This is a Statement of Work (SOW) for kitchen cabinet and flooring renovation at the U.S. Coast Guard Base Borinquen in Aguadilla, Puerto Rico. The project involves removing existing kitchen cabinets and installing new PVC and laminated cabinets, as well as installing floating floors throughout a housing unit. The work includes detailed requirements for cabinet and floor removal, installation, cleanup, and final inspection, with specific provisions for site access, safety, and contractor conduct.
Key project details include a site visit scheduled for September 3rd, 2025 at 9 am, with quotes due by noon on September 12th, 2025. The project is to be completed within 15 days after the notice to proceed, with work hours limited to 7:00 AM to 3:30 PM, Monday through Friday. Contractors must obtain security passes, comply with safety regulations, and coordinate with the USCG Facilities Engineering Department. The primary point of contact is LT Clara E. Dahill at (787) 975-9470, and quotes should be submitted via email to Eliezer A. Caraballo and Miguel A. Cruz-Rivera.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF HOMELAND SECURITY
UNITED STATES COAST GUARD
DISTRICT 7
BASE BORINQUEN
SCOPE OF SERVICES FOR
KITCHEN CABINETS AND FLOATING FLOORS
FACILITIES ENGINEERING
UNITED STATES COAST GUARD
BASE BORINQUEN
260 GUARD ROAD
AGUADILLA, PR 00603
- SCOPE OF WORK –
KITCHEN CABINETS AND FLOATING FLOORS
AT
U.S.C.G. BASE BORINQUEN, PR 00603
August 2025
PART 1 – STATEMENT OF WORK
1.1 Project Overview: This document sets forth the
scope of work to remove existing kitchen cabinets and install new PVC and laminated cabinets; install floating floor throughout the house unit.
Location: USCG Housing
1.2 SCOPE:
Provide all personnel, labor, equipment, materials, tools, supervision, and other items necessary for delivery.
1.2.1 Kitchen Cabinet Removal:
Preparation:
Clear the kitchen area of all contents (dishes, food, appliances).
Disconnect plumbing and electrical appliances as needed.
Removal Process:
Carefully remove existing cabinet doors and hardware.
Detach cabinets from the wall, ensuring to avoid damage to surrounding walls.
Properly dispose of old cabinets in accordance with local regulations.
1.2.2 Kitchen Cabinet Installation: (PVC and Laminated)
Cabinet Delivery: Verify delivery of new PVC and laminated cabinets and inspect for damages.
Installation Process:
Install base cabinets first, ensuring they are level and securely fastened to the wall.
Install wall cabinets, starting from the corners and working outward.
Ensure that all joints and edges are well-finished to prevent moisture damage.
Install cabinet doors and hardware, ensuring proper alignment and function.
Finishing Touches:
Install toe kicks and any crown molding as specified.
Ensure all cabinets are clean and free of debris.
1.2.3 Floating Floor Installation:
Preparation:
Clear all areas where the floating floor will be installed.
Ensure the subfloor is clean, dry, and level; make necessary repairs if needed.
Installation Process:
Lay down underlayment according to the manufacturer’s specifications.
Begin laying the floating floor planks, starting from one corner of the room.
Use spacers to maintain expansion gaps around walls and fixed objects.
Cut planks as necessary to fit around corners and edges.
Finishing Touches:
Install baseboards or trim to cover expansion gaps, if applicable.
Clean the floor and ensure it is free of dust and debris.
1.2.4 Cleanup and Final Inspection:
Dispose of all debris and leftover materials in compliance with local waste management.
Perform a final walkthrough with the homeowner to ensure satisfaction with work completed.
Provide care instructions for new PVC and laminated cabinets and flooring.
1.2.5 Budget Considerations:
Materials: Cost of new PVC and laminated cabinets, flooring, underlayment, and any additional materials.
Labor: Estimated hours for removal and installation.
Contingency: Set aside a percentage of the budget for unexpected costs.
1.3 INSPECTION PRIOR TO BID: Prospective bidders are encouraged to visit the site to familiarize themselves with the existing conditions. The site visit will be predetermined by the Contracting Officer and will be displayed on the Bid Requests. All site visit arrangements should be made by contacting LT Clara E. Dahill at (787) 975-9470 or Clara.E.Dahill-Baue@uscg.mil at least three days prior to the site visit date. Prospective bidders must have a copy of this SOW to gain access to the Housing areas. Have a valid driver’s license, vehicle registration and no firearms.
1.4 SUBMITAL OF QUOTES: Quotes with a detailed and complete breakdown of all labor, equipment, and material (separately) shall be submitted by e-mail to the Contracting Officer.
1.5 HOURS OF OPERATION: The services under this contract shall be performed during the normal duty hours indicated from 7:00 AM to 3:30 PM, Mondays through Fridays (excluding federal holidays), except as otherwise authorized by the Contracting Officer Representative.
1.6 AVAILABILITY OF UTILITY SERVICES: Reasonable amounts of electricity and potable water will be available to the Contractor without cost. The Contractor shall pay all costs incurred in connecting, converting, and transferring the utilities to the work. The Contractor shall be responsible for making connections. Temporary toilet facilities shall be provided and maintained by the Contractor for personnel.
1.7 CONTRACTOR SAFETY, SECURITY AND USE OF PREMISES: The Contractor will be working on a Coast Guard military installation and must be familiar with and obey established fire, safety, environmental and security regulations.
1.7.1 Security Passes: Contractor personnel shall obtain security passes from the Security Office prior to beginning work and must always carry this ID while working on this project. Each employee must show a valid driver’s license, birth certificate or company ID card to be issued a security pass. The Security Office, building 146 Wing Road, is open to contractors for ID issuance Monday thru Thursday, 0800 – 1200. Personnel shall not stray from the immediate area of work or direct avenues of ingress and egress unless authorized in advance by the Contracting Officer's Representative (COR).
1.7.2 Safety Practices: The Contractor shall ensure that the work area is clearly marked at all times and take necessary precautions to ensure safety hazards are minimized and mitigated. Perform and conduct the work to minimize obstruction to the paved driveways and parking and walkway area, and other interference with Coast Guard operations. Contractors must follow the latest OSHA regulations on this project. The contractor shall prepare a Job Safety Analysis (JSA) and turn it into COR. The contractor certifies that all contracted personnel is qualified and trained in Safe Work Practices, Personal Protective Equipment (PPE) and Hazard Communication (HazCom and SDS). In the event of an accident, report immediately to COR and prepare an incident report.
1.7.3 Hazardous Materials: The Contractor shall provide the Government with a list of all hazardous materials to be used in the performance of this project and ensure Safety Data Sheets (SDS) are available at the work site for all hazardous materials used. The Contractor shall provide and have at hand spill kit materials and containers to collect any spillage. Immediately contain and clean up the release or spill of any hazardous material and report the incident to the Environmental Protection Specialist, Mr. William González Hernandez at (787) 600-2672 or William.GonzalezHernandez@uscg.mil. The contractor shall not use any toxic substances materials as Asbestos, PCB, Lead, or prohibited refrigerants.
1.7.4 Equipment, Tools, and Vehicles: The contractor shall inspect on a daily basis and ensure that all equipment, tools, and vehicles:
· Do not have leaks and/or deteriorated hydraulic hoses.
· All electrical cords and electrical extensions need to be in good condition.
· Ladders need to be in good condition and comply with the user’s weight.
1.7.5 Protection of Property: The Contractor shall protect the existing surrounding equipment, personal belongings, and property during the course of this work. Any damage caused by the Contractor shall be corrected at Contractor’s expense. The Contractor will be responsible for repair of any damage incurred to turf, landscaping, buildings, utilities, or pavement as a result of their work at no additional cost to the government.
PART 2 – GENERAL REQUIREMENTS
2.1 The Contractor is responsible for verifying all dimensions, quantities, and conditions at the job site prior to commencing work.
2.2 Minor materials and work not specifically mentioned herein but necessary for the proper completion of the specified work shall be furnished without additional cost to the Government.
2.3 Contractor shall be required to commence work under this contract within the next 10 days after notice proceeding (NTP) given by the Contracting Officer. The project shall be completed within 5 days after commencement for a total of 15 days. The 15 days will include the time for submittals review and approved and to complete all project records (closeout documents). Any weather delays shall be immediately notified of the Contracting Officer’s Representative.
2.4 Contractor shall submit a schedule of activities prior project start and activity vision plan for the project.
2.5 The project is located at:
USCG Base Borinquen, 260 Guard Road, Aguadilla, Puerto Rico 00603
2.6 Contractor shall request a final inspection prior to departing the worksite. The Contractor shall request final inspection with at least 1 working days in advance for proper coordination and approval. The Contractor shall provide any materials, labor and equipment and others to provide a usable and complete project.
2.7 Contractor shall coordinate all work with the USCG Facilities Engineering Department (COR) Mr. Hector Laguer at (787)890-8465, the Facilities Engineer LT Clara E. Dahill-Baue at (787)975-9470, Local Housing Officer, and Environmental staff. Notify the USCG Facilities Engineering Department at least 3 working days in advance of work at the site to allow the USCG to provide notification to affected users.
2.8 The Contractor is authorized to work from 7:00 am – 4:00 pm Monday to Friday. Contractor shall provide the Contracting Officer with of names of all personnel who will be working on the site. The contractor may submit a revised list at any time during the project. Only personnel on the approved listing will be allowed on the site. All personnel shall carry proper identification (ID) when on site. Proper ID is defined as either the individual’s driver’s license ID or passport. The identification must be laminated and show a facial picture of the individual. Individuals without proper ID will be escorted off the Coast Guard premises.
2.9 Warranty Document: Document shall state the manufacturer and/or contractor shall repair or replace the complete component if deterioration is caused by defective materials or workmanship. Also included shall be a paragraph certifying that all work was performed according to the manufacturer’s recommendations. In addition, warranty shall specify that in the event of any deficiency created by an “Act of God” or any other event, if the contractor with the same original product does the repairs, the contractor shall continue honoring the existing warranty. Document shall be submitted to the COR or Facilities Manager Engineer for record.
2.10 The Contractor shall comply with the Immigration and Nationality Act (INA).
2.11 Contractor shall clean the job site daily and dispose debris outside of USCG property.
2.12 Contractor shall conduct operations to cause the least possible interference with the normal operations, streets, driveways, parking areas and others.
2.13 Contractor shall store materials only in locations authorized by the Contracting Officer. No fire and hazardous materials or flammable liquids shall be stored or otherwise maintained within a building or structure, except as approved, and in accordance with the local fire regulations.
2.14 Contractor shall comply with all safety requirements, personnel protective equipment (PPE) and OSHA Safety and Health Standards Digest, latest version, in all their activities and operations to perform the work. The Contractor shall comply with EM-385 and PROSHA requirements.
2.15 Cleaning up: All clothes, cotton, waste, sanding disks, and other cleaning materials which might constitute a fire hazard shall be placed in a metal container or destroyed at the end of each workday. Upon completion of the work, all staging, containers, and debris shall be removed from the site. Adjacent areas and surfaces negatively affected during the performance of this contract shall be left clean and returned to the original condition. The Contractor shall not use Coast Guard waste disposal facilities including garbage cans, trash piles or dumpster to dispose of cleaning materials.
2.16 Protection of Premises: The Contractor shall take all necessary precautions to protect the Government and private property from damage as a result of their operations. Existing property so damaged shall be promptly restored, repaired, or replaced to its original condition by the Contractor at their own expense.
2.17 Contractor shall coordinate all required work with the USCG Facilities Engineering Department, LT Clara E. Dahill Baue via e-mail at Clara.E.Dahill-Baue@uscg.mil, Tel: (787) 975-9470.
Base Borinquen
*** END ***