3 _ TCSG_407_DP Q_A Step I.pdf
PDF 95 KB Posted
- Solicitation number
- PE-40900-RFQC-2024-000000070
- Issued by
- Lowndes County, Georgia
About this file
This document contains Questions and Answers related to four CDL Truck Driving Range Projects across four Technical College System of Georgia (TCSG) campuses: Augusta Technical College (TCSG-407), North Georgia Technical College (TCSG-410), Chattahoochee Technical College (TCSG-411), and Northwestern Technical College (TCSG-418). The projects involve the expansion of CDL programs to additional campuses at TCSG-411 and TCSG-418. Specific details are provided regarding the design scope, which should include both civil and architectural disciplines, as well as the availability of building programs and existing CDL facility plans. The preliminary Stated Cost Limitations (SCL) are confirmed to be estimated construction costs only, with design fees being separate.
Regarding pricing and funding, the document states that design fees are separate from the estimated construction costs. TCSG will provide drawings for several CDL ranges constructed during FY2024 at the project kickoff meeting, along with DDS requirements and other design standards that may have been developed.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Shortlisted Firms.pdf | ||
| TCSG_DP RFQ Commerical Truck Driving Ranges.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers CDL Truck Driving Range Projects
TCSG-407 Augusta Technical College TCSG-410 North Georgia Technical College TCSG-411 Chattahoochee Technical College TCSG-418 Northwestern Technical College
1) Is there a template & size for each classroom building? No.
2) Will classrooms require water, sanitary, fire sprinkler? This could vary from one site to the other based upon site specifications.
3) Should team be comprised of civil & architect, or can they be separate? We intend to contract with a team or teams that are comprised of all the disciplines required to complete the full design scope. The team should include civil and architectural.
4) Please confirm the preliminary Stated Cost Limitations (SCL) are estimated construction costs only. Design fees are separate. Yes, that is correct.
5) Are building programs available for these 4 projects? Building programs are not available for the projects.
6) For the two colleges who have CDL programs and are expanding those programs to additional campuses (TCSG-411 and TCSG-418), are plans available for the existing CDL facilities?
TCSG will provide drawings for several CDL ranges constructed during FY2024 at the project kickoff meeting, along with DDS requirements and other design standards that may have been developed.
End of Questions and Answers