3-26-059 Proposal Book - Final.pdf

PDF 8 MB Posted

Attached to
Concrete Bridge Repairs
Solicitation number
26-059
Issued by
Winnebago County, Wisconsin

About this file

This is a Highway Work Proposal and Bid Document issued by Walworth County, Wisconsin for concrete bridge repairs on two county-owned bridges located on County Highway H in the Town of Bloomfield. The project (26-059) involves removing deteriorated concrete from portions of abutments, piers, decks, and other structural elements and replacing them with new concrete as specified in the plans. Work includes concrete surface repair (235 square feet combined across both bridges), medium riprap placement (20 cubic yards), and debris containment over waterways (two units). The bid solicitation was issued on May 14, 2026, with a final questions deadline of June 2, 2026, and sealed electronic bids due June 11, 2026 at 10:00 a.m. local time via the Bonfire procurement platform. A public bid opening will be conducted virtually on June 11, 2026 at 10:15 a.m. via Microsoft Teams. Contract completion is required by June 1, 2027, with liquidated damages of $945 per calendar day for delays. The estimated project award date is June 18, 2026.

Bidders must submit a bid bond equal to 5 percent of the bid amount payable to Walworth County and must be prequalified with the Wisconsin Department of Transportation or provide proof of responsibility through completion of at least three concrete repair or restoration projects exceeding $50,000 on commercial or municipal structures within the past five years. No prevailing wage rates (state or federal) apply to this project. Bidders must carry comprehensive insurance including Workers Compensation, Commercial General Liability ($1,000,000 per occurrence minimum), and Automobile Liability ($1,000,000 per occurrence minimum), with Walworth County named as additional insured. Bids may not be withdrawn for 30 days following the scheduled opening. The County reserves the right to accept or reject any or all bids and will award to the lowest responsive, responsible bidder. All work must comply with Wisconsin Department of Transportation Standard Specifications for Highway and Structure Construction (2025 Edition) and special provisions regarding traffic control, erosion control, environmental protection, and aquatic invasive species management.

View the file

Other files

File Type Posted
2-26-059 Plan Set.pdf PDF
1-26-059 List of Subcontractors.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HIGHWAY WORK PROPOSAL

Walworth County, Wisconsin

COUNTY PROJECT NO. PROJECT DESCRIPTION HIGHWAY

Walworth 26-059 Concrete Bridge Repairs

B-64-155 CTH-H

B-64-156 CTH-H

Proposal Guaranty Required:

5% of Bid Amount, Payable to Walworth County

Bid Submittal:

Date: June 11, 2026

Time (Local Time): 10:00 am

Contract Completion Time:

June 1, 2027

This Page Intentionally Left Blank

PROJECT ID 26-059

CONCRETE BRIDGE REPAIRS

Walworth County, Wisconsin

TABLE OF CONTENTS

Title No. of Pages

Proposal Cover 1

Table of Contents 1

Advertisement for Bids 2

Bid Requirements and Conditions 2

Bid Opening Teleconference 1

Insurance Requirements 2

Bid Preparation 1

List of Subcontractors 1

Special Provisions 6

Schedule of Items (Informational Only) 1

Bridge Inspection – Partial Reports (Informational Only) 13

ADVERTISEMENT FOR BIDS

PROJECT ID 26-059

CONCRETE BRIDGE REPAIRS

Walworth County, Wisconsin

NOTICE: Sealed (electronic) bids for CONCRETE BRIDGE REPAIRS will be received by the Walworth

County Purchasing Division, Department of Public Works, W4097 County Road-NN, Elkhorn, Wisconsin

53121, until 10:00 A.M. local time on Thursday, June 11, 2026, at which time all bids will be publicly opened virtually.

SCOPE: In general, the work under this project involves various spot-repairs on two county-owned bridges located on County Highway H in the Town of Bloomfield, WI. The work includes removing deteriorated concrete from portions of abutments, piers, decks, and other elements as shown on the plans, and replacing those portions with new concrete as specified.

ELECTRONIC BIDDING: Walworth County utilizes an internet-based procurement software called

‘Bonfire’ as the interface to exchange all official information between the County and Bidders.

Obtaining Bid Documents, Project Inquiries, and Bid Submittal will be accomplished through the Bonfire software platform.

Bidders may register for a Bonfire account at no charge through Walworth County’s Bonfire Portal at:

https://walworthcountywi.bonfirehub.com/

It is the bidder’s responsibility to check the project website for future announcements, addendums, etc.

prior to the bid deadline. Bids that do not acknowledge addendums may be rejected.

All questions must be received by the deadline(s) indicated. No information provided verbally, or by any other personnel, will be considered binding.

PROJECT COMPLETION: All work under this Contract shall be completed by June 1, 2027.

Liquidated damages for failure to complete the work in accordance with the date(s) set forth above shall be Nine Hundred Forty-Five dollars ($945.00) for each calendar day in excess thereof.

BID SECURITY: Bids must be accompanied by a Bid Bond the amount of five (5) percent of the bid price, payable to Walworth County, Wisconsin, as a guarantee that if the Bid is accepted, the Bidder will execute and file the proper contract documents within fifteen (15) days after notification of award of the contract. In case the successful bidder shall fail to execute such contract documents, the bid bond shall be forfeited to Walworth County as liquidated damages.

https://walworthcountywi.bonfirehub.com/

BIDDING SCHEDULE:

Bid Documents Issued: May 14, 2026

Pre-Bid Meeting: N/A

Final Questions Due: June 2, 2026 (10:00 a.m.)

Bids Due: June 11, 20026 (10:00 a.m.)

Estimated Project Award: June 18, 2026

WAGE RATES: Neither State of Wisconsin prevailing wage rates nor Federal (Davis-Bacon) prevailing wage rates are applicable to this project.

QUALIFICATIONS: Bidders shall be experienced in this type of work and shall be prequalified with the

Wisconsin Department of Transportation for work in the class and amount of their bid.

-OR-

Shall provide a minimum proof of responsibility in writing on the bid form of: Three (3) Concrete Repair or

Restoration Projects completed on commercial or municipal buildings, bridges or dams within the last five

(5) years, having a contract amount greater than Fifty Thousand Dollars ($50,000.00). Project and project owner information shall be provided with the bid submittal.

BID WITHDRAWAL: No bid shall be withdrawn for a period of thirty (30) days after the scheduled opening of bids. Bids may be withdrawn only in total and only by a written request to Walworth County

Purchasing, Department of Public Works, prior to the time and date of the scheduled bid deadline.

BID ACCEPTANCE – REJECTION: Walworth County reserves the right to accept or reject any or all bids, in whole or in part, received in response to this advertisement, to waive any irregularities in bidding, or to accept any bid they deem most advantageous to the County.

Published by the authority of: Walworth County

BID REQUIREMENTS AND CONDITIONS

The bidder, submitting this bid, agrees and declares as a condition thereof, to be bound by the following conditions and requirements.

All prospective bidders shall be on the Wisconsin Department of Transportation list of approved

Contractors. Any Contractor that appears on the Wisconsin Department of Transportation’s List of

Disapproved, Suspended, and Debarred Contractors will be disallowed.

The bidder declares that he has carefully examined the site of, and the bid, plans, specifications and contract forms for the work contemplated and it is assumed that the bidder has investigated and is satisfied as to the conditions to be encountered, as to the character, quality, and quantities of work to be performed and materials to be furnished, and as to the requirements of the specifications, special provisions, and contract. It is mutually agreed that submission of a bid shall be considered conclusive evidence that the bidder has made such examination.

The bidder submits herewith a proposal guarantee in proper form and amount payable to the party as designated in the advertisement inviting bids, to be retained by and become the property of the owner of the work in the event the undersigned shall fail to execute the contract and return the same to the County within fifteen (15) days after having been notified in writing to do so; otherwise to be returned.

The form of agreement or contract resulting from the acceptance of the bid shall be on forms either supplied by Walworth County or approved by Walworth County.

The bidder declares that he understands that the estimate of quantities in the schedule of items is approximate only and that the actual quantities may be greater or less in accordance with the specifications.

The bidder agrees to perform the said work, for and in consideration of the payment in the amount becoming due on account of work being performed, according to the unit prices in the schedule of items, and to accept such amounts in full payment of said work.

Retainage on project estimates will be applied in accordance with the Section 66.0901(9)(b), Statutes of

Wisconsin.

Walworth County is a tax-exempt municipality under WI Stats. 77.54(9a). The bidder shall investigate the statutory requirements for payment of sales and use taxes and, if required, shall include taxes in the bid.

Bidder shall comply with the provisions set forth in the Wisconsin Administrative Code and Statutes in order to obtain a state sales tax exemption on the purchase of certain items and shall forward this information to his suppliers in order that the sale of such material and equipment be properly recorded as a tax-exempt sale.

The bidder declares that all of the said work will be performed at his own cost and expense, that he will furnish all necessary materials, labor, tools, machinery, apparatus, and other means of construction in a manner provided on the plans, specifications, special provisions and contract of which this bid will become a part. The bidder further agrees that the plans, specifications and special provisions are made a part hereof, as fully and completely as if attached hereto.

The bidder, if awarded the contract, shall pay all claims as required by Section 779.14of the Wisconsin

Statutes and shall be subject to and discharge all liabilities for injuries pursuant to Chapter 102 of the

Wisconsin Statutes, and all acts amendatory thereto. He shall further be responsible for any damage to property or injury to persons occurring through his own negligence or that of his employees or agents, incident to performance of work under this contract.

Upon completion of the work and receipt of all required documentation and material reports, Walworth

County (or designee) may submit to the contractor a tentative-final estimate of the quantities of work performed by the contractor. Within 30 calendar days of receiving the tentative-final estimate, the contractor shall submit a written statement of agreement with the final quantities. In the event of a discrepancy, the contractor shall submit item-by-item documentation of the quantities to be reviewed. If the contractor does not submit a written statement within those 30-days, Walworth County will process the estimate as a final payment with no further negotiation.

Prior to release of final payment and retainage, the contractor shall submit lien waivers for the prime contractor and subcontractors on forms supplied by, or approved by Walworth County.

The bidder, if awarded the contract, shall permit authorized representatives of the Federal, State, and

County government to inspect and audit all data and records of the contractor as they relate to this contract. Said right shall extend to any subsidiary, subcontractor, or parent corporation which relate to the construction on this project.

It is expressly agreed and understood that the bidder is in all respects an independent contractor, and the bidder is in no respect an agent, servant, or employee of Walworth County.

Walworth County reserves the right to cancel any agreement that may result from this request for bids, with no penalty, if the Walworth County Board of Supervisors fails to appropriate funds for this contract.

BID OPENING TELECONFERENCE

1. PUBLIC BID OPENING

No in-person bid openings for Public Works projects will be conducted in Walworth County.

Vendors may participate in the public bid opening for this project as described in this Section.

The bids opened and read are considered preliminary and subject to review and verification of applicable bid requirements. Contract(s) will be awarded to the lowest responsive, responsible bidder unless stated otherwise in the request for bids.

2. INSTRUCTIONS FOR PROJECT 26-059

The County will host this bid opening on THURSDAY, JUNE 11, 2026, at 10:15 a.m. via Microsoft Teams.

Interested participants may attend electronically via the live stream video conference or may participate by using the audio-only option provided herein.

Microsoft Teams meeting

Join: https://teams.microsoft.com/meet/211880235411111?p=hUzOBmPGy6sDU1k7YO

Meeting ID: 211 880 235 411 111

Passcode: 37BC9Rd6

Dial in by phone

+1 414-219-0219,,133741157# United States, Milwaukee

Find a local number

Phone conference ID: 133 741 157# https://teams.microsoft.com/l/meetup-join/19%3ameeting_N2VlMjQ0ZmItYzk4MS00MDRkLTlhNzUtY2M3ZjBmNDA5YzVi%40thread.v2/0?context=%7b%22Tid%22%3a%22abdd0c04-3909-4e20-bbcb-7b8a0283a1af%22%2c%22Oid%22%3a%228de371d7-f0f4-4ae6-b61f-d0478201db3c%22%7d tel:+14142190219,,111044488 tel:+14142190219,,111044488 https://dialin.teams.microsoft.com/3545793f-3d5d-4816-a86c-5b26c488d908?id=111044488

INSURANCE REQUIREMENTS

1.01 Contractor shall furnish County with Certificate of Insurance indicating proof of the following insurance from companies licensed in the State of Wisconsin:

A. Workers Compensation and Employers' Liability - The Contractor shall procure and maintain during the life of this contract Workers’ Compensation insurance with a minimum limit as required by Wisconsin Statutes. The Contractor shall also carry Employers Liability limits of at least $100,000 Each Accident, $100,000 Disease – Each Employee, and $500,000 Disease – Policy Limit. Contractor shall require all subcontractors not protected under its insurance to take out and maintain such insurance throughout the project term.

B. Commercial General Liability - with a minimum limit of $1,000,000 per occurrence and

$2,000,000 aggregate combined single limit for bodily injury and property damage liability. The County reserves the right to require higher or lower limits where warranted.

1) If excavating, underground or collapse is involved, the limits of liability stated above shall be increased to $2,000,000 per occurrence.

2) If Asbestos and/or hazardous materials are involved, the limits of liability stated above shall be changed to $5,000,000 per occurrence.

3) This insurance shall include, but is not limited to, the following coverage:

a) Premises – Operations

b) Products and Completed Operations

c) Personal and Advertising Injury

d) Contractual Liability

e) Underground, Explosion, and Collapse

f) Contractor’s indemnity obligations under this contract

4) This insurance must not include the following:

a) Any exclusion for water intrusion or water damage

b) Any exclusion of coverage relating to earth subsidence or movement

c) Any exclusion for the insured’s vicarious liability, strict liability, or statutory liability (other than worker’s compensation)

d) Any limitation or exclusion based on the nature of Contractor’s work

e) Any limitation or exclusion for damages arising from the work performed by a subcontractor

f) Any limitation or exclusion for damages related to roofing, if the work involves roofing

g) Any provisions resulting in the erosion of insurance limits by defense costs other than those already incorporated in to ISO form CG 00 01

C. Automobile Liability – with a minimum limit of $1,000,000 per occurrence and $2,000,000 aggregate combined single limit for bodily injury and property damage liability. This insurance shall include coverage for all of the following:

1) Owned Automobiles

2) Hired Automobiles

3) Non-Owned Automobiles

D. Professional Liability – Not Required

E. Contractor’s Pollution – Not Required

F. Umbrella or Excess Coverage – Umbrella or Excess Coverage may be used in combination with the required primary coverage in (A.) through (E.) to meet the minimum insurance limits that are specified in this section, provided such insurance result in the same or greater coverage as the coverages required. In no event shall any Umbrella or Excess insurance provide narrower coverage than the primary policy. The Excess policy shall not require exhaustion of the underlying limits only through the actual payment by the underlying insurers.

G. Property Insurance – Contractor is responsible for obtaining or maintaining any other insurance deemed necessary, such as property or inland marine, to cover any property or equipment that is owned or rented by the Contractor and used within the scope of this project.

1.02 If any insurance specified above is a claims-made policy, the retroactive date must pre-date the commencement of furnishing any service under this contract, including design. An Extended Reporting Period, or “tail” coverage, must be provided for at least 2 years following completion of the work.

1.03 Walworth County, shall be named as additional insureds under the Contractor’s Commercial General

Liability, Automobile Liability, Employer’s Liability, Umbrella or Excess, and Pollution Liability insurance policies. Walworth County shall be listed as, “Walworth County, its employees, elected officials, representatives, members of its boards and/or commissions and engineering consultants.”

1.04 Unless prohibited by law, Walworth County shall be provided a waiver of subrogation by endorsement to the Commercial General Liability, Automobile Liability, Workers’ Compensation, Employer’s Liability, Contractor’s Pollution, and Umbrella or Excess Insurance.

1.05 Contractor’s insurance shall provide a thirty (30) day notice to the County prior to cancellation or material policy change. The notice shall be given to Walworth County Purchasing, Department of Public Works, W4097 County Road NN, Elkhorn, Wisconsin 53121. NOTE: Standard Cancellation Clause on a Certificate of Insurance is not acceptable. Upon receipt of notice from insurer, Owner shall have the right to stop the Work until the lapse in coverage has been cured by the procurement of replacement coverage by the Contractor. The furnishing of notice shall not relieve the Contractor of any contractual obligation to provide required coverage.

1.06 The Contractor’s certificate shall list the Certificate Holder and address as follows: Walworth County, Attn: Walworth County Purchasing, Department of Public Works, W4097 County Road NN, Elkhorn, Wisconsin 53121.

1.07 Contractor shall require all of its contractors and subcontractors performing work related to this contract to carry sufficient minimum insurance to cover liabilities arising from or out of the performance of this contract. Contractor shall require subcontractor to furnish Certificates of Insurance to Walworth County upon request.

BID PREPARATION

Walworth County utilizes an internet-based procurement software called ‘Bonfire’ as the interface to exchange all official information between the County and Bidders, including the preparation and submission of bids.

Bidders may register for a Bonfire account at no charge through Walworth County’s Bonfire

Portal at: https://walworthcountywi.bonfirehub.com/

Bidder shall assume full responsibility for timely delivery of Electronic Bids.

Within the Bonfire software:

Complete the electronic / online unit price Bid Form.

Upload a Bid Security to the electronic submittal.

Upload a List of Subcontractors to the electronic submittal.

CERTIFICATION

Submitting a bid (electronically on the internet) to the Walworth County Department of Public

Works, shall certify that the bidder has examined and carefully prepared his bid from the plans and specifications (highway work proposal), and all addenda, and has checked the same in detail before submitting said proposal or bid.

https://walworthcountywi.bonfirehub.com/

LIST OF SUBCONTRACTORS

Section 66.0901(7) of the Wisconsin Statutes provides that a bidder, as a part of his bid, shall submit a list of the subcontractors he proposes to contract with and the class of work to be performed by each, provided that to qualify for such listing, each subcontractor must first submit his bid in writing to the general contractor at least 48 hours prior to the time of bid closing. It further provides that a bid of a bidder shall not be invalid if any subcontractor, and the class of work to be performed by such subcontractor, has been omitted from a bid.

No subcontract, whether listed or later proposed, may be entered into without the written consent of the

Walworth County.

* * TO BE COMPLETED ELECTRONICALLY IN BONFIRE * *

Special Provisions

Table of Contents

Article Description Page #

1. Definition and Terms

2. General

3. Scope of Work

4. Control of the Work

5. Control of Materials

6. Legal Relations and Responsibility to the Public

7. Progress Payments

8. Retainage

9. Prosecution and Progress

10. Inspecting Work

11. Traffic

12. Traffic Control

13. Information to Bidders, Permits

14. Environmental Protection, Aquatic Exotic Species Control

15. Utilities

16. Erosion Control

17. Notice to Contractor – Modification or Elimination of Bid Items

18. Notice to Contractor – Erosion Control BMPs

19. Public Convenience and Safety

20. Traffic Control, Item SPV.0105.01

STSP’S Revised January 1, 2026

SPECIAL PROVISIONS

1. Definition and Terms.

References to Owner, Department, Secretary and State in the contract documents shall mean Walworth County Wisconsin.

References to Engineer in the contract documents shall mean the Owner’s designated representative.

References in the specifications to details shown on the plans shall also mean details bound with the Proposal.

References to WisDOT shall mean the Wisconsin Department of Transportation.

Reference to “standard spec” or “standard specifications” shall mean the State of Wisconsin, Department of Transportation, Standard Specifications for Highway and Structure Construction, 2025 Edition.

References to Construction Materials Manual (CMM) shall mean the Wisconsin Department of Transportation’s (WisDOT’s) Construction Materials Manual.

2. General.

Perform the work under this construction contract for Project 26-059 ‘Concrete Bridge Repairs’, Walworth County, Wisconsin as the plans show and execute the work as specified in the State of Wisconsin, Department of Transportation, Standard Specifications for Highway and Structure Construction, 2025 Edition, as published by the department, and these special provisions.

If all or a portion of the plans and special provisions are developed in the SI metric system and the schedule of prices is developed in the US standard measure system, the department will pay for the work as bid in the US standard system.

100-005 (20240703)

3. Scope of Work.

The work under this contract shall consist of concrete surface repair, riprap placement, restoration, traffic control and all incidental items necessary to complete the work as shown on the plans and included in the proposal and contract for multiple bridges.

104-005 (20090901)

4. Control of the Work.

The owner and engineer are not responsible for the contractor’s means, methods, techniques, sequences, or procedures, or for the contractor’s safety, health, and sanitation program.

The owner may suspend the work in writing for any reason at any time during the contract. Except as specified in standard spec 104.2.2.3 for owner-ordered suspensions, the engineer will allow no additional payment or time extension due to a suspension of work.

Revise the title and first paragraph of standard spec 104.2.2.3 by changing all occurrences of "engineer" and "engineer's" to "owner" and "owner's," respectively.

Delete the second paragraph (which begins with the phrase "The engineer may . . .") of standard spec 105.1.

Revise the first paragraph of standard spec 105.7 by deleting the phrase "and to suspend all work being improperly performed."

Revise the second paragraph of standard spec 105.8 by deleting the sentence "Temporarily suspend work, in writing, until the engineer is notified and decides all questions at issue."

5. Control of Materials.

Conform to standard spec 106 as modified in this special provision.

The department approved source, as referred to in standard spec 106.1.1 (3), shall mean the Wisconsin Department of Transportation’s approved source.

The department Approved Product Lists (APL), as referred to in standard spec 106.3.2 (1), shall mean the Wisconsin Department of Transportation’s APL.

Plants certified by the department, and the department’s approved vendor list, as referred to in standard spec 106.3.3.3.1 (1) part 2, shall mean the Wisconsin Department of Transportation’s plant certification and approved vendor list.

Delete standard spec 106.3.4.1 (3).

The department’s laboratory qualification program, as referred to in standard specs 106.3.4.1 (5) and

106.3.4.2.2.1 (3), shall mean the Wisconsin Department of Transportation’s laboratory qualification program.

The department may conduct verification testing, as referred to in standard spec 106.3.4.3.3.

The department will not perform independent assurance testing, as referred to in standard spec 106.3.4.3.4.

6. Legal Relations and Responsibility to the Public.

Revise the first sentence of standard spec 107.12 to read as follows:

The contractor and their insurer shall defend, indemnify, and save harmless the engineer and governmental entities that are involved in the project, or in which all or a part of the project site is located, including officers, agents, and employees of any of the foregoing from suits, actions, or claims brought because of injuries or damages sustained by any person or property arising from one or more of the following: [text continues as in the standard spec].

7. Progress Payments

Revise standard spec 109.6.2 to read as follows:

The owner will make one progress payment each month.

8. Retainage.

Revise the second paragraph of standard spec 109.6.3.3 to read as follows:

In addition to the above retainage, the owner will retain 5% of the value of the work completed, and 5% of the value of materials and equipment delivered and suitably stored, until 50% completion. At 50% completion, no additional amounts will be retained unless engineer certifies that the work is not proceeding satisfactorily but amounts previously retained will not be paid to the contractor until the owner finally accepts the work. When the contractor substantially completes the work under the contract or upon completion and acceptance of the work, and pending final payment, the engineer may choose to reduce the amount retained.

9. Prosecution and Progress.

Begin work within 10 calendar days after the engineer issues a written notice to do so.

Complete all project work for the contract by June 1, 2027.

When directed by the Engineer - the contractor shall schedule and conduct routine progress meetings.

Hold the meetings in a mutually agreed upon location and be prepared to discuss the work schedule.

Subcontractors shall be in attendance at the weekly progress meetings.

Notify the engineer if there are any changes in the schedule, early completions, or cancellations of scheduled work.

Provide the project engineer and emergency services with a telephone number with which the contractor or the contractor’s representative can be contacted during non-working hours in the event a safety hazard develops.

10. Inspecting Work.

Contractor shall notify Walworth County and the Owner’s designated representative at least 72 hours before placing starting work on any structure and placing any concrete. Contact information will be provided at the preconstruction meeting.

11. Traffic.

The bridges shall remain open during construction utilizing flagging operations and shoulder closures as necessary. Place advanced warning signs prior to any removals.

12. Traffic Control.

Perform this work in accordance with the requirements of section 643 of the standard specifications, and as shown on the plans, or as approved by the engineer, except as hereinafter modified.

No operation shall proceed until all applicable traffic control devices for such work are in the proper location.

The contractor shall have available at all times sufficient experienced personnel to promptly install, remove, and reinstall the required traffic control devices, or to perform flagging operations to route traffic in order to perform the operations.

The contractor shall coordinate traffic restrictions with the area police, sheriff, and fire departments so emergency vehicle access is maintained at all times.

The contractor shall not disturb, remove, or obliterate any traffic control signs, advisory signs, or beam guard in place along the traveled roadways without the approval of the engineer.

No traffic control signing shall be placed on existing signposts or power poles. Signs shall be mounted on posts provided by the contractor in accordance with the plan details and standard detail drawings.

13. Information to Bidders, Permits.

Walworth County has coordinated this project with the Wisconsin Department of Natural Resources (WDNR). While no permit(s) were required for this work, it should be noted that saw cut slurry and chipping debris shall be collected and not allowed to flow or fall into the water and/or wetlands.

Contractor shall inform the County and WDNR with proposed methods of debris containment prior to commencing work. Project contacts are listed on the General Notes sheet in the plan set.

14. Environmental Protection, Aquatic Exotic Species Control.

Exotic invasive organisms such as VHS, zebra mussels, purple loosestrife, and Eurasian water milfoil are becoming more prolific in Wisconsin and pose adverse effects to waters of the state. Wisconsin State Statutes 30.07, "Transportation of Aquatic Plants and Animals; Placement of Objects in Navigable Waters", details the state law that requires the removal of aquatic plants and zebra mussels each time equipment is put into state waters.

At construction sites that involve navigable water or wetlands, use the following cleaning procedures to minimize the chance of exotic invasive species infestation. Use these procedures for all equipment that comes in contact with waters of the state and/or infested water or potentially infested water in other states.

Ensure that all equipment that has been in contact with waters of the state, or with infested or potentially infested waters, has been decontaminated for aquatic plant materials and zebra mussels before being used in other waters of the state. Before using equipment on this project, thoroughly disinfect all equipment that has come into contact with potentially infested waters. Guidelines from the Wisconsin Department of Natural Resources for disinfection are available at:

http://dnr.wi.gov/topic/invasives/disinfection.html

Use the following inspection and removal procedures:

1. Before leaving the contaminated site, wash machinery and ensure that the machinery is free of all soil and other substances that could possibly contain exotic invasive species;

2. Drain all water from boats, trailers, bilges, live wells, coolers, bait buckets, engine compartments, and any other area where water may be trapped;

3. Inspect boat hulls, propellers, trailers and other surfaces. Scrape off any attached mussels, remove any aquatic plant materials (fragments, stems, leaves, seeds, or roots), and dispose of removed mussels and plant materials in a garbage can before leaving the area or invested waters; and

4. Disinfect your boat, equipment and gear by either:

4.1. Washing with ~212 F water (steam clean), or

4.2. Drying thoroughly for five days after cleaning with soap and water and/or high pressure water, or http://dnr.wi.gov/topic/invasives/disinfection.html

4.3. Disinfecting with either 200 ppm (0.5 oz per gallon or 1 Tablespoon per gallon) Chlorine for 10-minute contact time or 1:100 solution (38 grams per gallon) of Virkon Aquatic for 20- to 30-minute contact time. Note: Virkon is not registered to kill zebra mussel veligers nor invertebrates like spiny water flea. Therefore, this disinfect should be used in conjunction with a hot water (>104º F) application.

Complete the inspection and removal procedure before equipment is brought to the project site and before the equipment leaves the project site.

stp-107-055 (20130615)

15. Utilities.

This contract does not come under the provision of Administrative Rule Trans 220.

stp-107-066 (20080501)

Overhead and/or underground utilities may be located within the project limits. The contractor shall contact Diggers Hotline to verify locations prior to construction. Use caution to ensure the integrity of underground facilities and maintain code clearances from overhead facilities at all times.

16. Erosion Control

This project does not fall under the provisions of TRANS 401.

Where areas are disturbed, Re-topsoil graded areas, as designated by the engineer, immediately after grading is completed within those areas. Seed, fertilize, and mulch/erosion mat top-soiled areas, as designated by the engineer, within 24hrs after placement of topsoil. If graded areas are left exposed for more than 24hrs, seed those areas with temporary seed and mulch/erosion mat within 24 hrs.

Prior to seeding, coordinate with the WDNR Liaison Craig Webster, 141 NW Barstow, Room 180, Waukesha, WI 53188, (262) 574-2141 on the application of seed mix 20 and temporary seed.

When performing roadway cleaning operations, the contractor shall use equipment having vacuum or water spray mechanisms to eliminate the dispersion of dust. If vacuum equipment is employed, it shall have suitable self-contained particulate collectors to prevent discharge from the collection bin into the atmosphere.

Stockpile excess material or spoils on upland areas away from wetlands, floodplains and waterways.

Stockpiled soil shall immediately be protected against erosion with silt fence, temporary seed, mulch, or as directed by the engineer.

Do not pump water from the construction site to a storm water conveyance without the water first passing through a sediment basin and sediment bag in accordance with the Environmental Protection article of these special provisions.

17. Notice to Contractor – Modification or Elimination of Bid Items

The department will not allow for a Cost Reduction Incentive as described in subsection 104.10 of the standard specifications for any elimination and/or modification of any contract bid items. Further, the department will not apply standard spec 109.5 for the total elimination, or partial elimination, whether by department or the contractor, of contract bid items.

18. Notice to Contractor – Erosion Control BMPs

All necessary erosion control BMPs shall be in place prior to starting bridge rehabilitation activities. The contractor shall determine if additional erosion control devices are needed based on their means and methods with approval by the engineer. All additional devices/work will be incidental to the contract.

19. Public Convenience and Safety.

Revise standard spec 107.8(6) as follows:

Check for and comply with local ordinances governing the hours of operation of construction equipment.

Do not operate motorized construction equipment from 7 PM until the following 7 AM, unless prior written approval is obtained from the engineer.

stp-107-001 (20060512)

20. Traffic Control, Item SPV.0105.01

A Description

This special provision describes providing, erecting, maintaining, moving, and removing temporary traffic control signs, lights, drums, barricades, covering signs, and all necessary traffic control for the project.

B Materials

Furnish traffic control devices that conform to standard specification 643.2.

C Construction

Install signs conforming to standard specification 643.3 prior to bridge work. If shoulder or lane closures or restrictions are necessary to install signs or cover existing signs, adhere to State traffic control standards and complete this work during off peak travel times.

Protect and maintain local traffic in the work zone by proper use of barricades, drums, warning lights, signs, flaggers and other traffic control devices conforming to federal, state and local regulations.

Installing, maintaining, moving and removing all traffic control devices shall conform to standard specification 643.3.

Notify emergency services at least 24 hours in advance of full highway closures. Full closure of the highway, with approval from the engineer, shall be set up in a manner, with adequate advance warning, that allows local traffic to access alternative routes.

All traffic control devices shall be operational 24 hours a day, seven days a week, including holidays. The contractor shall furnish the name and 24-hour contact phone number of the individual under direct employ who will be responsible for maintenance of temporary traffic control on the project. An individual from a subcontractor may be provided in addition to, not in lieu of, the contractor’s individual. If notified by the engineer or department of a deficiency in traffic control, correct the deficiency within the time specified in standard specification 643.3.1.

Removal all temporary traffic control devices at the conclusion of the work or when the device is no longer necessary.

D Measurement

Traffic Control, including all work for road closures, shoulder closures, traffic control and safety devices will be considered incidental to the project and will not be measured or paid as an item of work.

E Payment

Payment for furnishing, erecting, re-erecting, moving, maintaining, covering and uncovering, and removing temporary traffic control signs, barricades, drums, and similar devices; lights; furnishing and using flaggers as necessary; covering and uncovering conflicting existing permanent signs; and providing a 24-hour contact for emergencies will be considered incidental to the project and will not be paid as an item of work.

Project ID: 26-059

CONCRETE BRIDGE REPAIRS

B-64-155

WisDOT Item No. Description Unit Est Qty

203.0335 Debris Containment over Waterway B-64-155 EACH 1

509.1500 Concrete Surface Repair SF 150

606.0200 Medium Riprap CY 20

B-64-156

WisDOT Item No. Description Unit Est Qty

203.0335 Debris Containment over Waterway B-64-156 EACH 1

509.1500 Concrete Surface Repair SF 85

INCIDENTAL

WisDOT Item No. Description Unit Est Qty

SPV.0105.01 Traffic Control LS 1

Note: See Project Special Provisions

Schedule of Items (For Information Only)

1B-64-155 13-Aug-2024 inspection as of 01-Oct-2024

STATE OF WISCONSIN

DEPARTMENT OF TRANSPORTATION

Inspection Report for

B-64-155 CTH H over NIPPERSINK CREEK

Aug 13, 2024

Type Prior Date Prior Team Leader Frequency (mos) Performed Routine 08-10-22 Makela, Joshua J (9669) 24 X SIA review 08-10-22 Makela, Joshua J (9669) 48

SNBI X

Uw-Profile 08-23-16 Krueger, Joseph (9647) X

Start Coordinates End Coordinates (optional)

Latitude 42°30'19.52"N Latitude

Longitude 88°19'55.08"W Longitude

Owner COUNTY Maintainer COUNTY

Team members Time Log Hours

Minutes

Leden, Andrew: Team Leader

Weather Temperature (f)

Condition Sunny

Name Number Signature Signature Date Inspector

Leden, Andrew 9705 Andrew Leden

10-01-24 E-signed by Andrew Leden(atleden)

2B-64-155 13-Aug-2024 inspection as of 01-Oct-2024

BRIDGE INSPECTION REPORT

Wisconsin Department of Transportation

DT2007 2003 s.84.17 Wis. Stats.

Identification & Location Feature On:

CTH H

Section Town Range:

S35 T01N R18E

Structure Number:

B-64-155 Feature Under:

NIPPERSINK CREEK

County:

WALWORTH

Location

0.1M N JCT CTH B TO N

Municipality:

GENOA CITY

Structure Name:

Geometry Traffic measurements in feet, except where noted Lanes ADT ADT year Traffic Pattern Approach Roadway Width:

Bridge Roadway Width:

34.0

Total Length:

133.9 On 2 1100 2018 two way traffic

Approach Pavement Width:

Deck Width:

36.0

Deck Area (sq ft):

Capacity Load Rating Inventory rating:

HS23

Overburden depth (in):

0.0

Last rating date:

01-13-10

Controlling:

Operating rating:

HS39

Deck surface material:

Concrete

Control location:

Posting: Emergency Vehicle Weight Limit (tons):

Re-rate for capacity (Y/N): Re-rate notes:

Hydraulic Classification Scour Critical Code(113):

Stable- above top footing (8)

Q100 (ft3/sec):

High water elevation (ft):

823.4

Velocity (ft/sec):

4.2

Sufficiency #:

99.8

Span(s) Span # Material Configuration Depth (in) Length (ft) Main

1 CONT PREST CONC Girder/Beam - I-Shaped Spread 36 43.1 2 CONT PREST CONC Girder/Beam - I-Shaped Spread 36 43.7 Y 3 CONT PREST CONC Girder/Beam - I-Shaped Spread 36 43.1

Expansion joint(s) Temperature: File:70 New:80

Clearance Item File Measurement (ft) File Date New Measurement (ft)

Highway min vertical on cardinal

Horizontal on cardinal

Construction History Year Work Performed FOS id

1982 New Structure 3707-00-70

Maintenance Items History Item Recommended by Status Status change Year completed Slope Protection - Other Work Krueger, Joseph (9647) COMPLETE 10/12/18 2018

Comment:

repair erosion at all quadrants

Status Comment:

Misc - Cut Brush Thomson, Cory L (9550) COMPLETE 08/30/22 2022

Comment:

Trim vegetation over east side of bridge and remove tree from under bridge span 1 west side.

Status Comment:

7B-64-155 13-Aug-2024 inspection as of 01-Oct-2024 page 7 Structure No.:B-64-155

UW Profile Item 1 2024 UW Profile Spreadsheet b64-155_xpd1.xlsx

Routine Item 1 West elevation view b64-155_24_Rd16.jpg

Routine Item 2 Longitudinal view looking north b64-155_24_Rd1.jpg

Routine Item 3 Longitudinal view looking south b64-155_24_Rd4.jpg

8B-64-155 13-Aug-2024 inspection as of 01-Oct-2024 page 8 Structure No.:B-64-155

Routine Item 4 Typical wearing surface condition b64-155_24_Rd2.jpg Linked Element(s):

Reinforced concrete deck - black steel reinforcing -> Wearing surface ( bare)

Routine Item 5 Typical transverse crack over pier b64-155_24_Rd3.jpg Linked Element(s):

Reinforced concrete deck - black steel reinforcing -> Wearing surface ( bare)

Routine Item 6 Span 1 typical underside b64-155_24_Rd7.jpg Linked Element(s):

Reinforced concrete deck - black steel reinforcing

9B-64-155 13-Aug-2024 inspection as of 01-Oct-2024 page 9 Structure No.:B-64-155

Routine Item 7 Span 2 typical view b64-155_24_Rd10.jpg Linked Element(s):

Reinforced concrete deck - black steel reinforcing

Routine Item 8 Span 3, typical view b64-155_24_Rd15.jpg Linked Element(s):

Reinforced concrete deck - black steel reinforcing

Routine Item 9 Span 2, west deck fascia, spalling with exposed rebar b64-155_24_Rd13.jpg

10B-64-155 13-Aug-2024 inspection as of 01-Oct-2024 page 10 Structure No.:B-64-155

Routine Item 10 Span 3, west deck fascia, spalling with exposed rebar b64-155_24_Rd14.jpg Linked Element(s):

Reinforced concrete deck - black steel reinforcing

Routine Item 11 Span 2, west deck fascia, spalling with exposed rebar b64-155_24_Rd12.jpg Linked Element(s):

Reinforced concrete deck - black steel reinforcing

Routine Item 12 Span 1, west deck fascia, spalling with exposed rebar b64-155_24_Rd6.jpg

11B-64-155 13-Aug-2024 inspection as of 01-Oct-2024 page 11 Structure No.:B-64-155

Routine Item 13 Span 3, East deck fascia, spalling with exposed rebar b64-155_24_Rd17.jpg Linked Element(s):

Reinforced concrete deck - black steel reinforcing

Routine Item 14 Span 2, east deck fascia, spalling with exposed rebar b64-155_24_Rd18.jpg

Routine Item 15 Spall at SW abutment corner b64-155_24_Rd8.jpg Linked Element(s):

Reinforced concrete abutment

Routine Item 16 Undermining at east end of south abutment b64-155_24_Rd9.jpg

12B-64-155 13-Aug-2024 inspection as of 01-Oct-2024

Reinforced concrete abutment

Routine Item 17 Void and spall at North pier, West end b64-155_24_Rd11.jpg Linked Element(s):

Reinforced concrete pier wall

Routine Item 18 Southwest tiger board tipped outward b64-155_24_Rd5.jpg

Signs - object markers

1B-64-156 13-Aug-2024 inspection as of 01-Oct-2024

STATE OF WISCONSIN

DEPARTMENT OF TRANSPORTATION

Inspection Report for

B-64-156 CTH H over W BR NIPPERSINK CREEK

Aug 13, 2024

Type Prior Date Prior Team Leader Frequency (mos) Performed Routine 08-10-22 Makela, Joshua J (9669) 24 X SIA review 08-10-22 Makela, Joshua J (9669) 48

SNBI X

Uw-Profile 08-23-16 Krueger, Joseph (9647) X

Start Coordinates End Coordinates (optional)

Latitude 42°30'48.65"N Latitude

Longitude 88°20'28.63"W Longitude

Owner COUNTY Maintainer COUNTY

Team members Time Log Hours

Minutes

Leden, Andrew: Team Leader

Weather Temperature (f)

Condition Sunny

Name Number Signature Signature Date Inspector

Leden, Andrew 9705 Andrew Leden

10-01-24 E-signed by Andrew Leden(atleden)

2B-64-156 13-Aug-2024 inspection as of 01-Oct-2024

BRIDGE INSPECTION REPORT

Wisconsin Department of Transportation

DT2007 2003 s.84.17 Wis. Stats.

Identification & Location Feature On:

CTH H

Section Town Range:

S26 T01N R18E

Structure Number:

B-64-156 Feature Under:

W BR NIPPERSINK CREEK

County:

WALWORTH

Location

1.0M N CTH B

Municipality:

BLOOMFIELD

Structure Name:

Geometry Traffic measurements in feet, except where noted Lanes ADT ADT year Traffic Pattern Approach Roadway Width:

Bridge Roadway Width:

34.0

Total Length:

104.3 On 2 3200 2022 two way traffic

Approach Pavement Width:

Deck Width:

36.0

Deck Area (sq ft):

Capacity Load Rating Inventory rating:

HS17

Overburden depth (in):

0.0

Last rating date:

01-13-10

Controlling:

INTERIOR DECK GIRDER Negative Moment

Operating rating:

HS29

Deck surface material:

Concrete

Control location:

SPAN 2

Posting: Emergency Vehicle Weight Limit (tons):

Re-rate for capacity (Y/N): Re-rate notes:

Hydraulic Classification Scour Critical Code(113):

Stable- above top footing (8)

Q100 (ft3/sec):

High water elevation (ft):

827.5

Velocity (ft/sec):

4.8

Sufficiency #:

95.0

Span(s) Span # Material Configuration Depth (in) Length (ft) Main

1 CONT PREST CONC Girder/Beam - I-Shaped Spread 36 50.0 Y 2 CONT PREST CONC Girder/Beam - I-Shaped Spread 36 50.0

Expansion joint(s) Temperature: File:75 New:82

Clearance Item File Measurement (ft) File Date New Measurement (ft)

Highway min vertical on cardinal

Horizontal on cardinal

Construction History Year Work Performed FOS id

1982 New Structure 3707-00-70

Maintenance Items History Item Recommended by Status Status change Year completed Approach - Wedge Approach Krueger, Joseph (9647) COMPLETE 10/12/18 2018

Comment:

Wedge approaches.

Status Comment:

7B-64-156 13-Aug-2024 inspection as of 01-Oct-2024 page 7 Structure No.:B-64-156

UW Profile Item 1 2024 UW Profile Spreadsheet b64-156_xpd1.xlsx

Routine Item 1 East elevation view b64-156_24_Rd10.jpg

Routine Item 2 West elevation view b64-156_24_Rd3.jpg

Routine Item 3 Longitudinal view looking north b64-156_24_Rd1.jpg

8B-64-156 13-Aug-2024 inspection as of 01-Oct-2024 page 8 Structure No.:B-64-156

Routine Item 4 Longitudinal view looking south b64-156_24_Rd2.jpg

Routine Item 5 Span 2, West soffit spalling with exposed rebar b64-156_24_Rd4.jpg Linked Element(s):

Reinforced concrete deck - black steel reinforcing

Routine Item 6 Span 2, East soffit spalling with exposed rebar b64-156_24_Rd6.jpg Linked Element(s):

Reinforced concrete deck - black steel reinforcing

Routine Item 7 Span 1, Southwest deck corner spall with exposed rebar b64-156_24_Rd7.jpg

9B-64-156 13-Aug-2024 inspection as of 01-Oct-2024

Routine Item 8 West soffit spalling with exposed rebar over pier b64-156_24_Rd8.jpg Linked Element(s):

Reinforced concrete deck - black steel reinforcing

Routine Item 9 Span 1, East soffit spalling with exposed rebar b64-156_24_Rd9.jpg Linked Element(s):

Reinforced concrete deck - black steel reinforcing

Routine Item 10 North abutment, spall at backwall at G3 b64-156_24_Rd5.jpg Linked Element(s):

Reinforced concrete abutment

Routine Item 11 Timber debris and sediment buildup at upstream nose b64-156_24_Rd11.jpg

26-059 00050 Proposal Cover
26-059 00100 Table of Contents
26-059 00200 Advertisement for Bids
26-059 00300 Bid Requirements and Conditions
26-059 00350 Bid Opening Teleconference
26-059 00400 Insurance Requirements 20230210 - Revised
26-059 00500 Bid Preperation
26-059 00600 List of Subcontractors
26-059 00700 Specials_Bridge_Rehab 20260507
26-059 00800 Schedule of Items - Informational
26-059 00900 Inspection Attachments
25-019-R Bridge Reports.pdf
B640155 Final Report - Partial
B640156 Final Report - Partial