This is an Addendum #1 to RFP 26-51-5211 issued by Forsyth County, Georgia's Procurement Department for the Chattahoochee Pointe Playground Design and Installation project. The addendum, dated April 2, 2026, supplements the original bidding documents for a playground facility designed for ages 5-12 to be located at Chattahoochee Pointe Park, 5790 Chattahoochee Pointe Drive, Suwanee, Georgia. The solicitation requires qualified firms to provide comprehensive playground services including design, equipment supply, surfacing installation, and subbase preparation, with the new design connecting to existing playground infrastructure. No pre-bid meeting is scheduled for this solicitation. Bidders are solely responsible for independently conducting site visits at their own time and expense to familiarize themselves with existing conditions and all factors affecting the work. Failure to conduct a site visit does not relieve bidders of their contractual obligations, and no additional compensation, time, or consideration will be granted for conditions that would have been reasonably observed during such a visit.
All questions and inquiries arising from site visits or the bidding process must be submitted through EUNA Procurement. The addendum clarifies that where specifications or drawings are supplemented, original requirements remain in effect unless specifically amended, voided, or superseded by the addendum provisions.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP 26-51-5211 Addendum # 1
Forsyth County Procurement
Adrienne Trammel, Procurement Agent III
ADDENDUM # 1
Solicitation Number: RFP 26-51-5211 Title: Chattahoochee Pointe Playground
Design and Installation
Date: April 2, 2026
Initially Solicited: April 2, 2026
This addendum supersedes and supplements all portions of the bidding documents and becomes part of the contract documents for the above-referenced project. Where any item called for in the specifications or indicated on the drawings is supplemented hereby, the original requirements shall remain in effect. Where any original item is amended, voided, or superseded hereby, the provision of such item not so specifically amended, voided or superseded shall remain in effect.
# Questions Answers
1. Is there a pre-bid meeting planned? No, there is no pre-bid meeting planned at this time.
Bidders are solely responsible for independently visiting the site, at their own time and expense, to familiarize themselves with existing conditions and all factors that may affect the Work. Failure to visit the site shall not relieve the Bidder of any obligation under the Contract Documents, and no additional compensation, time, or consideration will be granted for conditions that would have been reasonably observed during a site visit. All questions arising from any site visit shall be submitted through EUNA Procurement.