Summary: Walworth County Highway Work Proposal
This is a Highway Work Proposal Book for Project 26-009, a road reconditioning project administered by Walworth County Department of Public Works in Wisconsin. The project involves the reconditioning of approximately 3.2 miles of County Trunk Highway (CTH-H) extending from USH-12 northbound to the Jefferson County Line. The scope of work includes asphaltic milling, pulverizing, HMA pavement placement, base aggregate work, culvert replacements, concrete curb and gutter construction, minor ditching, modular block retaining wall installation, guardrail installation, driveway repaving, intersection grading and shaping, traffic control, pavement markings, and restoration work. Bid documents were issued on March 12, 2026, with final questions due by March 24, 2026, at 3:30 p.m. Sealed electronic bids are due on April 2, 2026, at 10:00 a.m. through the Bonfire procurement platform. All work must be completed by October 30, 2026, with an anticipated project award date of April 14, 2026. The project is funded through the Local Roads Improvement Program (LRIP). Bidders must be prequalified with the Wisconsin Department of Transportation and cannot appear on the state's disapproved, suspended, or debarred contractors list.
Bid security in the form of a bond equal to 5 percent of the bid amount, payable to Walworth County, is required. Neither Wisconsin prevailing wage rates nor federal Davis-Bacon prevailing wage rates apply to this project. Liquidated damages of $1,570.00 per calendar day will be assessed for failure to meet the October 30, 2026 completion deadline. The contract will be awarded to the lowest responsive, responsible bidder. The county reserves the right to accept or reject any or all bids, in whole or in part, and to waive any bidding irregularities. Contractors must maintain comprehensive insurance coverage including Workers Compensation with minimum Employers Liability limits of $100,000 per accident and $500,000 policy limit, Commercial General Liability of $1,000,000 per occurrence and $2,000,000 aggregate, Automobile Liability of $1,000,000 per occurrence and $2,000,000 aggregate, and Contractor's Pollution coverage of $1,000,000 per occurrence and $1,000,000 aggregate. The county must be named as an additional insured, and a 30-day cancellation notice is required. Retainage will be applied at 5 percent of work completed and materials delivered until 50 percent completion, with monthly progress payments thereafter. Bids cannot be withdrawn for 30 days following the scheduled bid opening.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1-26-009 List of Subcontractors.pdf | ||
| 2-26-009 Plan Set.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HIGHWAY WORK PROPOSAL
Walworth County, Wisconsin
COUNTY PROJECT NO. PROJECT DESCRIPTION HIGHWAY
Walworth 26-009 CTH-H; CTH-H USH 12 to Jefferson Co. Line
Proposal Guaranty Required:
5% of Bid Amount, Payable to Walworth County
Bid Submittal:
Date: April 2, 2026
Time (Local Time): 10:00 am
Contract Completion Time:
October 30, 2026
This Page Intentionally Left Blank
PROJECT ID 26-009
CTH-H
USH-12 to JEFFERSON CO. LINE
TABLE OF CONTENTS
Title No. of Pages
Proposal Cover 1
Table of Contents 1
Advertisement for Bids 2
Bid Requirements and Conditions 2
Bid Opening Teleconference 1
Insurance Requirements 2
Bid Preparation 1
List of Subcontractors 1
Special Provisions 19
Schedule of Items (Informational Only) 3
ADVERTISEMENT FOR BIDS
PROJECT ID 26-009
USH-12 TO JEFFERSON CO. LINE
NOTICE: Sealed (electronic) bids for the Reconditioning of CTH-H from USH-12 to Jefferson Co. Line will be received by the Walworth County Purchasing Division, Department of Public Works, W4097
County Road-NN, Elkhorn, Wisconsin 53121, until 10:00 A.M. local time on Thursday, April 2, 2026, at which time all bids will be publicly opened virtually.
SCOPE: In general, the work under this project consists of asphaltic milling, pulverizing, HMA pavement, culvert replacements, concrete curb and gutter, base aggregate, intersection grading and shaping, asphaltic millings for shoulders, minor ditching, guardrail, erosion control, traffic control, pavement markings, restoration and all incidental items necessary to complete the work as shown on the plans and included in the proposal and contract. The centerline length of the project is approximately 3.2-miles.
This is a Local Roads Improvement Program (LRIP) funded project.
ELECTRONIC BIDDING: Walworth County utilizes an internet-based procurement software called
‘Bonfire’ as the interface to exchange all official information between the County and Bidders.
Obtaining Bid Documents, Project Inquiries, and Bid Submittal will be accomplished through the Bonfire software platform.
Bidders may register for a Bonfire account at no charge through Walworth County’s Bonfire Portal at:
https://walworthcountywi.bonfirehub.com/
It is the bidder’s responsibility to check the project website for future announcements, addendums, etc.
prior to the bid deadline. Bids that do not acknowledge addendums may be rejected.
All questions must be received by the deadline(s) indicated. No information provided verbally, or by any other personnel, will be considered binding.
PROJECT COMPLETION: All work under this Contract shall be completed by October 30, 2026.
Liquidated damages for failure to complete the work in accordance with the date(s) set forth above shall be One Thousand Five Hundred Seventy dollars ($1,570.00) for each calendar day in excess thereof.
BID SECURITY: Bids must be accompanied by a Bid Bond the amount of five (5) percent of the bid price, payable to Walworth County, Wisconsin, as a guarantee that if the Bid is accepted, the Bidder will execute and file the proper contract documents within fifteen (15) days after notification of award of the contract. In case the successful bidder shall fail to execute such contract documents, the bid bond shall be forfeited to Walworth County as liquidated damages.
BIDDING SCHEDULE:
Bid Documents Issued: March 12, 2026
Pre-Bid Meeting: N/A
Final Questions Due: March 24, 2026 ( 3:30 p.m.)
Bids Due: April 2, 2026 (10:00 a.m.)
Project Award (anticipated): April 14, 2026
WAGE RATES: Neither State of Wisconsin prevailing wage rates nor Federal (Davis-Bacon) prevailing wage rates are applicable to this project.
QUALIFICATIONS: Bidders shall be experienced in this type of work and shall be prequalified with the
Wisconsin Department of Transportation for work in the class and amount of their bid.
BID WITHDRAWAL: No bid shall be withdrawn for a period of thirty (30) days after the scheduled opening of bids. Bids may be withdrawn only in total and only by a written request to Walworth County
Purchasing, Department of Public Works, prior to the time and date of the scheduled bid deadline.
BID ACCEPTANCE – REJECTION: Walworth County reserves the right to accept or reject any or all bids, in whole or in part, received in response to this advertisement, to waive any irregularities in bidding, or to accept any bid they deem most advantageous to the County.
Published by the authority of: Walworth County
BID REQUIREMENTS AND CONDITIONS
The bidder, submitting this bid, agrees and declares as a condition thereof, to be bound by the following conditions and requirements.
All prospective bidders shall be on the Wisconsin Department of Transportation list of approved
Contractors. Any Contractor that appears on the Wisconsin Department of Transportation’s List of
Disapproved, Suspended, and Debarred Contractors will be disallowed.
The bidder declares that he has carefully examined the site of, and the bid, plans, specifications and contract forms for the work contemplated and it is assumed that the bidder has investigated and is satisfied as to the conditions to be encountered, as to the character, quality, and quantities of work to be performed and materials to be furnished, and as to the requirements of the specifications, special provisions, and contract. It is mutually agreed that submission of a bid shall be considered conclusive evidence that the bidder has made such examination.
The bidder submits herewith a proposal guarantee in proper form and amount payable to the party as designated in the advertisement inviting bids, to be retained by and become the property of the owner of the work in the event the undersigned shall fail to execute the contract and return the same to the County within fifteen (15) days after having been notified in writing to do so; otherwise to be returned.
The form of agreement or contract resulting from the acceptance of the bid shall be on forms either supplied by Walworth County or approved by Walworth County.
The bidder declares that he understands that the estimate of quantities in the schedule of items is approximate only and that the actual quantities may be greater or less in accordance with the specifications.
The bidder agrees to perform the said work, for and in consideration of the payment in the amount becoming due on account of work being performed, according to the unit prices in the schedule of items, and to accept such amounts in full payment of said work.
Retainage on project estimates will be applied in accordance with the Section 66.0901(9)(b), Statutes of
Wisconsin.
Walworth County is a tax-exempt municipality under WI Stats. 77.54(9a). The bidder shall investigate the statutory requirements for payment of sales and use taxes and, if required, shall include taxes in the bid.
Bidder shall comply with the provisions set forth in the Wisconsin Administrative Code and Statutes in order to obtain a state sales tax exemption on the purchase of certain items and shall forward this information to his suppliers in order that the sale of such material and equipment be properly recorded as a tax-exempt sale.
The bidder declares that all of the said work will be performed at his own cost and expense, that he will furnish all necessary materials, labor, tools, machinery, apparatus, and other means of construction in a manner provided on the plans, specifications, special provisions and contract of which this bid will become a part. The bidder further agrees that the plans, specifications and special provisions are made a part hereof, as fully and completely as if attached hereto.
The bidder, if awarded the contract, shall pay all claims as required by Section 779.14of the Wisconsin
Statutes and shall be subject to and discharge all liabilities for injuries pursuant to Chapter 102 of the
Wisconsin Statutes, and all acts amendatory thereto. He shall further be responsible for any damage to property or injury to persons occurring through his own negligence or that of his employees or agents, incident to performance of work under this contract.
Upon completion of the work and receipt of all required documentation and material reports, Walworth
County (or designee) may submit to the contractor a tentative-final estimate of the quantities of work performed by the contractor. Within 30 calendar days of receiving the tentative-final estimate, the contractor shall submit a written statement of agreement with the final quantities. In the event of a discrepancy, the contractor shall submit item-by-item documentation of the quantities to be reviewed. If the contractor does not submit a written statement within those 30-days, Walworth County will process the estimate as a final payment with no further negotiation.
Prior to release of final payment and retainage, the contractor shall submit lien waivers for the prime contractor and subcontractors on forms supplied by, or approved by Walworth County.
The bidder, if awarded the contract, shall permit authorized representatives of the Federal, State, and
County government to inspect and audit all data and records of the contractor as they relate to this contract. Said right shall extend to any subsidiary, subcontractor, or parent corporation which relate to the construction on this project.
It is expressly agreed and understood that the bidder is in all respects an independent contractor, and the bidder is in no respect an agent, servant, or employee of Walworth County.
Walworth County reserves the right to cancel any agreement that may result from this request for bids, with no penalty, if the Walworth County Board of Supervisors fails to appropriate funds for this contract.
BID OPENING TELECONFERENCE
1. PUBLIC BID OPENING
No in-person bid openings for Public Works projects will be conducted in Walworth County.
Vendors may participate in the public bid opening for this project as described in this Section.
The bids opened and read are considered preliminary and subject to review and verification of applicable bid requirements. Contract(s) will be awarded to the lowest responsive, responsible bidder unless stated otherwise in the request for bids.
2. INSTRUCTIONS FOR PROJECT 26-009
The County will host this bid opening on Thursday, April 2, 2026, at 10:15 a.m. via Microsoft Teams.
Interested participants may attend electronically via the live stream video conference or may participate by using the audio-only option provided herein.
Microsoft Teams meeting
Join: https://teams.microsoft.com/meet/21673093408905?p=N6M8GRgi835BkKZ8k6
Meeting ID: 216 730 934 089 05
Passcode: nX7u2so9
Dial in by phone
+1 414-219-0219,,733973993# United States, Milwaukee
Phone conference ID: 733 973 993# https://teams.microsoft.com/meet/21673093408905?p=N6M8GRgi835BkKZ8k6 tel:+14142190219,,733973993
INSURANCE REQUIREMENTS
1.01 Contractor shall furnish County with Certificate of Insurance indicating proof of the following insurance from companies licensed in the State of Wisconsin:
A. Workers Compensation and Employers' Liability - The Contractor shall procure and maintain during the life of this contract Workers’ Compensation insurance with a minimum limit as required by Wisconsin Statutes. The Contractor shall also carry Employers Liability limits of at least $100,000 Each Accident, $100,000 Disease – Each Employee, and $500,000 Disease – Policy Limit. Contractor shall require all subcontractors not protected under its insurance to take out and maintain such insurance throughout the project term.
B. Commercial General Liability - with a minimum limit of $1,000,000 per occurrence and
$2,000,000 aggregate combined single limit for bodily injury and property damage liability. The County reserves the right to require higher or lower limits where warranted.
1) If excavating, underground or collapse is involved, the limits of liability stated above shall be increased to $2,000,000 per occurrence.
2) If Asbestos and/or hazardous materials are involved, the limits of liability stated above shall be changed to $5,000,000 per occurrence.
3) This insurance shall include, but is not limited to, the following coverage:
a) Premises – Operations
b) Products and Completed Operations
c) Personal and Advertising Injury
d) Contractual Liability
e) Underground, Explosion, and Collapse
f) Contractor’s indemnity obligations under this contract
4) This insurance must not include the following:
a) Any exclusion for water intrusion or water damage
b) Any exclusion of coverage relating to earth subsidence or movement
c) Any exclusion for the insured’s vicarious liability, strict liability, or statutory liability (other than worker’s compensation)
d) Any limitation or exclusion based on the nature of Contractor’s work
e) Any limitation or exclusion for damages arising from the work performed by a subcontractor
f) Any limitation or exclusion for damages related to roofing, if the work involves roofing
g) Any provisions resulting in the erosion of insurance limits by defense costs other than those already incorporated in to ISO form CG 00 01
C. Automobile Liability – with a minimum limit of $1,000,000 per occurrence and $2,000,000 aggregate combined single limit for bodily injury and property damage liability. This insurance shall include coverage for all of the following:
1) Owned Automobiles
2) Hired Automobiles
3) Non-Owned Automobiles
D. Professional Liability – Not Required
E. Contractor’s Pollution – with minimum requirements of $1,000,000 per occurrence and
$1,000,000 aggregate. Coverage must cover third-party injury and property damage, including cleanup costs, as a result of pollution conditions arising from Contractor’s operations and completed operations. Coverage must be carried for a minimum of two years following completion of the project.
F. Umbrella or Excess Coverage – Umbrella or Excess Coverage may be used in combination with the required primary coverage in (A.) through (E.) to meet the minimum insurance limits that are specified in this section, provided such insurance result in the same or greater coverage as the coverages required. In no event shall any Umbrella or Excess insurance provide narrower coverage than the primary policy. The Excess policy shall not require exhaustion of the underlying limits only through the actual payment by the underlying insurers.
G. Property Insurance – Contractor is responsible for obtaining or maintaining any other insurance deemed necessary, such as property or inland marine, to cover any property or equipment that is owned or rented by the Contractor and used within the scope of this project.
1.02 If any insurance specified above is a claims-made policy, the retroactive date must pre-date the commencement of furnishing any service under this contract, including design. An Extended Reporting Period, or “tail” coverage, must be provided for at least 2 years following completion of the work.
1.03 Walworth County, shall be named as additional insureds under the Contractor’s Commercial General
Liability, Automobile Liability, Employer’s Liability, Umbrella or Excess, and Pollution Liability insurance policies. Walworth County shall be listed as, “Walworth County, its employees, elected officials, representatives, members of its boards and/or commissions and engineering consultants.”
1.04 Unless prohibited by law, Walworth County shall be provided a waiver of subrogation by endorsement to the Commercial General Liability, Automobile Liability, Workers’ Compensation, Employer’s Liability, Contractor’s Pollution, and Umbrella or Excess Insurance.
1.05 Contractor’s insurance shall provide a thirty (30) day notice to the County prior to cancellation or material policy change. The notice shall be given to Walworth County Purchasing, Department of Public Works, W4097 County Road NN, Elkhorn, Wisconsin 53121. NOTE: Standard Cancellation Clause on a Certificate of Insurance is not acceptable. Upon receipt of notice from insurer, Owner shall have the right to stop the Work until the lapse in coverage has been cured by the procurement of replacement coverage by the Contractor. The furnishing of notice shall not relieve the Contractor of any contractual obligation to provide required coverage.
1.06 The Contractor’s certificate shall list the Certificate Holder and address as follows: Walworth County, Attn: Walworth County Purchasing, Department of Public Works, W4097 County Road NN, Elkhorn, Wisconsin 53121.
1.07 Contractor shall require all of its contractors and subcontractors performing work related to this contract to carry sufficient minimum insurance to cover liabilities arising from or out of the performance of this contract. Contractor shall require subcontractor to furnish Certificates of Insurance to Walworth County upon request.
BID PREPARATION
Walworth County utilizes an internet-based procurement software called ‘Bonfire’ as the interface to exchange all official information between the County and Bidders, including the preparation and submission of bids.
Bidders may register for a Bonfire account at no charge through Walworth County’s Bonfire
Portal at: https://walworthcountywi.bonfirehub.com/
Bidder shall assume full responsibility for timely delivery of Electronic Bids.
Within the Bonfire software:
Complete the electronic / online unit price Bid Form.
Upload a Bid Security to the electronic submittal.
Upload a List of Subcontractors to the electronic submittal.
CERTIFICATION
Submitting a bid (electronically on the internet) to the Walworth County Department of Public
Works, shall certify that the bidder has examined and carefully prepared his bid from the plans and specifications (highway work proposal), and all addenda, and has checked the same in detail before submitting said proposal or bid.
LIST OF SUBCONTRACTORS
Section 66.0901(7) of the Wisconsin Statutes provides that a bidder, as a part of his bid, shall submit a list of the subcontractors he proposes to contract with and the class of work to be performed by each, provided that to qualify for such listing, each subcontractor must first submit his bid in writing to the general contractor at least 48 hours prior to the time of bid closing. It further provides that a bid of a bidder shall not be invalid if any subcontractor, and the class of work to be performed by such subcontractor, has been omitted from a bid.
No subcontract, whether listed or later proposed, may be entered into without the written consent of the
Walworth County.
* * TO BE COMPLETED ELECTRONICALLY IN BONFIRE * *
26-009 1 of 19
Special Provisions
Table of Contents
Article Description Page #
1. General
2. Scope of Work
3. Prosecution and Progress
4. Traffic
5. General Information, Definitions, and Terms
6. Control of Work
7. Control of Materials
8. Legal Regulations and Responsibility to the Public
9. Holiday and Special Event Work Restrictions
10. Utilities
11. Notice to Contractor – Modification or Elimination of Bid Items
12. Notice to Contractor – Work by Others
13. Measurement and Payment
14. Grading and Shaping Intersection (Location), Item 205.9011.S
15. Breaker Run
16. HMA Pavement
17. Backfill Slurry, Item SPV.0035.01
18. Concrete Curb & Gutter Inlet, Item SPV.0035.02
19. Supplemental Traffic Control, Item SPV.0055.01
20. Inlet Covers Type BH, Item SPV.0060.01
21. Grading and Shaping for Curb & Gutter, Item SPV.0090.01
22. Grading and Shaping Ditches, Item SPV.0090.02
23. Traffic Control (Project), Item SPV.0105.01
24. Traffic Control (Detour), Item SPV.0105.02
25. Wall Modular Block Gravity Landscape, Item SPV.0165.01
26. Proof Rolling, Item SPV.0170.01
27. Asphaltic Millings for Shoulders, Item SPV.0195.01
26-009 2 of 19
STSP’S Revised January 1, 2026
SPECIAL PROVISIONS
1. General.
Perform the work under this construction contract for Project 26-009 CTH H (USH 12 to Jefferson County Line), Walworth County, Wisconsin as the plans show and execute the work as specified in the State of Wisconsin, Department of Transportation, Standard Specifications for Highway and Structure Construction, 2025 Edition, as published by the department, and these special provisions.
These special provisions and other documents in the Project Manual take precedence over any conflicting provisions in Part 1 of the State of Wisconsin Department of Transportation Standard Specifications for Highway and Structure Construction, 2025 Edition.
100-005 (20260101)
2. Scope of Work.
The work under this contract shall consist of asphaltic milling, pulverizing, HMA pavement, base aggregate, asphaltic millings for shoulders, concrete curb & gutter, culvert replacements, minor ditching, modular block retaining wall installation, MGS beam guard installation, driveway re-paving, intersection grading and shaping, traffic control, restoration, and all incidental items necessary to complete the work as shown on the plans and included in the proposal and contract.
104-005 (20090901)
3. Prosecution and Progress.
Begin work within 10 calendar days after the engineer issues a written notice to do so. Work that requires closure of the road shall not commence until WisDOT work on STH 67 is complete and the detour for CTH H can be implemented, expected in July 2026. See Work by Others article.
The contractor is expected to meet project schedules, including start and both interim and final completion dates. Failure to complete the work on time will subject the contractor to calendar day liquidated damages as provided in subsection 108.11 of the Standard Specifications.
Final grass restoration, including seeding, fertilizer, and erosion mat or mulch, shall be completed by September 25, 2026 to allow sufficient time for vegetation to establish prior to going dormant for the season.
All project work, including completing punch-list items, except any County-completed work, shall be complete by October 30, 2026.
The contractor shall have a superintendent or designated representative on the job site during all controlling work operations, including periods limited to subcontractor work operations, to serve as a primary contact person and to coordinate all work operations. Notify the engineer immediately upon discovery of differing conditions or plan discrepancies for review and direction.
The contractor shall schedule and conduct bi-weekly progress meetings (or at a frequency agreed to) at a location agreed to at the pre-construction conference. Subcontractors that are actively completing work or are scheduled to complete work in the two weeks following the progress meeting shall attend the bi-weekly progress meeting.
4. Traffic.
Close CTH H to through traffic to complete construction operations on the mainline highway within the parameters of Prosecution and Progress Special Provision and other plan notes. The engineer shall approve detour signage prior to closing the highway. Maintain access for local residents and businesses at all times except when completing work adjacent thereto. Provide full access at the end of each day.
Maintain a safe work zone for local traffic by furnishing, erecting, and maintaining traffic control devices along the project in accordance with all applicable federal, state, and local guidelines, including providing flaggers for single lane operation, if necessary. Comply with all local ordinances that apply to construction
26-009 3 of 19 operations, including working hours. All traffic control devices and signs shall be in place before work commences.
Maintain two-way access at the end of each day. Overnight closures and open trenches in the pavement will not be allowed. Equipment and materials shall not be stored within the travel way and shoulders.
Coordinate traffic restrictions and full (daytime only) roadway closures with the Walworth County Sheriff’s dispatch so emergency vehicle routes are known and access is maintained at all times. Contractor shall have steel plates available at all times during trench excavations to provide emergency access. Maintain access at all times for US Mail delivery, school busses, and garbage collection.
Butt joints exposed to traffic at the ends of the project, intersecting side roads, and driveways shall be constructed with a temporary wedge of asphalt millings or base aggregate. Temporary wedges will be required at these locations upon completion of the milling and surface removal operations and construction of butt joints until placement of the lower HMA layer. Temporary Wedges are incidental to construction.
Provide “Low Shoulder” signs in the time between completion of the HMA pavement and completion of the aggregate shoulder where a drop-off of greater than 2 inches exists. If opening the highway before placement of permanent pavement markings, erect “No Centerline Stripe” signs until completing road striping.
5. General Information, Definitions, and Terms.
Amend standard spec 101.3 as follows:
Department The Walworth County Department of Public Works.
Engineer The Walworth County Director of Public Works/Highway Commissioner or the County’s authorized representative limited by the particular duties assigned to the representative.
6. Control of Work.
Add the following to the beginning of paragraph (1) of Section 105.8:
The engineer or project engineer may designate an inspector or inspectors to act as the engineer’s field representative with limited authority during the progress of construction to observe daily operations.
Add the following to the list of authorized activities in paragraph (2) of Section 105.8:
4. Take field measurements and perform calculations of completed work as required by contract for progress payment as estimated by the engineer. Inspector may verify such measurements and calculations with the contractor.
5. Assist the contractor with obtaining interpretation and clarification of the contract documents from the engineer.
6. Consider and evaluate contractor suggestions for modifications to plans or specs and report such suggestions, along with inspector’s recommendation, if any, to the engineer for determination.
7. Observe, record, and report to the engineer appropriate details of tests performed by the contractor.
8. Prepare, keep, and maintain a daily report, diary, or log book for the days inspector is present on site to record contractor’s operations, weather, discussions, decisions, and general observation and provide copies to the engineer.
Add the following to the list of unauthorized activities in paragraph (3) of Section 105.8:
4. Authorize any deviation from or modification to the contract documents, extra work, or material substitutions.
26-009 4 of 19
5. Exceed the limitations of the engineer’s authority in 105.1, 105.7, and these special provisions.
6. Participate in any specialized tests or inspections the inspector is not otherwise qualified to perform.
7. Accept or approve shop drawings or material samples.
Add the following to Section 105.1 of the Standard Specifications:
The Department and engineer are not responsible for the contractor’s means, methods, techniques, sequences, or procedures; or for the contractor’s safety, health, and sanitation programs.
7. Control of Materials.
Add the following paragraph to Section 106.3.3.2 of the Standard Specifications:
Provide the engineer material documentation no later than three working days prior to delivery to the project. Failure to provide the engineer with required materials documentation may lead to reduced or no payment at the discretion of the department. Provide the results of any field or laboratory testing completed during construction within three working days of performance. Notify the engineer as soon as possible the results of any failed tests.
8. Legal Regulations and Responsibility to the Public.
Add the following paragraphs to Section 107.11.1 of the Standard Specifications:
The contractor shall protect all mailboxes not in direct conflict with the construction operations. The contractor shall remove all mailboxes that interfere with construction operations and erect them at temporary locations. As soon as construction operations permit, the contractor shall set the mailboxes at their permanent locations in accordance with US Postal Service requirements as directed by the engineer. The contractor shall replace, at no additional cost to the department, any mailbox or post which has been damaged by contractor’s operations.
Any elaborate mailbox structures are not expected to be replaced in kind. The contractor shall carefully remove and salvage parts of such structures and given to the owner. The contractor shall furnish and erect standard mailbox posts when replacing such mailboxes. Owners may replace their structure at the owner’s expense.
Handling of mailboxes within the project limits shall be incidental to the contract.
Add the following paragraph to Section 107.11.3 of the Standard Specifications:
The contractor shall protect all street address markers (a.k.a. fire numbers) not in direct conflict with the construction operations. The contractor shall carefully remove all street address markers that interfere with construction operations and erect them at temporary locations. As soon as construction operations permit, the contractor shall reset the street address markers at or near their previous location and orientation or as directed by the engineer. This work shall be incidental to the contract. The contractor shall replace, at no additional cost to the department, any post which has been damaged by contractor’s operations.
Revise the first sentence of Section 107.12 of the Standard Specifications to read as follows:
The contractor and their insurer shall defend, indemnify, and save harmless the engineer and governmental entities that are involved in the project, or in which all or a part of the project site is located, including officers, agents, and employees of any of the foregoing from suits, actions, or claims brought because of injuries or damages sustained by any person or property arising from one or more of the following:
26-009 5 of 19
9. Holiday and Special Event Work Restrictions.
Do not perform work on, nor haul materials of any kind along or across any portion of the highway carrying CTH H traffic, and entirely clear the traveled way and shoulders of such portions of the highway of equipment, barricades, signs, lights, and any other material that might impede the free flow of traffic during the following holiday and special event periods:
- From noon Friday, May 22, 2026 to 6:00 AM Tuesday, May 26, 2026 for Memorial Day;
- From noon Thursday, July 2, 2026 to 6:00 AM Monday, July 6, 2026 for Independence Day;
- From noon Friday, September 4, 2026 to 6:00 AM Tuesday, September 8, 2026 for Labor Day.
stp-107-005 (20210113)
10. Utilities.
This contract does not come under the provision of Administrative Rule Trans 220.
It is the contractor’s responsibility to coordinate all work with each utility. This includes giving proper notification when utility work is to be performed in conjunction with project construction activities. Call Diggers Hotline at least three business days before the start of any excavation work.
There are underground and overhead utility facilities located within the project limits. Use caution to ensure the integrity of underground facilities and maintain code clearance from overhead facilities at all times.
Except as noted below, the scope of work for this contract has been determined to not impact, interfere or conflict with existing utilities with the contract limits. Notify the engineer of any potential utility conflicts.
Coordinate with the engineer to adjust plans as needed to avoid any unanticipated utility conflicts.
Brightspeed has existing underground telecommunications facilities within the project limits. Copper cable runs along the west side of the highway for the entire length of the project limits at varying distances from the pavement. Fiber optic cable is also located along the west side of the highway from the southern project limit to Greening Road, where it crosses the south leg and continues along the south side of Greening Road.
No conflicts have been identified by the utility; however, conflicts may still be possible at culvert replacement or re-ditching locations. Contact the utility and the engineer if conflicts are encountered for review and resolution.
Charter Communications has existing underground telecommunications cables along the west side of the highway throughout the project limits at varying distances from the pavement. Underground services cross the road at various locations along this route.
No conflicts have been identified by the utility; however, conflicts may still be possible at culvert replacement or re-ditching locations. Contact the utility and the engineer if conflicts are encountered for review and resolution.
Edge Broadband
This utility has indicated they do not have any facilities within the project limits.
WE Energies – Electric has overhead electric power lines within the project limits as outlined below.
Approximately ten overhead service crossings occur within these limits. No conflicts are anticipated.
Maintain appropriate operating clearance from these lines.
• Southern project limit to Station 132+10: West Side
• Station 134+95 to Station 140+40: East Side
• Station173+25 to Station179+35: East Side
• Station 186+35 to Station198+90: West Side
• Station 200+90 to Station 208+85: East Side
• Station 210+50 to Station 220+50: West Side
• Station 222+75 to Station 240+40: East Side
• Station 242+10 to northern project limit: West Side
26-009 6 of 19
WE Energies – Gas has an existing underground gas main along the east side of the highway from the southern project limits through Station 111+85 at varying distances from the pavement. Services cross the road at Stations 102+90, 103+95, and 111+70.
No conflicts are anticipated.
11. Notice to Contractor – Modification or Elimination of Bid Items.
The department will not allow for a Cost Reduction Incentive as described in subsection 104.10 of the standard specifications for any elimination and/or modification of any contract bid items. Further, the department will not apply standard spec 109.5 for the total elimination or partial elimination, whether by the department or the contractor, of contract bid items.
12. Notice to Contractor – Work by Others.
The Walworth County Department of Public Works will perform the final signage for the project. Existing highway signs, where called to be removed, shall be left on-site. The County will pick up and salvage the existing signage. Coordinate work operations with Joe Kroll, County Engineer at 262-741-3441.
The Wisconsin Department of Transportation (WisDOT) is completing work on STH 67 (ID 3100-00-75), a portion of which will be used as the detour for CTH H, that is scheduled for completion by July 2026.
Contractor shall coordinate with the contractor of that project to verify schedule for reopening STH 67 to traffic to allow the detour to be implemented and closure of CTH H.
13. Measurement and Payment.
Amend section 109.1.1 of the Standard Specifications to add the following subsections:
109.1.1.1 Bid Items Designated as Pay Plan Quantity
109.1.1.1.1 General
If the schedule of items designates a bid item with a **P** in the item description, the department will not measure that bid item. The department will use the plan quantity, the approximate quantity the schedule of items shows, for payment unless one or both of the following occurs:
• Scope changes resulting in a quantity for the designated bid item that varies by more than 5 percent from plan quantity.
• Errors and omissions that affect the plan quantity by more than 5 percent.
109.1.1.1.2 Scope Changes
For engineer-directed quantity increases, the engineer will measure the additional work and pay for the addition quantity under the designated pay item. For engineer-directed quantity decreases, the engineer will measure the work eliminated and make an equitable reduction to the plan quantity under the designated bid item.
109.1.1.1.3 Errors and Omissions
The engineer will adjust the plan quantity of the designated pay item to an agreed quantity for an error or omission with no change in contract unit price.
109.1.1.2 Bid Items Designated as **R**
If the schedule of items designates a bid item with **R** in the item description due to budget restraints this item may not be used or may be used in part or in its entirety and the County will not make adjustments to the contract unit price as included in the section 104.2.2.4, section 104.2.2.5, and section 109.5.
Revise section 109.6.2 of the Standard Specifications to read as follows:
26-009 7 of 19
The department will make one progress payment each month.
Add the following paragraph to Section 109.6.3.2.1 of the Standard Specifications:
Provide copies of weight bills and delivery tickets to the engineer as the work progresses. Payment quantities will be determined from the approved weight bills and delivery tickets. Verify total daily tonnage with the engineer on a daily basis. Only quantities agreed upon as the work progresses will be paid.
Weight bills and delivery tickets must be provided to the engineer within 7 days of placement to be considered for payment.
Revise the second paragraph of section 109.6.3.3 of the Standard Specifications to read as follows:
In addition to the above retainage, the department will retain 5% of the value of the work completed, and 5% of the value of materials and equipment delivered and suitably stored, until 50% completion. At 50% completion, no additional amounts will be retained unless the engineer certifies that the work is not proceeding satisfactorily, but amounts previously retained will not be paid to the contractor until final acceptance of the work by the department. When the contractor substantially completes the work under the contract or upon completion and acceptance of the work, and pending final payment, the engineer may choose to reduce the amount retained.
14. Grading and Shaping Intersection (Location), Item 205.9011.S.
A Description
This special provision describes grading and shaping intersections.
B (Vacant)
C Construction
Grade and shape embankment slopes for intersections at the locations shown on the plans. Furnish materials and construct conforming to the following:
Common excavation and material disposal
Embankment
Borrow
Construction Staking
D Measurement
The department will measure Grading and Shaping Intersection (Location) as a single unit for each intersection, acceptably completed.
E Payment
The department will pay for measured quantities at the contract unit price under the following bid item:
ITEM NUMBER DESCRIPTION UNIT
205.9011.S.01 Grading and Shaping Intersection (Greening Road) EACH
205.9011.S.02 Grading and Shaping Intersection (Young Road) EACH
Payment is full compensation for construction staking, excavating, grading, shaping, and compacting, and for providing fill.
stp-205-010 (20210708)
15. Breaker Run.
Replace standard spec 311.2 (1) with the following:
Furnish either 3-inch clear crushed stone or concrete from a department-approved source substantially free of overburden materials, topsoil, organic materials, steel, recycled asphalt, and other deleterious
26-009 8 of 19 materials or Base Aggregate Dense 3-inch consisting of 100% crushed limestone meeting standard spec
305.2.2. Submit samples or allow engineer to inspect source material to obtain engineer’s approval prior to delivery to the site.
16. HMA Pavement.
Construct HMA Pavement conforming to standard spec 460, except as modified herein.
Tack Coat shall conform to standard spec 455, except Sections 455.2.2 and 455.2.3 will not apply.
HMA ride incentive in standard spec 740 shall not apply to this contract, but smoothness conforming to standard spec 450.3.2.9.1 will remain in effect.
Section 460.2.8.3 will not apply to this contract; however, the department reserves the right to complete random sampling and testing conforming to Standard Spec 460.2.8.3 if the department deems necessary.
The department will rely on the contractor’s QMP testing as monitored by the State and any corrections made to ensure HMA pavement mix placed on the project meets specifications. QMP testing requirements are incidental to HMA pavement. The contractor shall provide the engineer with all test results.
The department may not perform its own density testing per standard spec 460.3.3; however, the department reserves the right to order contractor-provided nuclear density testing of all asphalt pavements as they desire and determine necessary as incidental to the HMA pavement. The department will expect the density to meet the minimums required in table 460-3 and air voids within tolerances. Density incentives will only be paid conforming to standard spec 460.5.2.3 if a contractor-provided independent tester performs density testing. If any individual density test result falls more than 3.0 percent below the minimum required target density, the engineer may order work stopped to conduct a review of construction operations with the contractor.
17. Backfill Slurry, Item SPV.0035.01.
This special provision describes furnishing and placing slurry backfill in accordance with pertinent requirements of Section 209 except as hereinafter modified.
B Materials
Replace standard spec 209.2.2 with the following:
(1) Use aggregates conforming to the gradation in standard spec 501.2.7.2 for fine aggregate and for Size No. 1 in standard spec 501.2.7.3. Provide aggregates in the same proportion by weight as required for Grade A concrete in standard spec 501.2.7.4.2.2. Weigh aggregates at a batch plant suitable for batching concrete. Mix and deliver to the project site using a truck mixer. Add enough water to enable the mixture to flow readily to fill all annular spaces within the excavation.
C Construction
Replace standard spec 209.3 with the following:
Discharge from the truck in a manner to prevent segregation. Completely fill excavation in a single operation. Consolidation or compaction effort will not be required; however, provide ample time for the mixture to “set” prior to continuing any further operations on top of the slurry. The mixture will be considered “set” when all visible surface water has dissipated and an average-sized man can walk on top of the mixture without leaving footprints. At least twelve hours shall elapse before paving over backfill.
D Measurement
The department will measure Backfill Slurry by the cubic yard acceptably completed. Such volume shall be computed from actual measurements of the trench to be backfilled, up to the maximum trench width and length as shown on the plans. In irregular or inaccessible areas, the engineer may allow volume to be determined by other appropriate methods.
E Payment
The department will pay for measured quantities at the contract unit price under the following bid item:
ITEM NUMBER DESCRIPTION UNIT
26-009 9 of 19
SPV.0035.01 Backfill Slurry CY
Payment is full compensation for batching, mixing, delivery, placement, all labor, materials, equipment, and incidentals necessary to complete the work as specified.
18. Concrete Curb & Gutter Inlet, Item SPV.0035.02.
This special provision describes excavating, forming, placing and finishing concrete curb & gutter inlets in accordance with pertinent requirements of Section 602 for Concrete Surface Drains and the detail in the plans, except as hereinafter modified.
B Materials
Conform to standard spec 602.2.
C Construction
Conform to standard specs 602.3.1 and 602.3.5.
D Measurement
The department will measure Concrete Curb & Gutter Inlet by the cubic yard acceptably completed, based on the dimensions the plans show or the engineer directs.
E Payment
The department will pay for measured quantities at the contract unit price under the following bid item:
ITEM NUMBER DESCRIPTION UNIT
SPV.0035.02 Concrete Curb & Gutter Inlet CY
Payment is full compensation for excavation, shaping, preparing subgrade, forming, concrete, finishing, jointing, steel reinforcement, backfilling, and incidentals necessary to complete the work as specified.
19. Supplemental Traffic Control, Item SPV.0055.01.
This special provision describes providing a contingent cash allocation for additional traffic control on an as-needed basis, as determined by the engineer.
B Materials
Furnish temporary traffic control signs, barricades, drums, lights, supports, sign colors, sign legends, portable changeable message signs (PCMS), etc. in accordance spec 643.2.
C Construction
When the engineer or department requests in writing additional traffic control work not already included in the contract as part of the plans, plan details, standard detail drawings, notes, standard specifications, or special provisions; process in accordance with spec 104.2.2.1.
These additional traffic control measures may include, but are not limited to, custom signs, business signs, way-finding signs, additional signs or barricades placed on private property, or any other custom traffic control outside typical highway construction traffic control or otherwise shown on the plans.
Any additional, relocated, or differing standard signs, barricades, drums, lights, or supports to improve or enhance traffic control or detour signage already included in the contract, as determined by the engineer, will not be considered supplemental traffic control under this pay item and will be incidental to other contract items.
D Measurement
The Department will measure Supplemental Traffic Control by the authorized dollar value of work performed in accordance with Spec 109.4.4.
E Payment
The department will pay for measured quantities at the contract unit price under the following bid item:
26-009 10 of 19
SPV.0055.01 Supplemental Traffic Control DOL
Payment is full compensation from the allotment for an authorized dollar value of supplemental traffic control recommended by the engineer. Contract quantity will be correspondingly adjusted. All or none of the contract quantity may be used on this project. No adjustments to the contract will be made if less than the full allotment is used for this purpose.
20. Inlet Covers Type BH, Item SPV.0060.01.
This special provision describes furnishing and installing cast iron frames and “beehive” grates conforming to standard specification 611.
B Materials
Furnish a cast-iron inlet frame and beehive grate meeting AASHTO M105 Class 30 in accordance with the detail in the plans. Acceptable product Neenah R-2560-E5 or approved equal from another manufacturer.
C Construction
Construction shall conform to standard spec 611.3.3.
D Measurement
The department will measure Inlet Covers Type BH by the each unit acceptably completed.
E Payment
The department will pay for measured quantities at the contract unit price under the following bid item:
ITEM NUMBER DESCRIPTION UNIT
SPV.0060.01 Inlet Covers Type BH Each
Payment conforms to standard spec 611.5.4.
21. Grading and Shaping for Curb & Gutter, Item SPV.0090.01
This special provision describes excavating, filling, grading, shaping, and compacting as necessary to construct the curb and gutter and associated minor pavement widening as the plans show beyond intersection corners.
B (Vacant)
C Construction
Construction shall be in accordance with applicable parts of standard specs 205, 207, 208, and 211.
Dispose of all surplus and unsuitable material as specified in standard spec 205.3.12.
A runout area up to 10-feet beyond the limits of the proposed curb & gutter will be allowed for
D Measurement
The department will measure Grading and Shaping for Curb & Gutter by lineal foot acceptably completed parallel along the limits of the curb & gutter.
Measurement will include a runout area up to 10-feet beyond the limits of the proposed curb & gutter for forming and/or curb machine transition.
E Payment
The department will pay for measured quantities at the contract unit price under the following bid item:
SPV.0090.01 Grading and Shaping for Curb & Gutter LF
26-009 11 of 19
Payment is full compensation for all excavating, grading, shaping, and compacting; and for providing and placing fill.
Payment for grading and shaping work associated with curb & gutter at intersection corners is included in item “Grading and Shaping Intersection.”
The base course, surfacing and finishing items will be measured and paid for under other contract bid items.
22. Grading and Shaping Ditches, Item SPV.0090.02.
This special provision describes cutting, filling, shaping, and re-grading existing ditches as shown on the plans, realigning with a new culvert, improving ditch side-slopes, providing positive drainage, or as directed by the engineer.
B Materials
Topsoil and other unsuitable material shall not be used in embankments of backfill under pavements and shoulders.
Properly dispose of all surplus and unsuitable material conforming to standard spec 205.3.12.
C Construction
Excavate, fill, grade, and shape ditches as necessary at specified locations or as determined by the engineer. Ditching will be required for the following reasons:
1. Realign existing ditches with the location of a new culvert. Provide smooth, rounded transitions in the ditchlines to line up the existing ditch with the new culvert ends. Abrupt changes in direction that could cause embankment erosion will not be acceptable.
2. Improving ditch side-slopes. In areas of shoulder widening, build roadway embankment and push flowline out if necessary to improve ditch foreslope.
3. Filling and regrading. Some ditches will require filling and regrading to shallow a ditch that is too deep for conditions or providing swales where full-depth ditches cannot fit within County right-of-way, are impractical, or otherwise shown on the plans or directed by the engineer.
4. Provide positive drainage. Re-grade and shape existing ditches that have excessively silted in over time or are otherwise higher in elevation than new culvert inverts to eliminate pockets of standing water, where practical.
Construct drainage ditches with a minimum longitudinal slope of 1.0% (0.01 foot per foot) and side-slopes of 3H:1V maximum slope (4H:1V is preferred where practical). Longitudinal slopes as flat as 0.5% (0.005 foot per foot) may be allowed by the engineer in flat areas where providing 1% will result in excessively long ditches (greater than 100 feet longer than the length shown in the plans).