3-Attachment 4 - Technical Specifications.pdf
PDF 5 MB Posted
- Attached to
- Farallon Well No. 3 - Drilling Services
- Solicitation number
- IFB No. 32700084
- Issued by
- Maricopa County, Arizona
About this file
This is a Technical Specifications document prepared by Matrix New World Engineering for the City of Buckeye, Arizona, detailing drilling services required for the completion of Farallon Well No. 3, a production well located east of South Oglesby Road and north of Baseline Road in Buckeye, Arizona. The scope of work includes borehole reaming (or new surface casing drilling and pilot borehole drilling if the existing pilot borehole location is unsuitable), well casing and screen installation, well development through swabbing and airlift pumping, and post-construction aquifer testing consisting of a 20-hour step-rate discharge test and a 48-hour minimum constant-rate test with water-level recovery monitoring. The project involves drilling a minimum 28-inch diameter borehole to approximately 1,040 feet below ground surface, installing an 18-inch nominal diameter stainless steel production well casing with a louvered screen section, and conducting geophysical logging and formation sampling during pilot hole drilling. The contractor must submit bid prices for 14 line items covering mobilization/demobilization, surface casing construction, borehole drilling, geophysical logging, casing and screen materials, installation labor, annular materials, development, pumping activities, and final alignment testing and video survey, with final payment based on actual quantities.
The bid tab establishes payment on a unit-price or lump-sum basis as designated for each line item, with quantities identified as not guaranteed and final payment adjusted based on actual work performed. The contractor must possess no less than five years of experience with reverse circulation rotary drilling under similar Arizona Basin and Range conditions, hold a valid Arizona Department of Water Resources Well Driller's License and an Arizona Registrar of Contractors License (type A, A-4, A-16, or C-53), and provide certifications demonstrating compliance with equipment decontamination and welding standards prior to work commencement. The specifications include detailed requirements for drilling fluid control, material specifications (including Type 304L and 316L stainless steel casing and screen, Portland cement conforming to ASTM standards, and silica sand filter pack with specific gradation), and quality assurance measures such as plumbness and alignment testing and video survey documentation. The contractor bears responsibility for all site safety, equipment maintenance, environmental protection, utility location coordination, and cost implications of well loss, low penetration rates, and lost circulation conditions; the owner will compensate the contractor only for lost circulation and low penetration rate conditions when specified notification and documentation requirements are met and circumstances are not attributable to contractor fault.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2-IFB No. 32700084 Bid Table.xlsx | XLSX spreadsheet | |
| 1-IFB No. 32700084 - Farallon Well No. 3 Drilling Services.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Technical Specifications Farallon Well No. 3
B(01-04) 36 CBC
October 30, 2026
S:\MyDocs\SGCPRJ\2026V\26-01166 Buckeye Farallon Well 3\Specs\2026.10.30_WellTechSpecs_Farallon3.docx iv
LIST OF FIGURES
FIGURE NO. DESCRIPTION
1 Well Location Map
2 Preliminary Well Design
S:\MyDocs\SGCPRJ\2026V\26-01166 Buckeye Farallon Well 3\Specs\2026.10.30_WellTechSpecs_Farallon3.docx v
LIST OF TABLES
TABLE NO. DESCRIPTION
1 Bid Tab
S:\MyDocs\SGCPRJ\2026V\26-01166 Buckeye Farallon Well 3\Specs\2026.10.30_WellTechSpecs_Farallon3.docx vi
LIST OF APPENDICES
APPENDIX NO. DESCRIPTION
A Boring Log and Geophysical Logs – Pilot Borehole
B Submittal List
S:\MyDocs\SGCPRJ\2026V\26-01166 Buckeye Farallon Well 3\Specs\2026.10.30_WellTechSpecs_Farallon3.docx 1
1.0 INTRODUCTION
1.1 LOCATION
The work to be accomplished under the following specifications consists of completion of a production well at the Farallon Well No. 3 (Well 3) site east of S. Oglesby Road and north of Baseline Road in Buckeye, Arizona (Site). Cadastral coordinates are the southwest ¼ of the northwest ¼ of the southwest ¼ of Section 36, Township 01 North Range 04 West [B(01-04) 36 CBC. A map of the proposed well location is presented in Figure 1.
1.2 DEFINITIONS
Throughout this specification, the term OWNER shall be understood to represent City of Buckeye. The term CONSULTANT shall be understood to represent Matrix New World Engineering. The CONTRACTOR shall be the person, firm, or corporation with whom the OWNER will sign an agreement setting forth the terms and conditions for the work to be performed, as specified herein. The term SUBCONTRACTOR will apply to any person, firm, or corporation with whom the CONTRACTOR signs a secondary agreement for a portion of the scope of work.
1.3 SCOPE OF WORK
The location of the previously completed pilot borehole is under review. The scope of work may entail reaming the existing pilot borehole through the existing 36-inch nominal diameter surface casing to a target depth of 1,040 feet below ground surface (ft bgs). If the existing location is not the final desired location, then a new surface casing shall be drilled and installed followed by a minimum 16-inch diameter pilot borehole drilled to a target depth of 1,040 ft bgs. If pilot hole drilling is performed, lithologic cutting samples and geophysical logging will be conducted in the pilot borehole as specified herein. Groundwater levels in the area are estimated to be approximately 95 ft bgs. The geophysical logs and boring log from the pilot borehole are presented in Appendix A.
The well completion design (18-inch nominal diameter well casing) is presented in Figure 2 for bidding purposes. The scope of work presented herein also includes post well construction aquifer testing.
Borehole reaming, well installation, well development, well completion, and aquifer testing by the CONTRACTOR shall be conducted under the oversight of the CONSULTANT and OWNER. This oversight shall not supersede the CONTRACTOR’s responsibility of operations and site safety and the Health and Safety requirements as presented in Section 1.4.4.
S:\MyDocs\SGCPRJ\2026V\26-01166 Buckeye Farallon Well 3\Specs\2026.10.30_WellTechSpecs_Farallon3.docx 2
A list of applicable CONTRACTOR submittals is presented in Appendix B. This Submittal List is provided for information only and is not intended as an exhaustive list. The CONTRACTOR should refer to the Technical Specifications presented herein, for detailed submittal requirements for this project. The CONSULTANT or OWNER makes no guarantee or warrantee that this list includes all requirements placed on the CONTRACTOR.
1.4 PERFORMANCE OF WORK
1.4.1 Contractor Qualifications
The CONTRACTOR shall have no less than five years of experience using the reverse circulation rotary drilling method under similar aquifer conditions (Basin and Range physiographic province in Arizona) and shall have recent experience (within the last 2 years) in zonal sampling, falling head testing, and installing large capacity potable water production wells having similar dimensions. The CONTRACTOR shall assign a foreman to oversee all work required by this specification. The CONTRACTOR shall provide with its bid submittal a resume of the foreman, including years of experience using the reverse circulation rotary drilling method in the installation of large capacity production wells. After selection, the CONTRACTOR shall provide written certification that they have read and fully understand this technical specification prior to mobilization.
The CONTRACTOR shall hold a valid ADWR Well Driller’s License in the reverse circulation or mud rotary category, a Register of Contractor License type A, A-4, A-16, or C-53, and all other licenses and permits required by federal, state, city or municipal rules and regulations. The CONTRACTOR shall also provide with its bid submittal a copy of their Arizona Well Drillers license and a copy of their Arizona Registrar of Contractors license.
1.4.2 Operations
The CONTRACTOR shall employ only competent employees for the execution of work and shall always maintain a three-person crew and a minimum of two employees on site while the drilling rig is in operation.
All operations shall be performed under the direct and personal supervision of an Arizona licensed well driller with a Registrar of Contractor License type A, A-4, A-16, or C-53. The CONTRACTOR shall construct the production well in accordance with the Rules and Regulations of ADWR, Article 8, Well Construction and Licensing of Well Drillers, as amended June 18, 1990. Well construction shall also comply with the guidelines of the Arizona Department of Health Services (ADHS) Engineering Bulletin No. 10 (1978), and City of Buckeye Well Sites (Chapter 3, Section 5) Engineering Design Standards, adopted May 18, 2021, and all other applicable State, County, or local regulations.
S:\MyDocs\SGCPRJ\2026V\26-01166 Buckeye Farallon Well 3\Specs\2026.10.30_WellTechSpecs_Farallon3.docx 3
Should the well be lost due to any fault on the part of the CONTRACTOR, the well shall be abandoned at no cost to the OWNER, in accordance with ADWR Article 8, Rule R12-15-816, and a replacement well shall be constructed in the immediate area. The replacement well location will be selected by the CONSULTANT or OWNER. Payment for the replacement well will begin once the depth and status at which the original well was terminated has been reached per the bid tab. The replacement well shall be completed in accordance with all the terms and conditions stated herein. However, if the inability to complete the well is not due to any fault of the CONTRACTOR, the CONSULTANT may designate a replacement well location and the OWNER shall provide reasonable reimbursement.
Rejection of any materials, work, or equipment by the CONSULTANT is at the CONTRACTOR’s expense, and at no cost to the OWNER. If a work delay is caused by the CONTRACTOR failing to comply with any item of these specifications, the CONTRACTOR will bear the burden of additional expenses, including any additional CONSULTANT charges assessed to the OWNER as a direct result of the delay.
1.4.3 Confidentiality
The CONTRACTOR shall not disclose any information relating to this project or the well site to anyone other than the OWNER or CONSULTANT without written permission from the OWNER, except as may be required by law. At all times during the conduct of the CONTRACTOR'S services, the CONTRACTOR and its employees and agents shall treat the work conducted by the CONTRACTOR and its SUBCONTRACTORS and the results thereof as confidential and proprietary to the OWNER.
Photographs may be taken throughout the project by the CONSULTANT and OWNER.
Any questions regarding the purpose or scope of work directed to the CONTRACTOR from individuals or entities other than representatives of the OWNER or CONSULTANT while work is being conducted for this project should be directed by the CONTRACTOR to the CONSULTANT or OWNER.
The CONTRACTOR shall inform its employees of this provision and shall obtain non-disclosure agreements from all SUBCONTRACTORS who will be involved in the performance of any of the work and provide the OWNER with copies of the executed non-disclosure agreements. This provision shall survive the termination of the contracted work tasks.
1.4.4 Health and Safety
The CONTRACTOR is responsible for assuring that CONTRACTOR and SUBCONTRACTOR personnel conform to all state and federal health and safety rules and regulations. The entire responsibility for the health and safety of the CONTRACTOR’S employees is the sole responsibility of the CONTRACTOR.
The CONTRACTOR must provide a Site Safety Plan for this project for its employees in accordance with
S:\MyDocs\SGCPRJ\2026V\26-01166 Buckeye Farallon Well 3\Specs\2026.10.30_WellTechSpecs_Farallon3.docx 4 applicable Occupational Safety and Health Administration (OSHA) requirements. The CONTRACTOR must assure that all CONTRACTOR personnel and SUBCONTRACTORS at the well site are thoroughly familiar with the Site Safety Plan for the proposed work. The Site Safety Plan must be provided to the CONSULTANT and OWNER by the CONTRACTOR at least 15 days prior to mobilization to the well site.
A copy of the Site Safety Plan must be easily accessible on the site for the duration of the project. In addition, CONTRACTOR personnel are required to have been trained in the use of any personal protective equipment required by the Site Safety Plan. The CONTRACTOR shall meet the requirements of the Site Safety Plan at its own cost.
The CONTRACTOR shall have hearing protection available for authorized visitors of the OWNER or
CONSULTANT.
S:\MyDocs\SGCPRJ\2026V\26-01166 Buckeye Farallon Well 3\Specs\2026.10.30_WellTechSpecs_Farallon3.docx 5
2.0 PROTECTION OF SITE
2.1 GENERAL
The CONTRACTOR shall take all necessary precautions to preserve the well site, as nearly as practical, in its present condition. The CONTRACTOR shall be responsible for replacing any damaged items. All litter and debris will be cleaned up daily and placed in containers for offsite disposal by the CONTRACTOR in a legal manner. The CONTRACTOR should be aware of the potential for theft and vandalism and take appropriate measures at its own expense.
A plastic tarp shall be placed beneath the drilling rig during mobilization to protect the site from accidental leaks or spills of petroleum products and will remain beneath the rig until demobilization. Any spills or leaks of oil, hydraulic fluid, or petroleum must be addressed immediately. Tanks must have appropriate warning signage to prevent accidental injury of employees and/or onsite visitors. The CONTRACTOR shall submit to the OWNER and CONSULTANT a site plan for approval depicting the location of equipment, materials, cutting lay down area, and sound panels/exterior fencing.
Well drilling fluids shall be contained onsite in an above ground tank provided by the CONTRACTOR without damage to the property, contamination of other wells or waterways, or creation of a nuisance.
Excess clean water that is free of suspended sediment, and as approved by the CONSULTANT, may be disposed of in an undeveloped portion of the property in an area designated by the OWNER. Cuttings generated during drilling operations can be temporarily stored onsite, for final offsite removal and disposal by the CONTRACTOR. Drilling mud must be removed from the site at the CONTRACTOR’s expense.
After completion of the work, the CONTRACTOR shall remove all debris, waste, trash, and unused materials or supplies; and shall remove all signs of construction activities including temporary work areas, temporary structures, stockpiles of waste materials; and shall restore the site, as nearly as possible, to its original condition and satisfaction of the OWNER.
2.2 SITE ACCESS
The CONTRACTOR shall be responsible for creating access to the site and maintaining the access road in good condition throughout the drilling program. If required, the CONTRACTOR shall obtain and maintain a dust control permit. A copy of the dust control permit must be kept onsite. The CONTRACTOR shall maintain track-out control devices and clean up after any track-out that occurs. Any track-out measuring 25 cumulative feet must be cleaned immediately. CONTRACTOR is solely responsible for delays because of its failure to maintain site access and shall bear the additional expense.
S:\MyDocs\SGCPRJ\2026V\26-01166 Buckeye Farallon Well 3\Specs\2026.10.30_WellTechSpecs_Farallon3.docx 6
2.3 NOISE CONTROL
Sound barricades will not be required at the well site.
S:\MyDocs\SGCPRJ\2026V\26-01166 Buckeye Farallon Well 3\Specs\2026.10.30_WellTechSpecs_Farallon3.docx 7
3.0 UTILITIES
3.1 WATER
The CONTRACTOR is responsible to estimate the quantity of water necessary for the project and for obtaining potable water to the well site. The CONTRACTOR shall be responsible for obtaining the necessary permits and meters to obtain water and properly monitor usage from the source.
CONTRACTOR shall also be responsible for traffic crossings (if required) and any other connections or ancillary equipment required for the use of the water at the site.
3.2 ELECTRICITY
The CONTRACTOR shall provide, at its own expense, all power required for its operations under the contract and appropriate lighting for 24-hour operations.
3.3 UNDERGROUND UTILITIES
Location of all subsurface utilities at the well site (including installation of sound panels) shall be the responsibility of the CONTRACTOR. Utility damage, caused by negligent actions of the CONTRACTOR, shall be repaired at the CONTRACTOR’S expense in accordance with the Utility specifications. The CONTRACTOR shall notify Arizona 811 prior to drilling and confirm the absence of any underground utilities.
3.4 SANITARY FACILITIES
The CONTRACTOR will be required to have at the drill site a portable “chemical” toilet for personnel use.
S:\MyDocs\SGCPRJ\2026V\26-01166 Buckeye Farallon Well 3\Specs\2026.10.30_WellTechSpecs_Farallon3.docx 8
4.0 EQUIPMENT
The CONTRACTOR shall furnish and maintain in safe and efficient working condition, all equipment necessary to perform the specified work, including a drilling rig or rigs capable of performing the specified operations to the specified depths; and, development, pumping, testing, sampling, and auxiliary equipment as specified or required to complete the described tasks. The drilling rig, pumping equipment, and auxiliary equipment used for this project shall be well maintained and shall meet OSHA standards.
All high-pressure hoses shall be equipped with a safety chain for protection in the event of hose failure.
If compressed air is introduced into the well during drilling or well development, the air from the compressor must be treated by passage through a high-volume carbon or coalescing filter to remove organic contaminants (e.g., compressor lubrication oil). The drilling rig shall have a derrick rating and hook load capacity capable of lifting no less than 120,000 pounds or 1.5 times the total casing weight, whichever is greater. CONTRACTOR will be required to have, for air lifting purposes, a compressor capable of supplying a minimum of 750 cubic feet per minute (cfm) at 350 pounds per square inch (psi).
Airlifting will require a minimum of a 6-inch inside diameter eductor pipe with a minimum 1.5-inch inside diameter airline.
Prior to the start of drilling, the CONTRACTOR shall decontaminate the drill rig and downhole tools by steam cleaning. The method and extent of steam cleaning must be approved by the CONSULTANT. The CONTRACTOR will be required to provide a letter of certification to the CONSULTANT of the decontamination of the CONTRACTOR'S equipment, prior to utilization. The CONTRACTOR may certify, in writing, the decontamination of critical (downhole) pieces of drilling equipment in lieu of actual steam cleaning, provided the downhole pieces of drilling equipment have not been in contact with any potential contaminants, hazardous or toxic materials since the last decontamination. All necessary steam cleaning will be conducted at the CONTRACTOR'S expense. The CONTRACTOR shall submit with their bid indicating drill rig availability and specific equipment to be used.
S:\MyDocs\SGCPRJ\2026V\26-01166 Buckeye Farallon Well 3\Specs\2026.10.30_WellTechSpecs_Farallon3.docx 9
5.0 REPORTS, LOGS, AND RECORDS
5.1 GENERAL
The CONTRACTOR shall keep accurate and legible logs as described below. The forms for penetration rate log, daily driller's report, and drilling fluid control log must be approved by the CONSULTANT. The CONSULTANT will visit the site routinely to log cuttings and collect field notes regarding the drilling process to ensure that drilling operations are proceeding in accordance with specifications.
5.2 PENETRATION RATE LOG
During drilling of the pilot borehole (if performed), a time log shall be kept showing the actual penetration time required to drill each foot of the borehole using a Geolograph or equivalent. In lieu of a Geolograph, CONTRACTOR may manually track start and stop time of each drill rod. The types of bits used in each interval of the borehole shall be noted in this log and whether designed for soft, medium, or hard formations, including approximate weight of the drill string and weight on the bit, as measured by the weight indicator on the drill rig, in addition to the rotation speed of the bit during drilling of the various types of formation in the various sections of the borehole. This log shall be available for review by the CONSULTANT throughout the drilling program and shall be delivered to the CONSULTANT upon completion of drilling.
5.3 DAILY DRILLER’S REPORT
During drilling and construction of the well, a detailed driller's report shall be maintained and provided daily to the CONSULTANT at the well site or electronically. The daily driller's report forms must be International Association of Drilling Contractors (IADC) or equal approved by the CONSULTANT. The report shall give a complete description of all formations encountered including number of feet drilled, number of hours on the job, shutdown due to breakdown, type of bit used, weight of the collars included in the drill string, weight on the bit, amount and type of drilling fluids used, plumbness test results at each 100-foot interval, and length and type of casing set; and other pertinent data as may be requested by the
CONSULTANT.
5.4 DRILLER’S LOGS
During drilling of the pilot borehole, the CONTRACTOR shall prepare a detailed lithologic log in compliance with ADWR requirements. The lithologic log shall include the reference point for all depth measurements, a generalized description of each formation encountered, the depth at which each formation is encountered, and the thickness of each formation. The lithologic log prepared by the
S:\MyDocs\SGCPRJ\2026V\26-01166 Buckeye Farallon Well 3\Specs\2026.10.30_WellTechSpecs_Farallon3.docx 10
CONSULTANT will be made available to the CONTRACTOR to assist in preparation of the Well Driller Log. A copy of the CONTRACTOR lithologic log shall be furnished to the CONSULTANT and OWNER.
5.5 DRILLING FLUID RECORD
During drilling of the borehole, a log of drilling fluid properties shall be maintained. The drilling fluid record will be recorded on an American Petroleum Institute (API)-approved form and will document all items listed in Section 6.1. The drilling fluid log shall be available for review by the CONSULTANT and OWNER throughout the course of drilling and shall be delivered to the CONSULTANT upon completion of each day's work activities.
S:\MyDocs\SGCPRJ\2026V\26-01166 Buckeye Farallon Well 3\Specs\2026.10.30_WellTechSpecs_Farallon3.docx 11
6.0 DRILLING FLUID CONTROL PROGRAM
6.1 GENERAL REQUIREMENTS
The CONTRACTOR shall always maintain current records at the site to show:
1) the time, depth, and results of all drilling fluid tests;
2) all materials added to the system, i.e., kind, amount, time, and depth; and
3) variances or modifications from the agreed upon fluid program such as time, depth, reason, and authorization.
The CONTRACTOR is responsible for maintaining an adequate supply of drilling fluid additives (including lost circulation material) at the drilling site, and for the removal of all drilling fluids and additives from the borehole during development of the well.
6.2 DRILLING FLUID CONTROL PLAN
Drilling fluid tests will be required during periods when any drilling fluid additives are being circulated in the borehole. Physical and chemical properties of the drilling fluid are to be measured in accordance with the procedures of the API Standard RP 13B "Standard Procedures for Testing Drilling Fluids". Samples tested are those collected at the rig pump discharge line, with care taken to assure a true and representative sample.
Drilling fluid tests shall be conducted a minimum of:
1) every 24 circulating-hours;
2) when significant changes to the drilling fluid are made;
3) whenever conditions appear to have changed or when problems arise; or
4) at the request of the CONSULTANT.
A Marsh-type viscosity funnel and a mud scale will be available at the well site during all drilling operations, and upon request, will be made available to the CONSULTANT.
The CONTRACTOR shall provide a drilling fluid control plan to the CONSULTANT 48 hours prior to drilling. The plan will outline specific drilling fluids the CONTRACTOR plans to use, how anticipated changes in drilling conditions will affect the drilling fluid control plan, fluid testing procedures, and equipment that will be used. The drilling fluid control plan must be approved by the CONSULTANT.
S:\MyDocs\SGCPRJ\2026V\26-01166 Buckeye Farallon Well 3\Specs\2026.10.30_WellTechSpecs_Farallon3.docx 12
6.3 SPECIFIC CONDITIONS
During drilling of the borehole and the installation of the well, extra care will be required to minimize chemical and biological disturbance of the vadose zone and saturated alluvial matrix. The use of organic drilling fluid materials (such as starch, guar, or cottonseed hulls) will not be accepted for drilling. Safety Data Sheets (SDS) from the manufacturer for all drilling fluid additives must be provided to the CONSULTANT for review prior to their use. The CONTRACTOR shall be responsible for maintaining the quality of the drilling fluid to assure:
1. Protection of water bearing and potential water bearing formations exposed to the borehole.
2. Collection of representative samples of the formation material.
3. Maximum development capability and optimum potential yield of the completed well.
4. Mitigation of formation-caused drilling problems (e.g., heaving sands, swelling clays, lost circulation).
5. Protection of the integrity of the boring during drilling operations.
6. Ability to conduct thorough and accurate geophysical logging of the borehole.
6.4 LOST CIRCULATION
During drilling of the pilot borehole and/or reaming of the production well borehole, if there is no return of circulated drilling fluid for a period of at least two continuous hours, the OWNER will compensate the CONTRACTOR for the period of drilling under lost circulation conditions at the CONTRACTOR'S hourly rate. Also, the OWNER will provide compensation including the CONTRACTOR’S percent markup (not to exceed 5%) for all drilling fluid materials and additives used during the period of lost circulation. The conditions of this Section shall apply from the beginning of total lost circulation, with no returns at the land surface, and shall continue only until such time as drilling fluid circulation is regained, with full or partial returns of drilling fluid at the land surface. After an initial lost circulation event has occurred, should circulation be lost again, the conditions of this paragraph will go into effect immediately, and continue until such time as drilling fluid circulation is regained with full or partial returns of drilling fluid at the land surface.
Lost Circulation Conditions under this Section shall apply only when there is a loss of drilling fluid to the formation within the borehole, to the extent that the fluid level in the annulus outside the drill pipe cannot be maintained to a level above the base of the surface casing for at least one (1) hour, due to no fault of the CONTRACTOR, as determined by the CONSULTANT or OWNER.
The CONTRACTOR shall notify the CONSULTANT any time the CONTRACTOR experiences lost circulation and intends to invoke the lost circulation clause. Notification must be within the hour of
S:\MyDocs\SGCPRJ\2026V\26-01166 Buckeye Farallon Well 3\Specs\2026.10.30_WellTechSpecs_Farallon3.docx 13 observed lost circulation, and a written field order to continue shall be given to the CONTRACTOR, or no compensation for lost circulation will be made.
6.5 LOW PENETRATION RATE
During drilling or reaming operations, if a formation is encountered that results in a penetration rate of less than 3.0 feet per hour for a period of at least two continuous hours, while at least 1,500 pounds per diameter inch is applied to the drill bit, then the OWNER will compensate the CONTRACTOR for the period of Low Penetration Rate Conditions at the CONTRACTOR’S hourly rate, in lieu of footage compensation. The OWNER will also provide compensation at cost-plus 5 percent markup to the CONTRACTOR for all drilling bits used during Low Penetration Rate Conditions. During Low Penetration Rate Conditions, the CONTRACTOR will credit the prorated values of used drilling bits to the OWNER.
The CONTRACTOR is responsible for notifying the CONSULTANT immediately upon the occurrence of Low Penetration Rate Conditions, and to document the times, quantities, and circumstances of Low Penetration Rate Conditions during each occurrence. Failure of the CONTRACTOR to promptly notify the CONSULTANT of Low Penetration Rate Conditions will void the CONTRACTOR’S opportunity to implement this clause. The conditions of this Section shall apply from the beginning of Low Penetration Rate Conditions (less than 3.0 feet per hour) and shall continue only until such time as drilling is resumed at a rate of 3.0 feet per hour or greater.
Upon invocation of this Section, the CONTRACTOR will trip the drill string out of the hole for inspection of the drill bit by the CONSULTANT. The conditions of this Section shall apply only if the CONSULTANT’S inspection of the drilling bit does not indicate excessive bit wear that would substantially decrease the penetration rate. If the drill bit inspection indicates that this Section applies, the time expended for drilling bit removal will be paid by the OWNER under the conditions of this Section. If the CONSULTANT is not notified during the initial 2-hour period of low penetration, or if the bit inspection reveals excessive wear, the provisions of this clause will not be invoked.
S:\MyDocs\SGCPRJ\2026V\26-01166 Buckeye Farallon Well 3\Specs\2026.10.30_WellTechSpecs_Farallon3.docx 14
7.0 WELL DRILLING AND INSTALLATION
7.1 GENERAL DRILLING METHODS
The drilling of the boring will be conducted by the reverse circulation rotary drilling method. The borehole diameters of these specifications should be considered the minimum allowable. The CONTRACTOR shall be responsible for designing and controlling a drilling program that conforms to this specification.
7.2 SURFACE CASING (IF REQUIRED)
7.2.1 Drilling
If the existing surface casing will not be used, the new surface casing borehole for this production well shall be drilled to a minimum 46-inch diameter, to a depth of no less than 38 feet bgs. The CONSULTANT reserves the right to direct drilling of the surface casing borehole to a greater depth depending on geologic formations and other subsurface conditions. The surface casing boring may be drilled using a rotary drilling method or by use of the bucket auger (solid stem auger) drilling method.
During the drilling of the surface casing borehole, the CONTRACTOR shall collect and preserve for the CONSULTANT samples of the drilled cuttings collected at 10-foot intervals. Each sample shall be laid out in a sample storage area on a waterproof plastic tarp or ground cloth for each sampled interval in descending order.
7.2.2 Materials
7.2.2.1 Casing
The surface casing for this production well (Figure 2) shall be new and manufactured in accordance with ASTM Specification A53 Grade B low carbon steel. This casing shall have a 36-inch outside diameter (OD) and have a minimum 0.375-inch wall thickness. The minimum length of the surface casing shall be 40 feet to allow for two feet of stickup. The casing shall be factory assembled in not less than 40-foot lengths.
Prior to casing installation, the CONTRACTOR shall submit certified test reports to the CONSULTANT to demonstrate compliance with the physical and chemical properties of the surface casing steel that are specified herein.
S:\MyDocs\SGCPRJ\2026V\26-01166 Buckeye Farallon Well 3\Specs\2026.10.30_WellTechSpecs_Farallon3.docx 15
7.2.2.2 Cement Grout Seal
The surface casing cement grout seal material shall consist of a cement slurry containing 5.2 to 6.0 gallons of water per 94-pound sack of Portland cement. The Portland cement shall conform to ASTM Standard C150, Type II. The cement grout weight shall be measured prior to installation, as an indicator of the cement-water mix ratio. The cement grout slurry may contain sand or aggregate, which shall not exceed 50 percent by volume of the cement. The aggregate used should be clean and washed sand and gravel with no organic matter and not coarser than 1-inch minus. Water shall be added with the sand additive as required. Bentonite, as an additive, must be in powder form and shall not exceed five percent by weight of the cement, or cement and sand. Water added for bentonite shall not exceed 1.3 gallons per 1.88 pounds of bentonite (two percent by weight in cement). Accelerator additives, such as calcium chloride, shall not exceed two percent by weight of the cement. Sodium chloride, as an additive, shall not exceed two percent by weight of the water used to prepare the grout slurry. Water used for preparing the grout slurry shall be potable. The water source and the specific constituents of the cement grout must be approved by the CONSULTANT.
If the cement grout is not mixed onsite, the CONTRACTOR must provide the specific constituents of the cement grout to the CONSULTANT prior to placement of the grout. The cement grout slurry shall be mixed thoroughly and must be free of lumps to the satisfaction of the CONSULTANT. Cement grout that does not comply with this specification will be rejected.
7.2.3 Casing Installation
A design for the surface casing completion is shown on Figure 2. The CONTRACTOR will not be required to work continuously, on a 24-hour per day basis, while installing and grouting the surface casing. Surface casing, conforming to Section 7.2.2.1, shall be furnished, and placed from two feet above the ground surface to a minimum of 38 feet bgs. If the existing surface casing is utilized, the CONTRACTOR shall ensure the final stickup is two feet above ground upon well completion.
7.2.4 Surface Casing and Cement Grout Installation
The surface casing shall be maintained centered in the hole before the occurrence of the initial set of the cement grout. The cement grout slurry conforming to the specification in Section 7.2.2.2 shall be placed from the base of the surface casing to the ground surface utilizing a positive action cement pump and tremie pipe. Care shall be taken to maintain an equalization of pressures to the extent necessary to prevent collapse of the surface casing. The grout seal shall completely fill the annular space and form a continuous seal between the surface casing and the wall of the borehole. The surface casing grout seal
S:\MyDocs\SGCPRJ\2026V\26-01166 Buckeye Farallon Well 3\Specs\2026.10.30_WellTechSpecs_Farallon3.docx 16 may be placed in two separate installations to completely extend the top of the seal to the ground surface.
The method of grout installation must be approved by the CONSULTANT. A minimum curing time for the surface casing grout seal is 12 hours, and the cement grout must obtain a compressive strength of 500 psi.
7.3 PILOT WELL BOREHOLE DRILLING
If performed, the pilot borehole shall be constructed by initially drilling a minimum 16-inch diameter pilot borehole to approximately 1,040 ft bgs. Following completion of the pilot borehole and downhole geophysical logging, the borehole will be reamed to a minimum of 28 inches to the specified depth.
However, the CONSULTANT reserves the right to direct drilling of the pilot borehole to a greater or lesser depth, depending on geologic formations and other subsurface conditions. The pilot borehole shall be drilled using the method described in Section 7.1, and in compliance with the drilling fluid testing and reporting requirements of Section 6.0. During drilling of the pilot borehole, all operations shall be conducted on a 24-hour per day, 7-day per week basis.
During drilling of the pilot borehole, plumbness and alignment tests shall be performed by the CONTRACTOR by use of an inclinometer (Eastman mechanical drift indicator available from the Eastman Oil Well Survey Company, or equal) at 100-foot intervals. A 3-degree unit shall be used with the inclinometer. The maximum acceptable drift from vertical shall be no more than 0.50 degrees, unless otherwise approved by the CONSULTANT.
Tests for plumbness and alignment shall be made by the CONTRACTOR during the borehole drilling, and after the complete construction of the well. If the well borehole fails the plumbness and alignment tests (for completed borehole per AWWA A100-20, Section 4.7.9), the CONTRACTOR must submit to the CONSULTANT a written plan of corrective action and correct the plumbness and alignment to the satisfaction and approval of the CONSULTANT. Plumbness and alignment correction costs will be at the expense of the CONTRACTOR.
7.3.1 Lithologic Samples
During drilling of the pilot borehole, the CONTRACTOR shall collect and preserve for the CONSULTANT two duplicate samples of the drill cuttings. The samples shall be collected at 10-foot intervals from the base of the surface borehole to the bottom of the well borehole. The CONTRACTOR shall provide an acceptable means of sampling the drilled cuttings at the discharge pipe. Catching the drilled cutting samples in sieves or strainers will not be allowed. A sump-type or baffle-type sample catching device shall be provided by the CONTRACTOR. Each cutting sample shall be carefully collected from the
S:\MyDocs\SGCPRJ\2026V\26-01166 Buckeye Farallon Well 3\Specs\2026.10.30_WellTechSpecs_Farallon3.docx 17 sampling point, and the sample catching device shall be cleaned of all cuttings after each sample is taken.
The samples shall be placed in labeled (well ID, date, depth interval) sealable plastic bags furnished by the CONTRACTOR (two bags per sample interval). In addition, as an onsite visual record of the borehole stratigraphy, each sample shall be laid out in a sample storage area on a water-proof tarp or ground cloth for each sampled interval in descending order. The storage area and ground cloth must allow samples to be maintained in sequence and unmixed with surface material or other samples until they have been examined and logged by the CONSULTANT. The CONTRACTOR shall submit details of the proposed formation sampling method including the sampling equipment to be used to the CONSULTANT prior to the start of drilling. The sampling program must be approved by the CONSULTANT.
If the existing pilot borehole is reamed, then no additional lithologic sampling will be required.
7.3.2 Geophysical Logging
The CONTRACTOR will provide geophysical logging services following completion of the pilot borehole.
Analyses to be conducted include caliper, spontaneous potential, single point resistivity, 64-inch, 16-inch, and 8-inch normal resistivity, dual guard, sonic, gamma ray, magnetic deviation, and temperature logs.
Following completion of the pilot borehole reaming to the final well borehole diameter, the CONTRACTOR will provide an additional caliper log and magnetic deviation log.
7.3.3 Formation Zonal Samples
All formation water quality sampling and zonal testing were completed previously. No additional zonal activities are anticipated.
7.4 PRODUCTION WELL INSTALLATION
7.4.1 Pilot Borehole Reaming
After the completion of pilot hole geophysics, it is anticipated that the borehole will be reamed to a depth of approximately 1,040 ft bgs, as shown on Figure 2. If the existing pilot hole is utilized, then reaming of the borehole will be initiated as the initial task following mobilization and setup. The borehole for the well shall have a diameter of 28 inches from 38 to 1,040 ft bgs unless otherwise approved by the CONSULTANT. The boring shall be reamed using the methods described in Section 7, and in compliance with the drilling fluid control program described in Section 6.0. A 3-arm caliper log and magnetic deviation survey shall be conducted by a geophysical logging SUBCONTRACTOR after the boring has been reamed to its final diameter and depth. The maximum acceptable drift shall not exceed two-thirds the
S:\MyDocs\SGCPRJ\2026V\26-01166 Buckeye Farallon Well 3\Specs\2026.10.30_WellTechSpecs_Farallon3.docx 18 smallest inside diameter of that part of the borehole or well being tested per 100 feet of depth as specified by AWWA Specification document A100-20, Section 4.7.9. If the reamed borehole hole does not conform to AWWA A100-20, Section 4.7.9, the CONTRACTOR must submit to the CONSULTANT a written plan of corrective action. During the reaming of the boring, all operations shall be conducted on a 24-hour per day, 7-day per week basis.
7.4.1.1 Well Casing
The blank well casing (Figure 2) shall be new Type 304L stainless steel manufactured in accordance with ASTM Specification A778. This casing shall have an 18.625-inch outside diameter (OD) and have a minimum 0.312-inch wall thickness. A final stickup of a minimum 4 feet above land surface shall be installed prior to acceptance of the well. The bottom of the well casing will be sealed with a stainless steel “bull-nose” section as supplied by Roscoe Moss Co. The casing shall be factory assembled in not less than 40-foot-long sections, except as necessary based on overall length. Ends of casing lengths shall be as described in Section 7.4.2.1. A preliminary well design is shown in Figure 2.
Centralizers shall be constructed of the same material as the corresponding casing and welded to the casing. Centralizers will be durable and shall not bend, flex, or collapse during installation of the casing and screen. The casing shall be hung in suspension until the filter pack and cement grout seal have been installed.
Prior to casing installation, CONTRACTOR shall submit certified test reports or manufacturer provided specifications sheets to CONSULTANT to demonstrate compliance with the physical and chemical properties of the casing that are specified herein.
7.4.1.2 Well Screen
The louvered well screen shall be new 316L stainless steel and manufactured in accordance with ASTM A778. The well screen shall be 18.75-inch OD, with a wall thickness of 0.375 inches. Based on previous sieve analyses, the slot size of the louvers will be approximately 0.090 inches, spaced using the Roscoe Moss Ful-Flo pattern.
Prior to screen installation, the CONTRACTOR shall submit certified test reports or manufacturer specification sheets to the CONSULTANT and OWNER to demonstrate compliance with the physical and chemical properties of the well screen that are specified herein.
Centralizers shall be constructed every 80 feet of the same material as the corresponding screen and welded to the screen. Centralizers will be durable and shall not bend, flex, or collapse during installation
S:\MyDocs\SGCPRJ\2026V\26-01166 Buckeye Farallon Well 3\Specs\2026.10.30_WellTechSpecs_Farallon3.docx 19 of the casing and screen. The casing shall be hung in suspension until the filter pack and cement grout seal have been installed.
7.4.1.3 Sounding Tube
The well shall be equipped with an annular sounding tube to facilitate collection of water levels from the well. The sounding tube shall be constructed of new 2-inch ID, Schedule 40 304L stainless steel tubing.
Sections of the access tube shall be no less than 20 feet in length, and section joints shall have welded connections. The sounding tube shall be installed in the well annulus on the outside of the casing and shall terminate within the filter pack. The tube shall be perforated with vertical mill slots (0.050-inch) and shall have an end cap. A final stickup of a minimum 4 feet above land surface shall be installed prior to acceptance of the well (Figure 2). The sounder access tube shall NOT be welded to the well casing but hung freely during well installation.
7.4.1.4 Filter Pack
The filter pack shall be Silica Sand or approved equal, consisting of clean, well-rounded grains that are smooth and uniform. The filter pack shall be siliceous with a limit of 2 percent, by weight, calcareous material. The filter pack material shall be obtained from a source that has been approved by the Consultant and shall consist of well-rounded particles with an average density of not less than 2.5 grams per cubic centimeter and have a uniformity coefficient no greater than 1.5. Not more than 1 percent, by weight, of the material shall have a density of 2.25 grams per cubic centimeter or less. The filter pack shall contain no more than 2 percent by weight, thin, flat, or elongated pieces (pieces in which the largest dimension exceed three times the smallest dimension) determined by hand-packing. The filter pack material shall be free of shale, mica, clay, dirt, loam, organic impurities of any kind, and shall not contain iron or manganese in a form or quantity that will adversely affect the water quality. Filter pack material will consist of P.W. Gillibrand silica sand with a 6x9 gradation.
Samples of the filter pack sand and a sieve analysis (percent retained through U.S. standard sieve numbers 4, 8, 10, 16, 30, 40, 50, 100, and 200) of the filter pack material shall be submitted to the CONSULTANT for approval, a minimum of 3 days prior to delivery of the filter pack to the well site. The filter pack material shall be contained in a temporary storage area at the well sites in such a manner as to prevent contamination. The filter pack material shall be bagged in approximately 3,000-pound (about one cubic yard) “super sacks”. Each bag must be labeled with its actual weight. Any filter pack material delivered unbagged or unlabeled will be rejected.
S:\MyDocs\SGCPRJ\2026V\26-01166 Buckeye Farallon Well 3\Specs\2026.10.30_WellTechSpecs_Farallon3.docx 20
7.4.1.5 Bentonite and Fine Sand Seals
The bentonite seal material shall consist of sodium bentonite pellets, bentonite chips, or a bentonite slurry. The bentonite seal material shall contain no hazardous materials or gypsum. A product data sheet of the bentonite material shall be provided to the CONSULTANT for approval no less than three days prior to installation.
The fine sand seal will consist of #20x40 clean well-rounded silica sand and will conform to the same specifications as outlined in Section 7.4.1.4.
7.4.1.6 Cement Grout Seal
The cement grout seal material shall consist of a cement slurry containing 5.2 to 6.0 gallons of water per 94-pound sack of Portland cement. The Portland cement shall conform to ASTM Standard C150, Type II, or C595, Type IP. The cement grout weight shall be measured prior to installation, as an indicator of the cement-water mix ratio. The cement grout slurry may contain pozzolanic (fly ash) material as an additive, which complies to ASTM Standard C618, and which shall not exceed 50 percent by volume of the cement. Water shall be added for the pozzolan as required. Sand or aggregate material additives shall not be used. Bentonite, as an additive, must be in powder form and shall not exceed five percent by weight of the cement, cement and sand, or cement and pozzolan. Water added for bentonite shall not exceed 1.3 gallons per 1.88 pounds of bentonite (two percent by weight in cement). Accelerator additives, such as calcium chloride or sodium chloride shall not be used. Water used for preparing the grout slurry shall be potable. The water source and the specific constituents of the cement grout must be approved by the CONSULTANT and OWNER.
If the cement grout is not mixed onsite, the CONTRACTOR must provide the specific constituents of the cement grout to the CONSULTANT and OWNER seven days prior to placement of the grout. The cement grout slurry shall be mixed thoroughly and must be free of lumps to the satisfaction of the CONSULTANT.
Cement grout which is not adequately mixed will be rejected by the CONSULTANT due to possibilities of the slurry bridging during placement.
7.4.2 Casing and Sounding Tube Installation
During installation of the well casing and sounding tube, the boring shall be kept full of drilling fluids of the types specified in Section 6.0 and free from any obstructions detrimental to complete casing installation. The well casing shall be set centered in the hole so as not to interfere in any way with the grout seal, filter pack, well installation, or maximum efficient operation of a 16-inch OD vertical turbine pump for use in the 18-inch ID well casing. Details for this production well construction are shown in
S:\MyDocs\SGCPRJ\2026V\26-01166 Buckeye Farallon Well 3\Specs\2026.10.30_WellTechSpecs_Farallon3.docx 21
Figure 2. The CONTRACTOR will be required to work continuously, on a 24-hour per day, 7-day per week basis while installing and completing the well.
This well casing shall be set by the CONTRACTOR in the open borehole with the casing and well screen set at depth intervals specified by the CONSULTANT. Stainless steel casing centralizers shall be utilized and secured to the blank well casing and the well screen, at intervals of not greater than 80 feet. The casing shall be hung in suspension until the filter pack and cement grout seal have been installed.
The sounding tube (2-inch ID, 304L stainless steel) shall be installed in the annulus of the well borehole and have a minimum 4-foot stickup above land surface. The sounding tube shall NOT be welded to the well casing and shall be hung in suspension until the casing, filter pack, and cement grout seal have been installed. The top of the sounding tube shall be equipped with a water-tight threaded cap. The bottom of the sounding tube shall be capped. The CONTRACTOR shall log the number, length, and type of casing joints placed in the borehole in their order of placement, including time and date.
7.4.2.1 Joints in the Well Casing
Joints in the steel well casing and well screen shall be field welded in accordance with applicable provisions of the AWWA Standard C220 for welded joints. All well casing joints shall be aligned with alignment straps or other means as approved by the CONSULTANT prior to welding. A welding sequence will be followed which will avoid excessive distortion. The ends of the casing lengths shall be ground, or sufficiently scarfed, to remove sharp edges or burrs, and be free of all oil, grease, dirt, paint, cement, scale, slag or rust, or other foreign material. Section ends shall either be installed with joint collars or be beveled to a 30° angle, perpendicular to the axis of the casing, to facilitate proper alignment of joined casing sections, and shall not vary more than 0.010 inches at any point from a true plane at right angles to the axis of the casing. All welds shall be performed by an experienced welder, shall penetrate 100% of each beveled pipe end and completely fill the bevel, and be water-tight for prevention of poor quality or contaminated water penetrating into the well through the casing joints. An affidavit of compliance with welding provisions shall be provided to the CONSULTANT prior to acceptance of the well.
7.4.3 Annular Materials Installation
7.4.3.1 Filter Pack
Filter pack silica sand, conforming to the specifications of Section 7.4.1.4 shall be placed from the bottom of the well to the specified depth using a tremie pipe, and shall completely fill the annulus in the specified interval. The filter pack interval must extend at least 20 feet above the perforated interval (Figure 2).
Drilling fluid shall be maintained to the full depth of the well and the well casing, and screen shall be
S:\MyDocs\SGCPRJ\2026V\26-01166 Buckeye Farallon Well 3\Specs\2026.10.30_WellTechSpecs_Farallon3.docx 22 maintained in suspension until the filter material placement has been completed to the specified level.
Care must be taken to avoid bridging during installation of the silica sand filter pack. The CONTRACTOR shall keep a tally of all annulus material installed.
The filter pack shall be installed simultaneous with reverse circulation of drilling fluids down the annulus at a rate of no less than 250 gpm. At no time shall the bottom of the tremie pipe be located at a distance greater than 100 feet above the interval being filled during filter pack placement. The level of the filter pack shall be measured periodically during placement, as required by the CONSULTANT. The method of filter pack level measurement must be approved by the CONSULTANT. Placement of the filter pack will be continuous, except when additional precautions are necessary to prevent bridging, or measurements of the filter pack level are being conducted. The filter pack placement will proceed until the height of the filter pack is at least twenty (20) feet above the top of the screen.
Because a swabbing tool is to be used during filter pack installation to prevent bridging, it is imperative that the CONTRACTOR take extreme caution in order to prevent pressure differences, screen collapse or borehole collapse.
The quantity of filter pack material placed in the annulus shall not be less than that of the volume computed based on the results of the caliper log performed after borehole reaming.