3-03. J.2 Scope of Work.pdf

PDF 262 KB Posted

Attached to
Relocation of Pulse Fence - TDCJ Hughes Unit
Solicitation number
IW256103
Issued by
Comal County, Garland City, Texas

About this file

This Scope of Work document outlines the services required by the Texas Department of Criminal Justice (TDCJ) for the relocation of a pulse fence at the Alfred Hughes Unit in Gatesville, Texas. The project encompasses comprehensive civil construction, electrical installation, Gallagher system modifications, and full project coordination. Civil work includes trenching and directional boring for conduit pathways, hydro-vacuum excavation, core drilling through the existing 24" x 48" fence footer, construction of a new 36" x 48" concrete equipment pad with 3,000 PSI reinforced concrete, backfill and site restoration, and modifications to the existing Gallagher fence array including removal of existing wires and installation of a new dedicated controller for the sallyport zone. Electrical work requires installation of one 48" x 36" NEMA 3R enclosure mounted to the concrete base, a dedicated 110V, 20-amp power circuit tied to the existing emergency generator circuit, one quad outlet, 50 feet of 1-1/4" rigid conduit for exposed runs, 300 feet of 1-1/4" PVC conduit for underground pathways, and 300 feet of 1-1/4" weather heads for low-voltage terminations. All work must comply with the National Electrical Code and applicable local codes.

The vendor must provide all labor, materials, equipment, tools, and supervision while maintaining full project coordination with TDCJ and Cram Roofing Company, the contractor installing the new sallyport. Qualifications require that the NLEF intrusion detection system be provided by a single manufacturer with certified compatibility to the existing system, and the system installer must have been in business for a minimum of seven years with completed work at no fewer than seven correctional facilities. The scope excludes design and engineering services not explicitly included, permitting fees, work outside identified project boundaries, and repairs to unforeseen underground utilities. TDCJ will provide site access, escorts, and accessible work areas during mutually agreed-upon hours coordinated with facility operations.

View the file

Other files

File Type Posted
4-Solicitation Notification - IW256103.pdf PDF
1-01.IFB IW256103.pdf PDF
2-02. Terms and Conditions.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IW256103 Exhibit J.2

SCOPE OF WORK

Relocation of Pulse Fence Texas Department of Criminal Justice (TDCJ) – Alfred Hughes Unit

1. Project Overview The Vendor shall furnish all labor, materials, equipment, tools, and supervision required to relocate the pulse fence at the TDCJ Alfred Hughes Unit. This relocation is necessary to provide access for roofing contractors and their heavy equipment to the unit and laydown yards.

Work includes, but is not limited to, civil construction, electrical installation, Gallagher system modifications, installation of underground conduit pathways, construction of a concrete equipment base, installation of a National Electrical Manufacturers Association (NEMA) enclosure, and full project coordination with TDCJ and the current contractor, Cram Roofing Company, that will install a new sallyport once this is completed.

2. Civil Scope of Work The Vendor shall perform all civil work required for relocation of the pulse fence infrastructure, including trenching, concrete foundation work, fence penetration, and site restoration.

2.1 Trenching and Boring

Perform trenching and/or directional boring to establish pathways for new electrical and communication conduits.

Trenching depth and width shall comply with all applicable codes and site requirements.

Maintain proper separation between power and low-voltage pathways.

2.2 Concrete Base Preparation

Perform trenching and hydro-vacuum excavation at the designated equipment pad location.

Prepare and compact subgrade to ensure stability and long-term support.

2.3 Fence Penetration

Core drill or jackhammer through the existing exterior fence (Dimensions: 24 inch x 48 inch) footer to create conduit pathways.

Maintain the structural integrity and security performance of the fence system during and after penetration work.

2.4 Concrete Base Installation

Form, frame, and pour a new 36” wide x 48” long concrete equipment pad sized to accommodate the specified NEMA enclosure.

3,000 PSI Concrete base shall be level, reinforced, and finished for long term equipment support.

Allow adequate cure time before equipment installation.

2.5 Backfill and Restoration

Backfill trenches with suitable material and compact in lifts to prevent settlement.

Restore disturbed areas to near-original condition, including grading and surface repair.

2.6 Gallagher Fence Array Modifications

Remove existing Gallagher wires from the fence line to accommodate the new sallyport gate.

Install an additional new controller to create a dedicated sallyport zone to match existing hardware and configuration. (Existing equipment: Gallagher 6000 or 700 Controller and Dual F4 Energizers.)

Reconfigure existing zones as necessary to terminate properly and integrate the new zone.

3. Electrical Scope of Work The Vendor shall install all electrical components required to support the new sallyport system.

3.1 NEMA Enclosure

Provide and install one (1) 48" x 36" NEMA 3R enclosure.

-Example make and model: HWHK Series 48x36x16 / NEMA-3R

Mount enclosure securely to the newly constructed concrete base.

3.2 Power Circuit Installation

Provide and install one (1) dedicated 110V, 20-amp power circuit to the NEMA 5-20R duplex receptacles. The power must be tied into the existing emergency circuit so the equipment is on generator power.

Install one (1) quad outlet inside the enclosure.

All work shall meet NEC and applicable local codes.

3.3 Conduit Installation

Provide and install 1-1/4" rigid conduit (50’) for exposed or above-grade runs.

Provide and install 1-1/4" PVC conduit (300’) for underground pathways.

Install conduits for both electrical power and low-voltage communications.

Ensure all conduits are supported, sealed, and protected from environmental conditions.

3.4 Weather Heads

Provide and install 1-1/4" weather heads (300’ of PVC conduit) for low-voltage conduit terminations feeding the new fence zone.

Ensure weather-tight terminations to prevent moisture intrusion.

3.5 Labeling and Testing

Label all new circuits and equipment in accordance with industry standards.

Perform testing and verification of all electrical circuits to confirm proper operation.

Provide test documentation to TDCJ upon completion.

4. Project Management Scope of Work The Vendor shall provide full project management, communication, and coordination services.

4.1 Coordination with TDCJ

Coordinate all site access, escort requirements, and scheduling.

Ensure adherence to TDCJ security protocols and procedures.

4.2 Coordination with CRAM and TDCJ

Coordinate scheduling of removal and reinstallation of the existing electrified fencing system.

Align construction activities with approved outage windows and operational needs.

4.3 Electrified Fence Coordination

Coordinate the safe de-energizing and takedown of the electrified fencing system as needed for construction.

Coordinate reinstallation and re-energizing upon completion of sallyport installation.

4.4 Reporting and Communication

Notify TDCJ promptly of any delays, issues, or required changes.

5. Qualifications

The entire NLEF intrusion detection system must be provided by the same manufacturer and all equipment must be certified by the manufacturer as a fully compatible system with the existing system installed.

System installer must have been in the business of manufacturing proposed detection system for seven (7) years and have completed a minimum of seven (7) correctional facilities.

6. Exclusions (Unless Otherwise Noted)

Design and engineering services not explicitly included in this Scope of Work.

Permitting fees, if applicable.

Work outside the identified project boundaries.

Repairs to unforeseen underground utilities not identified prior to construction.

7. Assumptions

TDCJ will provide site access and escorts as scheduled.

Work areas will be accessible and free of unknown obstructions unless otherwise noted.

Work will occur during mutually agreed-upon hours in coordination with facility operations.