STATEMENT OF WORK

Relocate LOX Storage Farm TUMR 202107

156AW Muñiz Air National Guard Base (ANGB), Puerto Rico (PR)

1.0 GENERAL

1.1 Scope. The Contractor shall provide supervision, transportation, labor, materials, equipment, fuel and any other needed materials and quality control necessary, except as specified in Paragraph 3.0 as Government Furnished items, to relocate the LOX storage farm, located in Muniz Air National Guard Base, Carolina, PR as specified in this SOW.

1.2 Background. The primary purpose of the project is to relocate the LOX storage farm from bldg. 13 to Bldg. 95. This will require the demolition of existing structure, relocation of oxygen tank and install new fence. More details of the upgrade are below.

1.3 Period of Performance (PoP). The Period of Performance shall be 90 calendar days (3 months).

1.4 General Information.

1.4.1 Quality Control (QC). The Contractor shall develop and maintain an effective QC

Plan (QCP) to ensure services are perform in accordance with this SOW.

Contractor shall develop and implement procedures to identify, prevent, and ensure no recurrence of defective services. The contractor’s QCP is the means by which it assures itself that its work complies with the requirements of the contract. As a minimum, the Contractor shall develop QC procedures that address the areas identified in Technical Exhibit 1, Performance Requirements

Summary. A final QCP shall be submitted to the Contracting Officer

Representative (COR) NLT 10 days after contract award. After acceptance of the

QCP, the Contractor shall obtain the Contracting Officer’s (KO) acceptance in writing of any proposed changes to its QCP.

1.4.2 Quality Assurance (QA). The Government shall evaluate the Contractor’s performance under this contract in accordance with the Quality Assurance

Surveillance Plan (QASP). This plan is primarily focused on what the

Government must do to ensure that the Contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and acceptable quality level(s) (defect rate(s)).

1.4.3 Recognized Holidays: The following are recognized US holidays. The Contractor shall not perform services on these days.

1.4.3.1 New Year’s Day

1.4.3.2 Martin Luther King Jr.’s Birthday

1.4.3.3 President’s Day

1.4.3.4 Memorial Day

1.4.3.5 Independence Day

1.4.3.6 Labor Day

1.4.3.7 Columbus Day

1.4.3.8 Veteran’s Day

1.4.3.9 Thanksgiving Day

1.4.3.10 Christmas Day

1.4.4 Place and Performance of Services. The Contractor shall provide services between the hours of 0730-1600 on Monday through Friday, except on recognized US holidays or when the Government facility/installation is closed due to local or national emergencies, administrative closings, or similar Government-directed facility/installation closings. Performance shall be at Muñiz Air Base, Carolina, Puerto Rico 00979. The Contractor, shall at all times, maintain an adequate work force for the uninterrupted performance of all tasks defined within this SOW when the Government facility/installation is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the work force are essential.

1.4.4.1 Reserved

1.4.4.2 Unscheduled gate closures by the Security Police may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. Contractors are not compensated for unexpected closures or delays.

Vehicles operated by Contractor personnel are subject to search pursuant to applicable regulations. Any moving violation of any applicable motor vehicle regulation may result in the termination of the Contractor employee’s installation driving privileges.

1.4.4.3 The Contractor’s employees shall become familiar with and obey the regulations of the installation; including fire, traffic, safety and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval.

All Contractor employees shall carry proper identification with them at all times. The Contractor shall ensure compliance with all regulations and orders of the installation, which may affect performance.

1.4.4.4 Security Requirements. The Contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The

Contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the installation Security Office. The Contractor shall ensure compliance with all personal identity verification requirements as directed by DOD and/or local policy. Should the Force Protection Condition (FPCON) change, the

Government may require changes in Contractor security matters or processes. The Contractor shall coordinate all on-site activity, as required, in conjunction with the COR and the appropriate Muñiz Base representatives. Installation Entry Access List (EAL) is required fifteen to thirty (15-30) calendar days ahead for processing, prior to base access approval being granted, along with DD Form 369, Police Record Check and driver license copy.

1.4.4.5 Reserved.

1.4.4.6 For Contractors that do not require a CAC, but require access to a DoD facility or installation: Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures. Using the National Crime Information Center Interstate Identification (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014- 05/AR

190-13), and applicable installation, facility and area commander installation/facility access, and local security policies and procedures

(provided by a government representative).

1.4.4.7 COMSEC/IT Security. All communications with DOD organizations are subject to communications security (COMSEC) review. All telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. DOD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DOD organizations. Therefore, the Contractor is advice that any time Contractor place or receive a call they are subject to

COMSEC procedures. The Contractor shall ensure wide and frequent dissemination of the above information to all employees dealing with DOD information. The Contractor shall abide by all Government regulations concerning the authorized use of the Government's computer network, including the restriction against using the network to recruit Government personnel or advertise job openings.

1.4.4.8 Protection of Personally Identifiable Information (PII). The Contractor shall protect all Personally Identifiable Information (PII) encountered in the performance of services in accordance with DFARS 224.103 and DoDD

5400.11, Department of Defense Privacy Program, and DoD 5400.11-R. If a PII breach results from the Contractor’s violation of the aforementioned policies, the Contractor shall bear all notification costs, call-center support costs, and credit monitoring service costs for all individuals who’s PII has been compromised.

1.4.4.9 AT Level 1 Awareness Training (AT). All Contractor employees requiring access to Army Installations, facilities, and controlled access areas shall complete Level 1 AT within 10 calendar days after contract start date and within 10 calendar days of new employees commencing performance. The

Contractor shall submit certificates of completion for each affected

Contractor and subcontractor employee, to the COR, or to the KO if a COR is not assigned, within 10 calendar days after completion of training. Level

1 AT is available at http://jko.jten.mil/courses/atl1/launch.html.

1.4.4.10 Physical Security. The Contractor shall safeguard all Government property provided for Contractor use. At the close of each work period, Government facilities, equipment and materials shall be secured.

1.4.4.11 Key Control. This SOW does not require handling of keys or key cards issued by the government.

1.4.4.12 Special Qualifications. The Contractor shall ensure all employees possess all required licenses for operating heavy equipment, welding licenses, Material Handling Equipment (MHE) i.e. Forklift and any others, in the performance of this contract. The Government does not provide training to

Contractors. Contractors must ensure that any personnel performing under a contract are fully trained, licensed, certified and qualified to provide services.

1.4.4.13 Post Award Conference/Periodic Progress Meetings. The Contractor agrees to attend any post award conference convened by the KO in accordance with

Federal Acquisition Regulations Subpart 42.5. The KO, Contracting

Officer’s Representative (COR), and other Government personnel, as appropriate, may meet periodically with the Contractor to review the contactor’s performance. The Contractor shall resolve outstanding issues identify by the Government. Contractor attendance at these meetings shall be at no additional cost to the Government.

1.4.4.14 Contract Manager (CM). The Contractor shall designate a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the Contractor when the CM is absent, shall be designated in writing to the KO within 3 calendar days after contract award.

The CM or alternate shall have full authority to act for the Contractor on all contract matters relating to daily operation of this contract. The CM shall work through the COR, (or the KO if a COR is not assigned), to resolve issues, receive technical instructions, and ensure adequate performance of services. The CM shall ensure that Contractor employees do not perform any services outside the scope of the contract without an official modification issued by the KO. CM is responsible to inform the employees that works or services performed outside the scope of the contract are at the

Contractor cost and no cost to the Government.

1.4.4.15 Identification of Contractor Employees. All contractor personnel attending meetings, answering Government telephones and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are Government employees. The Contractor shall ensure that all documents or reports produced by Contractor personnel are suitably marked as Contractor products or that Contractor participation is appropriately disclosed. The contractor’s status as a “Contractor” shall be predominantly displayed in all correspondence types (to include signature blocks on email) and dealings with Government or non- Government entities/ Contractor personnel shall wear identification badges distinguishing themselves as such. The badges shall have the company name, employee name and the word “Contractor” displayed. The Contractor shall retrieve all identification media (including vehicle passes) from their employees who depart employment for any reason. All identification media (i.e., badges and vehicle passes shall be returned to the COR within the 10 days of an employee’s departure) or contract completion.

1.4.4.16 Combating Trafficking in Persons. The United States Government has adopted a zero tolerance policy regarding trafficking in persons. Contractors and Contractor employees shall not engage in any forms of trafficking in persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract. The Contractor shall notify its employees of the United States Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. Such actions may include, but are not limited to, removal from the contract, reduction in benefits, or termination of employment. The

Contractor shall take appropriate action, up to and including termination, against employees or subcontractors that violate the US Government policy as described at FAR 22.17.Contractor shall complete the following online training within 10 calendar days after contract award: Course number is N-

US189-HB; available at: http://jko.jten.mil/.

1.4.4.17 Reserved.

1.4.4.18 Data Rights: The Government has unlimited rights to all documents/material produced under this contract. All documents and materials, to include the source codes of any software, produced under this contract shall be Government owned and are the property of the

Government with all rights and privileges of ownership /copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the Contractor without written permission from the KO. All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. Provide a copy 10 calendar days after contract completion. This right does not abrogate any other Government rights.

1.4.4.19 Organizational Conflicts of Interest (OCI): The Contractor and subcontractor personnel performing services under this contract may receive have access to or participate in the development of proprietary or source selection. In addition to substantial (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.).

Perform evaluation services, which may create current or subsequent OCIs, as defined in FAR Subpart 9.5. The Contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The Contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO.

In the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may affect other remedies as he or she deems necessary, including prohibiting the Contractor from participation in subsequent contracted requirements which may be affected by the OCI.

1.4.4.20 Safety Plan: Provide a safety plan to the COR within 10 calendar days after contract award.

1.4.4.21 Environmental Plan: Provide an environmental plan to the COR within 10 calendar days after contract award.

1.4.4.22 Waste Management Plan: The Contractor shall submit a preliminary Waste

Management Plan and a final Waste Management Plan. The preliminary waste management plan and final Waste Management Plan should address key components (see Appendix F1 for key components). The Contractor shall submit to the COR for approval prior to commencement of demolition services, IAW UFGS 01 74 19, para 1.6 and UFGS 02 81 00, para 3.1.2.

The project waste diversion goal is 60%. Approval of the Contractor’s plan will not relieve the Contractor of responsibility for compliance with applicable environmental regulations or meeting project cumulative waste diversion requirement. This plan shall be coordinated with the installation waste management plan so there are no conflicts. This plan may be incorporated with the work plan. Disposal slips from landfill and/or recycler must be submitted to the Base Environmental Management Office to report amounts of debris landfilled or recycled.

1.4.4.23 The Contractor will provide and implement a recycling program to recuperate and process the existing refrigerant to prevent accidental release to the atmosphere. Provide certification and documentation to the Base

Civil Engineer. Provide documentation according to State Law 416 to Base

Civil Engineer.

2.0 Definitions and Acronym

2.1 Definitions

2.1.1 CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or services to the government. The term used in this contract refers to the prime.

2.1.2 CONTRACTING OFFICER (KO). A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.

2.1.3 CONTRACTING OFFICER (KO). A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.

2.1.4 CONTRACTING OFFICER'S REPRESENTATIVE (COR). An employee of the

U.S. Government designated by the KO to monitor Contractor performance. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the

Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.

2.1.5 DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.

2.1.6 DELIVERABLE. Anything that can be physically delivered and includes no manufactured things such as meeting minutes or reports.

2.1.7 KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the SOW. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

2.1.8 PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.

2.1.9 QUALITY ASSURANCE. The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.

2.1.10 QUALITY ASSURANCE SURVEILLANCE PLAN (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of Contractor performance.

2.1.11 QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of a product or service shall meet contract requirements.

2.1.12 SUBCONTRACTOR. One that enters into a contract with a prime Contractor. The

Government does not have privity of contract with the subcontractor.

2.1.13 WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.

2.1.13 WORK WEEK. Monday through Friday, unless specified otherwise.

2.2 Acronyms

AEI Army Enterprise Info Structure

AFARS Army Federal Acquisition Regulation Supplement

ANG Air National Guard

AR Army Regulation

AUP Acceptable Use Policy

BBP Better Business Practice

CDM Concept Development Meeting

CFR Code of Federal Regulations

CM Contract Manager

COMSEC Communications Security

CONUS Continental United States

COR Contracting Officer Representative

COTS Commercial-Off-the-Shelf

CUI Controlled Unclassified Information

DA Department of the Army

DD250 Department of Defense Form 250 (Receiving Report)

DD254 Department of Defense Contract Security Requirement List

DFARS Defense Federal Acquisition Regulation Supplement

DMDC Defense Manpower Data Center

DOD Department of Defense

FAR Federal Acquisition Regulation

FEMA Federal Emergency Management Agency

FPCON Force Protection Condition

FPM Final Planning Meeting

HQDA Headquarter Department of Army

IA Information Assurance

IPM Initial Planning Meeting

IT Information Technology

JTR Joint Travel Regulation

JTF Joint Task Force

KO Contracting Officer

MHE Material Handling Equipment

MOA Memorandum of Agreement

MPM Mid-Planning Meeting

MSR Monthly Status Report

NACI National Agency Check Inquires

NGB National Guard Bureau

NLT Not Later Than

OCI Organizational Conflict of Interest

OCONUS Outside Continental United States

ODC Other Direct Costs

OPSEC Operations Security

PCO Procuring Contracting Officer

PII Protection of Personally Identifiable Information

POC Point of Contact

PRS Performance Requirements Summary

SOW SCOPE of Work

QA Quality Assurance

QAP Quality Assurance Program

QASP Quality Assurance Surveillance Plan

QC Quality Control

QCP Quality Control Program

SME Subject Matter Experts

TAR Travel Authorization Request

TE Technical Exhibit

WWAF-RA Wide Area Workflow-Receipt and Acceptance

3.0 Government Furnished Property, Material, Equipment and Services (GFP/M/E/S). The

Government will provide the property, material, equipment, and/or services listed below solely for the purpose of performance under this contract.

3.1 Property: Government will authorize Contractor an area for material storage.

3.2 Materials: None.

3.3 Equipment: None.

3.4 Services: None.

3.5 Utilities: None.

4.0 Contractor Furnished Property, Materials, Equipment and Services (GFP/M/E).

4.1 General: Except for those items specifically stated to be Government-Furnished in

Paragraph 3.0, the Contractor shall furnish everything required to perform these services as indicated in Paragraph 1.1.

4.2 Bathrooms: The Contractor shall provide portable bathrooms for their employees during the period of performance accompanied by its periodical maintenance.

5.0 Requirements. The Contractor shall:

5.1 Demolish existing bldg. 13 shack. (removing all existing utilities) and dispose.

5.2 Install new 110ft approx. chain link fence FE6-TBR-72 9GA with three barbed-wire on single outrigger and two 20ft gate fence (double gates) at Bldg. 95.

5.3 Provide all necessary power for the following system:

5.3.1 Install three new lighting fixtures (explosion proof type), two receptacle outlet and an electrical distribution panel for existing bldg. 95 shack.

5.3.2 Install approximately 230 LF of new PVC SCH 40 electrical conduit, distribution box and wiring.

5.3.2.1 Point of connection will be the existing transformer located to the South side of Bldg. 95.

5.3.2.2 Electrical conduit shall be install parallel to existing chain link fence.

5.3.3 Additional details will be provide at the site visit.

5.4 Oxygen tank relocation should be coordinated with Messer Gas P.R. Inc (tanks owner)

787-835-2233/2247.

5.4.1.1 The Contractor is responsible for any cost associate with the oxygen tank relocation.

5.5 All concrete slab joint sealant shall be removed and replace with non-petroleum based Sealant

5.6 Install approximately 200 FT of new ¾” dia. Copper type ‘K” water pipe line with hose bibb at bldg. 95.

5.7 Install new three static grounding receptacle at bldg. 95.

6.0 All quantities and measurements herein are approximate. Contractor is responsible to conduct a site visit for verification prior to proposal submission.

7.0 The Government contracts on the understanding that the Contractor is complying with applicable laws concerning workplace safety.

7.1 The Contractor is subject to all citations and penalties for violation of applicable workplace safety laws. The burden of compliance rests with the Contractor.

7.2 The Contracting Officer may notify the Contractor of hazards in Contractor operations that endanger Government personnel or property and require appropriate abatement action. This provision does not constitute assumption of liability for

Occupational Safety and Health compliance on the part of the Government or negate other agency responsibility for enforcement of applicable laws.

7.3 Accident prevention principles must be thoroughly integrated into all operations.

Unsafe Conditions and practices, as identified by the Contracting Officer or designated representative, must be corrected immediately.

7.4 All debris generated by the Contractor’s operations shall be removed from the base.

Solid Waste Management: All waste materials and debris generated by work under this contract shall be processed, handled, transported, stored, and disposed of by the

Contractor in accordance with all federal, state, local, regulations, and laws. All waste streams will be quantified and reported to the Base Environmental Manager.

The Contractor shall be responsible for any permit or fees associated with the use of off-base disposal locations.

7.5 The Contractor shall be liable for any loss, destruction or damage and deterioration to Government property, including vegetation and landscaping, resulting from

Contractor operations. Any damage to government or personal property shall be repaired or replaced to the Contracting Officer’s satisfaction at the Contractor’s expense.

7.6 All work under this project shall meet applicable County, Territorial, Federal and

Air National Guard construction codes, regulations and policies.

7.7 Contractor shall coordinate with Contracting Officer to verify the existing site and facility conditions. Any differing conditions shall be notified in writing to request clarification.

7.8 Equipment or fixtures Government Furnished Contractor Installed (GFCI): None anticipated.

7.9 Comply with all Specifications applicable found and included by reference in the www.wbdg.org site. This will include all UFC and UFGS.

7.10 For additional information on drawings and specifications and for entering the Site premises contact the Base Civil Engineer (BCE) office in Building 25, Muñiz ANG

Base telephone (787) 253-5236. Must request Digging Permit before work start.

7.11 For additional contracting issues will be directed to the Contracting Officer in

Building 29, Muñiz ANG Base at telephone (787) 253-5238 or 7438.Must fill out

Base Access Letter before project start.

7.12 For additional Environmental information, contact the Environmental Manager

Office in Building 25, Muñiz ANG Base telephone (787) 253-5193.

7.13 For additional Safety information, contact the Safety Office in Building 22, Muñiz

ANG Base telephone at (787) 253-5275. Must request Confine Space Entry AF

Form 1024 before work start.

7.14 For additional Bioenvironmental information contact the Bioenvironmental Office in Building 16, Muñiz ANG Base telephone at (787) 253-5265

7.15 For additional Fire information, contact the Fire Department in Building 3, Muñiz

ANG Base telephone at (787) 253-5222. Must request permit to use open flame equipment or grinders.

7.16 For additional Security information contact the Base Defense Operation Center in

Building 99, Muñiz ANG Base telephone at (787) 253-5204

7.17 Contractors must be registered (current) in the System for Award Management

(SAM) internet program at: http://www.sam.gov

7.18 All invoices must be submitted using Wide Area Workflow (WAWF) internet program at: https://wawf.eb.mil

7.19 Contractor will verify status of all invoices My Invoice link at: https://wawf.eb.mil

7.20 Contractor Manpower Reporting Application (CMRA): The Contractor shall completely fill in all required data fields using the following web address:

http://www.ecmra.mil/ Reporting inputs shall be for the labor executed during the period of performance during each Government fiscal year (FY), which runs

October 1 through September 30.

7.21 Every day all refuse and remaining materials related to the work will be taken to a refuse container provided by the Contractor.

7.22 Only company cars with distinctive logos posted at passenger and driver doors will be authorized inside Base premises.

7.23 All personnel are required to show a valid not expired ID in the main entrance gate before entering the Base premises.

7.24 At the end of each working day, all areas will be clear from equipment, tools and materials.

7.25 Special precautions will be taken at no cost to government to protect base property during the project execution.

7.26 The use of Personal Protective Equipment is mandatory at all time while working on the project.

8.0 Applicable Publications: Publications applicable to this SOW are listed below:

Technical Exhibit 1 Performance Requirements Summary (PRS)

Publication (Chapter/Page)

Date of Publicatio n

Mandatory or Advisory

Website

Federal Acquisition Regulation

Mandatory https://www.acquisition.gov/?q=browsefar or http://farsite.hill.af.mil/

Defense Federal Acquisition Regulation http://www.acq.osd.mil/dpap/dars/dfarspgi/cu rrent/index.html or http://farsite.hill.af.mil/

AR 190-13 The Army Physical Security

February

Mandatory http://www.apd.army.mil/ProductMaps/PubFo rm/AR.aspx

AR 530-1 Operations Security

26 Sep

OK http://armypubs.army.mil/ProductMaps/PubF orm/AR.aspx

DoD 5220.22-M National Industrial Security Program

18 May

OK http://www.dtic.mil/whs/directives/corres/pub 1.html

DG 415-5 General Facilities Design

1 June 2011 Advisory https://www.wbdg.org/FFC/ARMYCOE/NATL GUARD/dg_415_5.pdf

UFC 4-010-01 1 Oct 2013 Mandatory https://pdc.usace.army.mil/library/ufc/4-010- 01/

DOD Min. AT/FP Standards for Buildings

29 CFR 1926 OSHA

Construction

January

Mandatory www.OSHA.gov

AR 385-10 Chapter 4 Safety Program http://www.ngbpdc.ngb.army.mil/pubs/385/ngr38 5_10.pdf

This PRS includes performance objectives the Government will use to determine Contractor performance and will compare Contractor performance to the Acceptable Quality Level (AQL).

Performance Objectives

Performance Standards

Acceptable Quality Levels AQL

Surveillance Method / By Whom

Demolition

Demolition service

Meets the standard 100% of the time as approved on the work schedule.

COR / Monthly.

Safety Standards

Compliance with safety requirements

Contractor shall have available all records as required on the SOW.

COR / Monthly.

A. SUBMITTAL LIST

DESCRIPTION TYPE QTY D REMARKS

Material Approval Submittals:

Shop Drawings Product data Lighting fixtures Water system Electrical system

AF Form

NLT 7 days after final shop drawings and 7 days before

NTP

Must be signed by:

Contracting COR

Contractor (return copy)

Environmental & Hazardous Material Plan

AF Form 3000 1

Approved 7 days before

NTP

Must be signed by:

Contracting COR

Contractor (return copy)

Quality Assurance Plan AF Form 3000 1

Approved 7 days before

NTP

Must be signed by:

Contracting COR

Contractor (return copy)

Safety Plan AF Form

Approved 7 days before

NTP

Must be signed by:

Contracting COR

Contractor (return copy)

Warranty Certificates AF Form

Before final invoice is certified

Must be signed by:

COR CE

B. DESIGN AND CONSTRUCTION STANDARDS AND REFERENCES:

ASTM (American Society for Testing and Materials) – Latest Edition

Unified Facilities Guide Specification (UFGS) Web Site:

http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs

SECTION 32 31 13.53 HIGH-SECURITY CHAIN LINK FENCES AND GATES

All federal applicable UFC, UFGS and ANG ETL’s must be verified at www.wbdg.org

C. INVOICE REQUIREMENTS:

Electronic pictures of work to be invoiced (Before and After)

Breakdown for Payment

Monthly Report from: Contractor Manpower Reporting Application (CMRA)

Progress Report of activities.

Project Schedule (CPM): Baseline Vs Update

D. CLOSEOUT DOCUMENTATION:

Recycling or landfill proof of disposition document.