SOW- acoustic wall fabric system.pdf

PDF 322 KB Posted

Attached to
Installation of AcoustiWall Fabric Stretch System
Solicitation number
31110PR260000002
Issued by

About this file

This Scope of Work (SOW) details a project for the U.S. Coast Guard Headquarters to replace acoustical fabric wall treatments in a 3-room conference center located in Washington, DC. The project requires furnishing and installing new AcoustiWall Fabric Stretch System across approximately 1,452 square feet of existing fabric-stretch wall surfaces. The installation is estimated to take 4-8 standard working days, with the contractor requiring full access to the installation areas during scheduled workdays.

Key contractor responsibilities include one-time mobilization, providing necessary height tools for installation, and creating layout drawings. The SOW explicitly excludes certain tasks such as furniture removal, handling wall-mounted obstructions (light switches, receptacles, strobes, TVs), and any electrical or wall modification work. Work will commence after formal acceptance of the SOW and issuance of a purchase order. The project aims to maintain a clean, professional appearance consistent with Coast Guard standards for their mission-critical meeting spaces.

View the file

Other files

File Type Posted
Question and answers 31110PR260000002.docx DOCX document
SF-1449 31110PR260000002.pdf PDF
12a. RFQ Schedule 31110PR260000002 19DEC25.pdf PDF
Pricing Spreadsheet.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNITED STATES COAST GUARD

Department of Homeland Security

Scope of Work (SOW)

Project: Installation of AcoustiWall Fabric Stretch System

Location: US Coast Guard DC – Conference Center LL6 2703 Martin Luther King Jr Ave SE Washington, DC 20593

Customer POC: Stephen Mong – stephen.a.mong@uscg.mil

1. Project Overview

The U.S. Coast Guard Headquarters operates a large, 3 room conference center that relies on the acoustical wall treatments to support daily mission-critical meetings and events. The existing acoustical wall surfaces have reached the end of their service life and require surfacing to maintain a clean, professional appearance consistent with Coast Guard standards.

To address this need, the awarded contractor will furnish and install new acoustical fabric across all fabric-stretch wall surfaces within the conference center, covering approximately 1452 square feet in total.

2. Period of Performance & Access Requirements

- Estimated installation duration: 4-8 standard working days.

- Work hours: Standard day-hours per contractor policy.

- Contractor requires full access to all installation areas during scheduled workdays.

3. Contractor Responsibilities / Included Services

3.1 Installation Scope

- Furnish and install new acoustical fabric.

- Install across all existing fabric stretch wall surfaces (~1,452 sq ft).

UNITED STATES COAST GUARD

Department of Homeland Security

3.2 Installation Inclusions

- One mobilization for installation on consecutive working days.

- All necessary height tools for installation.

- Provision of layout drawings.

4. Exclusions

The following work is not included and must be addressed by others:

- Removal of furniture obstructing access to wall surfaces.

- Removal or extension of wall-mounted obstructions such as light switches, receptacles, strobes, TVs, etc.

- Electrical work, wall modifications, or other trades.

7. Acceptance

Work will proceed after formal acceptance of this Scope of Work and issuance of a purchase order or equivalent authorization.

File details come from the government source that posted it. Updated .