This Statement of Work (SOW) details a remodeling project for the US Coast Guard Station in Los Angeles/Long Beach located in San Pedro, CA. The project involves comprehensive renovations of five bathrooms and two locker rooms, including complete fixture replacement, tile and flooring removal, and installation of new commercial-grade, waterproof LVP flooring. Additional scope includes CCTV camera inspection of underground sewage lines, potential sewage line repairs, and removal of the cloth drying area in the locker rooms.

The contractor is required to provide all labor, materials, and equipment, with work to be performed between 7:00 AM and 5:00 PM, Monday through Friday, excluding federal holidays. The Technical Point of Contact is Scott Whitehead (310-561-5597), who will select colors for new fixtures and finishes. Contractor requirements include maintaining valid vehicle registration and personnel identification, daily cleanup, minimizing impact to Coast Guard operations, and ensuring proper disposal of debris in accordance with industry standards and environmental regulations. Project completion will be monitored and accepted by the designated Coast Guard Technical POC.

View the file

Other files

File Type Posted
SOW REV2.pdf PDF
Solicitation Remodel Bathrooms and Locker Rooms.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

REMODEL BATHROOMS AND LOCKER ROOMS AT US COAST GUARD STATION LOS ANGELES /

LONG BEACH

PART 1 - GENERAL

The intent of this Statement of Work (SOW) is for the contractor to perform remodeling work on duty room bathrooms and locker rooms at USCG Station LA/LB in San Pedro, CA. This includes the removal and replacement of all fixtures in five bathrooms, removal and replacement of all tile and flooring, and the remodeling of two locker rooms with the removal of the clothes drying area and installation of new large built-in lockers. The contractor will provide all labor, materials and equipment required to fulfill these requirements. The Technical Point of Contact (POC) will select the color for the newly installed fixtures and finishes.

PART 2 - FACILITY AND SECURITY REQUIRMENTS

1. Contractor vehicles must have valid registration and insurance, and vehicle operators must have a valid driver license. All personnel shall have valid photo identification.

2. The contractor shall clean up all areas to ensure they are clear of debris daily. At completion of the project all construction areas will be returned to their original condition. The contractor shall remove all waste material generated and dispose of in accordance with industry standards and applicable environmental rules and regulations.

3. Minimizing impact to Coast Guard operations. Work performed at San Pedro, CA shall be completed between the hours of 7:00AM and 5:00PM, Monday thru Friday (excluding Federal Holidays) unless authorized by the Contracting Officer.

PART 3 - GOVERNMENT FURNISHED MATERIAL

1. Contractor will provide all materials to complete the work necessary. The government will provide electricity, parking, and laydown area as available from the unit. Bathroom facilities will not be available for contractor personnel.

PART 4 - TECHNICAL POINT OF CONTACT DESIGNATION

1. Technical POC for this task is:

Scott Whitehead Office: 310-561-5597 E-mail: Scott.E.Whitehead@uscg.mil

PART 5 – TASKS

1. Mobilization. Mobilize all necessary personnel and equipment to the site to safely execute the bathroom and locker room renovations.

2. Fixture Replacement. Replace all fixtures in five (5) bathrooms as per specifications provided.

3. Tile and Flooring Removal - Bathrooms. Remove all tile and flooring in the five (5) bathrooms in preparation for flooring installation.

4. Install new commercial grade, waterproof, hard-wearing LVP in all bathrooms, final color to be determined by the technical POC.

5. Locker Room Demolition. Remove the cloth drying area in two (2) locker rooms as specified.

6. Locker Installation. Install new large built-in lockers in the two (2) locker rooms.

7. Tile and Flooring Removal - Locker Rooms. Remove all tile and flooring in the two (2) locker rooms in preparation for flooring installation.

8. Install new commercial grade, waterproof, hard-wearing LVP in all locker rooms, final color to be determined by the technical POC.

7. Selection of Fixtures and Finishes. Coordinate with the Technical Point of Contact (POC) to select and approve the color of newly installed fixtures and finishes.

8. CCTV Camera Inspection. Inspect underground sewage lines using CCTV cameras to identify any issues.

9. Sewage Line Repair. Repair any identified issues in the underground sewage lines based on CCTV inspection findings.

10. Disposal. Dispose of all debris, old fixtures, and materials in accordance with industry standards and applicable environmental regulations.

11. Demobilization. Remove all equipment and personnel from the site and ensure the areas are returned to their original condition.

12. Make sure to include routine quality and safety checks throughout each task to ensure compliance with project standards and regulations.

PART 6 – ACCEPTANCE

1. Completion of work under this contract will be monitored and accepted by Coast Guard Technical POCs listed in

PART 4.

END