This document is an instruction sheet for completing the Combined Project Budget, Scope of Work and Funding Worksheet for the 2028 Capital Outlay Application administered by the New Mexico Aging and Long Term Services Department for senior centers seeking capital outlay funding. The application supports improvements to existing senior-service facilities, including renovations to spaces or building systems, correction of documented code or safety deficiencies, and construction of new additions that expand existing facilities. Applicants must complete one worksheet per project or project phase, providing detailed information on the specific work included in the application, existing conditions and needs, proposed work with measurable quantities, and the completed deliverable. The instructions distinguish between two renovation categories based on cost thresholds: projects of $225,000 or less and those exceeding $225,000, with the latter requiring proof of completed planning and design documentation. New additions require completed planning and design documentation regardless of cost. For phased projects, applicants must identify the specific phase requested, describe what it will accomplish, explain remaining work and funding needs, and clarify dependencies on future phases.

The application requires comprehensive budget documentation distinguishing between current-phase costs and full-project costs, supported by itemized estimates and identified sources including quotes or estimates. Applicants must identify all funding sources across categories of requested, secured, pending, and anticipated funding, with calculations to determine any unidentified funding gaps. Planning and permitting requirements vary by project type and cost, with smaller renovations potentially not requiring formal planning and design but still requiring identification of permitting requirements and status. Code compliance projects must describe deficiencies, proposed corrections, reviewing authorities, and correction deadlines, supported by inspection reports or assessments where available. The applicant review section requires attestation that scope, budget, funding request, and schedule describe the same work; that current-phase and full-project costs are properly distinguished; that required documentation is attached; and that costs and funding sources are not duplicated, with full disclosure of funding gaps, outstanding approvals, and remaining work.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Instructions for Completing the Combined Project Budget, Scope of Work and Funding Worksheet 2028 Capital Outlay Application guidance Complete one worksheet for the project or project phase included in your application. Explain what the requested funding will accomplish, how costs were estimated, what other funding is available, and whether the work is ready to proceed.

Distinguish the current phase (the work included in this application) from the full project (all phases from initial planning through final completion). Enter N/A for items that do not apply. Explain information that is not yet available.

1. Applicant and Project Information Provide the legal entity name, facility name, physical project address, project title and primary contact information. Use the same names throughout the application and attachments.

Select all applicable project types: renovation, code compliance, new addition or a combination.

Identify whether the request is for planning and design or renovation/construction.

For a phased project, provide a phase number and descriptive title, such as Phase 1 — Planning and Design or Phase 2 — Senior Center Renovation.

2. Scope of Work Describe the specific work included in this application. Avoid general statements such as “improve the facility.”

Worksheet item
What to include
Existing conditions and need
Describe the problem, location, effect on services and intended beneficiaries.
Proposed work
Explain what will be repaired, replaced, renovated, evaluated or constructed.
Work item and location
Identify the room, building area, site location or system affected.
Quantity or extent
Provide square footage, room counts, fixture counts or other measurable quantities. Label estimates.
Deliverable
Identify the completed result, such as a report, design documents, renovated space or completed addition.
Exclusions and dependencies
Identify excluded work and activities that must occur before this work can begin.
Relationship to full project
Explain connections to completed and future phases.
Independent use
Explain whether the completed phase can be used before future phases are finished.
Schedule and service continuity
Provide start and completion dates, closures, relocation plans and measures to maintain services.

Example scope description Renovate two existing restrooms within the senior center, including replacement of fixtures, modification of interior layouts and installation of associated finishes. This request does not include kitchen renovation or construction of additional space. Final quantities and costs will be supported by the attached scope and estimate.

3. Planning, Permitting and Readiness Identify completed planning and design, remaining activities and the parties responsible.

Renovations of $225,000 or less: Planning and design may not be necessary depending on scope. Explain the basis for the determination. Permits may still be necessary and must be identified.

Renovations greater than $225,000: Attach proof of completed planning and design appropriate to the proposed renovation.

New additions: Attach proof of completed planning and design for the construction included in the request.

If planning and design are incomplete, identify that work as the initial phase rather than presenting renovation or construction as ready to proceed.

Planning and design documentation may include assessments, environmental testing, engineering evaluations, drawings, specifications, cost estimates and other applicable preconstruction documents.

Permits and approvals For each required permit or approval, identify the issuing authority, status (not started, submitted or approved), anticipated approval date and responsible party. Attach approvals already obtained.

If no permits are required, identify who made that determination and the basis. If requirements are unknown, explain how and when they will be confirmed. Complete this section for smaller renovations as well.

Code compliance Describe the deficiency, proposed correction, reviewing authority and any correction deadline. Attach available inspection reports, notices or assessments.

4. Project Budget Provide itemized estimates for the current phase and the full project.

Budget column
How to complete
Current phase
Enter all costs of this application phase, including costs paid by other sources.
Full project
Enter the cost of all phases from beginning to end, including the current phase and applicable prior-phase costs.

The current phase is included in the full project. Do not add these columns together. For a single-phase project, the amounts may match.

Enter amounts for applicable cost categories and use N/A where appropriate.

Identify the estimate source, preparer and preparation/update date. Attach supporting quotes or estimates.

Explain contingency amounts and their basis.

Distinguish costs already incurred from costs remaining to complete the project.

Do not assume listed costs are eligible for funding; verify eligibility against final program requirements.

5. Funding Sources and Reconciliation List this application request separately from other sources. Identify the amounts allocated to the current phase and to other phases.

Status
Description
Requested
The amount sought through this application; submission does not make it secured.
Secured
Funding supported by an award, commitment or other documentation confirming availability. Identify conditions or restrictions.
Pending
A request has been submitted but a funding decision has not been received.
Anticipated
A potential source that has not yet been confirmed or formally requested.

Do not allocate the same dollars to more than one phase. Do not present funds already spent as available for future work.

Current-phase calculations

Line
Instructions
A — Current-phase cost
Enter the full cost of the phase included in this application.
B — Application request
Enter the amount requested in this application.
C — Other secured funding
Enter confirmed funding allocated to the phase, excluding this request.
D — Other pending/anticipated funding
Enter unconfirmed funding allocated to the phase.
E — Unidentified funding gap
Calculate A − B − C − D. If negative, explain excess funding or adjust allocations.
F — Amount not yet secured
Calculate A − C. This includes the application request and other unconfirmed amounts.

A project may have no unidentified gap and still lack secured funding. Explain the plan if pending or anticipated funds are not awarded, and identify restrictions and availability dates.

Full-project calculations Compare total full-project cost with identified funding across all phases on the same beginning-to-end basis. Count the application request once. Separately identify funding already spent on prior phases. Disclose the remaining gap and explain how it will be addressed.

6. Attachments and Applicant Review List attachments by recognizable document name and indicate what each supports. Include applicable estimates, planning/design documents, permits, inspection reports, funding commitments and schedules.

☐ Scope, budget, funding request and schedule describe the same work.

☐ Current-phase costs are distinguished from full-project costs.

☐ Required planning/design documentation is attached.

☐ Permitting requirements and status are identified, including for smaller renovations.

☐ Costs and funding sources are not duplicated.

☐ Funding gaps, outstanding approvals and remaining work are disclosed.

The preparer should enter their name and title, review the acknowledgment, and sign and date the completed worksheet.

Draft Assumptions to Confirm Before Release These instructions assume the $225,000 threshold applies to total renovation project cost rather than only the amount requested. Projects costing exactly $225,000 fall in the lower category. These instructions also treat new additions as new construction for planning-and-design documentation. Confirm these points and all final application requirements before release.