3-Site Civil Improvements and Building Safety Upgrades Addendum No. 1 4644.029.pdf

PDF 3 MB Posted

Attached to
Site Civil Improvements and Building Safety Upgrades
Solicitation number
US.261945
Issued by
Berks County, Pennsylvania

About this file

This Addendum No. 1 is issued by the Township of Spring, Pennsylvania in connection with its Site Civil Improvements and Building Safety Upgrades project (Entech No. 4644.029) for two separate contracts: Contract No. 1 (General Construction) and Contract No. 2 (Mechanical Construction). The addendum, dated November 11, 2026, clarifies project scope through the inclusion of architectural drawings (A-104, A-105, A-106, A-701, A-702, A-703), elevator shaft condition photographs for reference purposes, and responses to 28 previously submitted bidder questions. The addendum addresses key project elements including ballistic glass and panel details, electrical billboard specifications, foundation waterproofing systems, elevator shaft epoxy injection work, brick repointing scope clarifications, foundation crack repair procedures, interior work scheduling coordination, and excavation limits. Notably, the security camera system has been removed from the project scope, and the engineer has reduced the overall project scope to lower construction costs from the initial estimate. Bidders are advised that mandatory pre-bid attendance applies only to general contractors submitting through PennBid, and that permits will be waived by the Township, though all required permit applications, plan reviews, and inspections remain applicable. The bid opening date of December 2, 2026 at 2:00 p.m. remains in effect, with bids remaining subject to acceptance for 60 days after opening, or 120 days if delayed by government agency approvals, bond sales, or grant awards.

The contract contains multiple unit price line items for contingency work, including brick repointing (Bid Item No. 21), foundation crack repair per linear foot (Bid Item No. 22), and additional pressure-treated wood framing and concrete as may be required. All bid line items in the lump sum format are mandatory and cannot be omitted or submitted with zero-dollar amounts without rendering the bid non-responsive. The General Contractor is responsible for obtaining all permits and licenses, providing concrete testing (minimum one test during concrete placement), completing all required background checks and security clearances for personnel accessing secured areas, and coordinating all interior work with the Owner to minimize disruption to Police Department operations. All material shall comply with Pennsylvania prevailing wage requirements and steel products must be produced in the United States. The contract requires a 10 percent bid bond from an acceptable surety and includes warranty provisions requiring the contractor to remedy any defective materials or workmanship for three years from the date of substantial completion.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM NO. 1

Township of Spring

Site Civil Improvements and Building Safety Upgrades Contract No. 1 – General Construction

Contract No. 2 – Mechanical Construction

Entech No. 4644.029

November 11, 2026

The following addendum items hereby become an integral part and take precedence over the original drawings and project manual as though originally included therein at length and shall be so honored in the preparation of the Contractor’s bid and execution of the Contract.

Item 1.1 Project Manual

Elevator Shaft Photos

Addendum No. 1 includes photographs of the elevator shaft conditions for contractor reference and clarification purposes only. The photographs are being provided to assist bidders in understanding the existing conditions associated with the elevator shaft injection work.

Item 1.2 Previous Bid Questions and Answers

Please see attached.

Item 1.3 Project Drawings

Drawing A-104, A-105, A-106, A-701, A-702, A-703

ADD Drawings A-104, A-105, A-106, A-701, A-702, A-703 in their entirety to the project (Addendum No. 1).

END OF ADDENDUM NO. 1

The following includes all Questions and Answers from the previous bid, listed in the original chronological order. Due to the high estimated construction cost, the engineer reduced the project's scope to lower the overall construction cost. Questions and Answers “Applicable to this Rebid” are included below, while items that no longer apply are identified as "NOT applicable to this Rebid".

#1 - Pre-Bid Conference “NOT applicable to this Rebid” The updated project manual addresses this requirement.

#2 - Reason for Re-Bid “NOT applicable to this Rebid”

#3 - Engineer’s estimate?

“NOT applicable to this Rebid”

#4 - Brick Repointing “Applicable to this Rebid” Please Refer to Bid Item No. 21 in place of Bid Item No. 22 referenced in the previous answer below.

Question Status Is any brick repointing work to be included in the base bid, or will all repointing work be done by change order utilizing the unit pricing? If brick repointing is to be included in the base bid, please provide a SF of work to include.

Hollenbach Construction, Inc.

May 15, 2026 2:57 PM

#4 - Answer Brick repointing work is not included in the Base Bid unless specifically identified on the Drawings or Specifications. The intent of Bid Item No. 22 is to address localized repointing associated with installation of the new counter flashing at the perimeter waterproofing system. The Contractor shall include normal counter flashing installation procedures within the Base Bid. If adjacent mortar joints are damaged, loosened, or otherwise compromised during installation of the counter flashing, those localized repairs shall be compensated under the applicable unit price bid item.

Clint Davis May 15, 2026 4:08 PM

#5 - Foundation Crack Repair “Applicable to this Rebid” Please Refer to Bid Item No. 22 in place of Bid Item No. 23 referenced in the previous answer below.

Question Status Please verify all foundation crack repair work will be done by change order utilizing the unit pricing, and nothing should be included in the base bid for this work.

Hollenbach Construction, Inc.

May 15, 2026 2:59 PM

#5 - Answer Foundation crack repair associated with Bid Item No. 23 is separate from Bid Item No. 8 (Elevator Pit Chemical Grout Injection and Joint Sealing). Bid Item No. 23 is intended to address cracks discovered following excavation and removal of the existing foundation waterproofing system.

Contractors shall provide a unit price per linear foot for crack injection repair in the event cracks are exposed in the foundation during construction. No additional unidentified foundation crack repair quantities shall be included in the Base Bid.

Clint Davis May 15, 2026 4:10 PM

#6 - Interior Work Schedule “Applicable to this Rebid” Question Status Can all of the interior building work be done at the same time, or will we only be permitted to work in certain rooms at the same time?

Hollenbach Construction, Inc.

May 15, 2026 3:07 PM

#6 - Answer The Contractor may perform interior work concurrently in multiple areas, provided all work is coordinated with the Owner. Contractors shall comply with all security and access requirements identified in the Project Manual. Personnel performing interior work within the building shall complete all required background checks, clearances, and security coordination procedures prior to accessing secured areas of the facility. Coordination with the Owner shall be maintained at all times to minimize disruption to Police Department operations.

Clint Davis May 15, 2026 4:11 PM

#7 - Appendix B - List of Equipment & Materials “NOT applicable to this Rebid” The updated project manual addresses this requirement.

#8 - Bid Breakdown “Applicable to this Rebid” Question Status Please verify the bid breakdown on the GC bid form is for informational purposes only, and that individual line items can not be removed from the lump sum bid cost.

Hollenbach Construction, Inc.

May 15, 2026 3:09 PM

#8 - Answer The lump sum line items must not be omitted. Omissions or inclusion of zero-dollar amounts in the line items would result in the determination that bid is non-responsive.

May 18, 2026 2:43 PM

#9 - Alternates “NOT applicable to this Rebid” The updated project drawings addresses this requirement.

#10 - RE: RFI #4 Brick Repointing “Applicable to this Rebid” Please Refer to Bid Item No. 21 in place of Bid Item No. 22 referenced in the previous answer below.

Question Status The floor plans and elevations do not specifically identify any brick repointing. However, A-106 Architectural Repair/Misc Note #1 states "patch, repair and repoint deteriorated brick and mortar to match original color, texture & finish". Also, spec 040120.64 on drawing A-703, item 3.2.3 indicates “joints at locations of the following defects...”. This leaves it up to individual interpretation. If any brick repointing should be included in the base bid, please provide a quantity to include so all bids are equal.

Hollenbach Construction, Inc.

May 21, 2026 11:30 AM

#10 - Answer No, brick repointing work is not included in the Base Bid. Contractors are not expected to inspect and repoint all masonry joints around the building. The counter flashing scope includes removal of mortar at the flashing termination location and sealing of the reglet joint as part of the flashing installation and is not considered part of Bid Item No. 22. Bid Item No. 22 is intended only for localized mortar joint repairs adjacent to the counter flashing installation where joints become loosened, damaged, or otherwise compromised during construction. Contractors shall provide a unit price under Bid Form (Contract No. 1) Item No. 22 for potential localized repointing work.

Clint Davis May 21, 2026 2:03 PM

#11 - Site Visits “NOT applicable to this Rebid”

#12 - New Applied Glass Stops “Applicable to this Rebid” Question Status Detail 3 on A-104, are the new applied glass stops to be done vertically and horizontally, or just vertical?

Hollenbach Construction, Inc.

May 21, 2026 11:24 AM

#12 - Answer The applied glass stops shall be installed at the full perimeter of the glass.

May 21, 2026 3:40 PM

#13 - Elevator Shaft “Applicable to this Rebid” Question Status Could you please share pictures of the elevator shaft? Also, do you have any recommended subcontractors for the epoxy injection work?

Hollenbach Construction, Inc.

May 28, 2026 8:42 AM

#13 - Answer Addendum No. 3 includes photographs of the elevator shaft conditions for contractor reference and clarification purposes only. The photographs are being provided to assist bidders in understanding the existing conditions associated with the elevator shaft injection work. Chemical injection contractors have been notified and added to the PennBid vendor list for bidder convenience should quotes be needed for this portion of work.

Clint Davis May 29, 2026 12:02 PM

#14 - Camera cable pathways “NOT applicable to this Rebid” The security camera system has been removed from the project scope.

#15 - Camera downtime “NOT applicable to this Rebid” The security camera system has been removed from the project scope.

#16 - Expected order date “NOT applicable to this Rebid”

#17 - Camera model clarification “NOT applicable to this Rebid” The security camera system has been removed from the project scope.

#18 - Switch Specification project scope.

#19 - Training on Cameras project scope.

#20 - HEPA Filters

#21 - Mandatory PreBid Attendance Requirement “Applicable to this Rebid” Question Status Does the mandatory PreBid requirement apply only to General Contractors submitting bids through PennBid, or does it also apply to subcontractors?

Clint Davis Jun 01, 2026 4:13 PM

#21 - Answer Mandatory PreBid attendance applies only to General Contractors submitting bids through PennBid.

Subcontractors are not required to attend.

Clint Davis Jun 01, 2026 4:13 PM

#22 - Electrical Scope – Contract Division (Contract No. 1 vs Contract No. 2) “NOT applicable to this Rebid”

#23 - Required Permits “Applicable to this Rebid” Question Status Are the General Contractors responsible for obtaining all required permits?

Clint Davis Jun 02, 2026 2:47 PM

#23 - Answer Permits are required for this project. The General Construction Contractor (Contract No. 1) and the Mechanical Contractor (Contract No. 2) shall each be responsible for obtaining the permits associated with their respective contract scopes. Separate permit applications shall be submitted for each contract. The Township has advised that permit fees will be waived. However, all required permit applications, plan reviews, and inspections remain applicable.

Clint Davis Jun 02, 2026 2:47 PM

#24 - Concrete Testing “Applicable to this Rebid” Question Status Is the General Contractor responsible for performing concrete testing for the project?

Clint Davis Jun 02, 2026 2:53 PM

#24 - Answer Yes. The General Contractor shall be responsible for providing concrete testing as required for the project. At a minimum, one concrete test shall be performed during concrete placement. Testing is not required for every truckload unless otherwise required by the Contract Documents or applicable codes and standards.

Clint Davis Jun 02, 2026 2:53 PM

#25 - Current Fire Alarm Service Provider

#26 - HOT WATER PIPING:

“NOT applicable to this Rebid” The updated project drawings addresses this requirement.

#27 - Carrier unit - Cooling Only “NOT applicable to this Rebid”

#28 - Engineer Clarification – Excavation Limits Depicted on Sheet C-403 “Applicable to this Rebid” Question Status For bidding purposes, the Engineer is providing the following clarification regarding the grey shaded area shown on Sheet C-403.

Clint Davis Jun 03, 2026 4:25 PM

#28 - Answer The grey shaded area is intended to generally depict the anticipated excavation limits associated with the foundation waterproofing, foundation drain installation, and restoration work. It is not intended to define an exact excavation width. Temporary excavation limits, excavation support systems, and site slopes required for construction have not been shown on the Drawings. The Contractor shall determine and provide all excavation, shoring, sloping, and other measures necessary to safely perform the work in accordance with the Contract Documents, applicable laws, regulations, codes, and accepted industry practices. Actual excavation limits may vary based on field conditions and the Contractor's means and methods.

Jun 03, 2026 4:25 PM

A

B

2 3

C

D

1 2 3

4 5 6

A

B

D

AT

E R

EV

4 5

IS

SU

ED

F

O R

/R

EV

IS

ED

C

AP

PD

D

TO

W

N

SH

IP

O

F

SP

R

IN

G

TO

W N

SH

IP

O F

SP

R

IN

G

, B

ER

KS

C

O U

N

TY

, P

EN

N

SY

LV

AN

IA

SI

TE

C

IV

IL

IM

PR

OV

EM

EN

TS

A

ND

B

UI

LD

IN

G

SA

FE

TY

U

PG

RA

DE

S

/1

1/

BI

D

D

IN

G

SO

G

4644.029

PROJECT NO.

APPROVED BY:

SCALE:

CHECKED BY:

PREPARED BY:

DRAWING NO.

SOG

EMG / BB

AS NOTED

SOG

24-0010

MGA PROJECT NO.

AR

C

H

IT

EC

TU

R

AL

BA

LL

IS

TI

C G

LA

SS

A

ND

P

AN

EL

D

ET

AI

LS

A

ND

N

O

TE

S

A-104

P E

N N

A V

E N

U E

W Y

O M

IS

S

IN

G

P

A

.3

.4 w w w .M

G -A rc h it e c ts

.c o m

24-0010_Spring Twp PD.pln | V:\Drawings\24-0010.0_Entech-Spring Twp PD Security Upgrades\1-Design\24-0010_Spring Twp PD.pln | 5/11/2026 | 2:16 PM

A-104

1"

TYP.

2.01.02

5.50.01 9.29.01

2.01.04

2.01.022.01.04

CUT GYPSUM BOARD

FLUSH w/ EDGE OF

EXISTING DOOR FRAME

2.41.01

CUT GYPSUM BOARD

FLUSH w/ EDGE OF

EXISTING DOOR FRAME

2.41.01

GYPSUM BOARD

MAY REMAIN BEHIND

DOOR FRAME IF SECURE

2.01.01

2.01.01

2.01.03

2.01.03

7.44.01

7.44.02

7.92.01 SECURE SIDE

LOBBY SIDE

SECURE SIDE

LOBBY SIDE

DEMOLITION DETAIL

NEW WORK DETAIL

EX

IS

TIN

G

W A

LL

FR

A M

IN

G

2.41.01

2.01.03

2.01.04

2.01.03

2.01.04

7.44.02

9.29.01

SECURE SIDE

LOBBY SIDE

SECURE SIDE

LOBBY SIDE

DEMOLITION DETAIL

NEW WORK DETAIL

PARTITION TYPE

SEE FLOOR PLAN

2.41.152.41.162.41.16 2.41.01

2.01.02

2.01.02

2.01.03

2.01.04

7.44.02

9.29.01

8.81.01

7.92.02

8.81.03

TAMPER RESISTANT SCREWS (LOBBY SIDE)

OR REGULAR SCREWS (SECURE SIDE) @

8" o.c.

LOBBY SIDE

SECURE SIDE

DEMOLITION DETAIL

NEW WORK DETAIL @ G1, G2

LOBBY SIDE

SECURE SIDE

A-104

6' -1

0"

TY

PI

C

A L

D O

O R

PA

N

EL

2'-10"

TYPICAL DOOR

PANEL

7.44.01

5.50.01

SEE DETAIL:

A-102

A-102

A-102

A-102

A-102

A-102

4" 8"

1' -7

/8

4"

1' -8

1'

-8

/8

7' -2

4"

3/ 4"

1' -7

/8

4"

1' -8

1'

-8

/8

7' -2

7' -0

4" 8"

1' -7

/8

4"

1' -8

1'

-8

/8

1'-5 3/4"

3'-5 1/2"5'-0"

4" 8"

1' -7

/8

4"

1' -8

1'

-8

/8

7' -2

7' -0

5'-0"

4" 8"

1' -7

/8

4"

1' -8

1'

-8

/8

7' -2

7' -0

5'-0"

4" 8"

1' -7

/8

4"

1' -8

1'

-8

/8

1'-6"

5'-1 7/8"

COUNTERTOP

6'-8" 1'-5 5/8" 1'-5 5/8"

EXISTING

MAIL SLOT

8.81.01

8.81.01

8.81.01

8.81.01

8.81.01

8.81.01

8.81.01

8.81.01

8.81.01

8.81.01

8.81.01

8.81.01

8.81.01

8.81.01

8.81.01

8.81.01

8.81.01

8.81.01

8.81.01

8.81.01

8.81.01

8.81.018.81.018.81.01

8.81.018.81.018.81.01

8.81.018.81.018.81.01

2.01.06

2.01.06

2.01.06

2.01.06

2.01.06

2.01.06

2.01.06

2.01.062.01.06

2.01.06

2.01.06

2.01.06

2.01.06

2.01.06

2.01.062.01.062.01.06

2.01.062.01.06

8.81.02 9.92.03

8.81.02 9.92.03

8.81.02 9.92.03

8.81.02

9.92.03 9.92.03

G1 G2 G2.1 G3 G4 G5

EXISTING GLAZING STOPS

ON LOBBY SIDE

1'-5 5/8"1'-5 5/8"

KEYED NOTES

02 DEMOLITION

2.01 EXISTING CONDITIONS

2.01.01 EXISTING 3'-0" x 7'-0" WOOD DOOR PANEL

2.01.02 EXISTING HOLLOW METAL DOOR FRAME

2.01.03 EXISTING GYPSUM BOARD TO REMAIN

2.01.04 EXISTING STUD WALL FRAMING TO REMAIN

2.01.06 EXISTING METAL INFILL PANEL

2.41 SELECTIVE DEMOLITION

2.41.01 REMOVE EXISTING GYPSUM BOARD SHEATHING

2.41.15 REMOVE EXISTING GLAZING PANEL

2.41.16 REMOVE EXISTING WINDOW FRAME GLAZING STOP

05 METALS

5.50 METAL FABRICATIONS

5.50.01 CONTINUOUS ALUMINUM J-CHANNEL TRIM FOR

PERIMETER OF PANEL.

07 THERMAL AND MOISTURE PROTECTION

7.44 FACED PANELS

7.44.01 PROVIDE UL 752 LEVEL III BALLISTICS PANEL ATTACHED

TO SECURE SIDE OF THE EXISTING DOOR. PROVIDE

METAL EDGE CHANNEL AROUND ENTIRE PERIMETER.

SIZE TO 2" LESS THAN DOOR PANEL WIDTH AND

HEIGHT. ROUTE PANEL AS REQUIRED FOR DOOR

HARDWARE. BASIS OF DESIGN: WACO COMPOSITES

ARMORCORE BULLET RESISTANT FIBERGLASS PANEL;

7/16" THICK.

7.44.02 BULLET RESISTANT FIBERGLASS PANEL ANCHORED TO

EXISTING WALL STRUCTURE. UL 752 LEVEL III RATED.

BASIS OF DESIGN: WACO COMPOSITES ARMORCORE

BULLET RESISTANT FIBERGLASS PANEL; 7/16" THICK.

7.92 JOINT SEALANTS

7.92.01 CONTINUOUS SEALANT, CONTINUOUS FOR ENTIRE

DOOR FRAME PERIMETER

7.92.02 CONTINUOUS SEALANT w/ NEOPRENE SPACERS

08 OPENINGS

8.81 GLASS GLAZING

8.81.01 NEW UL 752 LEVEL III BALLISTICS GLAZING. BASIS OF

DESIGN: McGRORY GLASS BALLISTICDEFEND 3-GCP, 1 1/4" NOMINAL THICKNESS.

8.81.02 IN LOCATIONS WHERE GLAZING STOPS ARE LOCATED

ON NON-SECURE SIDE OF PARTITION, CONTRACTOR

TO INSTALL SECURITY PHILLIPS-HEAD SCREWS w/

TAMPER RESISTANT PIN. MATCH EXISTING SCREW SIZE

AND THREADING

8.81.03 NEW 1 5/8" WIDE, 12ga STEEL PLATE SURFACE

MOUNTED GLASS STOP; ROUND-OFF OR BEVEL ALL

EXPOSED EDGES. PRIME AND PAINT (TWO COATS) TO

MATCH EXISTING FRAME PAINT.

09 FINISHES

9.29 GYPSUM BOARD

9.29.01 FOLLOWING INSTALLATION OF BALLISTICS SHEATHING,

INSTALL NEW 1/4" GYPSUM BOARD SHEATHING.

FINISH TO LEVEL 4.

9.92 INTERIOR PAINTING

9.92.03 ALL DOOR AND INTERIOR WINDOW FRAMES

MODIFIED BY THIS SCOPE OF WORK SHALL RECEIVE

ONE FULL-COAT OF SEMI-GLOSS ACRYLIC LATEX

ENAMEL.

SCALE: 3" = 1'-0"2 DOOR PANEL DETAIL

SCALE: 3" = 1'-0"1 WALL PANEL DETAIL

SCALE: 3" = 1'-0"3 GLAZING FRAME DETAILS

SCALE: 1/2" = 1'-0"4

TYPICAL INTERIOR

DOOR ELEVATION

SCALE: 3/4" = 1'-0"5 INTERIOR GLAZING ELEVATIONS

SC

O

TT

O

. G

RA

H A

M A

IA

, L

EE

D

A P

BD

+C

Sc ot tG

M G

-A rc hi te ct s.c om

B

2 3

C

D

1 2 3

4 5 6

A

B

D

AT

E R

EV

4 5

IS

SU

ED

F

O R

/R

EV

IS

ED

C

AP

PD

D

TO

W

N

SH

IP

O

F

SP

R

IN

G

TO

W N

SH

IP

O F

SP

R

IN

G

, B

ER

KS

C

O U

N

TY

, P

EN

N

SY

LV

AN

IA

SI

TE

C

IV

IL

IM

PR

OV

EM

EN

TS

A

ND

B

UI

LD

IN

G

SA

FE

TY

U

PG

RA

DE

S

/1

1/

BI

D

D

IN

G

SO

G

4644.029

PROJECT NO.

APPROVED BY:

SCALE:

CHECKED BY:

PREPARED BY:

DRAWING NO.

SOG

EMG / BB

AS NOTED

SOG

24-0010

MGA PROJECT NO.

AR

C

H

IT

EC

TU

R

AL

EL

EC

TR

IC

AL

B

IL

LB

O

AR

D

PL

AN

A

ND

D

ET

AI

LS

A-105

P E

N N

A V

E N

U E

W Y

O M

IS

S

IN

G

P

A

.3

.4 w w w .M

G -A rc h it e c ts

.c o m

24-0010_Spring Twp PD.pln | V:\Drawings\24-0010.0_Entech-Spring Twp PD Security Upgrades\1-Design\24-0010_Spring Twp PD.pln | 5/11/2026 | 2:16 PM

AC wiring Diagram

A A

A A

5' -3

/8

" A

PP

X.

M

.O

8'-9"

1'-4" 6'-1" APPX

M.O.

1'-4"

5"5" 5'-3" 1'-4"1'-4"

1' -8

3" 1'

-2

3"

2' -3

/8

" A

PP

X.

M

.O

3' -0

(A

PP

X.

E

XI

ST

IN

G

8'-9"

1'-4" 6'-1" APPX

M.O.

1'-4"

2' -4

/4

1/ 2"

1/

2"2 5/8"

EDGE OF CAP ABOVE

2.01.09

2.41.20 10.14.01

2.01.09

2.01.09

2.01.09

2.41.20

2.41.21

2.41.22 10.14.02

10.14.03

10.14.03 10.14.01

10.14.01

2.41.22

10.14.0110.14.01

9.96.01

2.01.102.01.10

2.01.11 9.96.01

5.50.04

5.50.03

5.50.02

5.50.02

5.50.02

5.50.03

9.96.01

2.41.20

2.41.20

5.50.02 5.50.02

TOWNSHIP OF SPRING

P O L I C E

ELEVATION

PLAN

SECTION A-A

MANUFACTURER SHOP DRAWING

TOWNSHIP OF SPRING

P O L I C E

DEMOLITION ELEVATION

TO PULL BOX

EXISTING MONUMENT SIGNAGE PHOTO

A-105

#2800

SH

ILL

IN

G

TO

N

RD

SPO

HN RD.

NOTE: CONTRACTOR TO LOCATE EXISTING

LIGHTING CIRCUIT FOR MONUMENT SIGN. INSTALL

NEW FRP PULL BOX AND PVC CONDUIT TO NEW

DIGITAL DISPLAYS. EXTEND CIRCUIT WIRING TO

MONUMENT SIGN DISPLAYS

KEYED NOTES

02 DEMOLITION

2.01 EXISTING CONDITIONS

2.01.09 EXISTING MASONRY MONUMENT SIGN

2.01.10 EXISTING CAP TO REMAIN

2.01.11 EXISTING BRICK MASONRY TO REMAIN

2.41 SELECTIVE DEMOLITION

2.41.20 REMOVE EXISTING READER BOARD SIGNAGE PANEL IN ITS

ENTIRETY.

2.41.21 REMOVE AND REINSTALL "POLICE" LETTERING. FINAL HEIGHT TO BE

CONFIRMED w/ ARCHITECT. PATCH ABANDONED ANCHOR HOLES

TO MATCH MASONRY; BOTH SIDES.

2.41.22 REMOVE TOP HALF-HEIGHT SOLDIER COURSE; BOTH SIDES. STABILIZE

MASONRY AS REQUIRED AND INSTALL SUPPLEMENTAL GROUT AS

NEEDED TO PREPARE OPENING FOR NEW DISPLAY ANCHORAGE.

05 METALS

5.50 METAL FABRICATIONS

5.50.02 PROVIDE 304 STAINLESS STEEL, 1/2" No. 18 FLATTENED EXPANDED

METAL MESH w/ INSECT SCREEN BACKING (BLACK) BETWEEN

PERIMETER OF SIGN AND MASONRY OPENING. PROVIDE 3/8"

STAINLESS STEEL U-EDGE AROUND PERIMETERS. FIELD COORDINATE

STAINLESS STEEL ANGLE BRACKETS AND FASTENERS TO SECURE

MESH TO MASONRY OPENING, SPACED @ 28" o.c. MAX.

5.50.03 2 1/2" x 4" x 1/4" GALVANIZED STEEL ANGLES; 7 7/8" LONG w/

DRILLED HOLES MATCHING MANUFACTURER'S SHOP DRAWINGS; 8

LOCATIONS

5.50.04 MASONRY EXPANSION ANCHORS; GALVANIZED.

09 FINISHES

9.96 HIGH PERFORMANCE COATINGS | SPEC 099600

9.96.01 PAINT EXISTING LINTELS w/ EXTERIOR-GRADE ACRYLIC-LATEX

ENAMEL (TWO COATS).

10 SPECIALTIES

10.14 SIGNAGE

10.14.01 5'-3" x 2'-4 1/4" (APPX.) OUTDOOR-RATED, VIDEO-CAPABLE, DIGITAL LED MESSAGE CENTER. BASIS OF DESIGN: INFINITY-SMD

6.667mm PIXEL MATRIX, 8,000 NIT BRIGHTNESS DISPLAY BY OPTEC

DISPLAYS, INC. COORDINATE VENTILATION, ANCHORAGE, AND

CLOSURE PANELS w/ MANUFACTURER.

10.14.02 REINSTALL "POLICE" LETTERING. FINAL HEIGHT TO BE CONFIRMED w/

ARCHITECT. PATCH ABANDONED ANCHOR HOLES TO MATCH

MASONRY; BOTH SIDES.

10.14.03 NEW SURFACE MOUNTED 1" CONDUIT; PAINTED. VERIFY SIZE FOR

EXISTING CIRCUIT WIRING.

SCALE: 1/2" = 1'-0"2 SIGNAGE DETAILS

1 SITE PLAN

SCALE: 1" = 30'

SC

O

TT

O

. G

RA

H A

M A

IA

, L

EE

D

A P

BD

+C

Sc ot tG

M G

-A rc hi te ct

B

2 3

C

D

1 2 3

4 5 6

A

B

D

AT

E R

EV

4 5

IS

SU

ED

F

O R

/R

EV

IS

ED

C

AP

PD

D

Entech Engineering - Printed: May. 11, 2026 H:\0004644.029\04-CAD\SheetFiles\New Work\A-106.dwgLa st

E di te d by : m hi es te r

/1

1/

BI

D

D

IN

G C

AD

TO

W

N

SH

IP

O

F

SP

R

IN

G

TO

W N

SH

IP

O F

SP

R

IN

G

, B

ER

KS

C

O U

N

TY

, P

EN

N

SY

LV

AN

IA

SI

TE

C

IV

IL

IM

PR

O

VE

M

EN

TS

A N

D B

U

IL

D

IN

G S

AF

ET

Y U

PG

R

AD

ES

A-106

PROJECT NO.

APPROVED BY:

SCALE:

CHECKED BY:

PREPARED BY:

DRAWING NO.

4644.029

CAD

CAD

MAH

AS NOTED

FL

O

O R

P

LA

N , W

AT

ER

PR

O

O

FI

N G

S

EC

TI

O

N S, D

ET

AI

LS

A N

D N

O

TE

S

AR

C H

IT

EC

TU

R

AL

SCALE:1 1/8" = 1'-0"

BASEMENT FLOOR PLAN

8' 16'4'0

GENERAL SHEET NOTES

1. REFER TO G-001 FOR DRAWING INDEX, GENERAL PROJECT

NOTES, DRAWING CONVENTIONS AND CODE SUMMARY.

2. REFER TO AND COORDINATE WITH PLUMBING, ELECTRICAL, AND

MECHANICAL DRAWINGS FOR ADDITIONAL WORK REQUIREMENTS.

GENERAL ARCHITECTURAL

NOTES

1. IT IS RECOMMENDED THE CONTRACTOR VISIT THE PROJECT SITE

PRIOR TO BIDDING TO BECOME FAMILIAR WITH THE BUILDING

STRUCTURE AND EXISTING CONDITIONS.

2. CONTRACTOR SHALL PROVIDE ALL MATERIALS, TOOLS, EQUIPMENT

AND NECESSARY FACILITIES, AND PERFORM ALL LABOR AND SERVICES

OF EVERY DESCRIPTION AS MAY BE NECESSARY TO COMPLETE THE

SCOPE OF WORK DEFINED BY THE DRAWINGS AND IN THE

SPECIFICATIONS FOR ALL WORK.

3. FABRICATE AND INSTALL ALL WORK IN STRICT ACCORDANCE WITH THE

IBC, ALL APPLICABLE STATE AND LOCAL CODES, AND THE GENERAL

AND SUPPLEMENTARY CONDITIONS OF THE CONTRACT.

4. CONTRACTOR SHALL RECONSTRUCT, REPAIR, OR REPLACE EXISTING

BUILDING CONSTRUCTION THAT IS DISTURBED ABOVE, BELOW, OR

AROUND THE PROJECT AREAS OF WORK. ALL WORK SHALL MATCH

EXISTING.

5. CONTRACTOR TO LEGALLY DISPOSE OF ALL REMOVED ITEMS AND

MATERIALS UNLESS INDICATED FOR REINSTALLATION.

6. CONTRACTOR IS RESPONSIBLE FOR FIELD VERIFYING ALL DIMENSIONS.

7. DIMENSIONS ARE AT THE CENTERLINE OF WALL UNLESS OTHERWISE

NOTED.

ARCHITECTURAL REPAIR /

MISC. NOTES

NEW WATERPROOFING /

FOUNDATION DRAINAGE NOTES

1. EXCAVATE AROUND BUILDING FOUNDATION AS INDICATED TO EXPOSE

EXISTING FOUNDATION WALL AND EXISTING WATERPROOFING

CONDITIONS. PROTECT ADJACENT STRUCTURES, UTILITIES, AND EXISTING

IMPROVEMENTS DURING EXCAVATION.

2. REMOVE SOIL AND DEBRIS FROM FOUNDATION SURFACE. PREPARE

SUBSTRATE TO RECEIVE NEW WATERPROOFING SYSTEM. REMOVE SHARP

PROTRUSIONS THAT MAY DAMAGE MEMBRANE.

3. PROVIDE NEW EXTERIOR FOUNDATION WATERPROOFING SYSTEM AT

EXCAVATED AREAS. WATERPROOFING SHALL BE A CONTINUOUS SYSTEM

FROM TOP TERMINATION TO ABOVE THE FOUNDATION DRAIN ZONE.

4. PROVIDE NEW ROLLED SHEET WATERPROOFING MEMBRANE (MINIMUM

36-INCH WIDE MEMBRANE PREFERRED) INSTALLED PER MANUFACTURER

REQUIREMENTS. LAP, SEAL, AND DETAIL ALL SEAMS, CORNERS, AND

TRANSITIONS TO MAINTAIN A CONTINUOUS WATERPROOF BARRIER.

5. PROVIDE COLD FLUID-APPLIED WATERPROOFING AT TRANSITIONS,

IRREGULAR SUBSTRATES, PENETRATIONS, AND WHERE REQUIRED TO

MAINTAIN SYSTEM CONTINUITY.

6. INSTALL DELTA®-DRAIN (OR APPROVED EQUAL FOUNDATION DRAINAGE

COMPOSITE MEMBRANE) OVER NEW WATERPROOFING SYSTEM. INSTALL

WITH GEOTEXTILE FACING SOIL SIDE. PROVIDE CONTINUOUS

INSTALLATION AND PROTECT WATERPROOFING DURING BACKFILL

OPERATIONS.

7. TERMINATE DELTA®-DRAIN AT TOP EDGE WITH DELTA®-MOLD STRIP (OR

APPROVED EQUAL TERMINATION STRIP). TUCK FILTER FABRIC BEHIND

FLAT TAB TO PREVENT SOIL FINES FROM ENTERING DRAINAGE GAP.

8. PROVIDE NEW TOP TERMINATION FLASHING/COUNTERFLASHING AND

SEALANT TO PROTECT WATERPROOFING SYSTEM TERMINATION AND TIE

INTO EXISTING BRICK VENEER. DO NOT BLOCK OR COVER EXISTING

WEEPHOLES.

9. INSTALL NEW UPPER FOUNDATION DRAIN AND CONNECT TO SITE

DRAINAGE SYSTEM AS INDICATED. COORDINATE WITH DRAINAGE STONE

AND GEOTEXTILE FABRIC.

10. INSTALL NEW RAIN LEADER UNDERGROUND PIPING WITHIN EXCAVATED

ZONE AND COORDINATE WITH FOUNDATION DRAINAGE SYSTEM AND

WATERPROOFING INSTALLATION.

11. BACKFILL EXCAVATED AREA WITH CLEAN, FREE-DRAINING STONE

WRAPPED WITH GEOTEXTILE FABRIC AS INDICATED TO PROVIDE

FILTRATION AND DRAINAGE ALONG FOUNDATION WALL.

12. CONTRACTOR SHALL COORDINATE WATERPROOFING, DELTA®-DRAIN,

FOUNDATION DRAIN, AND BACKFILL SEQUENCING. DO NOT BACKFILL

UNTIL WATERPROOFING SYSTEM HAS BEEN INSPECTED AND ACCEPTED.

13. PROVIDE JOINT SEALANT AND TERMINATION SEALANT COMPATIBLE WITH

WATERPROOFING MEMBRANE, METAL FLASHING, AND MASONRY

SUBSTRATES TO MAINTAIN A CONTINUOUS WEATHER- AND WATER-TIGHT

SYSTEM.

SHEET KEYNOTES

1. REMOVE AND REPLACE PLASTER AND LATH IN ALL AFFECTED AREAS.

INSPECT EXISTING INSULATION AND REMOVE AND REPLACE ANY

INSULATION IMPACTED BY MOISTURE. ALL CMU SUBSTRATE TO DRY

COMPLETELY PRIOR TO REPAIRS. INSTALL NEW INSULATION WHERE

REQUIRED AND RECONSTRUCT WALL ASSEMBLY USING

CORRISION-RESISTANT METAL LATH AND CEMENTIOUS PLASTER FINISH.

2. CONTRACTOR TO PROVIDE DRYWALL CEILING.

3. CONTRACTOR TO REPLACE EXISTING LIGHT. SEE ELECTRICAL PLANS

4. COORDINATE WORK WITH MECHANICAL AND ELECTRICAL DRAWINGS

AND SPECIFICATIONS. NEW LIGHT FIXTURES AND HVAC SUPPLY AND

RETURN DIFFUSERS SHALL REMAIN IN EXISTING LOCATIONS WITHIN THE

ACOUSTICAL CEILING.

5. PREPARE, PRIME AND PAINT EXISTING RAILING, THEN REINSTALL.

6. INSTALL NEW ALUMINUM RAILING SIMILAR IN DESIGN, PROFILE AND

FINISH TO MATCH EXISTING ALUMINUM RAILING ON SITE. COORDINATE

WITH OWNER PRIOR TO FABRICATION.

E A-106

SCALE:E 1/4" = 1'-0"

STAIRWELL SECTION

4' 8'2'0

WALL A

WALL C

W

AL

L B

F A-106G

A-106

SCALE:F 1/4" = 1'-0"

WATERPROOFING SECTION

HVAC VAULT

4' 8'2'0

DELTA DRAIN SYSTEM

AND WATERPROOFING

MEMBRANE

COLD JOINT PROTECTION

(VERTICAL AND

HORIZONTAL JOINTS)

SCALE:G 1/4" = 1'-0"

WATERPROOFING ELEVATION

HVAC VAULT

4' 8'2'0

DELTA DRAIN SYSTEM

AND WATERPROOFING

MEMBRANE

COLD JOINT TAPE FLASHING

(VERTICAL AND

HORIZONTAL JOINTS)

DELTA WATERPROOFING MEMBRANE

COLD JOINT

TAPE FLASHING

(VERTICAL AND

HORIZONTAL JOINTS)

EXISTING VENTS

1. PATCH, REPAIR AND REPOINT DETERIORATED BRICK AND MORTAR TO

MATCH ORIGINAL COLOR TEXTURE AND FINISH

2. REINSTALL EXISTING HANDRAIL.

3. PROVIDE FLASHING, COUNTERFLASHING AND CAULKING.

4. PREPARE AND PAINT EXISTING EXTERIOR REAR STOOP DOOR AND

WOOD SURROUND. MATCH EXISTING PAINT COLOR.

5. PREPARE, PAINT AND REINSTALL REAR STOOP ENTRANCE RAILING.

MATCH EXISTING PAINT COLOR.

6. PROVIDE METAL FRY REGLET, FLASHING AND CAULKING WHERE THE

BRICK FACE MEETS THE NEW CONCRETE SIDEWALK. DO NOT COVER

EXISTING WEEPHOLES.

384'-0" MIN.

REPLACE EXISTING

ACOUSTIC CEILING (ATC)

TILE IF DAMAGED BY WATER

NEW 2'x4' SUSPENDED

ACOUSTIC CEILING (ATC) SYSTEM

8'-0" (TYP.)

RECORDS

ROOM

2' -0

M

IN

2' -0

M

IN

FLASHING/COUNTERFLASHING

6' -0

" D

EE

P (W

ES

T

SI

D

E) 4'

-0 " D

EE

P

(A

LL

O

TH

ER

L

O C

AT

IO

N S

U N

LE

SS

N O

TE

D

O

TH

ER

W

IS

E)

DELTA DRAIN TO OVERLAP

FOUNDATION DRAIN

EXISTING

WATERPROOFING

DELTA DRAIN SYSTEM

EX

IS

TI

N

G F

O U

N D

AT

IO

N

FILLER

SEALANT

FLASHING / COUNTER FLASHING

3" 1'

-0

SCALE:A NONE

WATERPROOFING DETAIL

6' -0

" D

EE

P (W

ES

T

SI

D

E) 4'

-0 " D

EE

P

(A

LL

O

TH

ER

L

O C

AT

IO

N S

U N

LE

SS

N O

TE

D

O

TH

ER

W

IS

E)

DELTA DRAIN TO OVERLAP

FOUNDATION DRAIN

DELTA DRAIN SYSTEM

FILLER SEALANT

FLASHING /

COUNTER FLASING

EXISTING

WATERPROOFING

WATERPROOFING

MEMBRANE

WATERPROOFING

MEMBRANE

PROPOSED

CONCRETE SIDEWALK

SEALANT

EXPANSION JOINT MATERIAL

SCALE:B NONE

WATERPROOFING DETAIL

6' -0

" D

EE

P (W

ES

T

SI

D

E) 4'

-0 " D

EE

P

(A

LL

O

TH

ER

L

O C

AT

IO

N S

U N

LE

SS

N O

TE

D

O

TH

ER

W

IS

E)

DELTA DRAIN TO OVERLAP

FOUNDATION DRAIN

FLASHING /

COUNTER FLASING

SEALANT

EXPANSION JOINT MATERIAL

PROPOSED CONCRETE CURB

FLASHING /

COUNTER FLASING

SEALANT

FILLER

FILLER

SEALANT AT

EXISTING JOINT

DELTA DRAIN SYSTEM

WATERPROOFING

MEMBRANE

EX

IS

TI

N

G F

O U

N D

AT

IO

N

EX

IS

TI

N

G F

O U

N D

AT

IO

N

EX

IS

TI

N

G F

O U

N D

AT

IO

N

SCALE:C NONE

WATERPROOFING DETAIL

VERIFY EXISTING ADA RAMP FOUNDATION LOCATION.

DO NOT UNDERMINE OR DISTURB RAMP FOUNDATION

DURING TRENCHING FOR NEW FOUNDATION DRAIN.

PROVIDE TEMPORARY SUPPORT AS REQUIRED.

EXISTING

WATERPROOFING

NOTE:

SEE DRAWING C-403 FOR BACKFILL AND RESTORATION DETAILS

NOTE:

SEE DRAWING C-403 FOR BACKFILL AND RESTORATION DETAILS

NOTE:

SEE DRAWING C-403 FOR BACKFILL AND RESTORATION DETAILS

D A-106

SCALE:D 1/4" = 1'-0"

ELEVATOR SHAFT SECTION

4' 8'2'0

1. PROVIDE SPECIALTY EPOXY AND/OR POLYURETHANE INJECTION

AT THE ELEVATOR SHAFT FOUNDATION WALLS AND PIT SLAB AS

REQUIRED TO MITIGATE GROUNDWATER INFILTRATION AND SEAL

SUBSURFACE VOIDS.

2. INJECTION WORK SHALL BE PERFORMED ONLY AT THE ELEVATOR

PIT/SHAFT AREA AND BY A QUALIFIED SPECIALTY INJECTION

SUBCONTRACTOR.

3. ENGINEER/ARCHITECT DOES NOT DESIGN SPECIALTY INJECTION

SYSTEMS. CONTRACTOR SHALL RETAIN QUALIFIED SPECIALTY

PERSONNEL TO DETERMINE APPROPRIATE MATERIALS,

INJECTION LAYOUT, PRESSURES, SEQUENCING, AND REACTION

CONTROL BASED ON FIELD CONDITIONS.

4. INJECTION MAY INCLUDE PIT SIDEWALLS, SLAB, COLD JOINTS,

CRACKS, AND SEALING AT THE PISTON SLEEVE INTERFACE, AS

REQUIRED.

5. CONTRACTOR SHALL CONTROL INJECTION PRESSURES AND

EXPANSION TO PREVENT SLAB MOVEMENT OR DAMAGE TO

ELEVATOR COMPONENTS.

6. CONTRACTOR SHALL SUBMIT PRODUCT DATA AND A SPECIALTY

INJECTION PLAN FOR ENGINEER REVIEW FOR GENERAL

CONFORMANCE ONLY. CONTRACTOR REMAINS SOLELY

RESPONSIBLE FOR SYSTEM PERFORMANCE AND

MEANS/METHODS.

7. PROVIDE MANUFACTURER'S STANDARD WARRANTY AND

CORRECT ANY DAMAGE OR LEAKAGE RESULTING FROM

DEFECTIVE INSTALLATION.

ELEVATOR SHAFT - EPOXY

INJECTION NOTES

RAIN LEADER

RAIN LEADER

RAIN LEADER

INJECTION

POINT

INJECTION

POINT

INJECTION

POINT

INJECTION

POINT

NOTE:

SEE THIS SHEET FOR EPOXY INJECTION NOTES FOR

ELEVATOR SHAFT REPAIR

4" M

IN

8" M

IN

6" PENNDOT 2A

AGGREGATE COMPACTED

6" PENNDOT 2A

AGGREGATE COMPACTED

8" M

IN

APPLY CONTINUOUS SEALANT

BETWEEN FLASHING AND ASPHALT

PROVIDE TERM BAR

IF RECOMMENDED BY

MEMBRANE MANUFACTURER

PROVIDE TERM BAR

IF RECOMMENDED BY

MEMBRANE MANUFACTURER

CROSS SLOPE

1% MIN. / 2% MAX.

INJECTION

POINT (TYP.)

SC

O

TT

O

. G

RA

H A

M A

IA

, L

EE

D

A P

BD

+C

Sc ot tG

M G

-A rc hi te ct

SECTION 001000 - GENERAL NOTES

1. ALL WORK SHALL BE IN ACCORDANCE WITH APPLICABLE STATE AND

LOCAL BUILDING CODES AND ALL OTHER GOVERNING AGENCIES AND

REGULATIONS.

2. CONTRACTOR SHALL VERIFY ALL CONDITIONS AND DIMENSIONS IN

THE FIELD PRIOR TO COMMENCEMENT OF THE WORK. VERIFY LAYOUT

IN RELATION TO PROPERTY, BENCHMARKS, AND OTHER FIXED

CONDITIONS. REPORT DISCREPANCIES TO THE ARCHITECT

IMMEDIATELY UPON DISCOVERY.

3. NOTIFY ARCHITECT OF DISCREPANCIES REGARDING THE CONTRACT

DOCUMENTS OR DESIGN INTENT IMMEDIATELY UPON DISCOVERY.

CONTRACTOR SHALL BE RESPONSIBLE FOR OBTAINING

CLARIFICATION PRIOR TO PROCEEDING WITH THE WORK OR RELATED

WORK.

4. CONTRACTOR SHALL OBTAIN ALL REQUIRED TRADE PERMITS, AND

LICENSES.

5. CONTRACTOR SHALL REMOVE ALL RUBBISH AND DEBRIS FROM THE

SITE DURING COURSE OF PROJECT, AND DISPOSE OF LEGALLY

OFF-SITE MAXIMIZING RECYCLING. PROVIDE DAILY CLEANING AND

FINAL CLEANING.

6. CONTRACTOR SHALL PERFORM ALL CUTTING, PATCHING, AND

PROTECTION REQUIRED TO PERFORM THE WORK INDICATED ON THE

CONTRACT DOCUMENTS.

7. CONTRACTOR SHALL PROVIDE ALL INSPECTIONS AND TESTS

REQUIRED BY STATE AND LOCAL AUTHORITIES INCLUDING BUT NOT

LIMITED TO MECHANICAL, PLUMBING, AND ELECTRICAL WORK. REFER

TO INDIVIDUAL DRAWINGS AND SPECIFICATIONS FOR ADDITIONAL

TESTING REQUIREMENTS.

8. ALL DIMENSIONS ARE EITHER TO FACE OF MASONRY OR THE CENTER

OF FRAMING STUD, UNLESS NOTED OTHERWISE. DRAWINGS ARE NOT

TO BE SCALED.

9. INSTALL ALL EQUIPMENT AND MATERIALS PER MANUFACTURER ’ S

INSTRUCTIONS AND RECOMMENDATIONS, UNLESS SPECIFICALLY

OTHERWISE INDICATED, OR WHERE LOCAL CODES AND REGULATIONS

TAKE PRECEDENCE.

10. CONTRACTOR SHALL PROVIDE SUPERVISION WHILE ANY

SUBCONTRACTORS OR WORKERS ARE ON THE JOB SITE AND SHALL

SUPERVISE AND DIRECT ALL WORK.

11. CONTRACTOR SHALL BE SOLELY RESPONSIBLE FOR ALL

CONSTRUCTION MEANS, METHODS, TECHNIQUES, SEQUENCES,

PROCEDURES, SITE SAFETY, AND COORDINATING THE WORK OF ALL

TRADES UNDER THIS CONTRACT.

12. NO PRODUCTS CONTAINING ASBESTOS OR OTHER HAZARDOUS

MATERIALS SHALL BE INSTALLED ON THIS PROJECT OR USED DURING

THE CONSTRUCTION OF THE PROJECT. IT SHALL BE THE

RESPONSIBILITY OF THE CONTRACTOR TO CERTIFY TO THE OWNER

THAT THIS REQUIREMENT HAS BEEN MET. SUBCONTRACTORS SHALL

VERIFY TO THE CONTRACTOR THAT NO ASBESTOS OR OTHER

HAZARDOUS PRODUCTS ARE USED IN THEIR WORK.

13. FURNISH AND INSTALL TEMPORARY PROTECTION AND BARRICADES.

THE BUILDING WILL NOT BE POPULATED IN NORMAL OPERATION

DURING ALL CONSTRUCTION WORK. PROVIDE DUST PARTITIONS

BETWEEN WORK AREAS AND OCCUPIED PORTIONS OF BUILDING.

14. FURNISH AND INSTALL TEMPORARY UTILITIES, TEMPORARY OFFICE,

TEMPORARY TOILETS, AND OTHER TEMPORARY FACILITIES AS

APPROPRIATE.

15. CONDUCT CONSTRUCTION PROGRESS MEETINGS WITH OWNER AND

DESIGN PROFESSIONAL AT AGREED UPON TIME AND DATE, BI-WEEKLY

DURING DURATION OF CONSTRUCTION. ARCHITECT TO PROVIDE

MINUTES OF THESE MEETINGS FOR REVIEW AT NEXT MEETING.

16. DELEGATED DESIGN: WHEN PROFESSIONAL DESIGN SERVICES OR

CERTIFICATIONS RELATED TO SYSTEMS, MATERIALS, OR EQUIPMENT

ARE REQUIRED BY THESE DOCUMENTS, THE ARCHITECT/ENGINEER

WILL SPECIFY PERFORMANCE AND DESIGN CRITERIA THAT SUCH

SERVICES MUST SATISFY. THE CONTRACTOR SHALL CAUSE SUCH

SERVICES AND CERTIFICATIONS TO BE PROVIDED BY A PROPERLY

LICENSED DESIGN PROFESSIONAL, WHOSE SIGNATURE AND SEAL

SHALL APPEAR ON ALL DRAWINGS, CALCULATIONS, SHOP DRAWINGS

AND OTHER RELATED SUBMITTALS. THE OWNER AND

ARCHITECT/ENGINEER SHALL BE ENTITLED TO RELY UPON THE

ACCURACY AND COMPLETENESS OF THOSE DELEGATED SERVICES.

THE ARCHITECT/ENGINEER WILL REVIEW SUBMITTALS ONLY FOR THE

LIMITED PURPOSE OF CHECKING FOR CONFORMANCE WITH THE

PERFORMANCE AND DESIGN CRITERIA.

17. INFORMATION REGARDING EXISTING BUILDING CONDITIONS AND

FINISHED FLOOR ELEVATIONS WERE OBTAINED FROM DRAWINGS

PROVIDED BY OWNER. NOTIFY ARCHITECT OF DISCREPANCIES

REGARDING THE CONTRACT DOCUMENTS OR DESIGN INTENT

IMMEDIATELY UPON DISCOVERY. CONTRACTOR SHALL BE

RESPONSIBLE FOR OBTAINING CLARIFICATION PRIOR TO PROCEEDING

WITH THE WORK OR RELATED WORK.

18. THE CONTRACTOR SHALL PROTECT ADJACENT PROPERTIES AND

ADJACENT BUILDING SITE FEATURES BEYOND THE GENERAL

BOUNDARY OF CONSTRUCTION OPERATIONS, AND

CURBING/PAVEMENT AND OTHER SITE FEATURES WITHIN GENERAL

BOUNDARY OF CONSTRUCTION FROM DAMAGE AND DEBRIS.

IMMEDIATELY MAKE REPAIRS OR CORRECTIONS TO RETURN THE

DAMAGED ITEMS TO THEIR PREVIOUS STATE. THE CONTRACTOR

SHALL BE RESPONSIBLE FOR REPLACING ALL ITEMS DAMAGED

DURING CONSTRUCTION.

19. COORDINATE IN FIELD WITH ARCHITECT ALL LOCATIONS FOR

MECHANICAL SYSTEM TERMINAL DEVICES (REGISTERS, GRILLES,

ETC.), PLUMBING DEVICES AND FIXTURES, AND LIGHT FIXTURES AND

ELECTRICAL DEVICES THAT ARE NOT DIMENSIONALLY LOCATED IN

ARCHITECTURAL DRAWINGS.

20. STUD WORK AND BLOCKING IS SHOWN SCHEMATICALLY IN DRAWINGS.

THE CONTRACTOR SHALL PROVIDE STUD WORK AND BLOCKING AS

REQUIRED BY CONDITIONS AND/OR BY THE ENGINEER, ARCHITECT,

AND MANUFACTURER TO MAKE THE INSTALLATION COMPLETE.

21. PROVIDE SEPARATION LAYERS BETWEEN ALL DISSIMILAR MATERIALS

AND BETWEEN METAL AND MASONRY SURFACES. DO NOT INSTALL

ALUMINUM COMPONENTS IN FRESH MORTAR.

22. UNLESS NOTED OTHERWISE, ALL DUCTWORK, PIPING, WIRING AND

CONDUITS, WHETHER SHOWN IN ARCHITECTURAL DRAWINGS OR NOT,

ARE TO BE CONCEALED WITHIN NEW FINISHES.

23. REFERENCE MECHANICAL, PLUMBING, AND ELECTRICAL DRAWINGS

FOR LOCATIONS OF DUCT WORK, EQUIPMENT AND PLUMBING LINES,

WHICH ARE LOCATED WITHIN CAVITIES. COORDINATE IN FIELD WITH

ARCHITECT ALL LOCATIONS FOR MECHANICAL SYSTEM TERMINAL

DEVICES (REGISTERS, GRILLES, ETC.), PLUMBING DEVICES AND

FIXTURES, AND LIGHT FIXTURES AND ELECTRICAL DEVICES THAT ARE

NOT DIMENSIONALLY LOCATED IN ARCHITECTURAL DRAWINGS. NOTE

THAT THERE ARE MEP DRAWINGS THAT ARE PART OF ARCHITECT'S

DOCUMENTS.

24. WHERE GYPSUM WALL BOARD FINISHES ARE INTERRUPTED BY

STRUCTURAL MEMBERS OR DUCTS/PIPES/CONDUITS, SCRIBE GYPSUM

WALL BOARD TIGHT TO STRUCTURE AND SEAL JOINTS TO PROVIDE A

SMOOTH UNIFORM FINISH.

25. COORDINATION

A. COORDINATE CONSTRUCTION OPERATIONS INCLUDED IN THE

VARIOUS TRADES OF THE WORK TO ASSURE EFFICIENT AND

ORDERLY INSTALLATION OF EACH PART OF THE WORK.

COORDINATE CONSTRUCTION OPERATIONS OF DIFFERENT TRADES

THAT DEPEND ON EACH OTHER FOR PROPER INSTALLATION

SEQUENCE, CONNECTION, AND OPERATION.

B. SCHEDULE CONSTRUCTION AND COORDINATE OPERATIONS IN THE

SEQUENCE REQUIRED TO OBTAIN THE BEST RESULTS WHERE

INSTALLATION OF ONE PART OF THE WORK DEPENDS ON THE

INSTALLATION OF OTHER COMPONENTS, BEFORE OR AFTER ITS

OWN INSTALLATION.

C. MAKE PROVISIONS TO ACCOMMODATE ITEMS SCHEDULED FOR

LATER INSTALLATION.

D. INSPECTION OF CONDITIONS: REQUIRE THE INSTALLER OF EACH

MAJOR COMPONENT TO INSPECT BOTH THE SUBSTRATE AND

CONDITIONS UNDER WHICH THE WORK IS TO BE PERFORMED. DO

NOT PROCEED UNTIL UNSATISFACTORY CONDITIONS HAVE BEEN

CORRECTED IN AN ACCEPTABLE MANNER.

E. COORDINATE TEMPORARY ENCLOSURES WITH REQUIRED

INSPECTIONS AND TESTS TO MINIMIZE THE NECESSITY OF

UNCOVERING COMPLETED CONSTRUCTION FOR THAT PURPOSE.

26. CUTTING AND PATCHING

A. EXAMINE SURFACES TO BE CUT AND PATCHED AND CONDITIONS IN

WHICH CUTTING AND PATCHING IS TO BE PERFORMED BEFORE

CUTTING. IF UNSAFE OR UNSATISFACTORY CONDITIONS ARE

ENCOUNTERED, TAKE CORRECTIVE ACTION BEFORE PROCEEDING.

B. CUT EXISTING CONSTRUCTION USING METHODS TO MINIMIZE AND

LEAST LIKELY TO DAMAGE ELEMENTS RETAINED OR ADJOINING

CONSTRUCTION.

C. RESTORE FINISHES OF PATCHED AREAS AND EXTEND FINISH

RESTORATION INTO RETAINED ADJOINING CONSTRUCTION IN A

MANNER THAT WILL ELIMINATE EVIDENCE OF PATCHING AND

REFINISHING.

D. PATCHING OF FIRE RATED ASSEMBLIES SHALL BE PERFORMED

SUCH THAT THE ASSEMBLY RETAINS ITS FIRE RATING.

27. SUBMITTALS

A. COORDINATE SUBMITTAL PREPARATION WITH CONSTRUCTION,

FABRICATION, AND OTHER SUBMITTALS, AND ACTIVITIES THAT

REQUIRE SEQUENTIAL OPERATIONS. TRANSMIT IN ADVANCE OF

CONSTRUCTION OPERATIONS TO AVOID DELAY. SUBMITTALS SHALL

BE PROVIDED FOR ALL WORK OF THE PROJECT. CONTRACTOR

SHALL PROVIDE A SCHEDULE OF ALL SUBMITTALS BEFORE

COMMENCING CONSTRUCTION ACTIVITIES.

B. PROCESSING: ALLOW (14) CALENDAR DAYS FOR REVIEW. ALLOW

MORE TIME IF THE ARCHITECT MUST DELAY PROCESSING TO

PERMIT COORDINATION. THE ARCHITECT RESERVES THE RIGHT TO

WITHHOLD ACTION ON A SUBMITTAL REQUIRING COORDINATION

UNTIL RELATED SUBMITTALS ARE RECEIVED.

C. SHOP DRAWINGS: SUBMIT NEWLY PREPARED INFORMATION DRAWN

TO SCALE. INDICATE DEVIATIONS FROM THE CONTRACT

DOCUMENTS. DO NOT REPRODUCE THE CONTRACT DOCUMENTS

OR COPY STANDARD INFORMATION. SUBMIT ONE CORRECTABLE,

REPRODUCIBLE PRINT AND ONE BLUE OR BLACK LINE PRINT ON

SHEETS AT LEAST 8-1/2 INCHES BY 11 INCHES BUT NO LARGER

THAN 30 INCHES BY 42 INCHES. THE ARCHITECT WILL RETURN THE

REPRODUCIBLE PRINT.

D. SAMPLES: SUBMIT FULL-SIZE SAMPLES CURED AND FINISHED AS

SPECIFIED, AND IDENTICAL WITH THE MATERIAL PROPOSED.

MOUNT THE SAMPLES TO FACILITATE REVIEW OF QUALITIES.

SUBMIT SAMPLES FOR REVIEW OF SIZE, KIND, COLOR, PATTERN,

AND TEXTURE, FOR A CHECK OF THESE CHARACTERISTICS, AND

FOR A COMPARISON OF THESE CHARACTERISTICS BETWEEN THE

FINAL SUBMITTAL AND THE ACTUAL COMPONENT AS DELIVERED

AND INSTALLED.

E. PRODUCT DATA: COLLECT PRODUCT DATA INTO A SINGLE

SUBMITTAL FOR EACH ELEMENT OF CONSTRUCTION. MARK EACH

COPY TO SHOW APPLICABLE CHOICES AND OPTIONS. WHERE

PRODUCT DATA INCLUDES INFORMATION ON SEVERAL PRODUCTS,

MARK COPIES TO INDICATE APPLICABLE INFORMATION. SUBMIT 4

COPIES. THE ARCHITECT WILL RETAIN ONE AND RETURN THE

OTHERS MARKED WITH ACTION TAKEN.

28. MATERIALS & EQUIPMENT

A. SOURCE LIMITATIONS: TO THE FULLEST EXTENT POSSIBLE.

PROVIDE PRODUCTS OF THE SAME KIND FROM A SINGLE SOURCE.

B. DELIVER, STORE AND HANDLE PRODUCTS ACCORDING TO THE

MANUFACTURER'S RECOMMENDATIONS, USING MEANS AND

METHODS THAT WILL PREVENT DAMAGE, DETERIORATION, AND

LOSS, INCLUDING THEFT. STORE PRODUCTS SUBJECT TO DAMAGE

BY THE ELEMENTS ABOVE GROUND, UNDER COVER IN A

WEATHERTIGHT ENCLOSURE, WITH VENTILATION ADEQUATE TO

PREVENT CONDENSATION. MAINTAIN TEMPERATURE AND HUMIDITY

WITHIN THE RANGE REQUIRED BY THE MANUFACTURER'S

INSTRUCTIONS.

C. PROVIDE DUST PROOF TEMPORARY ENCLOSURES AROUND

CONSTRUCTION OPERATIONS.

D. PROPRIETARY SPECIFICATION REQUIREMENTS: WHERE

SPECIFICATIONS NAME ONLY A SINGLE PRODUCT OR

MANUFACTURER, PROVIDE THE PRODUCT SPECIFIED. NO

SUBSTITUTIONS WILL BE PERMITTED.

E. SEMI-PROPRIETARY SPECIFICATION REQUIREMENTS: WHERE

SPECIFICATIONS NAME 2 OR MORE PRODUCTS OR

MANUFACTURERS, PROVIDE ONE OF THE PRODUCTS INDICATED.

NO SUBSTITUTIONS WILL BE PERMITTED.

F. DESCRIPTIVE SPECIFICATIONS REQUIREMENTS: WHERE

SPECIFICATION DESCRIBE A PRODUCT OR ASSEMBLY, LISTING

EXACT CHARACTERISTICS REQUIRED, WITH OR WITHOUT THE USE

OF A BRAND NAME PROVIDE A PRODUCT OR ASSEMBLY THAT

PROVIDES THE CHARACTERISTICS AND OTHERWISE COMPLIES

WITH THE CONTRACT REQUIREMENTS.

29. WARRANTIES

A. WARRANTY WORK AGAINST DEFECTIVE MATERIALS OR

WORKMANSHIP FOR A PERIOD OF THREE (3) YEARS FROM THE

DATE OF SUBSTANTIAL COMPLETION. REMEDY ANY AND ALL

DEFECTS IN THE WORK UPON WRITTEN NOTIFICATION FROM THE

OWNER. SUBMIT A WRITTEN WARRANTY TO THE OWNER THAT ALL

MATERIALS AND WORKMANSHIP SHALL BE FREE FROM DEFECTS

FOR A PERIOD OF THREE YEARS AFTER THE DATE OF SUBSTANTIAL

COMPLETION. THERE WILL BE NO ADDITIONAL COST TO REPAIR OR

REPLACE ANY SUCH WORK THAT IS FOUND TO BE DEFECTIVE

WITHIN THE WARRANTY PERIOD.

END OF SECTION 001000

ARCHITECTURAL SPECIFICATIONS

SP

EC

IF

IC

AT

IO

N S

- 1

AR

C H

IT

EC

TU

R

AL

A

B

2 3

C

D

1 2 3

4 5 6

A

B

D

AT

E R

EV

4 5

IS

SU

ED

F

O R

/R

EV

IS

ED

C

AP

PD

D

Entech Engineering - Printed: May. 11, 2026 H:\0004644.029\04-CAD\SheetFiles\New Work\A-701.dwgLa st

E di te d by : m hi es te r

/1

1/

BI

D

D

IN

G C

AD

TO

W

N

SH

IP

O

F

SP

R

IN

G

TO

W N

SH

IP

O F

SP

R

IN

G

, B

ER

KS

C

O U

N

TY

, P

EN

N

SY

LV

AN

IA

SI

TE

C

IV

IL

IM

PR

O

VE

M

EN

TS

A N

D B

U

IL

D

IN

G S

AF

ET

Y U

PG

R

AD

ES

A-701

PROJECT NO.

APPROVED BY:

SCALE:

CHECKED BY:

PREPARED BY:

DRAWING NO.

4644.029

CAD

CAD

MAH

AS NOTED

SECTION 061000 - ROUGH CARPENTRY

PART 1 - GENERAL

1.1 SUMMARY

A. THIS SECTION INCLUDES THE FOLLOWING:

1. FRAMING WITH DIMENSION LUMBER.

2. WOOD BLOCKING, CANTS, AND NAILERS.

1.2 DEFINITIONS

A. EXPOSED FRAMING: FRAMING NOT CONCEALED BY OTHER

CONSTRUCTION.

B. DIMENSION LUMBER: LUMBER OF 2 INCHES NOMINAL OR GREATER BUT

LESS THAN 5 INCHES NOMINAL IN LEAST DIMENSION.

C. LUMBER GRADING AGENCIES, AND THE ABBREVIATIONS USED TO

REFERENCE THEM, INCLUDE THE FOLLOWING:

1. NELMA: NORTHEASTERN LUMBER MANUFACTURERS' ASSOCIATION.

2. NLGA: NATIONAL LUMBER GRADES AUTHORITY.

3. SPIB: THE SOUTHERN PINE INSPECTION BUREAU.

4. WCLIB: WEST COAST LUMBER INSPECTION BUREAU.

5. WWPA: WESTERN WOOD PRODUCTS ASSOCIATION.

1.3 SUBMITTALS

A. PRODUCT DATA: FOR EACH TYPE OF PROCESS AND

FACTORY-FABRICATED PRODUCT. INDICATE COMPONENT MATERIALS

AND DIMENSIONS AND INCLUDE CONSTRUCTION AND APPLICATION

DETAILS.

B. RESEARCH/EVALUATION REPORTS: FOR THE FOLLOWING, SHOWING

COMPLIANCE WITH BUILDING CODE IN EFFECT FOR PROJECT:

1. WOOD-PRESERVATIVE-TREATED WOOD.

1.4 DELIVERY, STORAGE, AND HANDLING

A. STACK LUMBER FLAT WITH SPACERS BETWEEN EACH BUNDLE TO

PROVIDE AIR CIRCULATION. PROVIDE FOR AIR CIRCULATION AROUND

STACKS AND UNDER COVERINGS.

PART 2 - PRODUCTS

2.1 WOOD PRODUCTS, GENERAL

A. LUMBER: DOC PS 20 AND APPLICABLE RULES OF GRADING AGENCIES

INDICATED. IF NO GRADING AGENCY IS INDICATED, PROVIDE LUMBER

THAT COMPLIES WITH THE APPLICABLE RULES OF ANY RULES-WRITING

AGENCY CERTIFIED BY THE ALSC BOARD OF REVIEW. PROVIDE LUMBER

GRADED BY AN AGENCY CERTIFIED BY THE ALSC BOARD OF REVIEW TO

INSPECT AND GRADE LUMBER UNDER THE RULES INDICATED.

1. FACTORY MARK EACH PIECE OF LUMBER WITH GRADE STAMP OF

GRADING AGENCY.

2. WHERE NOMINAL SIZES ARE INDICATED, PROVIDE ACTUAL SIZES

REQUIRED BY DOC PS 20 FOR MOISTURE CONTENT SPECIFIED.

WHERE ACTUAL SIZES ARE INDICATED, THEY ARE MINIMUM DRESSED

SIZES FOR DRY LUMBER.

3. PROVIDE DRESSED LUMBER, S4S, UNLESS OTHERWISE INDICATED.

B. MAXIMUM MOISTURE CONTENT OF LUMBER: 19 PERCENT UNLESS

OTHERWISE INDICATED.

2.2 WOOD-PRESERVATIVE-TREATED LUMBER

A. PRESERVATIVE TREATMENT BY PRESSURE PROCESS: AWPA C2, EXCEPT

THAT LUMBER THAT IS NOT IN CONTACT WITH THE GROUND AND IS

CONTINUOUSLY PROTECTED FROM LIQUID WATER MAY BE TREATED

ACCORDING TO AWPA C31 WITH INORGANIC BORON (SBX).

1. PRESERVATIVE CHEMICALS: ACCEPTABLE TO AUTHORITIES HAVING

JURISDICTION AND CONTAINING NO ARSENIC, CHROMIUM, OR

AMMONIA.

B. KILN-DRY LUMBER AFTER TREATMENT TO A MAXIMUM MOISTURE

CONTENT OF 19 PERCENT. DO NOT USE MATERIAL THAT IS WARPED OR

DOES NOT COMPLY WITH REQUIREMENTS FOR UNTREATED MATERIAL.

C. MARK LUMBER WITH TREATMENT QUALITY MARK OF AN INSPECTION

AGENCY APPROVED BY THE ALSC BOARD OF REVIEW.

D. APPLICATION: TREAT ALL ROUGH LUMBER PRODUCTS UNLESS

OTHERWISE INDICATED.

2.3 DIMENSION LUMBER FRAMING

A. MAXIMUM MOISTURE CONTENT: 19 PERCENT.

B. NON-LOAD-BEARING INTERIOR PARTITIONS: CONSTRUCTION OR

STANDARD OF THE FOLLOWING SPECIES:

1. SOUTHERN PINE - SPIB.

2.4 MISCELLANEOUS LUMBER

A. GENERAL: PROVIDE MISCELLANEOUS LUMBER INDICATED AND LUMBER

FOR SUPPORT OR ATTACHMENT OF OTHER CONSTRUCTION, INCLUDING

THE FOLLOWING:

1. BLOCKING.

2. NAILERS.

B. FOR ITEMS OF DIMENSION LUMBER SIZE, PROVIDE CONSTRUCTION OR

NO. 2 GRADE LUMBER WITH 19 PERCENT MAXIMUM MOISTURE CONTENT

AND ANY OF THE FOLLOWING SPECIES:

1. MIXED SOUTHERN PINE; SPIB.

C. FOR BLOCKING AND NAILERS USED FOR ATTACHMENT OF OTHER

CONSTRUCTION, SELECT AND CUT LUMBER TO ELIMINATE KNOTS AND

OTHER DEFECTS THAT WILL INTERFERE WITH ATTACHMENT OF OTHER

WORK.

2.5 FASTENERS

A. GENERAL: PROVIDE FASTENERS OF SIZE AND TYPE INDICATED THAT

COMPLY WITH REQUIREMENTS SPECIFIED IN THIS ARTICLE FOR MATERIAL

AND MANUFACTURE.

1. WHERE ROUGH CARPENTRY IS EXPOSED TO WEATHER, IN GROUND

CONTACT, PRESSURE-PRESERVATIVE TREATED, OR IN AREA OF HIGH

RELATIVE HUMIDITY, PROVIDE FASTENERS WITH HOT-DIP ZINC

COATING COMPLYING WITH ASTM A 153/A 153M.

B. NAILS, BRADS, AND STAPLES: ASTM F 1667.

C. POWER-DRIVEN FASTENERS: NES NER-272.

D. WOOD SCREWS: ASME B18.6.1.

E. LAG BOLTS: ASME B18.2.1.

F. BOLTS: STEEL BOLTS COMPLYING WITH ASTM A 307, GRADE A; WITH

ASTM A 563 HEX NUTS AND, WHERE INDICATED, FLAT WASHERS. HOT

DIPPED GALVANIZED BOLTS.

PART 3 - EXECUTION

3.1 INSTALLATION, GENERAL

A. SET ROUGH CARPENTRY TO REQUIRED LEVELS AND LINES, WITH

MEMBERS PLUMB, TRUE TO LINE, CUT, AND FITTED. FIT ROUGH

CARPENTRY TO OTHER CONSTRUCTION; SCRIBE AND COPE AS NEEDED

FOR ACCURATE FIT. LOCATE FURRING, NAILERS, BLOCKING,

GROUNDS, AND SIMILAR SUPPORTS TO COMPLY WITH REQUIREMENTS

FOR ATTACHING OTHER CONSTRUCTION.

B. FRAMING STANDARD: COMPLY WITH AF&PA'S "DETAILS FOR

CONVENTIONAL WOOD FRAME CONSTRUCTION," UNLESS OTHERWISE

INDICATED.

C. PROVIDE BLOCKING AND FRAMING AS INDICATED AND AS REQUIRED TO

SUPPORT FACING MATERIALS, FIXTURES, SPECIALTY ITEMS, AND TRIM.

D. PROVIDE FIRE BLOCKING IN FURRED SPACES, STUD SPACES, AND OTHER

CONCEALED CAVITIES AS INDICATED AND AS FOLLOWS:

1. FIRE BLOCK CONCEALED SPACES OF WOOD-FRAMED WALLS AND

PARTITIONS AT EACH FLOOR LEVEL, AT CEILING LINE OF TOP STORY,

AND AT NOT MORE THAN 120 INCHES O.C. WHERE FIRE BLOCKING IS

NOT INHERENT IN FRAMING SYSTEM USED, PROVIDE CLOSELY

FITTED SOLID WOOD BLOCKS OF SAME WIDTH AS FRAMING

MEMBERS AND 2-INCH NOMINAL- THICKNESS.

E. SORT AND SELECT LUMBER SO THAT NATURAL CHARACTERISTICS WILL

NOT INTERFERE WITH INSTALLATION OR WITH FASTENING OTHER

MATERIALS TO LUMBER. DO NOT USE MATERIALS WITH DEFECTS THAT

INTERFERE WITH FUNCTION OF MEMBER OR PIECES THAT ARE TOO

SMALL TO USE WITH MINIMUM NUMBER OF JOINTS OR OPTIMUM JOINT

ARRANGEMENT.

F. COMPLY WITH AWPA M4 FOR APPLYING FIELD TREATMENT TO CUT

SURFACES OF PRESERVATIVE-TREATED LUMBER.

G. SECURELY ATTACH ROUGH CARPENTRY WORK TO SUBSTRATE BY

ANCHORING AND FASTENING AS INDICATED, COMPLYING WITH THE

FOLLOWING:

1. NES NER-272 FOR POWER-DRIVEN FASTENERS.

2. TABLE 2304.9.1, "FASTENING SCHEDULE," IN ICC'S INTERNATIONAL

BUILDING CODE.

H. USE COMMON WIRE NAILS, UNLESS OTHERWISE INDICATED. SELECT

FASTENERS OF SIZE THAT WILL NOT FULLY PENETRATE MEMBERS

WHERE OPPOSITE SIDE WILL BE EXPOSED TO VIEW OR WILL RECEIVE

FINISH MATERIALS. MAKE TIGHT CONNECTIONS BETWEEN MEMBERS.

INSTALL FASTENERS WITHOUT SPLITTING WOOD; DO NOT COUNTERSINK

NAIL HEADS, UNLESS OTHERWISE INDICATED.

3.2 WOOD BLOCKING, AND NAILER INSTALLATION

A. INSTALL WHERE INDICATED AND WHERE REQUIRED FOR SCREEDING OR

ATTACHING OTHER WORK. FORM TO SHAPES INDICATED AND CUT AS

REQUIRED FOR TRUE LINE AND LEVEL OF ATTACHED WORK.

COORDINATE LOCATIONS WITH OTHER WORK INVOLVED.

B. ATTACH ITEMS TO SUBSTRATES TO SUPPORT APPLIED LOADING. RECESS

BOLTS AND NUTS FLUSH WITH SURFACES, UNLESS OTHERWISE

INDICATED.

3.3 WALL AND PARTITION FRAMING INSTALLATION

A. GENERAL: PROVIDE SINGLE BOTTOM PLATE AND DOUBLE TOP PLATES

USING MEMBERS OF 2-INCH NOMINAL THICKNESS WHOSE WIDTHS EQUAL

THAT OF STUDS, EXCEPT SINGLE TOP PLATE MAY BE USED FOR

NON-LOAD-BEARING PARTITIONS. FASTEN PLATES TO SUPPORTING

CONSTRUCTION, UNLESS OTHERWISE INDICATED.

1. FOR INTERIOR PARTITIONS AND WALLS, PROVIDE 2-BY-4-INCH

NOMINAL- SIZE WOOD STUDS SPACED 16 INCHES O.C., UNLESS

OTHERWISE INDICATED.

2. PROVIDE CONTINUOUS HORIZONTAL BLOCKING AT MIDHEIGHT OF

PARTITIONS MORE THAN 96 INCHES HIGH, USING MEMBERS OF

2-INCH NOMINAL THICKNESS AND OF SAME WIDTH AS WALL OR

PARTITIONS OR AS INDICATED ON DRAWINGS.

B. CONSTRUCT CORNERS AND INTERSECTIONS WITH THREE OR MORE

STUDS.

C. FRAME OPENINGS WITH MULTIPLE STUDS AND HEADERS. PROVIDE

NAILED HEADER MEMBERS OF THICKNESS EQUAL TO WIDTH OF STUDS.

SUPPORT HEADERS ON JAMB STUDS.

1. FOR NON-LOAD-BEARING PARTITIONS, PROVIDE DOUBLE-JAMB

STUDS AND HEADERS NOT LESS THAN 4-INCH NOMINAL DEPTH FOR

OPENINGS 48 INCHES AND LESS IN WIDTH, 6-INCH NOMINAL DEPTH

FOR OPENINGS 48 TO 72 INCHES IN WIDTH, 8-INCH NOMINAL DEPTH

FOR OPENINGS 72 TO 120 INCHES IN WIDTH, AND NOT LESS THAN

10-INCH NOMINAL DEPTH FOR OPENINGS 10 TO 12 FEET IN WIDTH.

3.4 PROTECTION

A. PROTECT WOOD THAT HAS BEEN TREATED WITH INORGANIC BORON

(SBX) FROM WEATHER. IF, DESPITE PROTECTION, INORGANIC

BORON-TREATED WOOD BECOMES WET, APPLY EPA-REGISTERED

BORATE TREATMENT. APPLY BORATE SOLUTION BY SPRAYING TO

COMPLY WITH EPA-REGISTERED LABEL.

END OF SECTION 061000

SECTION 071416 - COLD FLUID-APPLIED WATERPROOFING

(AUXILIARY / TRANSITIONS)

PART 1 - GENERAL

1.01 SUMMARY

A. SECTION INCLUDES:

1. COLD FLUID-APPLIED WATERPROOFING USED AT TRANSITIONS,

DETAILING, AND TIE-INS ASSOCIATED WITH BELOW-GRADE

FOUNDATION WATERPROOFING IMPROVEMENTS.

2. WATERPROOFING AT CRACKS, JOINTS, PENETRATIONS, AND

IRREGULAR SUBSTRATES WHERE SHEET MEMBRANE CANNOT

BE APPLIED CONTINUOUSLY, INCLUDING TREATMENT OF

CONCRETE COLD JOINTS USING HYDROPHILIC CONCRETE

JOINT TAPE IN COMBINATION WITH FLUID-APPLIED

WATERPROOFING.

3. SEALANT AND ACCESSORY MATERIALS REQUIRED FOR

COMPLETE WATERPROOFING SYSTEM CONTINUITY.

B. RELATED SECTIONS:

1. SECTION 071326 - SELF-ADHERING SHEET WATERPROOFING

(PRIMARY MEMBRANE).

2. SECTION 071416 - DRAINAGE COMPOSITE / FOUNDATION

DRAINAGE MEMBRANE.

3. SECTION 079200 - JOINT SEALANTS.

4. DIVISION 31 - EARTHWORK (EXCAVATION, BACKFILL, AND

COMPACTION) (SPECIFICATION PROVIDED IN PROJECT

MANUAL)

1.02 REFERENCES

A. ASTM STANDARDS (LATEST EDITIONS).

B. MANUFACTURER PUBLISHED INSTALLATION REQUIREMENTS AND

DETAILS.

C. LOCAL CODE REQUIREMENTS APPLICABLE TO BELOW-GRADE

WATERPROOFING AND DRAINAGE SYSTEMS.

1.03 SUBMITTALS

A. PRODUCT DATA: SUBMIT MANUFACTURER DATA SHEETS FOR:

1. FLUID-APPLIED WATERPROOFING MATERIAL

2. PRIMER (IF REQUIRED)

3. REINFORCING FABRIC (IF REQUIRED)

4. SEALANTS AND TERMINATION ACCESSORIES

B. SHOP DRAWINGS / DETAILS:

1. WATERPROOFING TERMINATION DETAIL AT TOP OF

FOUNDATION WALL (TIE-IN TO BRICK VENEER).

2. WATERPROOFING TIE-IN TO FOUNDATION DRAIN SYSTEM.

3. PENETRATION AND TRANSITION DETAILS.

C. INSTALLER QUALIFICATIONS:

1. WATERPROOFING INSTALLER SHALL BE EXPERIENCED IN

BELOW-GRADE FOUNDATION WATERPROOFING INSTALLATIONS

AND SHALL FOLLOW MANUFACTURER INSTALLATION

REQUIREMENTS.

1.04 QUALITY ASSURANCE

A. PRE-INSTALLATION CONFERENCE:

1. CONTRACTOR SHALL COORDINATE WATERPROOFING

INSTALLATION WITH EXCAVATION, FOUNDATION DRAIN

INSTALLATION, AND BACKFILL OPERATIONS.

2. COLD JOINT TREATMENT SHALL CONSIST OF BOTH

HYDROPHILIC JOINT TAPE AND FLUID-APPLIED

WATERPROOFING; NEITHER SYSTEM ALONE IS ACCEPTABLE.

B. MOCK-UP (IF REQUESTED):

1. PROVIDE A SMALL TEST AREA DEMONSTRATING

WATERPROOFING MEMBRANE, TERMINATION, AND DELTA

DRAIN INSTALLATION PRIOR TO FULL PRODUCTION.

1.05 DELIVERY, STORAGE, AND HANDLING

A. DELIVER MATERIALS IN ORIGINAL UNOPENED CONTAINERS WITH

LABELS…

This is the start of the file's text. The full file is on GovTribe.