This is a Statement of Work (SOW) for plant removal services at the United States Coast Guard Rio Bayamon Housing complex in Bayamon, Puerto Rico, with a project number XXX and an effective date of November 2026.
The contractor shall remove all plants, shrubs, bushes, and vegetation planted by previous residents from 25 homes at the facility, including cutting specified plants to their base and removing all roots or stubs to prevent regrowth. The scope of work encompasses debris disposal through collection and proper disposal of all resulting plant material, site cleanup to leave front, side, and backyards clean and visually presentable, and sod replacement in grassed areas as needed to maintain overall appearance. All work must be performed by licensed contractors in respective trades and conducted during weekdays from 0800 to 1400 hours, excluding weekends and federal holidays. The contractor must hold a kick-off meeting within 10 days of award and submit required documentation including a roster of personnel, construction progress schedule with major milestones, safety plan addressing hazards such as elevated working surfaces, and product data sheets for manufactured items. The contractor shall maintain compliance with International Code Council (ICC) standards, Coast Guard regulations, and local regulations. A one-year warranty or manufacturer's standard warranty period, whichever is longer, covers all supplied goods, systems, equipment, designs, and work. Project coordination contacts are LCDR Mark Funke at (787) 360-1101 and DCC Ryan Hope at (206) 815-7510, with daily work updates required via phone or text to DCC Hope at (253) 258-8674. A mandatory site visit is required to view all material needing removal.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. GUARD BASE SAN JUAN
SAN JUAN, PUERTO RICO 00901
STATEMENT OF WORK FOR
PLANT REMOVAL VACANT HOMES
AT
UNITED STATES COAST GUARD
RIO BAYAMON HOUSING
BAYAMON, PR
PROJECT NUMBER: XXX
NOVEMBER 2026
Reviewer Signature Date
Base San Juan Facilities
Engineer
LCDR M. Funke
Base San Juan Public Works
Officer
LT. C. Baker
BASE San Juan PN:XXX
PN XXX COCONUT TREE AND TREE REMOVAL
1. General
1.1. General Work Requirements
The work includes furnishing all labor, tools, equipment, materials, supervision and incidentals for work at the U.S. Coast Guard Rio Bayamon Housing. Work generally includes, but is not limited to, the following:
• Removal of plants, shrubs, bushes.
• Remove associated stums and roots.
• Replacement of sod or landscape restoration to the area of tree removal.
1.2. Qualifications and Performance Requirements
1.2.1. Qualifications
A. All work shall be performed by licensed contractors with licenses in respective trades.
1.2.2. Performance and Specific Work Requirements
The objective of this project is to safely and efficiently remove plants, shrubs and any vegetation that was planted by previous residents in 25 homes at Río Bayamón Housing
Complex. The work includes removing the plants down to their base, removing all debris from the premises, and leaving all designated areas clean, well-maintained, and visually presentable. For each designated residential unit, the contractor will provide all necessary labor, materials, tools, equipment, and supervision required to perform the following:
• Remove all plants, shrubs, bushes or vegetation: Cut down specified plants to their base and remove all roots or stubs to prevent them from regrowing.
• Debris Disposal: Collect, transport, and properly dispose of all resulting plant material.
• Site Cleanup: Ensure that all affected front, side, and backyards are left clean, well-maintained, and visually presentable.
• If removed from an area with grass replace with SOD if needed to maintain an overall appearance and aesthetically pleasing appearance.
• Project Schedule: Submit proposed project schedule to DCC Ryan Hope via email at ryan.j.hope@uscg.mil.
• A site visit is required to view all material that needs to be removed.
mailto:ryan.j.hope@uscg.mil
• Project Schedule Plan: All work is to be done during the weekdays from
0800 to 1400. Excluding weekends and Federal Holidays.
• Project Supervisor shall update DCC Ryan Hope at the end of each work day via phone or text at (253) 258-8674.
1.3. Project Location
U.S. Coast Guard Rio Bayamon Housing
500 Carr 177.
Bayamon, PR 00959
2. Applicable Documents and Code Compliance
2.1. The contractor shall assume full responsibility to ensure work is in compliance with all
ICC, Coast Guard Regulations, and local regulations, unless otherwise specified.
3. Submittals
3.1. Within 10 days after award the contractor shall hold a kick-off meeting for all interested parties to go over expectations, requirements, and proposed plan of execution.
3.2. Submittal List
A. Roster Of Personnel
B. Project Schedule
(1) Prepare a Construction Progress Schedule. It shall include all major milestones and events for the entire duration of the construction contract.
C. Safety Plan
(1) At a minimum, describe the general safety program and identify specific safety provisions for hazards incidental to the contract work such as elevated working surfaces, or similar conditions of the work. Comply with the paragraph titled Safety
Program.
D. Product Data
(1) Submit the product data sheet for each manufactured item. It shall include the manufacturer's descriptive literature of cataloged products, equipment drawings, diagrams, performance and characteristic curves and catalog cuts. Submit complete descriptive data for each type of material. Clearly mark data to indicate the type of material to be provided.
4. Warranty
The Contractor shall warrant that all goods supplied, systems, equipment, designs, and work covered by this Scope of Work and subsequent contract shall be satisfactory for its intended purpose, shall conform to and perform as called for in the Contract requirements specifications and shall be free from all defects and faulty materials and workmanship. Any goods supplied, systems, equipment, designs, or work found to be defective within the time specified below shall be repaired, remedied, or replaced, hereinafter called “corrective work”, by the Contractor, free of all charges including transportation. The duration is to be one year or the manufacturer’s standard warranty period, whichever is longer.
5. Coordination
Contact LCDR Mark Funke (787-360-1101), or DCC Ryan Hope (206) 815-7510 regarding all questions pertaining to the project.