUMMARY

01.1000.1 ABBREVIATIONS

01.1010.1 WORK COVERED BY CONTRACT DOCUMENTS

01.1010.2 SCHEDULING

01.1010.3 CONTRACTOR USE OF PREMISES

01.1010.4 SUBSTANTIAL COMPLETION

01.2100 ALLOWANCES

01.2200 UNIT PRICES

01.2300 ALTERNATES

01.3000 ADMINISTRATIVE REQUIREMENTS

01.3000.1 SUBMITTALS

01.3113 INSURANCE REQUIREMENTS

01.4000 QUALITY REQUIREMENTS

01.4100 REGULATORY REQUIREMENTS

01.5000 TEMPORARY FACILITIES AND CONTROLS

01.5100 TEMPORARY UTILITIES

01.7700 CLOSE OUT PROCEDURES

02.4119 SELECTIVE DEMOLITION

09.9000 PAINTING AND COATINGS

2. CONSTRUCTION DRAWINGS: CONTRACTOR IS RESPONSIBLE FOR REVIEWING ALL

CONSTRUCTION DRAWING PAGES AND BECOMING FAMILIAR WITH THE COMPLETE SET TO

SATISFY THE SCOPE OF WORK RELATED TO THE BID CATEGORY.

a. DRAWING INDEX CAN BE FOUND ON THE TITLE PAGE.

3. Furnish and install all painting as shown and specified in the Construction Documents for this project.

4. Painting of steel lintels as required.

5. Contractor responsible for final touch-up.

6. Fire barrier signage/ stenciling on fire walls within concealed space above ceiling per Barrier Free

Dimensions.

7. Dust control measures for all work in this Bid Category.

8. Daily clean-up at work areas.

9. Contractor to meet Project Schedule, this includes weekend work or daily overtime.

a. Project Manager/Project Foreman required to attend the following meetings:

i. Pre-Construction Kick Off

ii. Bi-Weekly Progress Meeting

iii. Any meetings required by the Local Ordinance, Architect, and/or Civil Engineer

10. All work must be done in accordance with MIOSHA Regulations.

11. Warranties as specified.

12. Submit shop drawings to scale so they can be accurately commented on/coordinated with other trades.

13. When shop drawings are returned from the Architect to Contractor marked “Rejected” or “Revise and

BID CATEGORY NO. 06 - FIRE PROTECTION

1. Complete Fire Protection work as shown on the drawings and as specified in the following sections:

SPECIFICATION MANUAL AND FRONT ENDS

00.4100 BID FORM

01.0000 GENERAL REQUIREMENTS

01.0001 ELECTRONIC MODEL/DRAWING FILE EXCHANGE AGREEMENT

01.1000.0 SUMMARY

01.1000.1 ABBREVIATIONS

01.1010.1 WORK COVERED BY CONTRACT DOCUMENTS

01.1010.2 SCHEDULING

01.1010.3 CONTRACTOR USE OF PREMISES

01.1010.4 SUBSTANTIAL COMPLETION

01.2100 ALLOWANCES

01.2200 UNIT PRICES

01.2300 ALTERNATES

01.3000 ADMINISTRATIVE REQUIREMENTS

01.3000.1 SUBMITTALS

01.3113 INSURANCE REQUIREMENTS

01.4000 QUALITY REQUIREMENTS

01.4100 REGULATORY REQUIREMENTS

01.5000 TEMPORARY FACILITIES AND CONTROLS

01.5100 TEMPORARY UTILITIES

01.7700 CLOSE OUT PROCEDURES

02.4119 SELECTIVE DEMOLITION

07.8413 FIRESTOPPING

21.0001 FIRE PROTECTION SUMMARY OF WORK

21.0500 COMMON WORK RESULTS FOR FIRE SUPPRESSION

21.1300 FIRE SUPPRESSION SYSTEMS

2. CONSTRUCTION DRAWINGS: CONTRACTOR IS RESPONSIBLE FOR REVIEWING ALL

CONSTRUCTION DRAWING PAGES AND BECOMING FAMILIAR WITH THE COMPLETE SET TO

SATISFY THE SCOPE OF WORK RELATED TO THE BID CATEGORY.

a. DRAWING INDEX CAN BE FOUND ON THE TITLE PAGE.

3. Applicable fees, permits, inspections, etc. as required for the completion of the work in this bid category.

Include sealed drawings for permitting and approvals. Provide the CM with a copy of the permit(s).

4. Selective Demolition as shown on page FP2.1H

a. Remove existing heads as needed for demolition of the ceiling as shown.

5. Rework existing fire protection system for new layout as shown.

6. Furnish and install new fire protection heads in the new ceiling as shown and specified.

7. Fire caulking/ fire rating at all penetrations in fire rated assemblies created by this scope of work.

8. Include all tie ins and draining of the existing system as required to complete work.

9. It is the responsibility of this contractor to cut in all fire protection heads into the acoustical ceiling pads.

10. All work to be completed to meet industry standards.

11. Dust control measures for all work in this Bid Category.

12. Daily clean-up at work areas.

13. Contractor to meet Project Schedule, this includes weekend work or daily overtime.

a. Project Manager/Project Foreman required to attend the following meetings:

i. Pre-Construction Kick Off

ii. Bi-Weekly Progress Meeting

iii. Any meetings required by the Local Ordinance, Architect, and/or Civil Engineer

14. All work must be done in accordance with MIOSHA Regulations.

15. Warranties as specified.

16. Submit shop drawings to scale so they can be accurately commented on/coordinated with other trades.

17. When shop drawings are returned from the Architect to Contractor marked “Rejected” or “Revise and

BID CATEGORY NO. 07 - MECHANICAL

1. Complete Mechanical work as shown on the drawings and as specified in the following categories:

SPECIFICATION MANUAL AND FRONT ENDS

00.4100 BID FORM

01.0000 GENERAL REQUIREMENTS

01.0001 ELECTRONIC MODEL/DRAWING FILE EXCHANGE AGREEMENT

01.1000.0 SUMMARY

01.1000.1 ABBREVIATIONS

01.1010.1 WORK COVERED BY CONTRACT DOCUMENTS

01.1010.2 SCHEDULING

01.1010.3 CONTRACTOR USE OF PREMISES

01.1010.4 SUBSTANTIAL COMPLETION

01.2100 ALLOWANCES

01.2200 UNIT PRICES

01.2300 ALTERNATES

01.3000 ADMINISTRATIVE REQUIREMENTS

01.3000.1 SUBMITTALS

01.3113 INSURANCE REQUIREMENTS

01.4000 QUALITY REQUIREMENTS

01.4100 REGULATORY REQUIREMENTS

01.5000 TEMPORARY FACILITIES AND CONTROLS

01.5100 TEMPORARY UTILITIES

01.7700 CLOSE OUT PROCEDURES

02.4119 SELECTIVE DEMOLITION

07.8413 FIRESTOPPING

22.0500 PLUMBING SUMMARY OF WORK

22.0523 GENERAL DUTY VALVES FOR PLUMBING PIPING

22.0529 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT

22.0553 IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT

22.0719 PLUMBING PIPING INSULATION

22.1116 DOMESTIC WATER PIPING

22.1119 DOMESTIC WATER PIPING SPECIALTIES

22.1316 SANITARY WASTE AND VENT PIPING

22.1319 SANITARY WASTE PIPING SPECIALTIES

23.0500 HVAC SUMMARY OF WORK

23.0513 COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT

23.0528 ROOF-MOUNTED HANGERS AND SUPPORTS FOR HVAC PIPING AND

EQUIPMENT

23.0553 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT

23.0593 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23.0713 DUCT INSULATION

23.0923 DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC

23.0993 SEQUENCE OF OPERATIONS FOR HVAC CONTROLS

23.1123 NATURAL-GAS PIPING

23.3100 HVAC DUCTS AND CASINGS

23.3300 AIR DUCT ACCESSORIES

23.3423 HVAC POWER VENTILATORS

23.3700 AIR OUTLETS AND INLETS

23.7433 PACKAGED OUTDOOR HEATING AND COOLING MAKE-UP AIR UNITS

2. CONSTRUCTION DRAWINGS: CONTRACTOR IS RESPONSIBLE FOR REVIEWING ALL

CONSTRUCTION DRAWING PAGES AND BECOMING FAMILIAR WITH THE COMPLETE SET TO

SATISFY THE SCOPE OF WORK RELATED TO THE BID CATEGORY.

a. DRAWING INDEX CAN BE FOUND ON THE TITLE PAGE.

3. Applicable fees, permits, inspections, etc. as required for the completion of the work in this bid category.

Provide the CM with a copy of the permit(s).

4. Selective Demolition as shown on pages P1.1H & M1.1H.

5. Rough-In all plumbing & mechanical as shown or as required for Food Service Equipment.

6. Furnish and install all plumbing and HVAC as specified and shown.

a. All equipment needs to be included.

7. Fire caulk any penetrations at rated assemblies.

8. Any coring through masonry or concrete to complete work in this scope must be included.

9. All DDC and controls must be included as specified and shown.

10. Testing, adjusting, and balancing of new and existing HVAC equipment as specified and as required.

11. Floor protection for any welding or soldering.

12. Dust control measures for all work in this Bid Category.

13. Daily clean-up at work areas.

14. Contractor to meet Project Schedule, this includes weekend work or daily overtime.

a. Project Manager/Project Foreman required to attend the following meetings:

i. Pre-Construction Kick Off

ii. Bi-Weekly Progress Meeting

iii. Any meetings required by the Local Ordinance, Architect, and/or Civil Engineer

15. All work must be done in accordance with MIOSHA Regulations.

16. Warranties as specified.

17. Submit shop drawings to scale so they can be accurately commented on/coordinated with other trades.

18. When shop drawings are returned from the Architect to Contractor marked “Rejected” or “Revise and

BID CATEGORY NO. 08 - ELECTRICAL

1. Complete Electrical work as shown on the drawings and as specified in the following sections:

SPECIFICATION MANUAL AND FRONT ENDS

00.4100 BID FORM

01.0000 GENERAL REQUIREMENTS

01.0001 ELECTRONIC MODEL/DRAWING FILE EXCHANGE AGREEMENT

01.1000.0 SUMMARY

01.1000.1 ABBREVIATIONS

01.1010.1 WORK COVERED BY CONTRACT DOCUMENTS

01.1010.2 SCHEDULING

01.1010.3 CONTRACTOR USE OF PREMISES

01.1010.4 SUBSTANTIAL COMPLETION

01.2100 ALLOWANCES

01.2200 UNIT PRICES

01.2300 ALTERNATES

01.3000 ADMINISTRATIVE REQUIREMENTS

01.3000.1 SUBMITTALS

01.3113 INSURANCE REQUIREMENTS

01.4000 QUALITY REQUIREMENTS

01.4100 REGULATORY REQUIREMENTS

01.5000 TEMPORARY FACILITIES AND CONTROLS

01.5100 TEMPORARY UTILITIES

01.7700 CLOSE OUT PROCEDURES

02.4119 SELECTIVE DEMOLITION

07.8413 FIRESTOPPING

26.0500 COMMON WORK RESULTS FOR ELECTRICAL

26.0505 SELECTIVE DEMOLITION FOR ELECTRICAL

26.0519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

26.0523 CONTROL-VOLTAGE ELECTRICAL POWER CABLES

26.0526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

26.0529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

26.0533.13 CONDUIT FOR ELECTRICAL SYSTEMS

26.0533.16 BOXES FOR ELECTRICAL SYSTEMS

26.0533.23 SURFACE RACEWAYS FOR ELECTRICAL SYSTEMS

26.0544 SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND

CABLING

26.0553 IDENTIFICATION FOR ELECTRICAL SYSTEMS

26.0583 WIRING CONNECTIONS

26.0919 ENCLOSED CONTACTORS

26.0943 NETWORK LIGHTING CONTROLS

26.2416 PANELBOARDS

26.2726 WIRING DEVICES

26.2813 FUSES

26.2816 ENCLOSED SWITCHES AND CIRCUIT BREAKERS

26.2913 ENCLOSED MOTOR CONTROLLERS

26.2923 VARIABLE-FREQUENCY MOTOR CONTROLLERS

26.5119 LED INTERIOR LIGHTING

27.0500 COMMON WORK RESULTS FOR COMMUNICATIONS

27.0505 SELECTIVE DEMOLITION FOR COMMUNICATIONS

27.0528 PATHWAYS FOR COMMUNICATIONS SYSTEMS

27.1000 STRUCTURED COMMUNICATIONS CABLING SYSTEM

2. CONSTRUCTION DRAWINGS: CONTRACTOR IS RESPONSIBLE FOR REVIEWING ALL

CONSTRUCTION DRAWING PAGES AND BECOMING FAMILIAR WITH THE COMPLETE SET TO

SATISFY THE SCOPE OF WORK RELATED TO THE BID CATEGORY.

a. DRAWING INDEX CAN BE FOUND ON THE TITLE PAGE.

3. Applicable fees, permits, inspections, etc., as required for the completion of the work in this bid category.

Provide the CM with a copy of the permit(s).

4. Demolition of and removal of electrical, security, and fire alarm systems as required to facilitate new construction and/or remodeling. It is this contractor’s responsibility to survey existing conditions to determine the extent that this affects this scope of work. Patching of surfaces to receive new finishes or fire ratings as a result of your demolition. Example: screw holes at wire-mold.

5. Remove all Ceiling Mounted Devices including but not limited to power, data, ceiling fans, wireless routers, exit lights, etc.

6. Selective Demolition as noted on page E1.1H.

7. Furnish and install electrical/communications rough-ins as shown for Food Service Equipment.

8. Furnish and install complete Electrical & Communications system as specified and shown.

9. Include all fire alarm system modifications as required.

10. Reinstall Ceiling Mounted Devices after the new ceiling is installed.

11. Fire caulk any penetrations at rated assemblies.

12. Temporary electrical (Power and Lighting) system(s). Remove upon the direction of the Construction

Manager.

13. Technology and communications related (voice, data, video, etc.) boxes, raceways and pull wires as required by the documents. Coordinate with appropriate contractor(s).

14. Furnish and install electrical sleeves.

15. Final hook-up of mechanical equipment.

16. Receive power supplies, mount and energize with 120V.

17. Metal support framing specifically required for support of electrical systems.

18. Include wiring of FCU’s. FCU’s will be supplied and started by the Mechanical contractor.

19. Install conduit at all exposed ceilings for communications/ security and fire detection.

20. It is this contractor’s responsibility to ensure all rough-in boxes are installed level, plumb, and solidly grouted. Final product and cover plates must be level and plumb.

21. Existing clock/ intercom/ camera demolition where shown on drawings. Patching of any holes using qualified trades that is required by removals. All demolition associated with your specification sections. Existing items/ fixtures/ devices to be salvaged, stored for re-use/ re-installation as indicated per drawings.

22. Furnish and install blank cover plates at all removed electrical fixtures/ devices at walls, ceilings, and floors not noted for demolition.

23. Include, using qualified trades, saw cutting/ removal/ excavation/ backfill/ compaction/ new concrete at any areas needed for electrical not shown on demolition drawings.

24. Provide and install all plywood mounting boards as required for any fire alarm, communications, and electrical mounting requirements.

25. Coordinate and layout locations of all underground electrical conduit serving millwork furniture with

Communications and General Trades contractors.

26. Furnish and install disconnect switches, wiring, conduit and other equipment/ wiring per Div. 26 as required for a complete and proper electronic access control system.

27. Installation of conduits for DDC.

28. Project Foreman needs to have a Journeyman’s license.

29. Dust control measures for all work in this Bid Category.

30. Daily clean-up at work areas.

31. Contractor to meet Project Schedule, this includes weekend work or daily overtime.

a. Project Manager/Project Foreman required to attend the following meetings:

i. Pre-Construction Kick Off

ii. Bi-Weekly Progress Meeting

iii. Any meetings required by the Local Ordinance, Architect, and/or Civil Engineer

32. All work must be done in accordance with MIOSHA Regulations.

33. Warranties as specified.

34. Submit shop drawings to scale so they can be accurately commented on/coordinated with other trades.

35. When shop drawings are returned from the Architect to Contractor marked “Rejected” or “Revise and

BID CATEGORY NO. 09 - FOOD SERVICE EQUIPMENT

1. Complete Food Service Equipment work as shown on the drawings and as specified in the following sections:

SPECIFICATION MANUAL AND FRONT ENDS

00.4100 BID FORM

01.0000 GENERAL REQUIREMENTS

01.0001 ELECTRONIC MODEL/DRAWING FILE EXCHANGE AGREEMENT

01.1000.0 SUMMARY

01.1000.1 ABBREVIATIONS

01.1010.1 WORK COVERED BY CONTRACT DOCUMENTS

01.1010.2 SCHEDULING

01.1010.3 CONTRACTOR USE OF PREMISES

01.1010.4 SUBSTANTIAL COMPLETION

01.2100 ALLOWANCES

01.2200 UNIT PRICES

01.2300 ALTERNATES

01.3000 ADMINISTRATIVE REQUIREMENTS

01.3000.1 SUBMITTALS

01.3113 INSURANCE REQUIREMENTS

01.4000 QUALITY REQUIREMENTS

01.4100 REGULATORY REQUIREMENTS

01.5000 TEMPORARY FACILITIES AND CONTROLS

01.5100 TEMPORARY UTILITIES

01.7700 CLOSE OUT PROCEDURES

02.4119 SELECTIVE DEMOLITION

11.4000 FOOD SERVICE EQUIPMENT

2. CONSTRUCTION DRAWINGS: CONTRACTOR IS RESPONSIBLE FOR REVIEWING ALL

CONSTRUCTION DRAWING PAGES AND BECOMING FAMILIAR WITH THE COMPLETE SET TO

SATISFY THE SCOPE OF WORK RELATED TO THE BID CATEGORY.

a. DRAWING INDEX CAN BE FOUND ON THE TITLE PAGE.

3. Furnish and install Food Service Equipment.

4. Coordinate all rough-ins with MEP Contractors.

5. Furnish and install all stainless steel equipment as shown in the FSE package.

6. Dust control measures for all work in this Bid Category.

7. Daily clean-up at work areas.

8. Contractor to meet Project Schedule, this includes weekend work or daily overtime.

a. Project Manager/Project Foreman required to attend the following meetings:

i. Pre-Construction Kick Off

ii. Bi-Weekly Progress Meeting

iii. Any meetings required by the Local Ordinance, Architect, and/or Civil Engineer

9. All work must be done in accordance with MIOSHA Regulations.

10. Warranties as specified.

11. Submit shop drawings to scale so they can be accurately commented on/coordinated with other trades.

12. When shop drawings are returned from the Architect to Contractor marked “Rejected” or “Revise and

DIVISION 01 – GENERAL REQUIREMENTS

01 1000.0 SUMMARY

01 1000.1 ABBREVIATIONS

1. CM: Construction Manager

01 1010.1 WORK COVERED BY CONTRACT DOCUMENTS

1. The Project for West Ottawa Public Schools:

a. Macatawa Bay Servery & Cafeteria Renovations

3700 140th Ave., Holland, MI 49424

01 1010.2 SCHEDULING

1. All work to be scheduled and approved by the Owner and CM.

2. Bidding Dates:

a. Pre-Bid Walk Thru: February 26, 2024 at 9:00 A.M

b. RFI’s Due: February 29, 2024 by 4:00 P.M.

c. Bids Due: March 5, 2024 at 1:00 P.M.

d. Mandatory Post Bid Interviews: March 6, 2024

3. Construction Dates:

a. Begin Construction: June 8th, 2024

b. Substantial Completion: August 16, 2024

4. Project Schedule is forthcoming.

01 1010.3 CONTRACTOR USE OF PREMISES

1. Use of the premises will be coordinated by the CM.

2. Each contractor will make premises usable by the Owner with the coordination of the CM.

3. It shall be the responsibility of the contractor to obtain and pay for additional storage as needed.

4. All work areas shall be kept in a clean and professional manner.

01 1010.4 SUBSTANTIAL COMPLETION

1. All contractors shall coordinate their schedule with the CM for Substantial Completion with the following requirements:

a. Access for Owner’s Personnel

b. Access to receive Owner’s Furniture

c. Operation of Electrical and Mechanical systems.

01.2100.0 ALLOWANCES

1. Allowance No. 1: None

01 2200.0 UNIT PRICES

1. Unit prices to include all costs, including overhead and profit.

a. Unit Price No. 1: None

01 3000.0 ADMINISTRATIVE REQUIREMENTS

1. Provide Proof of Insurance to the CM prior to construction. Insurance needs to stay valid through final payment of the project. “DESCRIPTION OF OPERATIONS/LOCATIONS/VEHICLES” box must be filled out specifically for this project.

2. Provide all Performance, Labor, and Material Bonds as required for this project.

a. This Bond should cover 100% of the cost of the contract.

01 3000.1 SUBMITTALS

1. All Submittals from the sub-contractors shall be sent to the CM for initial review. The CM will upload to Procore for distribution and review by the Architect.

01 3113.0 INSURANCE REQUIREMENTS

1. Indemnification and Subcontractor's Liability

a. Subcontractor hereby assumes the entire responsibility and liability for all Work, supervision, labor and materials provided under any Work Order issued pursuant to this

Subcontract, whether or not erected in place and for all plant, scaffolding, tools, equipment, supplies and other things provided by Subcontractor until final acceptance of the entirety of the Work by Owner. In the event of any loss, damage or destruction thereof from any cause of the Work as a result of the acts or omissions of Subcontractor, its employees, sub-subcontractors, suppliers or agents of any type, Subcontractor shall be liable therefor, and shall repair, rebuild and make good said loss, damage or destruction at

Subcontractor's cost, Subcontractor shall be liable therefor, and shall repair, rebuild and make good said loss, damage or destruction at Subcontractor's cost, subject only to the extent that any net proceeds are payable under any builder's risk property insurance that may be maintained by Owner or Construction Manager, if any.

b. Subcontractor shall be liable to Construction Manager for all costs Construction Manager incurs as a result of any failure of Subcontractor, or any of its suppliers, vendors or subcontractors of any tier, to fully and properly perform their obligations and duties with respect to the Work.

c. To the fullest extent permitted by law, the Subcontractor shall indemnify, defend, and hold harmless the Construction Manager, Owner and their respective officers, directors, employees and agents (“Indemnified Parties”) from and against all claims, damages, demands, losses, expenses, fines, causes of action, suits or other liabilities, (including all costs reasonable attorneys' fees, consequential damages, and punitive damages), arising out of or resulting from, or alleged to arise out of or arise from, the performance of

Subcontractor's Work under the Subcontract, and any Work Order whether such claim, damage, demand, loss or expense is attributable to bodily injury, personal injury, sickness, disease or death, or to injury to or destruction of tangible property, including the loss of use resulting therefrom; but only to the extent attributable to the negligence of the

Subcontractor or any entity for which it is legally responsible or vicariously liable:

regardless of whether the claim is presented by an employee of Subcontractor. The indemnity obligations referenced herein shall not be construed to negate, abridge or otherwise limit any other obligations of the Subcontractor or rights of Construction

Manager hereunder. This indemnification shall not be limited in any way by any limitation on the amount or type of damages, compensation or benefits payable by or for the

Subcontractor under any workers' compensation act, disability benefits acts or other employee benefits act and includes any loss or injury suffered by an employee of the subcontractor. This indemnification shall be in addition to any indemnity liability imposed by the Contract Documents, and shall survive the completion of the Work or the termination of the Subcontract.

d. To the fullest extent permitted by law, the Subcontractor shall also indemnify, defend, and hold harmless the Indemnified Parties from and against all claims, damages, demands, losses, expenses, fines, causes of action, suits or other liabilities, (including all costs reasonable attorneys' fees, consequential damages, and punitive damages), arising out of or resulting from, or alleged to arise out of, the failure of Subcontractor, or any of its suppliers or subcontractors of any tier, to compensate any of its employees or independent contractors in accordance with any applicable federal, state or local law regarding the payment of wages. Subcontractor's assumption of liability is independent from, and not limited in any manner by, the Subcontractor's insurance coverage obtained pursuant to Article 5 or otherwise.

2. Subcontractor's Insurance

Prior to commencing the Work, Subcontractor shall procure, and thereafter maintain, at its own expense, until final acceptance of the Work or later as required by the terms of the Subcontract or any individual Work Order, insurance coverage required by this Subcontract. At a minimum, and subject to modification in individual Work Orders, the types of insurance and minimum policy limits specified shall be maintained in a form and from insurers acceptable to Construction Manager as set forth below. All insurers shall have at least an A- (excellent) rating by A.M. Best and be qualified to do business in the state where the project is located.

This insurance will provide a defense and indemnify the Construction Manager, but only with respect to liability for bodily injury, property damage and personal and advertising injury caused in whole or in part by the Subcontractor’s acts or omissions or the acts or omissions of those acting on the Subcontractor’s behalf.

Proof of this insurance shall be provided to the Construction Manager before the Work commences, as set forth below. To the extent that the Subcontractor subcontracts with any other entity or individual to perform all or part of the Subcontractor's Work, the Subcontractor shall require the other Sub-Subcontractors to furnish evidence of equivalent insurance coverage, in all respects, Terms and conditions as set forth herein, prior to the commencement of work by the

Sub-Subcontractor. In no event shall the failure to provide this proof, prior to the commencement of the Work, be deemed a waiver by the Construction Manager of Subcontractor's or the Sub-

Subcontractor's insurance obligations set forth herein.

In the event that the insurance company(ies) issuing the policy(ies) required by this exhibit deny coverage to the Construction Manager, the Subcontractor or the Sub-Subcontractor will, upon demand by the Construction Manager, defend and indemnify the Construction Manager at the

Subcontractor or Sub-Subcontractor’s expense.

Commercial General Liability Insurance

$1,000,000 Each Occurrence Limit (Bodily Injury and Property Damage)

$2,000,000 General Aggregate per Project

$2,000,000 Products & Completed Operations Aggregate

$1,000,000 Personal and Advertising Injury Limit

Business or Commercial Automobile Liability Insurance

$1,000,000 combined single limit per accident

Workers' Compensation and Employers' Liability Insurance

$100,000 Each Accident; $100,000 Each Employee for Injury by Disease; $500,000 Aggregate for

Injury by Disease

Excess or Umbrella Liability

$1,000,000 Occurrence /aggregate

The Construction Manager's Commercial General Liability policy shall not contain an exclusion or restriction of coverage for the following:

a. Claims by one insured against another insured, if the exclusion or restriction is based solely on the fact that the claimant is an insured, and there would otherwise be coverage for the claim.

b. Claims for property damage to the Construction Managers’s Work arising out of the products-completed operations hazard where the damaged Work or the Work out of which the damage arises was performed by a Subcontractor.

c. Claims for bodily injury other than to employees of the insured.

d. Claims for indemnity under Article 4 Indemnification arising out of injury to employees of the insured.

e. Claims or loss excluded under a prior work endorsement or other similar exclusionary language.

f. Claims or loss due to physical damage under a prior injury endorsement or similar exclusionary language.

g. Claims related to residential, multi-family, or other habitational projects, if the Work is to be performed on such a project.

h. Claims related to roofing, if the Work involves roofing.

i. Claims related to exterior insulation finish systems (EIFS), synthetic stucco or similar exterior coatings or surfaces, if the Work involves such coatings or surfaces.

j. Claims related to earth subsidence or movement, where the Work involves such hazards.

k. Claims related to explosion, collapse and underground hazards, where the Work involves such hazards.

3. Additional Insured

The Construction Manager and Owner, along with their respective officers, agents and employees, shall be named as additional insureds for Ongoing Operations and Products/Completed Operations on the Subcontractor's and any Sub-Subcontractor's Commercial General Liability Policy and

Excess or Umbrella Policy, all of which must be primary and noncontributory with respect to these additional insureds. The Subcontractor shall continue to carry Completed Operations Liability

Insurance for at least the length of the Statute of Repose in the state where the subject work is performed after either ninety (90) days following Substantial Completion of the Work or final payment to the Construction Manager on any individual Project, whichever is later.

The Construction Manager and Owner, along with their respective officers, agents and employees shall be named as additional Insureds on the Business or Commercial Automobile Liability Policy, which must be primary and noncontributory with respect to these additional insureds. It is expressly understood by the parties to this Subcontract that it is the intent of the Parties that any insurance obtained by the Construction Manager is deemed excess, Non-contributory and not co-primary in relation to the coverage(s) procured by the Subcontractor, the Sub-Subcontractor or any of their respective consultants, officers, agents, subcontractors, employees or anyone directly or indirectly employed by any of them, or by anyone for whose acts any of the aforementioned may be liable by operation of statute, government regulation or applicable case law. To the fullest extent permitted by applicable state law, a Waiver of Subrogation Clause shall be added to the General Liability, Automobile, Excess or Umbrella and Workers Compensation policies in favor of Construction

Manager and Owner, and this clause shall apply to the Construction Manager’s and Owner’s officers, agents and employees, with respect to all Projects during the policy term.

Prior to commencement of Work on any individual Project, Subcontractor shall submit a Certificate of insurance in favor of Construction Manager and Additional Insured Endorsement (in a form acceptable to the Construction Manager) as required hereunder. The Subcontractor’s Insurance policies shall provide for thirty (30) days’ written notice to Construction Manager for cancellation or any change in coverage and be evidenced by the Certificate of Insurance. Copies of insurance policies shall promptly be made available to the Construction Manager upon request.

01 4000.0 QUALITY REQUIREMENTS

1. All contractors are expected to perform work that meets or exceeds industry standards.

2. All testing will be paid for by the Owner.

a. In the event that the testing fails, it will be the contractor’s responsibility to pay for any re-testing until the test passes industry standards.

3. All testing will need to be scheduled and coordinated with the CM.

4. In the event of re-testing existing soils due to failure, the re-testing will be paid for by Owner.

01 4100.0 REGULATORY REQUIREMENTS

1. Contractors are responsible for applying for any/all permits required by State and Local officials to do work in the State of Michigan.

a.…

This is the start of the file's text. The full file is on GovTribe.

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .