This is a Statement of Work (SOW) for maintenance and repair services at USCG Base Portsmouth.
The contractor shall provide comprehensive switchgear maintenance services including inspection, cleaning, breaker servicing, and DC control power battery replacement at USCG Base Portsmouth, Portsmouth, Virginia. Task One requires vacuum and interior cleaning of switchgear vertical sections, inspection of hinges, latches, interlocks, door gaskets, busbars, insulators, and supports, and racking out/inspection of one 1200A main breaker, three 1200A feeder breakers, and one 1200A generator breaker. The contractor must inspect primary stabs, finger clusters, ground shoes, secondary disconnect contacts, arc chutes, inter-phase barriers, and charging mechanisms, then provide a written inspection report to the USCG. Task Two requires safe isolation and disconnection of four existing 12V 32A control power batteries, inspection and cleaning of the battery rack/tray for acid damage and rust, supply and installation of four new OEM-equivalent 12-volt 32-amp batteries with proper torque and anticorrosion treatment, energization of the battery charger with verification of DC output polarity and system connection, and testing of charger alarms and indicators to ensure steady DC control voltage to switchgear trip and close circuits. The contractor must furnish all labor, tools, specialized equipment, PPE, materials, and certified technicians.
The period of performance shall not exceed 15 working days after contract award, with work generally performed between 0700 and 1530 EST Monday through Friday, except federal holidays. The place of performance is 4000 Coast Guard Blvd, Portsmouth, Virginia. A Project Manager must be available to the QAE via telephone during business hours and respond to technical issues within 24 hours. Contractor employees require pre-vetted base access with valid identification; site visits must be pre-arranged three days in advance with Nathan Chappell, QAE Representative, at (206)815-2176 or Nathan.C.Chappell@uscg.mil. The contractor must comply with federal safety regulations (29 CFR 1910 and 1926), environmental protection requirements (40 CFR), and must coordinate Lock Out/Tag Out procedures with Facilities Division. Travel costs are included in the overall contract cost. All written reports must be in Microsoft Office-compatible electronic format. The contractor furnishes all necessary facilities, materials, equipment, and services. Upon completion, the QAE will conduct inspection with authority to reject deficiencies or require corrections.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Wage rate determination.pdf | ||
| SF-18 RFQ Base Portsmouth.pdf | ||
| Poster SCA Poster.pdf | ||
| FAR Clauses and Deviations Services.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PR #: 31040PR270000084
STATEMENT OF WORK
LAST UPDATED: 11/12/2026 PAGE 1/6
STATEMENT OF WORK (SOW)
FOR
USCG Base Portsmouth Main Switchgear Cleaning, Visual Inspection, Breaker Servicing, Battery Replacement and DC Control Power Maintenance
1.0 GENERAL
1.1 SCOPE
The Contractor shall furnish new batteries and all necessary labor, tools, specialized equipment, personal protective equipment (PPE), materials, and certified technicians to inspect and clean the switchgear vertical sections. Switchgear DC Control Battery Replacement & Charger Operational Check. Verify de-energization, zero energy verification, and apply facility-approved LOTO protocols. If work on the control battery system must occur while switchgear is online, strict DC arc/shock protective boundaries must be enforced.
2.1 TASK ONE. Switchgear Vertical Sections: Inspection and Cleaning
2.1.1 Vacuum and clean exterior panels, louvers, filters, and access doors.
2.2.2 Clean switchgear interior compartments. Wipe down insulators, busbar supports, and barriers. Ensure louver screens and ventilation pathways are clear of dust and debris. Clean breaker frames, operating linkages, and arc chutes.
2.2.3 Inspect hinges, latches, interlocks, and door gaskets for physical damage, binding, or deterioration. Inspect internal vertical sections, busbars, supports, and insulators.
2.2.3 Rack out/draw out the One (1) 1200A Main Breaker , Three (3) 1200A Feeder/Breakers One (1) Generator Breaker 1200 A into the disconnected/test position (or remove to breaker maintenance cart).
2.2.4 Inspect primary stabs, finger clusters, ground shoes, and secondary disconnect contacts for signs of wear, burning, galling, or misalignment. Inspect arc chutes, inter-phase barriers, and charging mechanism assemblies.
2.2.5 Provide a inspection report to the USCG
2.2 TASK TWO. Switchgear DC Control Battery Replacement & Charger Operational
Check
2.2.1 Safely isolate and disconnect the existing four (4) 12V 32A control power batteries.
Remove old batteries and dispose of/recycle them in strict accordance with EPA and local environmental regulations (provide recycling manifests).
LAST UPDATED: 11/12/2026 PAGE 2/6
2.2.2 Clean battery rack/tray, inspecting for acid damage, rust, or structural integrity issues. Apply neutralizing wash if necessary.
2.2.3 Supply and install four (4) new OEM-equivalent 12-volt, 32-amp batteries. Clean, treat, and torque all inter-cell connectors, terminals, and cable using anti-corrosion grease and calibrated torque tools
2.2.2 Energize the installed battery charger and verify proper DC output polarity and system connection. Measure and document open-circuit and loaded output voltage.Verify charger operating modes.
2.2.3 Test functional charger alarms and indicators (e.g., AC Failure, Low DC Voltage, High DC Voltage, Ground Fault detection). Verify that the switchgear trip and close control circuits receive steady, uninterrupted DC control voltage.
3.0KEY PERSONNE
Project Manager
3.1 PROJECT MANAGER
3.1.1 The Project Manager must be available to the QAE via telephone between the hours of 0700 and 1530 EST, Monday through Friday, and must respond to a request for discussion or resolution of technical problems within 24 hours of notification.
3.2 EMPLOYEE IDENTIFICATION
3.2.1 The QAE will provide a Base Access request form. The Contractor will need to return the Base Access form with list of all employees to the QAE Representative five (5) days prior to commencing work. The USCG Base Portsmouth Security Office will be given a copy of the employee list, and a pass will be issued for entry. A valid state license plate and safety inspection sticker is required. All vehicles operated on government property shall be maintained in a good state of repair.
3.3 EMPLOYEE CONDUCT
Contractor’s employees must comply with all applicable Government regulations, policies and procedures (e.g., fire, safety, sanitation, environmental protection, security, and possession of weapons) when visiting or working at Government facilities. The Contractor must ensure Contractor employees present a professional appearance at all times and that their conduct must not reflect discredit on the United States or the Department of Homeland Security. The Project Manager must ensure Contractor employees understand and abide by Department of Homeland Security established rules, regulations and policies concerning safety and security.
3.4 REMOVING EMPLOYEES FOR MISCONDUCT OR SECURITY REASONS
The Government may, at its sole discretion (via the Contracting Officer), direct the Contractor to remove any Contractor employee from DHS facilities for misconduct or security reasons.
Removal does not relieve the Contractor of the responsibility to continue providing the services
LAST UPDATED: 11/12/2026 PAGE 3/6
required under the contract. The Contracting Officer will provide the Contractor with a written explanation to support any request to remove an employee.
3.5 SITE VISIT
A site visit is recommended to conduct field verification of any/all quantities and measurements before submitting bids. Interested parties shall make arrangements for a site visit with the QAE.
3.5.1 DESIGNATED CONTRACTING OFFICER’S QA EVALUATOR (QAE)
REPRESENTATIVE
Nathan Chappell. (206)815-2176 Nathan.C.Chappell@uscg.mil.
3.5.2 All site visits are to be pre-arranged a minimum of three (03) days in advance. To arrange a site visit, the QAE will email a base access form to be filled out.
3.5.3 CONDITIONS AFFECTING THE WORK
The Offeror should visit the site and take such other steps as may be reasonably necessary to ascertain the nature and location of the work, the general and local conditions which can affect the cost of the work thereof. Failure to do so will not relieve bidders from responsibility for estimating properly the difficulty or cost of successfully performing the work. The government will assume no responsibility for any understanding or misrepresentations concerning conditions made by any of its officers or agents prior to the execution of the contract, unless included in the request for quotes, the specification or related documents. All contractors that require Base access will have to be pre-vetted for entry prior to commencement of work.
3.6 SECURITY
Each contractor that does not have Real ID on their Driver licenses will need to present one of the following credentials:
. U.S. Department of Defense ID, including IDs issued to Active Duty, Reserve, National Guard, retirees and dependents.
. RAPIDGate Credential . HSPD-12 PIV card . State-issued Enhanced Driver's License . U.S. passport . U.S. passport card . DHS trusted traveler cards (Global Entry, NEXUS, SENTRI, FAST) . Permanent resident card . Border crossing card . Federally recognized Tribal Nation/Indian Tribe, including Enhanced Tribal Cards (ETCs) . Foreign government-issued passport . Canadian provincial driver's license or Indian and Northern Affairs Canada card . Transportation worker identification credential . U.S. Citizenship and Immigration Services Employment Authorization Card (I-766) . U.S. Merchant Mariner Credential . Veteran Health Identification Card (VHIC)
LAST UPDATED: 11/12/2026 PAGE 4/6
3.7 AWARD OF THE CONTRACT: The contractor must immediately notify the contracting officer’s QAE representative of his intended start date. The work shall be done in accordance with the specification.
4.0 PERIOD OF PERFORMANCE
The period of performance for this contract must not exceed 15 working days after contract award or as negotiated with Contracting Officer and Facilities Engineering.
4.1 PLACE OF PERFORMANCE
The primary place of performance will be at 4000 Coast Guard Blvd, Portsmouth, VA
4.2 HOURS OF OPERATION
Contractor employees must generally perform all work between the hours of 0700 and 1530 EST, Monday through Friday (except Federal holidays). However, there may be occasions when Contractor employees must be required to work other than normal business hours, including weekends and holidays, to fulfill requirements under this SOW. If the contractor desires to carry on work on Saturday, Sunday, holidays or outside the station’s regular hours, he may submit his request in writing to the Contracting Officer’s QAE Representative for approval consideration. The contractor shall allow ample time to enable satisfactory arrangements to be made by the government to inspect the work in progress.
4.3 TRAVEL
Travel shall not be included as an additional/separate line item. Travel is required for delivery and installation purposes and shall be included as part of the overall cost.
4.4 GENERAL REPORT REQUIREMENTS
The Contractor must provide all written reports in electronic format with read/write capability using applications that are compatible with DHS workstations (Microsoft Office Applications).
1.0 4.5 CONTRACTOR FURNISHED PROPERTY
The Contractor must furnish all facilities, materials, equipment and services necessary to fulfill the requirements of this contract.
4.6 GOVERNMENT ACCEPTANCE PERIOD
Upon completion of work, contact the Contracting Officer QAE Representative to arrange for inspection/acceptance of work.
4.6.1 The QAE will conduct an inspection of the work conducted by the Contractor and will have the right to reject or require correction of any deficiencies found that are contrary to the information contained in the Contractor’s accepted proposal. In the event of a rejected deliverable, the Contractor will be notified in writing by the QAE of the specific reasons for rejection. The Contractor may have an opportunity to correct the rejected deliverable and return it per delivery instructions.
LAST UPDATED: 11/12/2026 PAGE 5/6
5.0 OTHER APPLICABLE CONDITIONS
5.1 SECURITY/SAFETY
All contractors working on CG Base Portsmouth shall abide by all federal safety regulations as published by the Occupational Health and Safety Administration, 29 CFR 1910 (series) and 29 CFR 1926 (series). Contractor written safety programs shall be reviewed by the Base Safety Officer prior to starting work.
Written notification must be provided to the Base Safety Officer; in their capacity as Base Fire Marshal of any activity that could potentially cause fire or explosion or that changes or reduces the capability of fighting a fire or explosion. Some examples of qualifying activities are: a fire hydrant or fire suppression system that must be taken out of service for any reason, electrical work that affects fire alarm systems, introduction of hazardous or flammable material onto the Base, and blocking of any egress routes or emergency vehicle routes. Inclusion of this information in the contract constitutes written notification as long as the outsource review sheet is signed by Base Safety Officer.
Lock Out/Tag Out requires notification and coordination with facilities and will not be conducted by a contractor on Base Portsmouth. A Facilities Division representative is required for all contractors Lock Out/Tag Out needs.
Every employee working on Base Portsmouth has the right to a safe and healthy work place.
The contractor has the responsibility and right to stop unsafe work. QAE’s and the Safety Officer may also institute a work stoppage relating to unsafe practices or immediate danger to life and health situations.
5.2 ENVIRONMENTAL PROTECTION REQUIREMENTS:
All contractors working on CG Base Portsmouth shall abide by all federal environmental regulations as published by the Environmental Protection Agency, 40 CFR (series). Contractors written environmental management and pollution prevention programs shall be reviewed by the Environmental Protection Specialist prior to starting work and must be in accordance with ICSPORTSVA INSTM5090.2, the Unit Environmental Guide.
Written notification must be provided to the Environmental Protection Specialist of any activity that could potentially cause a permit violation on Base Portsmouth. Some examples of qualifying activities are: any activity that could result in a spill or discharge into a waterway or introducing a hazardous material into the environment.
Copies of the following must be provided to the Environmental Protection Specialist prior to starting work in affected areas: Material Safety Data Sheets, permits, and notices of intent.
Hazardous materials used by a contractor are required to be disposed of by that contractor.
Disposal must be in accordance with federal, state, and local guidelines.
5.3 PERMITS: The contractor shall, without additional expense to the government, obtain all appointments, licenses, and permits required for the prosecution of the work. The contractor shall comply with all applicable federal, state and local laws.
LAST UPDATED: 11/12/2026 PAGE 6/6
5.4 WORKMANSHIP: All work shall be accomplished with the best standard practices, and by workmen thoroughly experienced in the required trades. The work shall be supervised by experienced personnel and shall be satisfactory for the Contracting Officer.
5.5 ORAL MODIFICATION: No oral statement of any person other than the contracting officer shall in any manner or degree, modify or otherwise affect the terms of this contract.