2A04_-_SOW_V2_20-027_Saratoga_NFH_Water_Treatment_Rehab_1.pdf
PDF 73 KB Posted
- Attached to
- Saratoga NFH Water Treatment Rehabilitation - WY
- Solicitation number
- 140FC124R0001
About this file
This statement of work outlines requirements for the rehabilitation of water treatment systems at the Saratoga National Fish Hatchery in Wyoming. The contractor will be responsible for providing all labor, materials, and equipment to complete repairs and replacements according to government-provided specifications and drawings, including repairing concrete masonry damage, replacing various piping systems, covering holes left by removal of drum filters, and replacing the lower sealed column with a Water Spike system. The contractor must also complete as-built drawings reflecting any approved deviations from the original project specifications. The contracting officer and technical representatives for the project are identified as points of contact.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION C
STATEMENT OF WORK
TO
20-027 WATER TREATMENT REHAB
AT
SARATOGA NATIONAL FISH HATCHERY
I. GENERAL CONDITIONS
A. The Contractor shall provide all material, equipment, and labor required to complete the work as described in all the attached Government provided documents and changes mentioned in Section II.
II. CHANGES IN REQUIREMENTS
A. Changes to Government Furnished Documents. The referenced items have drawings numbers listed for association.
1. The A/E shall utilize all Government furnished documents to complete the project. The baseline project shall be considered the specifications package and drawing number 6R-WY-75-17-041. The items listed below are non-inclusive and the Contractor shall consider all minor changes based on this list.
2. Only work to be included in contract, excluding changes
a. Repair CMU damage in two locations (outside corner and near degassing columns)
i. A01
b. Monitoring, sensors, or any other mechanisms to assist in maintenance/monitoring.
i. C01, C10, and E01
c. All piping replacements
i. C04, C05, C06, and C07
d. Degassing columns, see “Changes” below
e. Generator
i. E02
f. All relevant demolition
i. C02, C03, C08, C09, A02, and S01
g. General Construction
i. S00, S02, S03, S04, E03, and V01
3. Removal
a. Drum filters
i. Any hole in the pedestal shall be covered by grating from the removal of the drum filter.
ii. E03
b. All other major components not listed.
i. A03
4. Changes
a. Lower sealed column end replacement with Water Spike
i. https://warrenwaterbroom.com/water-spike/
ii. C06
b. The existing UV system shall remain unchanged and not included in this contract.
i. E03
B. Complete final as-builts as constructed. USFWS can approve red lines if the deviation is minimal.
III. POINTS OF CONTACT
A. Hatchery Manager
1. Lee Bender (307-326-5662)
B. Contracting Officer Representative / Technical Representative
1. Michael Wandersee (303-236-4479)
END OF STATEMENT OF WORK