3. CSI Specs.pdf
PDF 238 KB Posted
- Attached to
- 127EAW21R0074 - Tamarack Sno-Park Repaving
- Solicitation number
- 127EAW21R0074
- Issued by
-
Department of Agriculture Forest Service
About this file
This document package includes technical specifications and a federal contract opportunity notice for the Tamarack Sno-Park Repaving Project. The technical specifications outline requirements for signage, paint, and other construction elements. Signage must meet standards for posts, custom maps, information boards, and aluminum signs. Painting requirements include primers and coatings for metal, wood, concrete block, and other surfaces. The related federal contract opportunity is a solicitation from the Department of Agriculture Forest Service for repaving work at the Tamarack Sno-Park. The total value is between $250,000 to $500,000 with a small business set aside. The response deadline for submissions is August 17, 2021, with an organized pre-proposal site visit not scheduled.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 127EAW21R0074-A00003.pdf | ||
| 1. Statement of Work - Revised 26 Aug.pdf | ||
| 127EAW21R0074_A00002.pdf | ||
| Schedule - Revised 24 Aug 2021.docx | DOCX document | |
| RFI Official Responses - 1.pdf | ||
| 127EAW21R0074_A00001 - 1.pdf | ||
| 2. Supplemental Specifications.pdf | ||
| 4. Fire Plan.pdf | ||
| 1. Statement of Work.pdf | ||
| 127EAW21R0074 - Tamarack Sno-Park Repaving.pdf | ||
| 6. Davis-Bacon Act WD # CA20210018.pdf | ||
| 7. RFI Form.docx | DOCX document | |
| 5. Tamarack Sno-Park Plans.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Specifications D-i Tamarack Sno-Park Repaving Project
TAMARACK SNO-PARK REPAVING PROJECT
TECHNICAL SPECIFICATIONS
SHOP DRAWINGS AND SUBMITTALS
SIGNS
PAINT
Specifications D-2 Tamarack Sno-Park Repaving Project
SHOP DRAWINGS AND SUBMITTALS
GENERAL
SCOPE
A. Perform all work necessary and required for the construction of the project as indicated. Such work includes but is not limited to the following:
1. Shop Drawings
2. Samples
3. Catalog Data
4. Operation and Maintenance Manuals
5. Certificates and Warranties
MEASUREMENT AND PAYMENT
A. No separate measurement or payment will be made for the work associated with this section, all costs associated with the work, materials and full compliance of this section shall be included in other bid items and no separate payment shall be made therefore.
SUBMITTALS
A. Submittals shall include all pertinent data required to understand the quality of components, dimensional relationships, integration with other materials, assembly techniques, structural aspects, color, finish, texture, and other such characteristics as may be necessary to fully describe the item and its intended use.
PRODUCTS
A. Not Used.
EXECUTION
SUBMITTALS
A. Submittals and shop drawings shall be submitted in a timely fashion to allow ten
(10) working days for review by the Forest Service. No work shall begin until shops drawings and submittals are approved. Four (4) copies of all submittals shall be submitted to the Forest Service. At the Forest Service’s discretion, electronic copies of all submittals may be submitted in lieu of hard copies.
SHOP DRAWINGS
A. Original Submittal: Four (4) legible copies of all shop drawings shall be submitted for approval as required under 1300.2.1 above prior to fabrication, installation, or
Specifications D-3 Tamarack Sno-Park Repaving Project order placement to allow for checking and coordination. If approved, the submittal summary and only one (1) copy of the shop drawings will be returned to the contractor. At the Forest Service’s discretion, electronic copies of all shop drawings may be submitted in lieu of hard copies.
B. Resubmittal: When a resubmittal is required, the submittal summary and only one
(1) copy of the shop drawings indicating so will be returned to the Contractor. After revision of the original, four (4) copies shall be resubmitted for approval.
C. Approval: Once approved, the submittal summary and only one (1) copy of the shop drawings will be returned to the contractor. Variation from the approved documents shall be likewise submitted and approved before being carried out. Approval of satisfactory submittals and substitutions will be made within 10 working days of receipt.
SAMPLES
A. Original Submittal: Two samples of each item for which samples are required, unless otherwise specified, shall be furnished for approval. Approval shall be obtained prior to delivery of the material to the project site. These samples shall be representative of the actual material proposed for use in the project and of sufficient size to demonstrate design, color, texture, and finish as they will appear in the completed installation.
B. Resubmittals: All rejected samples will be returned upon request and any or all resubmittals required shall consist of two new samples.
C. Approval: Upon approval, one sample so noted will be returned and the remainder will be retained by the Forest Service until completion of the work. When requested, all approved samples will be returned for installation providing identity is maintained in an approved manner until final acceptance of the project.
CATALOG DATA
A. Submittals: Four (4) legible copies of catalog data are required for the original submittal and each resubmittal. Catalog data shall be submitted along with shop drawings. Only one (1) copy of the shop drawings will be returned to the contractor.
B. Data: Each submittal shall have all pertinent data contained therein that is applicable to the item submitted for approval.
IDENTIFICATION
A. Catalog Data: Each separate catalog brochure or page submitted shall have the identification shown. Catalog of brochures submitted containing multiple items for approval need have only cover identification. In such cases the identification shall include page and catalog item numbers.
Specifications D-4 Tamarack Sno-Park Repaving Project
B. In the event one or more of the multiple items are not approved in any submittal, the additional copies required will not be requested until all items are approved.
TIMING
A. The Contractor shall provide submittals far enough in advance of the scheduled dates of installation to provide time for reviews, securing necessary approvals, for possible revisions and resubmittals and for placing orders and securing delivery.
B. No portion of the work requiring an approved submittal shall be started nor shall any material be fabricated or installed prior to the approval of such item.
END OF SECTION 1300
Specifications D-5 Tamarack Sno-Park Repaving Project
PART 1
SIGNS
GENERAL
SCOPE
A. This section covers the requirements to perform work including but not limited to furnishing and installing signage as shown on the Drawings, and as otherwise directed by the Forest Service.
MEASUREMENT AND PAYMENT
A. Measurement and/or payment will be made for the work described in this Section, as shown on the schedule of items under the title(s):
1. INSTALL ENTRANCE SIGN
2. INSTALL BULLETIN BOARDS
3. INSTALL ACCESSIBLE SIGN
4. INSTALL STOP SIGN
RELATED SECTIONS
A. Related work specified in other sections includes, but is not limited to:
1. SECTION 2100 – CLEARING AND DEMOLITION
2. SECTION 2200 – EARTHWORK
3. SECTION 09900 - PAINTING
SUBMITTALS
A. Submit supplier details and installation instructions for each type of sign to be installed in the work.
B. Submittals shall conform to Section 01300. Proofs shall be submitted for each of the signs listed below.
1. Entrance Signs
2. Bulletin Boards with Custom Map and Custom Information Board
3. Stop Sign
4. Accessible Parking Sign (w/ Van Accessible Sign)
QUALITY CONTROL / ASSURANCE
Specifications D-6 Tamarack Sno-Park Repaving Project
A. Conform to the Contract Documents including but not limited to General
Conditions, Special Conditions, Permits, Technical Conditions, Drawings, and
Standard Specifications.
B. Field verify all new and existing dimensions affecting the work of this contract before ordering products.
PRODUCTS
GENERAL
A. All materials shall conform to sizes, qualities and quantities as shown on the
Drawings or described in the specifications.
B. All campground signage components of a similar material type shall be from a single manufacturer, who is fully experienced, reputable, and qualified to provide continuous quality control through plant inspection and certification of materials.
C. Materials shall be from new stock, delivered in good condition, and no used or damaged stock is allowed.
D. Furnish the marker/sign panel, post, fasteners and hardware materials shown on the
Drawings for the applicable item of work. Furnish the sign panel, post, fasteners and hardware materials shown on the Drawings for the applicable item of work.
E. For required materials as shown on the Drawings, conform to the applicable provisions of Section 718, Traffic Signing and Marking Material of the FP-14
Standard Specifications.
F. All aluminum signs shall be "Reflective Aluminum - Clear Coat Overlay with Edge
Film".
POSTS
A. All sign posts shall be 6"x6" Douglas Fir rough cut pressure treated and stained in accordance with Section 09900 unless shown otherwise on the drawings. All posts shall have 1" 45 degree chamfer on the top end.
B. All materials shall conform to sizes, qualities and quantities as shown on the
Drawings or described in the specifications.
CUSTOM MAP, INFORMATION BOARD, AND ALUMINUM SIGNS
A. The signs shall be manufactured by Wood Product Signs, Routed Recycle Plus, Inc.
4890 County Road 76, Parlin, CO 81239. (970) 641-1675.
www.woodproductsigns.com. or approved equal by the Forest Service.
EXECUTION
Specifications D-7 Tamarack Sno-Park Repaving Project
A. All signs and campsite markers shall be installed AS SHOWN ON THE
DRAWINGS.
B. Contractor shall not install any signage until the locations and/or layout has been staked/marked in the field by Contractor, and accepted by the Forest Service.
C. Confine all operations to work / grading limits of the project and prevent damage to natural features and surroundings.
D. Existing utilities shown on the Drawings are approximate. The Contractor is responsible for ascertaining the location of, and protection for, all utilities to be encountered in the performance of the required work.
E. Treated wood products and preservative treatments shall conform to the latest
American Wood Protection Association (AWPA) Standards.
F. Conform to federal and state environmental protections for water and lands, in handling and construction of treated wood materials.
G. Implement protective measures and conform to permit requirements for all sawing/ cutting of treated wood and painting/finishing operations.
H. Control and properly dispose of all treated wood product wastes (including cuttings) generated from construction according to federal and state regulations. Recycle or dispose of treated wood product wastes only at certified facilities approved to recycle or receive such materials.
I. Horizontal locations, grades and mounting heights for signage facilities are to be established from referenced benchmarks, as shown on the Drawings, and as otherwise directed by the Forest Service for best fit to field conditions.
J. Excavation widths and depths shall be as shown on Drawings, but should be no wider than what is required to safely place and compact the backfill material around the post.
K. After setting posts in position, fill any void space around the base with native material or clean well drained inorganic granular material (free of rock). Thoroughly tamp and water fill material as necessary to secure post in place.
L. Treat all post field cuts with copper naphthenate (or approved equal).
M. Install marker and sign posts plumb and straight, oriented properly for marker/sign panel face. Backfill shall be as shown on the Drawings.
N. Attach marker/sign panels and hardware with the types and sizes of fasteners shown on the Drawings, conforming to the Specifications. Use antitheft fasteners.
O. The Contractor shall protect newly installed facilities for the duration of the work.
P. Repair and replace any damaged parts with new materials.
Specifications D-8 Tamarack Sno-Park Repaving Project
Q. Repair protective coatings and paints per the manufacturer requirements to retain all warranties.
R. All exposed bolt heads shall be etched and painted in accordance with Section
09900 and AS SHOWN ON THE DRAWINGS.
END OF SECTION 2590
Specifications D-9 Tamarack Sno-Park Repaving Project
PAINT
SCOPE
A. This section covers furnishing all labor, materials and equipment necessary to apply specified paints and protective coatings.
MEASUREMENT AND PAYMENT
A. No separate measurement or payment will be made for the work associated with this section, all costs associated with the work, materials and full compliance of this section shall be included in other bid items and no separate payment shall be made therefore.
RELATED SECTIONS
A. SECTION 2590 – SIGNS
SUBMITTALS
A. Paint and Primer
DEFINITIONS
A. The terms “paint” and “protective coating” shall include linings, enamels, paints, stains, sealers, catalysts, thinners, and other organic or inorganic paint products.
SURFACES TO BE COATED
A. Concrete surfaces, plumbing and electrical fixtures, exposed pipes, bolts, and metal components. Nonferrous metals and stainless steel shall not be coated unless otherwise noted.
QUALITY CONTROL / ASSURANCE
A. SURFACES TO BE PAINTED AND DRY MIL THICKNESSES:
1. Metal
a) Piping not Submerged: All piping not submerged, except nonferrous and stainless steel pipe, shall receive one coat of chlorinated rubber base primer of a minimum dry film thickness of 1.2 mils, and 3 coats of chlorinated rubber base paint of a minimum dry film thickness of 2.0 mils per coat.
b) Equipment and Valves: Other equipment and valves, except not submerged nonferrous and stainless steel surfaces, shall be painted in accordance with
Paragraph 1 above. Equipment such as control panels furnished with the manufacturer’s finish shall not be field painted provided that abraded areas are
Specifications D-10 Tamarack Sno-Park Repaving Project touched up using the same type and color of material that was used for the original finish. Machined working surfaces shall not be painted.
c) Structural Steel and Miscellaneous Metalwork: All structural steel and miscellaneous metalwork, Paragraph 1 above, and all such metal submerged during normal operations shall be painted in accordance with Paragraph 2 above.
d) Damaged Galvanized Coating: All damaged zinc coating shall be spotted with
Galvonox.
2. Wood: Wood surfaces shall be dipped in stain preservative for 15 seconds and stacked to prevent markings.
3. Concrete Block: All concrete block shall have two coats of clear silicone waterproofing applied in accordance with the manufacturer’s recommendations.
PRODUCTS
GENERAL
Items to be Coated Coating Used Product Description
Metal:
Doors and Frames Primer
Two Coats of Exterior Zinsser Cover
Stain Primer Classic Oil 100.
Paint
Two Coats of Exterior Acrylic Latex
Paint & Primer. Item No. 16006.
ACE Royal Satin Acrylic Latex
House & Trim Paint & Primer.
Dark Chocolate
Ferrous Galvanizing (touchup) Galvanax, made by Subox Inc.
Atmospheric Exposure (Exposed
Pipes, Bolts, Metal Components) Primer
Two Coats of Exterior Zinsser Cover
Stain Primer Classic Oil 100.
Paint
Two Coats of Exterior Acrylic Latex
Paint & Primer. Item No. 16006.
ACE Royal Satin Acrylic Latex
House & Trim Paint & Primer.
Dark Chocolate
Buried to within 2 feet of water Primer Bitumastic Koppers Super Service, Black
Finish Bitumastic Koppers Super Service, Black
Wood:
Atmospheric Exposures Stain
Two Coats of Exterior Acrylic Latex
Stain. Item No. 1962174.
ACE Wood Royal Solid
Transparency. Deck & Siding Stain.
Dark Chocolate
Underground or water contact Penetrant Pentachlorophenol
Felt Spacer Pads Penetrant Penta
Specifications D-11 Tamarack Sno-Park Repaving Project
Concrete Blocks Clear Silicone Waterproofing Water Bar sealant, 2 coats
EXECUTION
PREPARATION OF SURFACES
A. Surfaces to be painted shall be free of dirt, dust, scale, or any other substance which may interfere with the adhesion of the specified coat. Surfaces that cannot by properly prepared by the painter for finishing shall not be painted or finished until they are rectified, unless instructed otherwise by the Forest Service.
APPLICATION:
A. The paint shall be thoroughly mixed before applying. Liquid shall not be added to thin paint unless permitted by the Forest Service. Heating in hot water will be permitted.
B. Paint may be applied with hand brushes or by spraying. The finished sur-faces shall be free from runs, drips, ridges, waves, laps, brush marks and other blemishes.
Welds shall receive special attention to assure their receiving a coating of the required thickness.
C. Paint shall not be applied when the air temperature is below 40°F., or when the air is misty. It shall not be applied upon damp or frosted surfaces.
D. Special care shall be taken not to injure or splatter adjacent work. Should adjacent work be injured or splattered, it shall be cleaned and the original surface restored.
E. Cloth, cotton wastes, or other materials which constitute a fire hazard shall be placed in closed metal containers or be destroyed at the end of each day’s work.
F. Coatings shall be applied in conformance with the manufacturer’s recommendations.
G. Safety: All applicable State and Federal safety requirements shall be followed during all painting. Adequate protective equipment and support systems shall be made available to the Inspector for his use during the inspection of the work.
END OF SECTION 9900