3_North South Base Water Ph. 2 Submittal Schedule - DRAFT.pdf

PDF 261 KB Posted

Attached to
Horizontal Construction Multiple Award Contract (MAC)
Solicitation number
FA4626-26-R-0008
Issued by

About this file

This is a Schedule of Materials Submittals for a federal construction contract at Malmstrom Air Force Base in Montana. The document specifies required contractor submissions for Project 1080765, "Repair North South Base Water Systems - Phase II" under Solicitation/Contract No. FA4626-26-R-0008.

The schedule lists 41 line items organized by construction division requiring various technical submittals prior to work commencement and project completion. Division 01 (General Requirements) items include as-built drawings, O&M manuals, equipment data, shop drawings, start of work notifications, progress schedules, quality control plans, and regulatory documentation. Division 02 (Sitework) items encompass traffic control plans, temporary water supply plans, material submittals for trench excavation, flowable fill mix designs, asphalt concrete pavement specifications, water distribution materials and certifications, sodding and seeding documentation, tree planting credentials and maintenance programs, and reinforcing steel and structural concrete specifications. Submittal requirements vary in copy quantity (ranging from 1 to 4 copies) and submission timing, with most items required prior to start of work (PTSW), before delivery (BD), or prior to final inspection (PTFI). Specific timeframes include 3 to 30 days before the applicable event. The document includes submission tracking columns for contractor and government use, recording receipt dates, approval status, and remarks. Abbreviations clarify timing requirements such as ANA (After Notice of Award), ATT (After Test Taken), and PTWS (Prior to Start of Work).

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MALMSTROM AFB, MONTANA

SCHEDULE OF MATERIALS SUBMITTALS Project Number Project Title: Solicitation/Contract No.

FA4626-26-R-0008

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACTOR/ADMINISTRATOR

L

IN

E N

U M

B E

R

ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL

C E

R T

IF

IC

A T

IO

N

O F

C O

M

PL

IA

N

C E

SH

O

P D

R A

W

IN

G S

SA

M

PL

E

S

C O

L O

R S

E L

E C

T

IO

N

M A

N U

FA

C

T U

R E

R 'S

E C

O M

M E

N D

A T

IO

N

S

M A

N U

FA

C

T U

R E

W

A R

R A

N T

Y

C A

T A

L O

G D

A T

A

O

PE

R A

T

IN

G

ST

R U

C T

IO

N

S

N O

T

IF

IC

A

T

IO

N

O T

H E

R

R E

Q U

IR

D

SU

B

M

IS

SI

O

N D

A T

(B Y

C O

N T

R A

C T

O R

D A

T E

R E

C E

IV

E

C

O N

T R

A C

T

IN

G

D A

T E

T O

C

IV

IL

N

G

IN

E E

R

IN

G

R E

T U

R N

S U

SP

E

SE

T

E

SU

B

M

IT

T A

L N

U M

B E

R S

C O

N T

R A

C T

SU

B M

IT

T

L

FI

A L

A

PP

R O

V A

L

REMARKS

APPROVED

DIS-

APPROV

ED

DIVISION 01 - GENERAL REQUIREMENTS

01000 General Requirements - 3.5 As-Built Field Data and Drawings 2 3d -

PTFI AutoCAD CD

2 01000 General Requirements - 3.5 Final As-Built Drawings 2 30d - AFI AutoCAD CD

3 01000 General Requirements - 3.7 O&M Instructions/Manual 1 2 1d - ATT 2 hardcopy, 1 CD

4 01000 General Requirements - 3.8 Contractor Furnished Equipment Data 3 10 d -

PTFI

5 01000 General Requirements - 3.10 Shop Drawings 3 7 - BD

6 01000 General Requirements - 3.11 Start of Work Notification 3 5 d - PTE

7 01000 General Requirements - 3.12 Notice of Pre-Final and Final Inspections 3 14d - PTE

Red line “As-Built” dwgs shall be provided by the Contractor at final inspection.

8 01000 General Requirements - 3.13 AF Form 103 14d - PTSW AF Form 103 Work Clearance

9 01000 General Requirements - 3.14 Utility Outages 3 14d - PTE

10 01000 General Requirements - 3.18 Quality Control Plan and Specified Quality Control Submittals 4 10d -

ANA

11 01000 General Requirements - 3.19 Progress Schedule and Report 3 PTWS

12 01000 General Requirements - 3.20 1354 Checklist 3 10d -

PTFI

Checklist delivered to Contractor at Pre-Construction Conference

13 01000 General Requirements - 3.22 1354 Nuclear Densometer Info 3 30 - PTE

14 010010 Site Security - 1.1 Contractor Entry Authorization List (EAL) 4 14d -

PTSW EAL

Number of Copies Required

1080765 Repair North South Base Water Systems - Phase II

DATE CONTRACTOR

NOTIFIED

AF Form 66 3_Submittal Schedule - North South Base Water-5/21/2026

01330a-1

REQUIRED TECHNICAL SUBMITTALS

DRAFT

FA4626-26-R-0008

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACTOR/ADMINISTRATOR

L

IN

E N

U M

B E

R

ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL

C E

R T

IF

IC

A T

IO

N

O F

C O

M

PL

IA

N

C E

SH

O

P D

R A

W

IN

G S

SA

M

PL

E

S

C O

L O

R S

E L

E C

T

IO

N

M A

N U

FA

C

T U

R E

C

O M

M E

N D

A T

IO

N

S

M A

N U

FA

C

T U

R E

R

R A

N T

Y

C A

T A

L O

G D

A T

A

O

PE

R A

T

R U

C T

IO

N

S

N O

T

IF

IC

A

T

IO

N

O T

H E

R

R E

Q U

IR

M

IS

SI

O

N D

A

C O

N T

R A

C T

O R

D A

T E

R E

C E

IV

E

N

T R

A C

T

IN

G

D A

T E

T O

C

G

IN

E E

R

IN

G

R E

T U

R N

S U

SP

E

T

E

SU

B

M

IT

T A

L N

U M

B E

R S

C O

N T

R A

C T

SU

B M

IT

T

A L

A

PP

R O

V A

L

REMARKS

APPROVED

DIS-

APPROV

ED

Number of Copies Required

1080765 Repair North South Base Water Systems - Phase II

DATE CONTRACTOR

NOTIFIED

15 13600 Environmental Protection - 2.3 Copies of Environmental Permits, SWPPP, NOI 4 5d -

PTSW

16 13600 Environmental Protection - 8.2.1 HAZMAT Inventory 4 30d - PTSW Form

17 13600 Environmental Protection - 8.6 HAZMAT Report 4 10d -

PTFI

18 13600 Environmental Protection - 11.5.2 Solid Waste Disposal Summary 4 10th of

Month Form

DIVISION 2 - SITEWORK

19 01570 Traffic Control - 1.3.B Traffic Control Plan 4 10d -

PTSW

20 01580 Temp Water Supply - 1.2.A Temporary Water Plan 4 10d -

PTSW

21 02221 Trench Excavation and Backfill for Pipelines and Appurtenant Structures - 1.3.C Material Submittals 4 15d -

PTSW Lab Results

22 02225 Flowable Fill - 1.3.B Mix Design 4 15d - PTSW Lab Results

23 02230 Street Excavation Backfill Compaction - 1.3.C Materials Submittals 4 15d -

PTSW Lab Results

24 02235 Gravel Base Course - 1.3 and 1.4 Materials Submittals 4 15d - PTSW Lab Results

AF Form 66 3_Submittal Schedule - North South Base Water-5/21/2026

01330a-2

FA4626-26-R-0008

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACTOR/ADMINISTRATOR

L

IN

E N

U M

B E

R

ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL

C E

R T

IF

IC

A T

IO

N

O F

C O

M

PL

IA

N

C E

SH

O

P D

R A

W

IN

G S

SA

M

PL

E

S

C O

L O

R S

E L

E C

T

IO

N

M A

N U

FA

C

T U

R E

C

O M

M E

N D

A T

IO

N

S

M A

N U

FA

C

T U

R E

R

R A

N T

Y

C A

T A

L O

G D

A T

A

O

PE

R A

T

R U

C T

IO

N

S

N O

T

IF

IC

A

T

IO

N

O T

H E

R

R E

Q U

IR

M

IS

SI

O

N D

A

C O

N T

R A

C T

O R

D A

T E

R E

C E

IV

E

N

T R

A C

T

IN

G

D A

T E

T O

C

G

IN

E E

R

IN

G

R E

T U

R N

S U

SP

E

T

E

SU

B

M

IT

T A

L N

U M

B E

R S

C O

N T

R A

C T

SU

B M

IT

T

A L

A

PP

R O

V A

L

REMARKS

APPROVED

DIS-

APPROV

ED

Number of Copies Required

1080765 Repair North South Base Water Systems - Phase II

DATE CONTRACTOR

NOTIFIED

25 02348 Encasement & Carrier Pipe - 3.1 Smooth Wall Encasemednt Pipe 1 PTSW Cat. Cuts - Electronic

26 02348 Encasement & Carrier Pipe-3.3 Casing End Seals 1 PTSW Cat. Cuts - Electronic

27 02348 Encasement & Carrier Pipe - 3.4 Casing Spacers 1 PTSW Cat. Cuts - Electronic

28 02510 Asphalt Concrete Pavement - 1.3.A Agg. Source, Agg Gradation, Mix Design 4 15d -

PTSW Lab Results

29 02510 Asphalt Concrete Pavement - 1.3.B Asphalt Source and Certificate of Compliance 4 15d -

PTSW Lab Results

30 02660 Water Distribution - 2..2.A Materials Manufacturer Certifications 4 PTSW Certifications

31 02660 Water Distribution - 2.2.A.1 Pipe Materials, Fitiings, Coatings and Appurtenances 4 PTSW Cat. Cuts

32 02925 Sodding - 1.2.A Sod Certification and Fertilizer Description 4 15d - PTSW Certifications

33 02926 Seeding-2.1A Seed Mix 1 15d - PTSW Certifications - Electronic

34 02926 Sodding-2.2A Topsoil 1 15d - PTSW Certifications - Electronic

35 02926 Seeding 2.3A Fertilizer 1 15d - PTSW Certifications - Electronic

36 02930 Tree Planting - 1.2.A Plant Label, Fertilizer Certification and Stakes/Ties/ Materials 4 4 10d-BD Certifications

AF Form 66 3_Submittal Schedule - North South Base Water-5/21/2026

01330a-3

FA4626-26-R-0008

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACTOR/ADMINISTRATOR

L

IN

E N

U M

B E

R

ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL

C E

R T

IF

IC

A T

IO

N

O F

C O

M

PL

IA

N

C E

SH

O

P D

R A

W

IN

G S

SA

M

PL

E

S

C O

L O

R S

E L

E C

T

IO

N

M A

N U

FA

C

T U

R E

C

O M

M E

N D

A T

IO

N

S

M A

N U

FA

C

T U

R E

R

R A

N T

Y

C A

T A

L O

G D

A T

A

O

PE

R A

T

R U

C T

IO

N

S

N O

T

IF

IC

A

T

IO

N

O T

H E

R

R E

Q U

IR

M

IS

SI

O

N D

A

C O

N T

R A

C T

O R

D A

T E

R E

C E

IV

E

N

T R

A C

T

IN

G

D A

T E

T O

C

G

IN

E E

R

IN

G

R E

T U

R N

S U

SP

E

T

E

SU

B

M

IT

T A

L N

U M

B E

R S

C O

N T

R A

C T

SU

B M

IT

T

A L

A

PP

R O

V A

L

REMARKS

APPROVED

DIS-

APPROV

ED

Number of Copies Required

1080765 Repair North South Base Water Systems - Phase II

DATE CONTRACTOR

NOTIFIED

37 02930 Tree Planting - 1.2.B Plantsman Credentials 4 14d - PTSW Credentials Letter

38 02910 Tree Planting - 1.2.C Tree Maintenance Program 4 10d - PTFI Tree Maintenance Program

39 03210 Reinforcing Steel-2.1A Bar Reinforcement 1 PTSW Cat. Cuts - Electronic

40 03210 Reinforcing Steel 2.1B Wire and Wire & Mesh Fabric 1 PTSW Cat. Cuts - Electronic

41 03310 Structural Concrete - 1.3.B Mix Design 4.2.D Source of Supply Submittals 4 15d -

PTSW Lab Results

Schedule of Abbreviations:

AFI = After Final Inspection PTE= Prior to Event

ANA= After Notice of Award PTFI= Prior to Final Inspection

ATT= After Test Taken PTSW = Prior to Start of Work

BBCW= Before Beginning Concrete Work

BD= Before Delivery

AF Form 66 3_Submittal Schedule - North South Base Water-5/21/2026

01330a-4