RR Towers Replacement Los Angeles World Airports
(LAWA)
Los Angeles, CA
90% SUBMITTAL
Specifications, Contract Drawings
FOR OFFICIAL USE ONLY
Prepared for:
Department of Transportation
Federal Aviation Administration
15000 Aviation Boulevard
Lawndale, CA 90261
Prepared by:
LAX RR-1 RR TOWER REPLACEMENT
TABLE OF CONTENTS
SECTION J.2-01 DIVISION 01 – GENERAL REQUIREMENTS
01 11 00 - SUMMARY OF WORK
01 31 13 - PROJECT COORDINATION
01 32 10 - CONSTRUCTION PROGRESS DOCUMENTATION
01 33 00 - SUBMITTAL PROCEDURES
01 35 26 – GOVERNMENTAL SAFETY REQUIREMENTS
01 35 29 - HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES
01 45 00 - QUALITY CONTROL
01 50 00 - TEMPORARY FACILITIES AND CONTROLS
01 60 00 - PRODUCT REQUIREMENTS
01 71 23 - FIELD ENGINEERING
01 71 33 - PROTECTION OF ADJACENT CONSTRUCTION
01 74 00 - CLEANING AND WASTE MANAGEMENT
1 77 00 - CLOSEOUT PROCEDURES
SECTION J.2-02 TECHNICAL SPECIFICATIONS
DIVISION 02 - EXISTING CONDITIONS
2 41 31 - SELECTIVE SITE DEMOLITION
2 09 00 - LEAD ABATEMENT
DIVISION 03 – CONCRETE
3 30 00 - CAST-IN-PLACE CONCRETE
DIVISION 04 – MASONRY
NOT USED
DIVISION 05 – METALS
05 12 00 - STRUCTURAL STEEL FRAMING
05 50 00 – METAL FABRICATIONS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 92 00 - JOINT SEALANTS
DIVISION 08 – OPENINGS
DIVISION 09 – FINISHES
09 97 00 – SPECIAL COATINGS
DIVISION 10 – SPECIALTIES
DIVISION 11 – EQUIPMENT
DIVISION 12 – FURNISHINGS
DIVISION 13 - SPECIAL CONSTRUCTION
13 36 13 - SELF SUPPORTING TOWERS
13 36 14 - SELF SUPPORTING TOWER INSTALLATION
DIVISION 14 - CONVEYING EQUIPMENT
DIVISION 21 - FIRE SUPPRESSION
DIVISION 22- PLUMBING
DIVISION 23 - HEATING VENTILATING AND AIR CONDITIONING
DIVISION 26 – ELECTRICAL
26 05 00 - COMMON WORK RESULTS FOR ELECTRICAL
26 05 26 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
26 05 29 - HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
26 05 33 - RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS
26 05 53 - IDENTIFICATION FOR ELECTRICAL SYSTEMS
26 41 13 - LIGHTNING PROTECTION FOR STRUCTURES
DIVISION 27 – COMMUNICATIONS
27 05 00 - RF ANTENNA CABLES AND COMMUNICATION CABLES
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
DIVISION 31 - EARTHWORK
31 10 00 - SITE CLEARING
31 20 00 - EARTHMOVING
31 23 19 - DEWATERING
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 15 00 - AGGREGATE SURFACING
DIVISION 33 - UTILITIES
DIVISION 41- MATERIAL PROCESSING & HANDLING EQUIPMENT
SECTION J.2-03 CONSTRUCTION DRAWINGS
GENERAL DRAWINGS
LAX-D-RR-G001 – TITLE SHEET, DRAWING INDEX AND VICINITY MAP
CIVIL DRAWINGS
LAX-D-RR-C001 – ABBREVIATIONS AND GENERAL CIVIL NOTES
LAX-D-RR-C002 – NEW TOWERS & DEMARC ENCLOSURE LOCATION
LAX-D-RR-C003 – DEMARC ENCLOSURE ELEV. SECTIONS & DETAIL
DEMOLITION DRAWINGS
LAX-D-RR-D001 – DEMOLITION PLAN
ELECTRICAL DRAWINGS
LAX-D-RR-E001 - SYMBOLS, LEGEND, NOTES, AND ABBREVIATIONS
REFERENCE DRAWINGS
EXISTING TOWER DRAWINGS - LAX RR ERECT STEEL TOWERS
WP-D-640-40847-4A LOCATION PLAN, PLOT PLAN & TOWER ELEVATIONS
WP-D-640-40847-4B 60 FOOT GOVERNMENT FURNISHED TOWER DETAILS
WP-D-640-40847-4C 60 FOOT CONTRACTOR FURNISHED TOWER DETAILS
WP-D-640-40847-4D CHAIN LINK FENCE - PLOT PLAN, LOCATION PLAN &
DETAIL
SECTION J.2-04 - APPENDIX REFERENCE DOCUMENT
A - ASBESTOS AND LEAD ANALYTICAL REPORT – WHITE
ENVIRONMENTAL CONSULTANTS
B - ASBESTOS CONTAINING MATERIAL REPORT – FAA
C - SOILS and FOUNDATION INVESTIGATION JUNE 2010 - META ENGINEERING
D - GEOTECHNICAL REPORT – META ENGINEERING
E - FAA-C-1217G - INTERIOR ELECTRICAL WORK (electronic file only – not printed)
F - FAA-C-1391d - INSTALLATION AND SPLICING OF UNDERGROUND CABLES
(electronic file only – not printed)
G -FAA-STD-019e - LIGHTNING AND SURGE PROTECTION, GROUNDING, BONDING AND SHIELDING REQUIREMENTS FOR FACILITIES AND
ELECTRONIC EQUIPMENT (electronic file only – not printed)
H -PROJECT SCHEDULE – PRELIMINARY SCHEDULE
DIVISION 01 –
GENERAL REQUIREMENTS
LAX RR-1 TOWER REPLACEMENT
SUMMARY OF WORK
SUMMARY OF WORK
01 11 00 -1
SECTION 01 11 00 SUMMARY OF WORK
PART 1 GENERAL
1.1 Section Includes
A. These Specifications, together with referenced specifications, standards and drawings included in the Contract Documents, cover the Contract requirements for construction of one new Remote
Transmit Receiver (RR) Tower and associated work at Los Angeles International Airport, Los
Angeles, CA.
1.2 Related Sections
A. Drawings and General Conditions of the Contract, including other Division 1 through Division 48
Specification Sections, and any attachments to this Contract apply to this section and to the
Contractor’s performance of the Work.
1.3 DEFINITIONS, ACRONYMS, ABBREVIATIONS, AND REFERENCES
A. See Part I – Section H Special Contract Requirements for other definitions relevant to these specifications.
Contractor
GFE/GFP Government Furnished Equipment/Property.
NTP Notice to Proceed.
Project Manager (PM) Refers to the Contractor’s representative as identified in the Documents to monitor the performance of the Contract and progress of construction, and to identify, advise of, and assist in resolving any discrepancies that may arise during the course of construction.
The PM or the RE acts as the on-site “eyes and ears” of the Contractor, as well as the liaison for coordination of the Work.
Provide The word “provide” as it appears in Contract specifications and drawings means, “furnish and install.”
Quality Conformance to the requirements established by the contract specifications and drawing.
Record Documents Drawings, Specifications, Addenda, Change Orders and other
Modifications; also approved Shop Drawings, Product Data, Samples, and similar submittals required to be provided by Contractor.
Record Drawings Drawings submitted by Contractor to show the construction of a particular structure or Work as actually completed under the Contract.
Request for Information (RFI) The method used by the Contractor to document and transmit field generated technical issues relating to design and construction of the Project.
Resident Engineer (RE) Contractor representative identified and assigned to monitor the performance of the Contract and progress of construction on site.
Risk Management Plan (RMP) - Comprehensive plan that identifies, and mitigates risk associated with Safety, Security, and Quality.
RR Remote Receiver.
SUMMARY OF WORK
SUMMARY OF WORK
01 11 00 -2
Schedule of Values The method used by the Contractor to allocate values to various portions of the
Work that, when approved by the Contractor, provides the basis for application for payment.
Shop Drawings Specific drawings, schedules, diagrams, and other data prepared for this
Contract by the Contractor, their lower tier Subcontractors, manufacturers, suppliers, or distributors, to illustrate a portion of the Work.
Contractor The entity identified as such in the Form of Agreement of this Contract and all of its lower tier Subcontractors.
Submittal A submittal is a Contractor's or manufacturer's drawing, brochure, sample, certificate, warranty, or other material which provides detail for construction and quality control of the permanent Work and includes deliverables such as schedules, product cut sheets, Work procedures, or product samples that are required under the terms of the Contract.
Test Plan A detailed step-by-step procedure for testing major equipment and systems.
Test Results Documentation of specified quality assurance test results.
1.4 Summary of Work
A. General:
This specification, along with related documents specified in Paragraph 1.1, covers the requirements for all work associated with the demolition of two existing RR antenna towers and associated infrastructure and the construction of one new self-supporting RR antenna tower and its associated infrastructure located at the existing LAX RR facility.
This project requires close coordination with FAA and Los Angeles World Airports (LAWA) personnel for the location of underground utilities, installation of new underground services, installation of new equipment and associated cutovers in the new tower, and demolition of the existing RR towers.
The Contractor is responsible for accomplishing all items of work in accordance with the applicable drawings, specifications and conditions of the Contract. Additional labor, materials, equipment, and/or appurtenances not specifically detailed or specified, but required to complete the project, shall be provided by the Contractor as an integral part of the scope of work specified.
A minimum of 20% of the Work is to be performed by the Contractor’s own forces.
B. Major Items of Work:
The following items are a brief summary of the project and are provided solely for the purpose of revealing the general nature of the work involved.
The Contract scope includes several items of work. Items include, but are not necessarily limited to:
I. Foundation Site Preparation and Site Grading:
a. Procure the services of a licensed surveyor to locate the center of the new tower foundation.
b. Contractor shall excavate and dispose of all unsuitable soil.
c. Contractor shall construct engineered sub-grade according with the Geotechnical
Report, attached as Appendix Reference Document D to this solicitation, and the
SUMMARY OF WORK
SUMMARY OF WORK
01 11 00 -3 project Plans and Specifications. Excavated sub-grade will be inspected by
Contractor’s Resident Engineer and Geotechnical Engineer upon completion of excavation and before proceeding with next phase. Compaction tests will be provided by Contractor and performed by an independent testing agency or the
Geotechnical Engineer.
d. Contractor is responsible for all final grading with crushed rock material around the shelter, cable rack, and as shown on the plans.
II. Foundation:
a. Construct concrete foundation in accordance with foundation drawings by Tower
Manufacturer for one (1) new self-supporting 20’ antenna tower. All inspection and hold points shall be in accordance with the specifications, project plans and shall be included in the Contractor’s Quality plan.
b. All concrete shall be in accordance with Specification 03 30 00 Cast-in-Place Concrete.
c. Quality Control concrete testing, hired by Contractor shall be done by an independent testing agency.
III. New Towers Installation and Hookup:
Contractor will purchase and deliver one (1) new 20’ self-supporting RR antenna tower. The tower will be delivered to the site by tower fabricator, and installed on the foundation by the
Contractor. Contractor shall be responsible for touching up any damaged paint and/or galvanization sections of the tower during construction. Contractor is responsible to terminate tower power and ground connections for testing and acceptance by the FAA. FAA will transfer all existing Tower antenna frequencies to new Tower antennas.
IV. Above Ground Cable Rack and Sun Shield Structure
a. Provide new stainless steel cable tray, sun shield, support structural steel, and foundations per the construction drawings. The Contractor shall provide all excavation, concrete work, backfill, support steel, cable tray, conduit, junction boxes, and cable tray fittings, required to complete the above ground cable tray system.
V. RF Cable Installation
a. The Contractor shall provide RF cable between new antenna tower mounted RF J-
Boxes and RR shelter Polyphasor demarc box per the construction drawings. Cables shall be tested prior to termination in accordance with the construction specifications.
b. Provide one stainless steel RF J-Box at platform level mounted on unistrut. RF
Box shall include ground bulkhead connector bar and support hardware. Provide one interior mounted stainless steel Polyphasor demarc enclosure with associated ground bar, conduits, and grounding as shown in the construction drawings.
SUMMARY OF WORK
SUMMARY OF WORK
01 11 00 -4
c. Install RF cable supports and RF cable shield grounding kit on antenna tower.
VI. Electrical Grounding and Lightning Protection at Antenna tower:
a. Excavate and backfill perimeter trench around new antenna tower for new EES.
b. Install new EES and bond new antenna tower EES to existing RR facility EES per the construction drawings.
c. Provide air terminals and down conductors on antenna tower as shown in the construction drawings.
d. Provide antenna tower electrical ground bonds to ladder, RF J-Box, structural steel, antenna mounts, and RF cable shields as shown in the construction drawings.
e. Provide conductors/conduit to bond down conductors and RF J-boxes.
VII. Electrical Power Work – Towers
a. Provide new solar powered security lighting for each new antenna tower. Lights shall be mounted at same elevation and orientation as existing installation.
b. Perform electrical cable tests and equipment operational tests.
VIII. Demolition:
Prior to any demolition, an independent underground utility locate will be performed, some areas may require hand digging to ensure no interruptions will occur. The demolition activities are as follows:
a. Demolish existing antenna towers as shown in the construction drawings.
Demolition shall be phased based on the transition plans prepared by the FAA.
Contractor shall demolish all associated antenna material including conduits, antenna mounts, grounding, junction boxes, RF cables, power cables, and lightning protection materials.
b. Perform abatement where activities impact existing regulated materials in accordance to project specifications, local, state and federal requirements. Remove and properly dispose of all waste materials from the site.
IX. General Scope Items.
a. Perform electronic subsurface locates in areas of excavation using an independent electronic subsurface locating Contractor. Perform onsite review of marked locates with FAA, Airport Personnel, and RE prior to excavation activities.
b. The site is an operational facility and will remain operational during construction, which will be accomplished by phasing construction activities and electronics installation and testing (by others). The FAA shall have complete site access, including access to the existing buildings, existing and new towers for the duration of the Contract.
1.5 Risk Management Plan
A. Contractor shall develop and submit a RMP for approval as set out in Part I Section H within 5 days from Contract Award. Construction must not commence until the RMP has been
SUMMARY OF WORK
SUMMARY OF WORK
01 11 00 -5 approved by the Risk Specialist. The Contractor shall comply with all safety, health, and emergency response provisions of this Contract.
1.6 Project Schedule
A. Contractor shall develop and submit to the Contractor a preliminary Construction Progress
Schedule (Schedule) and preliminary Schedule of Values for approval within 5 days from
Contract award. The Contractor’s approved Schedule of Values and Schedule are conditions for payment. The Contractor’s Schedule shall comply with the requirements of Section 01 32
00, Construction Progress Documentation. The Contractor shall provide the following information with the Schedule:
1.7 Pre-Construction Meeting
A. The CONTRACT ADMINISTRATOR will schedule a pre-construction meeting after Notice of
Award. Required attendance includes Contractor, Contractor’s Superintendent, and major lower tier Contractors. An agenda will be provided but must include at a minimum the review of the
RMP, Schedule, and Schedule of Values. The Contractor must submit other items identified in
Section G.3 Progress Payments or Payment Procedures at the Pre-Construction Conference for review at the meeting. Acknowledgements of all the reviews made at the session will be noted in the meeting minutes.
1.8 Access Requirements
A. General Access and Use. Access to the Worksite must be with approval of the RE. Access to the
Worksite will be thoroughly discussed prior to the start of actual construction. Only vehicles essential to the construction effort will be permitted in the construction area. All construction equipment and materials must be removed from the driveways at the end of each work day as directed by the RE.
B. Access to certain locations for the project may be restricted due to facility operations. Contractor may be required at various times to yield to facility operations that may require use of the Site.
Upon receiving such a notice, Contractor must vacate the subject area. Unless otherwise indicated, Contractor shall have complete and exclusive use of the premises within the construction staging area limits for the execution of the Work.
1.9 Contractor and Government Furnished Property
A. These Specifications identify labor, materials, plant and equipment to perform the Work. All material not specifically indicated as furnished by Contractor must be furnished by Contractor.
B. Government Furnished Equipment/Government Furnished Property provided by the Contractor.
The Contractor must be accountable for all GFE/GFP or equipment/property acquired under this
Contract. The Contractor must not accept any GFE/GFP without documentation signed by both the Contractor and Contractor indicating actual items and quantities received/transferred.
GFE/GFP furnished but not installed shall be returned to the Contractor with documentation signed by both the Contractor and Contractor indicating actual items and quantities received/transferred. The Contractor must adequately control, preserve, protect and maintain all
GFE/GFP and Contractor acquired property. GFE/GFP includes the following:
1. none
SUMMARY OF WORK
SUMMARY OF WORK
01 11 00 -6
1.10 Compliance with Local and Other Codes
A. The Contractor shall be responsible for coordination of all work at the Worksite, and for obtaining local permits. The Contractor must obtain and comply with any necessary licenses/permits that comply with applicable Federal, State, and Local regulations in connection with the scope of the work. The Contractor will not be required to pay any amount for any action taken by a state or political subdivision.
1.11 Right of Access
A. The FAA reserves the right to enter the premises during the term of the Contract for quality assurance work inspections and/or maintenance of existing navigational and communication facilities. South Coast Air Quality Management also reserves the right of continued and uninterrupted access to its equipment and leasehold located in the vicinity. Contractor’s equipment staging locations will be coordinated with the RE for accommodate this requirement.
1.12 Site Inspection
A. After NTP and prior to initiating Work, Contractor and RE must conduct joint inspections of the jobsite to determine the existing conditions and note any existing damage or defects. Existing damage or defects will be used as the basis for determination of damages caused by the
Contractor's operations.
1.13 Site Damage
A. Contractor shall be responsible for the cost of any repair caused by Contractor’s operations or the operations of its lower tier SubContractors. All damage to the existing Site including, but not limited to, existing utilities and cables, facilities, equipment, buildings, and vegetation must be repaired. All such repairs must match the original finish and must be made utilizing materials, equal to or of greater quality than the original materials, as approved by RE. All repairs must be made with no additional cost to FAA.
1.14 Layout of Work
A. The Contractor must layout its work from established base lines and bench marks indicated on the drawings, and will be responsible for all measurements in connection with the layout. The
Contractor shall furnish, at its own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the Work. The Contractor shall be responsible for the execution of the Work to the lines and grades that may be established or indicated by the
RE. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contractor until authorized to remove them. If such marks are destroyed by the Contractor or through its negligence before their removal is authorized, the Contractor may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 Special Scheduling Requirements
A. Protect existing facilities and equipment from physical or electrical damage as a result of accidental or incidental negligence, such as, but not limited to, disruption of standby power to the
SUMMARY OF WORK
SUMMARY OF WORK
01 11 00 -7 facility or equipment.
SUMMARY OF WORK
SUMMARY OF WORK
01 11 00 -8
B. All preparatory work must be completed by the Contractor prior to shutdown/cutover to minimize downtime. The requested time and date of shutdown and cutover must be approved by the RE a minimum of two working days in advance of the requested shutdown or cutover. FAA personnel will perform the actual shutdown/cutover of systems that affect operations.
C. In the event any services are interrupted, restore services with a full crew available to restore such services on a 24-hour basis, including Work during holidays and weekends, at no additional cost to FAA or delay in the Schedule.
D. Request any utility interruptions in writing 5 days before the scheduled interruption, unless otherwise specified. RE review is required before interruption. In this notification, the Contractor must certify that all equipment, materials, and personnel necessary to conduct such testing will be available on the scheduled date and that the systems have been pre-checked by personnel and are ready for performance and acceptance testing.
E. Contractor must also confirm that all operations and maintenance manuals have been submitted and approved. No performance and acceptance testing will be permitted until the operations and maintenance manuals have been approved.
F. At the option of Contractor, FAA personnel will travel to the site to witness testing. If the testing must be postponed or canceled for whatever reason not the fault of the Contractor, the Contractor must provide FAA not less than 3 days advance notice (notice may be facsimile or email) of this postponement or cancellation.
G. Coordinate all required outages with Contractor through the RE. The Contractor must determine quantity and duration of outages required to complete the Work. The Contractor may have to schedule work and outages at a time when air traffic is at a minimum. This could mean late night or early morning hours.
H. Do not interrupt services outside of permitted, scheduled outage periods.
3.2 Inspection of Work
A. FAA retains the right to inspect all Work on the project, but has no obligation to do so.
Contractor’s inspections and tests are for the sole benefit of Contractor and do not:
1. Relieve the Contractor or its lower tier SubContractors of the responsibility to provide adequate quality control measures.
2. Relieve the Contractor or its lower tier contractors of the responsibility for damage to or loss of material before acceptance.
3. Constitute or imply acceptance.
B. The presence or absence of the RE does not relieve the Contractor or its lower tier subcontractors from any Contract requirement, nor is the RE authorized to change any requirement of the Contract.
3.2 Submittals
A. Contractor must submit document, data, and/or material submittals in accordance with Section 01
33 00, Submittal Procedures, and/or as specified elsewhere in the Technical Specifications.
3.3 Contract Closeout
A. The Contractor is responsible for Contract closeout in accordance with Section 01 77 00, Closeout Procedures.
SUMMARY OF WORK
SUMMARY OF WORK
01 11 00 -9
3.4 Project Specific Work Plans
A. Required Work Plans. The Contractor shall be required to submit written work plans in accordance with the submittal requirements set out in Section 01 33 00, Submittal Procedures, for critical items of work set out in this Section, in the Technical Specifications, or elsewhere in the Contract
Documents. Work associated with the required work plans shall not commence until approval has been provided.
B. Work Plan -- Underground Utility Damage Prevention. The Contractor is responsible for complying with all OSHA regulations related to underground utility damage prevention. The
Contractor shall take all reasonable steps necessary to make certain that all active, abandoned, or unknown utilities are identified. Such steps are to include the utilization of an individual or firm acceptable to the Contractor and knowledgeable in Subsurface Utility Engineering (SUE) techniques, and competent to perform utility designation in conformance with the National Utility
Locating Contractors Association (NULCA) Standard 101 for Professions Competence Standards for Locating Technicians or other written standard acceptable to the Contractor.
1. Preparation
a. All existing underground utilities depicted on the drawings, (which include but are not limited to: power, control, and communications cables; telephone, water and sewer lines;
and other utilities) are shown in their approximate locations only. Other utility lines may exist but not be depicted. It is the Contractor’s responsibility to ensure that locations of all underground airport, FAA, public, and/or private utilities are established prior to work in the area.
b. The Contractor shall at its expense satisfactorily repair and/or pay the cost of repair for all damages to underground utilities that result from the Contractor’s or its lower tier
SubContractors’ operations during the period of the Contract. The Contractor is responsible for completing any required repair work to any underground utility that is damaged by its workers, equipment, work, or SubContractors immediately, and with equal material approved by the RE.
c. If the Contractor damages a cable that has been previously located, then the Contractor shall be required to repair the cable and, at its expense, install either a pull box or manhole depending on the type and/or size of the cable. The RE will determine whether a pull box or manhole is required. All costs related to the repair of the damaged cable shall be the responsibility of the Contractor.
d. Do not interrupt existing utilities serving facilities occupied by the FAA or others except when permitted in writing by the RE and then only after acceptable temporary utility services have been provided. Provide a minimum 48-hours notice to the RE. Do not proceed with the interruption of any utility without written notice from the RE.
e. Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by earthwork operations.
f. Protect subgrade and foundation soils against freezing temperatures or frost. Provide protective insulating materials as necessary. Protect subgrade and foundation soils from softening and damage by rain or water accumulation.
g. Provide erosion control measures to prevent erosion or displacement of soils and discharge of soil-bearing water runoff or airborne dust to adjacent properties and walkways.
2. Pre-excavation Requirements for Underground Utility Installations.
SUMMARY OF WORK
SUMMARY OF WORK
01 11 00 -
a. Prior to any excavation, the Contractor shall layout in the field the centerline of all proposed utilities. In addition, the Contractor shall white line (by white spray paint or other means acceptable to the RE) the limits of construction including the area(s) to be excavated. The Contractor shall also identify the proposed placement of grounding rods.
b. The Contractor shall identify the location of existing underground utilities on as-built drawings, including any unknown or abandoned utility found during construction. The
Contractor shall ensure that all Airport officials, FAA technicians, other utility owners/operators, and any One-Call System performing utility designation/location services designate/mark existing utilities within the construction limits as well as the entire path of excavation, including five feet to either side of proposed utilities. The
Contractor shall be solely responsible for notifying relevant utility owners/operators and
One-Call System sufficiently in advance to ensure that delays to construction does not occur.
c. After completion of the utility designation described above, the Contractor shall hire a professional Subsurface Utility Engineering (SUE) or utility designation/locating company, to designate and sweep the entire excavation area, including five feet to either side of proposed utilities, to confirm the locations of the marked utilities and identify and mark any additional unidentified utilities that may be within the limits of excavation.
d. The Contractor, in accordance with Section 01 31 13 Project Coordination, shall notify the RE of the preferred date and time for a pre-work meeting for all excavation work. The
RE will coordinate the pre-work meeting with utility owners, local Airport Authority, FAA, the Contractor, and others as applicable to walk the excavation area and review applicable documentation. The Contractor shall arrange to have its excavator and SUE (or designation firm) at the pre-work meeting. The Contractor shall provide a written excavation work plan that includes a contingency plan to restore to service all utilities including cables that may be placed out of service or damaged during performance of the work. The work plan at a minimum must include:
i. A list of qualified Contractors such as plumber, electrician, fiber optical cable splicer, and others as applicable for emergency repair purposes. Due to current
FAA/TSA/Airport security requirements, the Contractor shall ensure that these
Contractors have passed any airport security and registration requirement so they can be presented immediately at the job site when emergency repair is warranted.
ii. The Contractor shall coordinate with the RE to request an Emergency
Procedures Plan from the Airport Authority or facility manager. This plan will outline special procedures during emergencies, disasters, accidents and injuries.
The Contractor shall review the Emergency Procedures Plan with all its personnel prior to construction and every quarter thereafter.
iii. The Contractor shall investigate and provide a list of sketches/drawings to all disconnects to electrical circuits, jet fuel lines, natural gas, and main water sources that feed the services in the project area and its vicinity. All disconnects and shut-off valves shall be noted with special notation and procedures if required by the utility owners/operators.
iv. Name of the SUE or utility designation firm including training and experience of the technician who will be performing the utility designation as well as equipment that will be used for sweeping the area to be excavated.
AWP-1193 LAX RR TOWER REPLACEMENT
Hilo, HI
SUMMARY OF WORK
Parsons For Official Use Only
01 11 00 -10
v. Name of the excavator including training and experience of the equipment operator who will be doing the work.
f. Contractor shall expose all utilities that it will be crossing through non-destructive mechanical excavation methods such as vacuum excavation or similar mechanical method(s) approved by the RE (“potholing”) or by hand digging. When a cable is located, the Contractor shall hand-excavate a trench five (5) feet each side of the exposed cable to verify that another cable is not adjacent to the exposed cable. All critical or high priority facilities must be exposed by potholing or hand digging every 100 feet (or less if on a curve) if the Contractor is working on or parallel to a critical or high priority utility.
All exposed utilities must be properly supported and protected during construction.
g. Contractor shall continuously maintain utilities, facilities and/or systems that are or may be affected by work associated with the project. The Contractor shall provide the RE with written reports on any cable cuts in accordance with Subsection 3.2 C. below.
h. If the Contractor does not find an underground utility that was previously marked, the excavation shall be stopped, the RE shall be notified, and the Contractor shall contact the appropriate owner/operator of the utility or make contact with the appropriate owner/operator, using the One-Call System when warranted.
i. Every attempt shall be made to preserve the location markings during excavation.
Location markings that are no longer visible shall be refreshed by calling the one-call system and/or the utility owners/operators for remarking.
j. All existing utilities that have been exposed during exploratory potholing or excavation must be supported to prevent stretching, kinking, or damage to the existing utility.
3. Excavation
a. Preserve, protect and maintain existing operable drains, sewers, and electrical ducts during grading, excavating and backfilling operations. Keep excavations dry. Locations indicated for existing utility facilities are approximate. Pipes or other manmade obstructions, in addition to those indicated, may be encountered. Movement of construction machinery and equipment over pipes and utilities during construction shall be at the Contractor’s risk. Perform all work adjacent to non-Government utilities as indicated in accordance with procedures outlined by utility owner. Excavation made with power driven equipment is not permitted within five feet of any known existing utility.
Start hand excavation on each side of the indicated obstruction and continue until the obstruction is uncovered. Support uncovered lines until approval for backfill is granted by the RE. No excavated material shall be disposed of in such a manner as to obstruct the flow of any stream, endanger a partly finished structure, impair the efficiency or appearance of any structure, or be detrimental to the completed work in any way.
b. An observer, acceptable to the RE, shall be present to assist the equipment operator when operating equipment around known underground facilities and utilities. Adhere to the following during excavation:
i. All mechanized excavation shall start with 6 to 10 inches of excavation on the surface. The equipment operator shall immediately cease operation and notify the RE if utility warning tapes, sand, or bedding material is uncovered at any time during excavation.
SUMMARY OF WORK
01 11 00 -11
ii. All excavations within 5 feet of any facility, known utility ground markings, riser guard, pole (with riser), meter, or other structure shall be performed by hand digging or other means such as vacuum excavating.
iii. If the Contractor discovers damage, causes damage, or even contacts an existing underground utility, the owner/operator of that utility, and RE shall be notified immediately. The Contractor shall be responsible for making necessary repair and/or replacement in accordance with this section and the terms and conditions of the Contract.
iv. If there is a critical or high priority utility line in the dig area, make arrangements for the utility owner/operator to be on the job site during the excavation. If the utility owner/operator refuses to be present, document this response by appending it to the request form.
v. Only those Contractor employees qualified by training, licensed or experienced (as appropriate) shall be permitted to operate machinery, tools or equipment.
c. The Contractor and RE shall coordinate on a daily basis with the excavator and the excavating work crew regarding the work to be performed that day with an emphasis on the excavation work plan and anticipated utility crossings.
C. Work Plan - Crane Work.
1. Provide a work plan to the Contractor’s Resident Engineer and FAA, at least 1 week prior to the arrival of any crane at the work site. Approval of work plan by FAA shall be obtained prior to crane arrival.
2. On the day of arrival of the crane at the work site, and every day the crane is at the work site thereafter, notify the Resident Engineer of its presence and location.
3. The following information for each crane must be given to the Resident Engineer:
Boom or lead height
Weight
4. Crane must be grounded.
5. Crane must have an up-to-date Certificate of Insurance.
6. Crane operator must have an up-to-date Operator License.
7. Crane must have appropriate flags and lights on top.
D. Work Plan - Fall Protection. Whenever activities are to be performed 6 feet or higher above a lower level by Contractor or lower-tier Contract personnel, the Contractor shall:
1. Include a detailed Fall Protection Plan as part of the Safety and Health Plan submittal. The
Fall Protection Plan shall identify specific situations where fall protection is required by all
Contractor and lower-tier Contractor personnel who will be engaged in activities at elevations of 6 feet or higher, identify the fall protection system and associated components to be used, and explain the specific methods and procedures to be followed to assure 100% fall protection.
2. 100% fall protection means that the employee is protected 100% of the time by an approved fall protection system regardless of activity. 100% of the time an employee is engaged in activities at elevations of 6 feet or higher; the employee must be protected - without exception.
3. Guardrail Systems when used as the means of fall protection on the job shall comply with 29
CFR 1926.502(b). Additionally, these systems shall:
SUMMARY OF WORK
01 11 00 -12
a. Be provided on every open-sided floor or platform 4 feet or more above adjacent floor or ground level on all open sides, except where there is an entrance to a ramp, stairway, or fixed ladder.
b. Consist of a top rail, intermediate rail, and posts, and shall have a vertical height of 42 inches nominal from upper surface of top rail to floor, platform, runway, or ramp level.
When used mid-rails shall be half the distance between the top rail and to floor, platform, runway, or ramp level.
c. Be capable of withstanding, without failure, a force of at least 200 pounds applied within
2 inches of the top edge of the top rail, in any outward or downward direction, at any point along the top edge.
d. Be capable of withstanding, without failure, a force of at least 150 pounds applied to the mid-rail, in any outward or downward direction.
e. Use toeboards or screens when objects could fall to a lower level.
4. Safety Net Systems when used as the means of fall protection on the job site shall comply with 29 CFR 1926.502(c). Additionally, these systems shall:
a. Be installed as close as practicable under the walking/working surface on which employees are working, but in no case more than 30 feet below such level.
b. Extend outward from the outermost projection of the work surface as follows:
Vertical distance from working level to horizontal plane of net:
Minimum required horizontal distance of outer edge of net from the edge of the moving surface:
Up to 5 feet
More than 5 feet up to 10 feet
More than 10 feet
8 feet
10 feet
13 feet
c. Be capable of absorbing an impact force equal to that produced by the required drop test.
The drop-tested shall be performed at the job site after initial installation and before being used as a fall protection system, whenever relocated, after major repair, and at 6-month intervals if left in one place. The drop-test shall consist of a 400 pound bag of sand 30 ± inches in diameter dropped into the net from the highest walking/working surface at which employees are exposed to fall hazards, but not from less than 42 inches above that level.
d. Be installed with sufficient clearance under them to prevent contact with the surface or structures below when subjected to an impact force equal to the required drop test.
e. Be inspected at least once a week for wear, damage, and other deterioration. Defective nets and components shall be removed from service.
f. Be inspected daily, at the beginning and end of each shift, and all materials, scrap pieces, equipment, and tools which have fallen into the safety net must be removed as soon as possible from the net.
g. Be inspected after any occurrence that could affect the integrity of the safety net system.
Defective nets and components must be removed from service.
5. Personal Fall Arrest Systems when used as the means of fall protection on the job site shall comply with 29 CFR1926.502(d). The Contractor shall identify, in writing, an observer to
SUMMARY OF WORK
01 11 00 -13 be present on the ground at all times when personnel are engaged in activities requiring the use of these systems. (This person shall have certification by training and experience as a competent person in fall protection and shall not have any other duties that will encumber the observing duties.) Additionally, these systems shall:
a. Utilize full body harnesses (which meet ANSI AI0.14-1991) to distribute the fall arrest forces as defined in 29 CFR 1926.500(b). Body belts shall not be used.
b. Utilize shock absorbing lanyards or retractable lifelines with locking type snap hooks to prevent “roll-out.”
c. Limit the free fall distance, as defined in 29 CFR 1926.502(d)(16)(iii), to less than six feet and minimize associated swing hazards.
d. Ensure anchor points meet the 5,000-lb. strength requirements outlined in 29 CFR
1926.502(d)(15).
e. Ensure that all fall protection systems and components are inspected prior to each use and continue to be inspected by a competent person in accordance to the requirements set forth in 29 CFR 1926.502(d)(21). The Contractor shall maintain records of inspection at the job site for review by Parsons personnel and/or regulatory agencies.
6. Positioning Device Systems must comply with 29 CFR 1926.502(e). The Contractor shall identify, in writing, an observer to be present on the ground at all times when personnel are engaged in activities requiring the use of these systems. (This person shall have certification by training and experience as a competent person in fall protection and shall not have any other duties that will encumber the observing duties.) Additionally, these systems shall:
a. Utilize full body harnesses (which meet ANSI Al0. 14-1991). Body belts shall not be used.
b. Utilize positioning lanyards with locking type snap hooks to prevent "roll-out."
c. Limit the free fall distance, as defined in 29 CFR 1926.502(e)(l), to less than two feet.
d. Ensure anchor points meet the 3,000-lb. strength requirements outlined in 29 CFR
1926.502(e)(2).
e. Ensure that all positioning device systems and components are inspected prior to each use and continue to be inspected by a competent person in accordance to the requirements set forth in 29 CFR 1926.502(e)(9). The Contractor shall maintain records of inspection at the job site for review by Contractor’s personnel and/or regulatory agencies.
6. Warning Lines and Controlled Access Zones when used as means of fall protection must comply with the requirements of 29 CFR I 926.502(f & g). Additionally, use of warning lines and controlled access zones must require the designation of a competent person to perform as a safety monitor. The competent person shall be on the same working level as employees, be able to readily observe and communicate orally with employees on the working level, and not have any other duties that will encumber the safety monitoring duties.
7. Fall Protection training shall be provided as described in 29 CFR 1926.503(a) and 29 CFR l926.2l(b)(2), be conducted by a competent person according to 29 CFR 1926.503(a)(2), and be current within 12 months of issuance of the Notice To Proceed.
8. A training certification record showing the names of employees trained, the date(s) of the training, training topics, and the signature of the trainer in accordance with 29 CFR l926.503
(b & c) shall be submitted to Contractor.
9. A Notice To Proceed will not be issued until written evidence is received by Contractor showing compliance with the fall protection training requirement. All Contractor
SUMMARY OF WORK
01 11 00 -14 employees will be required to have, on file with Contractor, their training records before they will be permitted on the job site. Delays and related costs associated with the Contractor's failure to comply shall be the sole responsibility of the Contractor.
E. Required Forms to be Submitted. The following forms must be completed and submitted to the
Contract Administrator at least five (5) working days prior to the Pre-Construction Conference:
1. Contractor Site Specific Safety Plan
2. Hazard Assessment of the work site (including identification of hazards, protective measures required and written certification)
3. Training documentation (records and certifications) for all Contractor and lower-tier
Contractor personnel engaged in work at the site:
4. Competent person training documentation where required by 29 CFR 1910 and 29 CFR 1926 such as for fall protection, excavations over four feet deep, crane and rigging operations, working in confined spaces, lockout/tagout of energy sources and equipment, and working with live electricity.
5. Additional training records may be required on a case-by-case basis.
END OF SECTION 00 11 00
PROJECT COORDINATION
01 31 13-1
SECTION 01 31 13 PROJECT COORDINATION
A. This section specifies requirements for requests for information as well as special and regularly scheduled progress meetings.
1.2 Related Sections
A. General Conditions of the Contract; Section 01 11 00, Summary of Work; Section 01 32 00, Construction Progress Documentation; and Section 01 33 00, Submittal Procedures.
1.3 Request for Information (RFI) Procedures
A. Use of RFI Form. Contractor will utilize sample form attached to this section. Contractor will accurately complete the form for any RFI and upload to the project KSN website.
B. RFIs identifying a technical question relating to the design or construction of the project shall be submitted to the RE for disposition by the PM. RFI are to be uploaded to the project KSN in accordance with subparagraph 1.3 A. Attach drawings, sketches, and other clarifying documents along with recommended resolution if known. PM will respond and transmit Contractor’s response to the RFI to the Contractor with copies to the RE and SA.
C. If Contractor determines that Contractor’s response to the RFI may impose a cost or a schedule impact on the Work, Contractor must inform the PM in writing with copies to the RE and SA within (3) working days from receipt. Contractor is not to proceed with any Work that incurs additional cost or time on the basis of an RFI. If no cost or schedule impact notification is received from Contractor within specified time, Contractor will be deemed to have accepted
Contractor’s response and responsibility for Work described therein.
D. Contractor must maintain its own RFI log. The RFI number must be prefixed by Contractor assigned number followed by a dash followed by a sequential number starting at 001.
1.4 Weekly Progress Meetings
A. Meetings with Contractor shall be held weekly with date, time and location to be specified by
RE. The purpose of these meetings will be to conduct a joint review, review the quality of the on-going Work, and agree on project progress and subsequent submittals of updated and actual progress schedules. Contractor shall provide an agenda of items to be reviewed during the meeting. The agenda shall include as a minimum an action items list, updated RFI log, Master
Submittal list, submittal schedule, 2-week look-ahead schedule and any safety related items.
1.5 Pre-installation/Pre-work Meetings
A. When required in individual specification sections, convene a pre-installation meeting at
Worksite before starting work requiring a written work plan. The purpose of the meeting will be to review the Contractor’s work plan, determine acceptability of the Contractor’s work plan, and provide authorization to proceed with the Work if the work plan is acceptable. Require attendance of parties directly affecting, or affected by, work of the specific section and RE.
Notify the RE and PM a minimum of five (5) days before the meeting.
PROJECT COORDINATION
01 31 13-2
Not Used
END OF SECTION 01 31 13
PROJECT COORDINATION
01 31 13-3
LAX RR TOWER REPLACEMENT
CONSTRUCTION PROGRESS DOCUMENTATION
01 32 10-1
SECTION 01 32 10
CONSTRUCTION PROGRESS DOCUMENTATION
1.1 Summary
A. This section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work.
1.2 Related Sections
A. Related Sections include the following: General Conditions of the Contract Part I Section G; Section 01 11
00, Summary of Work; Section 01 31 13, Project Coordination; and Section 01 33 00, Submittal Procedure.
1.3 General Requirements for Construction Schedule
A. Prescheduling Conference: The Contractor and SubContractor shall conduct a conference to review methods and procedures related to the Contractors Proposed Construction Schedule and Contractor’s
Preliminary Construction Schedule including the following:
1. Review any software limitations, content and format for reports.
2. Discuss constraints including mobilization, phasing of new towers installation and demolishing existing towers, staging requirements, work moratoriums, and demobilization.
3. Review delivery dates for Contractor Furnished Property or Government Furnished Property.
4. Review schedule for work of any other separate contracts planned for the site.
5. Review time required, and procedures, for review of submittals and resubmittals.
6. Review requirements for tests and inspections by independent testing and inspecting agencies.
7. Review time required for completion, startup procedures, and acceptance requirements.
8. Review and finalize list of construction activities to be included in schedule.
9. Review process for updating schedule.
B. Coordination: Coordinate preparation and processing of schedules and reports with performance of construction activities, and scheduling and reporting of separate lower tier SubContractors. Coordinate the Contractor's Construction Schedule with the Schedule of Values, List of Lower Tier Contractors, Submittals Schedule, Progress Reports, Payment Requests, and any other required schedules and reports.
A. Secure time commitments for performing critical elements of the Work from parties involved.
B. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.
C. Submitting Schedule Information: Contractor shall submit all schedule information…