This document is a Statement of Work (SOW) for two Cutter Line Insulation Monitor (LIM) Cabinets for the U.S. Coast Guard's Fast Response Cutters located at Base Guam in Santa-Rita, Guam. The U.S. Coast Guard intends to sole-source the contract to ESL Power Systems, Inc., citing their specialized expertise in constructing short tie equipment that meets specific Coast Guard electrical requirements. The cabinets must be manufactured to precise specifications, including 14GA 304 domestic stainless steel construction, powder-coated finish, and specific electrical configurations of 6A at 450VAC three-phase and 6A at 480VAC one-phase.

The SOW details comprehensive requirements for the LIM cabinets, including internal components such as transformers, switches, relays, warning lights, alarm horns, and surge protection devices. The supplier is responsible for packaging, transportation to the designated location at 1 Victor Pier Santa-Rita, Guam, and must provide a detailed shipping manifest. Submittal requirements include a complete material list, shop drawings, component data sheets, and shipping information. The cabinets must comply with various standards including NFPA, UL, IEEE, and U.S. Coast Guard Configuration Standard Technical Order, with all materials required to be new and free from defects.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

CUTTER LINE INSULATION MONITOR (LIM) CABINETS MATERIALS AND TRANSPORT Forces Micronesia Sector Guam

I. GENERAL DESCRIPTION

A. Provide all materials and transport for two (2) Cutter Line Insulation Monitor (LIM) Cabinets. The cabinets are to be manufactured according to the specifications outlined in Section II for the two (2) future 154’ Fast Response Cutter’s (FRC) located at U.S. Coast Guard Base Guam, Santa-Rita Guam.

B. A sole source justification (JOTFOC) will be provided for the ESL Power Systems, Inc.

C. Transport to 1 Victor Pier Santa-Rita, Guam 96915

D. Materials and equipment shall meet all applicable Codes and EPA, federal, state, and local regulations, including but not limited to:

a. National Fire Protection Association (NFPA) including but not limited to:

• NFPA 70 National Electrical Code, 2023

• NFPA 70E Safe Workplace Practices, 2012

b. Underwriters Laboratories, Inc. (UL)

c. U.S. Coast Guard Configuration Standard Technical Order (CSTO) Electrical Shore Ties (Rev A)

II. MATERIAL SPECIFICATIONS

A. Line Insulation Monitor (LIM):

Quantity: 2 Type: ESL TYPE 4X CONTROL ENCLOSURE Electrical Specifications:

6A, 450VAC, 3-PHASE, 3-WIRE

6A, 480VAC, 1-PHASE, 3-WIRE

Material: 14GA 304 DOMESTIC STAINLESS STEEL Finish: Powder Coated TCI ASA61 Gray (after fabrication) Standards Compliance: IEEE C57.12.29, UL 50 Labeled Mounting: Complete with mounting tabs Approximate Dimensions: 34"H X 18"W X 11"D Door: Hinged, clamped, pad lockable access solid door and deadfront.

B. Internal Components (per Cabinet):

(1) Control Step Down Transformer 480:120VAC

(1) 2-Position Switch to Turn Control Power On/Off

(1) Phase Loss Relay (EATON D65PLR480)

(1) Red LED Indicating Light to Illuminate on Phase Loss

(1) Line Insulation Monitor (BENDER ISO685W-D-B)

(1) Amber Strobe Warning Light

(1) Red Strobe Warning Light

(1) Alarm Horn (Continuous) with Silence Pushbutton and Relay

(1) Bypass Switch for the Line Insulation Monitor with Indicating Lights

(1) Surge Protection Device

(1) Red LED Indicating Light to Illuminate when SPD is to be Replaced

(1) Time Delay Relay with (2) Latching Relays Fusing and Terminal Blocks as Required

C. Transport:

The supplier is responsible for all the packaging and transportation of the two (2) cabinets to Forces Micronesia Sector Guam, 1 Victor Pier Santa-Rita, Guam 96915.

The supplier must provide a detailed shipping manifest.

The supplier is responsible for ensuring the cabinets are adequately protected during transport to prevent damage.

III. SUBMITTAL REQUIREMENTS

A. Material List: A complete list of materials included with each cabinet, referencing the specifications in Section II.

B. Shop Drawings: Shop drawings of the cabinet enclosure, including dimensions and material specifications.

C. Component Data Sheets: Data sheets for each of the internal components listed in Section II.B.

D. Shipping Information: Proposed shipping method, carrier, and estimated delivery timeframe.

IV. SAFETY AND SECURITY

A. All materials must be new and free from defects.

B. Packaging must be appropriate for the materials and comply with all applicable shipping regulations.

C. The supplier is responsible for ensuring the safe transport of the materials to the designated delivery location.

V. MISCELLANEOUS

A. Any deviations from the specifications outlined in this SOW must be approved in writing.

B. The supplier is responsible for all costs associated with the provision of materials and transport.

C. Keep the Contracting Officer and /or COR fully informed on the progress of the work, from the start through completion of this project.

--End of statement of work--