285-22-RFQ-0019.pdf
PDF 1 MB Posted
- Attached to
- Residential Water Well, Lockport New York
- Solicitation number
- 285-22-RFQ-0019
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Manual_Exhibit_5-5_1A_IEERepresentationForm.pdf | ||
| Appendix A IHS Standards.pdf | ||
| TNCR_5345 - IHS PLANS Well.pdf | ||
| Wage Rate Niagara 20220225.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 8/2014)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED PAGE OF PAGES
285-22-RFQ-0019
Indian Health Service Nashville Area Office 711 Stewarts Ferry Pike
See Solicitation Package Section B-M
Attachments:
Appendix A – HIS Standards.pdf
Wage Rate Niagara 20220225.pdf
TNCR_5345 - IHS PLANS Well.pdf
Manual_Exhibit_5-5_1A_IEERepresentationForm.pdf
Paul Carr paul.carr@ihs.gov
1 424/26/2022
1500CST
5/27/2022
Indian Health Service Nashville Area Office 711 Stewarts Ferry Pike
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE.
AWARD (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 8/2014) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
27. PAYMENT WILL BE MADE BY
10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
TABLE OF CONTENTS
B. SUPPLIES OR SERVICES/PRICES
C. DESCRIPTION/SPECIFICATIONS
D. PACKAGING AND MARKING
E. INSPECTION AND ACCEPTANCE
F. DELIVERIES OR PERFORMANCE
G. CONTRACT ADMINISTRATION DATA
H. SPECIAL CONTRACT REQUIREMENTS
I. CONTRACT CLAUSES
J. LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
K. REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS OF BIDDERS
L. INSTRUCTIONS, CONDITIONS, AND NOTICES TO BIDDERS
M. EVALUATION FACTORS FOR AWARD
B. Supplies or Services/Prices
This requirement is 100% set-aside for Indian Owned Small Business. The North American
Industry Classification System (NAICS) code for this acquisition will be - 237110, Water and
Sewer Line and Related Structures Construction. The small business size standard is $39.5
Million.
B.1. Price Schedule
Item Description Unit Unit Cost Estimated
Quantity Total Cost
Table 1: INDIVIDUAL DRILLED
WELLS
1A 10-Inch Well Drilling Per Foot $ 20 $
1B 6-Inch Well Drilling Per Foot $ 40 $
1C 6-Inch PVC Well Casing - SCH.
Per Foot $ 20 $
1D Well Development Per Hour $ 3 $
1E Sanitary Grouting Per Foot $ 20 $
1F Test Pumping Per Hour $ 2 $
1G Chemical Sampling and Analysis Each $ 1 $
TOTAL, TABLE 1
Table 2: INDIVIDUAL WATER
SYSTEMS
2A Pitless Adapter and Well Cap Each $ 1 $
2B 1/2 HP Submersible Pump Each $ 1 $
2C 1" PE 160 PSI Drop Pipe Per Foot $ 60 $
2D Submersible and Buried Cable Per Foot $ 100 $
2E 1" PE 160 PSI Water Service Line Per Foot $ 100 $
2F Pressure System Each $ 1 $
2G Freezeless Riser Each $ 1 $
2H Rock Removal CY $ 10 $
2I
Site Restoration (final grading, topsoil, seed and restoration including lawn and driveway)
Each $ 1 $
TOTAL, TABLE 2
3 Well Abandonment Each $ 1 $
SUM TOTAL $
Total of Unit Price Bids = Total Bid Price $
Tuscarora Water Supply Facility
Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security. This Bid will remain subject to acceptance for 60 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of the Government.
Estimated quantities are not guaranteed, and are solely for the purpose of comparison of Bids, and final payment for all unit price Bid items will be based on actual quantities, determined as provided in the Contract Documents. Items not Included in bid shall be considered incidental and shall be included as part of the line items to furnish a complete and working system.
Prepared By: _______________________________________________________
Company: _________________________________________________________
License Number: ___________________________Unique ID : ______________________
City: ____________________________ State: __________ Zip Code:________________
Telephone: ___________________________ E-Mail: _____________________________
Signature: ________________________________Date:____________________________
C. Description/Specifications
C.1. STATEMENT OF WORK
The work to be performed under this Contract shall consist of furnishing all tools, equipment, materials, supplies, and manufactured articles and for furnishing all transportation and services, including fuel, power, and essential communications, and for fulfillment of all labor and any associated cost with one or more of the following:
Construction of individual drilled water wells: including well, casing, pump, pitless unit;
Construction of household water systems: including water service lines, pressure system;
Completion of water analysis, well logs, test pump reports, and as-constructed requirements.
The work shall be complete, and all work materials, and services not expressly shown or called for in the Contract Documents that may be necessary for the complete and proper construction of the work in good faith shall be performed furnished and installed by the CONTRACTOR as though originally specified or shown, at no increase or cost to the Owner.
All work shall be in accordance to industry standards to include but not limited to:
Well Driller must be registered with the New York State Department of Environmental
Conservation
Work must be in compliance with the provisions of Appendix 5-B of the New York State
Department of Health regulations (10NYCRR Appendix 5-B)
New York State Building Standards and Codes (includes: 2015 International Residential
Code, 2015 International Plumbing Code)
Niagara County Department of Health County Code(s), as applicable
Appendix A – IHS Standards
Tribal Regulation(s), as applicable
C.2. WORK COVERED BY CONTRACT DOCUMENTS
The Project, of which the Work under the Contract Documents is a part, is generally described as follows: Installation of onsite individual well and water system consisting of 60-feet of a 6-inch drilled and cased well, properly grouted and capped; 1 ½ HP submersible pump; 60-feet of drop pipe; 60-feet submersible pump cable; 40-feet of 1” water service line; 40-feet of buried cable; 1 pressure tank; and 1 freezeless riser with copper tubing. Well construction shall include test pumping, well drilling logs, well development, cleaning and chemical analysis of well, locator warning tape and all other appurtenances to make a complete and working system.
C.3. CONTRACTOR USE OF PROJECT SITE
The CONTRACTOR's use of the project sites shall be limited to construction operations, including on-site storage of materials and equipment. Further use of the owners' facilities and storage areas must be approved by the OWNER.
C.4. DIRECTIVES, INSTRUCTIONS AND REFERENCES
The work performed under this contract shall be performed in compliance with the codes, references, and standards listed below:
New York State Department of Health, Drinking Water Regulations, Part 5, Subpart 5-1
Appendix 5-A "Recommended Standards for Water Works" http://10statesstandards.com/waterstandards2007.html
Appendix 5-B "Standards for Water Wells" https://www.health.ny.gov/regulations/nycrr/title_10/part_5/appendix_5b.htm
Appendix 5-C "Acceptable Methods for the Analysis of Contaminants in Drinking Water" https://www.health.ny.gov/regulations/nycrr/title_10/part_5/appendix_5c.htm
2015 International Plumbing Code (3rd Printing as adopted by New York State);
https://codes.iccsafe.org/public/document/code/448/8071162
New York State Department of Conservation; Water Withdrawal, Conservation & Drought;
Water Well Contractor Program
National Electric Code (NFPA 70)
National Electrical Safety Code (IEEE C2)
County Code(s), as applicable
Tribal Regulation(s), as applicable
Applicable Health and Human Services (HHS), Indian Health Service (IHS), directives, instructions, and references not listed in this section will be provided in the individual task orders.
http://10statesstandards.com/waterstandards2007.html https://www.health.ny.gov/regulations/nycrr/title_10/part_5/appendix_5b.htm https://www.health.ny.gov/regulations/nycrr/title_10/part_5/appendix_5c.htm https://codes.iccsafe.org/public/document/code/448/8071162
D. Packaging and Marking
This section is intentionally left blank.
E. Inspection and Acceptance
52.236-5 Material and Workmanship. (APR 1984)
(a) All equipment, material, and articles incorporated into the work covered by this contract shall be new and of the most suitable grade for the purpose intended, unless otherwise specifically provided in this contract. References in the specifications to equipment, material, articles, or patented processes by trade name, make, or catalog number, shall be regarded as establishing a standard of quality and shall not be construed as limiting competition. The Contractor may, at its option, use any equipment, material, article, or process that, in the judgment of the Contracting Officer, is equal to that named in the specifications, unless otherwise specifically provided in this contract.
(b) The Contractor shall obtain the Contracting Officer's approval of the machinery and mechanical and other equipment to be incorporated into the work. When requesting approval, the Contractor shall furnish to the Contracting Officer the name of the manufacturer, the model number, and other information concerning the performance, capacity, nature, and rating of the machinery and mechanical and other equipment. When required by this contract or by the Contracting Officer, the Contractor shall also obtain the Contracting Officer's approval of the material or articles which the Contractor contemplates incorporating into the work. When requesting approval, the Contractor shall provide full information concerning the material or articles. When directed to do so, the
Contractor shall submit samples for approval at the Contractor's expense, with all shipping charges prepaid. Machinery, equipment, material, and articles that do not have the required approval shall be installed or used at the risk of subsequent rejection.
(c) All work under this contract shall be performed in a skillful and workmanlike manner.
The Contracting Officer may require, in writing, that the Contractor remove from the work any employee the Contracting Officer deems incompetent, careless, or otherwise objectionable.
(End of clause)
52.246-12 Inspection of Construction. (AUG 1996)
(a) Definition. Work includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not -
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) below.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer's written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the
Government not to conform to contract requirements, unless in the public interest the
Government consents to accept the work with an appropriate adjustment in contract price.
The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may (1) by contract or otherwise, replace or correct the work and charge the cost to the
Contractor or (2) terminate for default the Contractor's right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately.
Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government's rights under any warranty or guarantee.
52.246-13 Inspection - Dismantling, Demolition, or Removal of Improvements. (AUG 1996)
(a) Unless otherwise designated by the specifications, all workmanship performed under the contract is subject to Government inspection at all times and places where dismantling or demolition work is being performed. The Contractor shall furnish promptly, and at no increase in contract price, all reasonable facilities, labor, and materials necessary for safe and convenient inspection by the Government. The
Government shall perform inspections in a manner that will not unduly delay the work.
(b) The Contractor is responsible for damage to property caused by defective workmanship. The Contractor shall promptly segregate and remove from the premises any unsatisfactory facilities, materials, and equipment used in contract performance, and promptly replace them with satisfactory items. If the Contractor fails to proceed at once in a workmanlike manner with performance of the work or with the correction of defective workmanship, the Government may (1) by contract or otherwise, replace the facilities, materials, and equipment or correct the workmanship and charge the cost to the
Contractor and (2) terminate for default the Contractor's right to proceed. The Contractor and any surety shall be liable, to the extent specified in the contract for any damage or cost of repair or replacement.
F. Deliveries or Performance
F.1. PREFORMANCE LOCATION
The location for this project is Lockport, New York
F.2. OUTCOMES AND DELIVERABLES
The final work product construction of individual water well and facilities for home in this requirement that meet the technical drawings and specifications provided by IHS. The well and facilities provided shall be operable and complete and consist of providing safe drinking water to the home
Contractor is required to provide record drawings (as-builts) for each system constructed.
The Contractor shall complete the WORK within the time specified in the agreement.
Construction work shall not be normally permitted on Saturdays, Sundays, or Federal and/or
Tribal holidays. The Contractor may submit a written request to the Owner at least 72 hour in advance, for permission to work on any Saturday, Sunday, or Federal holiday. Written approval must be obtained before the Contractor may work on any such day.
Record drawings are required before final payment can be made for each site.
F.3. PERIOD OF PERFORMANCE AND DELIVERABLE SCHEDULE
Performance shall begin 14 days after receipt of Notice to Proceed. Construction shall be completed within 30 days after commencement of performance.
Construction work shall not be normally permitted on Saturdays, Sundays, or Federal and/or
Tribal holidays. The CONTRACTOR may submit a written request to the COR at least 72 hours in advance, for permission to work on any Saturday, Sunday, or Federal holiday.
52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 14 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 30 days after commencement of work. The time stated for completion shall include final cleanup of the premises.
G. Contract Administration Data
G.1. MODIFICATIONS
The Contracting Officer (CO) is the only person authorized to approve changes or modify any of the requirements contained in this contract. In the event the contractor effects any such change at the direction of any other person other than the CO, the change will be considered to have been made without authority and no adjustment will be made in the contract costs to cover any increase incurred as a result thereof.
Contractual problems, of any nature, that may arise during the life of this contract must be handled in conformance with very specific public laws and regulations (i.e., Federal Acquisition
Regulation). Only the CO is authorized to formally resolve such problems. The Contractor must bring all such contractual problems to the immediate attention of the CO. Requests for modifications of this contract must be sent to the CO with a copy sent to the COR as designated in the COR appointment letter.
G.2. GOVERNMENT POINTS OF CONTACT
Contracting Officer:
All contract administration will be effected by the Contracting Officer. Communications pertaining to contractual administrative matters will be addressed to the Contracting Officer. No changes in or deviation from the scope of work shall be effected without a written modification to the contract executed by the Contracting Officer authorizing such changes.
Contracting Officer Representative (COR):
A COR will be designated on authority of the Contracting Officer to monitor and coordinate all technical aspects and assist in the administration of the contract. All contacts with all agencies of the Government and interfacing with other contractors required in the performance of this contract will be accomplished only through the direction and with the coordination of the COR. A letter of designation will be issued to the COR with a copy supplied to the Contractor, stating the responsibilities and limitations of the COR.
G.3. INVOICING INSTRUCTIONS
The Government shall not be required to pay or withhold any tax in respect of or out of the income of Contractor. Contractor and Indian Health Service, Nashville Area, agree and acknowledge that the IHS, NAO are not providing and shall have no obligation to provide health, life, worker’s compensation, or disability insurance, pension benefits, vacation, or sick leave pay, training or any other personal benefit of any kind as request is for a contracted service.
Contractor understands that the government does not pay any IRS requirements (taxes), insurance or any other benefits for the contractor under this contract. This is in accordance with (FAR
52.229-3 FEDERAL, STATE, AND LOCAL TAXES (Apr 2003) and FAR 52.229-4 FEDERAL, STATE, AND LOCAL TAXES (NON-COMPETITIVE CONTRACT [APR 2003]). Clauses may be assessed electronically at https://www.acquisition.gov/far/index.html
The Contractor shall be required to provide an original and one copy of invoices to: Indian Health
Service, Nashville Area Office, Attn: Financial Management, 711 Stewarts Ferry Pike, Nashville, Tennessee 37214. The Invoices should be submitted though The Invoice Processing Platform
(IPP). More information can be obtained at https://www.ipp.gov/vendors/index
B. Each invoice shall include the following information:
(1) Contractor's name, Unique Entity ID (UEI) and Invoice Date;
(2) Contract Number or other Authorization for delivery of services;
(3) Description, price, quantity, and address of services actually rendered;
(4) Payment terms;
(5) Other substantiating documentation or information as required by the contract; and
(6) Name, title, phone number, and complete mailing address of official to whom payment is to be sent.
C. Please view 52.214-4 “Contract Terms and Conditions—Commercial Items” section (g)
“Invoice” for more detail on invoice requirements.
https://www.ipp.gov/vendors/index
H. Special Contract Requirements
52.246-21 Warranty of Construction. (APR 1984)
(a) In addition to any other warranties in this contract, the Contractor warrants, except as provided in paragraph (i) of this clause, that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material, or design furnished, or workmanship performed by the Contractor or any subcontractor or supplier at any tier.
(b) This warranty shall continue for a period of 1 year from the date of final acceptance of the work. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 1 year from the date the
Government takes possession.
(c) The Contractor shall remedy at the Contractor's expense any failure to conform, or any defect. In addition, the Contractor shall remedy at the Contractor's expense any damage to Government-owned or controlled real or personal property, when that damage is the result of -
(1) The Contractor's failure to conform to contract requirements; or
(2) Any defect of equipment, material, workmanship, or design furnished.
(d) The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause. The Contractor's warranty with respect to work repaired or replaced will run for 1 year from the date of repair or replacement.
(e) The Contracting Officer shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage.
(f) If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the Contractor's expense.
(g) With respect to all warranties, express or implied, from subcontractors, manufacturers, or suppliers for work performed and materials furnished under this contract, the Contractor shall -
(1) Obtain all warranties that would be given in normal commercial practice;
(2) Require all warranties to be executed, in writing, for the benefit of the
Government, if directed by the Contracting Officer; and
(3) Enforce all warranties for the benefit of the Government, if directed by the
Contracting Officer.
(h) In the event the Contractor's warranty under paragraph (b) of this clause has expired, the Government may bring suit at its expense to enforce a subcontractor's, manufacturer's, or supplier's warranty.
(i) Unless a defect is caused by the negligence of the Contractor or subcontractor or supplier at any tier, the Contractor shall not be liable for the repair of any defects of material or design furnished by the Government nor for the repair of any damage that results from any defect in Government-furnished material or design.
(j) This warranty shall not limit the Government's rights under the Inspection and
Acceptance clause of this contract with respect to latent defects, gross mistakes, or fraud.
I. Contract Clauses
52.203-3 Gratuities. (APR 1984)
52.203-5 Covenant against Contingent Fees. (MAY 2014)
52.203-7 Anti-Kickback Procedures. (MAY 2014)
52.203-17 Contractor Employee Whistleblower Rights and Requirement To Inform
Employees of Whistleblower Rights. (APR 2014)
52.204-13 System for Award Management Maintenance. (OCT 2016)
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations. (NOV 2015)
52.219-6 Notice of Total Small Business Set-Aside. (NOV 2011)
52.222-3 Convict Labor. (JUN 2003)
52.222-4 Contract Work Hours and Safety Standards - Overtime Compensation. (MAY
2018)
52.222-6 Construction Wage Rate Requirements. (MAY 2014)
52.222-7 Withholding of Funds. (MAY 2014)
52.222-8 Payrolls and Basic Records. (MAY 2014)
52.222-9 Apprentices and Trainees. (JUL 2005)
52.222-10 Compliance with Copeland Act Requirements. (FEB 1988)
52.222-11 Subcontracts (Labor Standards). (MAY 2014)
52.222-12 Contract Termination - Debarment. (MAY 2014)
52.222-13 Compliance with Construction Wage Rate Requirements and Related
Regulations. (MAY 2014)
52.222-14 Disputes Concerning Labor Standards. (FEB 1988)
52.222-15 Certification of Eligibility. (MAY 2014)
52.222-21 Prohibition of segregated facilities. (APR 2015)
52.222-26 Equal Opportunity. (SEP 2016)
52.222-27 Affirmative Action Compliance Requirements for Construction. (APR 2015)
52.222-50 Combating Trafficking in Persons. (MAR 2015)
52.222-55 Minimum Wages Under Executive Order 13658. (DEC 2015)
52.222-62 Paid Sick Leave Under Executive Order 13706. (JAN 2017)
52.223-18 Encouraging Contractor Policies To Ban Text Messaging While Driving. (AUG
2011)
52.225-9 Buy American - Construction Materials. (MAY 2014)
52.225-13 Restrictions on Certain Foreign Purchases. (JUN 2008)
52.232-5 Payments Under Fixed-Price Construction Contracts. (MAY 2014)
52.232-27 Prompt Payment for Construction Contracts. (JAN 2017)
52.232-33 Payment by Electronic Funds Transfer - System for Award Management. (JUL
2013)
52.232-39 Unenforceability of Unauthorized Obligations. (JUN 2013)
52.232-40 Providing Accelerated Payments to Small Business Subcontractors. (DEC 2013)
52.233-1 Disputes. (MAY 2014)
52.233-3 Protest After Award. (AUG 1996)
52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004)
52.236-2 Differing Site Conditions. (APR 1984)
52.236-3 Site Investigation and Conditions Affecting the Work. (APR 1984)
52.236-12 Cleaning Up. (APR 1984)
52.236-13 Accident Prevention. (NOV 1991)
52.236-15 Schedules for Construction Contracts. (APR 1984)
52.236-21 Specifications and Drawings for Construction. (FEB 1997)
52.243-4 Changes. (JUN 2007)
52.244-6 Subcontracts for Commercial Items. (NOV 2017)
52.253-1 Computer Generated Forms. (JAN 1991)
52.222-23 Notice of Requirement for Affirmative Action To Ensure Equal Employment
Opportunity for Construction. (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative
Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the
Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for minority participation for each trade
5.8%
Goals for female participation for each trade
6.9%
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any
Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal
Opportunity clause, (2) specific affirmative action obligations required by the clause entitled Affirmative Action Compliance Requirements for Construction, and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The
Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from
Contractor to Contractor, or from project to project, for the sole purpose of meeting the
Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for
Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the-
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the covered area is New York, Suffolk County.
(End of provision)
52.222-36 Equal Opportunity for Workers with Disabilities. (JUL 2014)
(a) Equal opportunity clause. The Contractor shall abide by the requirements of the equal opportunity clause at 41 CFR 60-741.5(a), as of March 24, 2014. This clause prohibits discrimination against qualified individuals on the basis of disability, and requires affirmative action by the Contractor to employ and advance in employment qualified individuals with disabilities.
(b) Subcontracts. The Contractor shall include the terms of this clause in every subcontract or purchase order in excess of $15,000 unless exempted by rules, regulations, or orders of the Secretary, so that such provisions will be binding upon each subcontractor or vendor. The Contractor shall act as specified by the Director, Office of
Federal Contract Compliance Programs of the U.S. Department of Labor, to enforce the terms, including action for noncompliance. Such necessary changes in language may be made as shall be appropriate to identify properly the parties and their undertakings.
52.249-2 Termination for Convenience of the Government (Fixed-Price). (APR 2012) -
Alternate I (SEP 1996)
(a) The Government may terminate performance of work under this contract in whole or, from time to time, in part if the Contracting Officer determines that a termination is in the
Government's interest. The Contracting Officer shall terminate by delivering to the
Contractor a Notice of Termination specifying the extent of termination and the effective date.
(b) After receipt of a Notice of Termination, and except as directed by the Contracting
Officer, the Contractor shall immediately proceed with the following obligations, regardless of any delay in determining or adjusting any amounts due under this clause:
(1) Stop work as specified in the notice.
(2) Place no further subcontracts or orders (referred to as subcontracts in this clause) for materials, services, or facilities, except as necessary to complete the continued portion of the contract.
(3) Terminate all subcontracts to the extent they relate to the work terminated.
(4) Assign to the Government, as directed by the Contracting Officer, all right, title, and interest of the Contractor under the subcontracts terminated, in which case the Government shall have the right to settle or to pay any termination settlement proposal arising out of those terminations.
(5) With approval or ratification to the extent required by the Contracting
Officer, settle all outstanding liabilities and termination settlement proposals arising from the termination of subcontracts; the approval or ratification will be final for purposes of this clause.
(6) As directed by the Contracting Officer, transfer title and deliver to the
Government (i) the fabricated or unfabricated parts, work in process, completed work, supplies, and other material produced or acquired for the work terminated, and (ii) the completed or partially completed plans, drawings, information, and other property that, if the contract had been completed, would be required to be furnished to the Government.
(7) Complete performance of the work not terminated.
(8) Take any action that may be necessary, or that the Contracting Officer may direct, for the protection and preservation of the property related to this contract that is in the possession of the Contractor and in which the Government has or may acquire an interest.
(9) Use its best efforts to sell, as directed or authorized by the Contracting
Officer, any property of the types referred to in subparagraph (b)(6) of this clause; provided, however, that the Contractor (i) is not required to extend credit to any purchaser and (ii) may acquire the property under the conditions prescribed by, and at prices approved by, the Contracting Officer. The proceeds of any transfer or disposition will be applied to reduce any payments to be made by the Government under this contract, credited to the price or cost of the work, or paid in any other manner directed by the Contracting Officer.
(c) The Contractor shall submit complete termination inventory schedules no later than
120 days from the effective date of termination, unless extended in writing by the
Contracting Officer upon written request of the Contractor within this 120-day period.
(d) After expiration of the plant clearance period as defined in subpart 49.001 of the
Federal Acquisition Regulation, the Contractor may submit to the Contracting Officer a list, certified as to quantity and quality, of termination inventory not previously disposed of, excluding items authorized for disposition by the Contracting Officer. The Contractor may request the Government to remove those items or enter into an agreement for their storage. Within 15 days, the Government will accept title to those items and remove them or enter into a storage agreement. The Contracting Officer may verify the list upon removal of the items, or if stored, within 45 days from submission of the list, and shall correct the list, as necessary, before final settlement.
(e) After termination, the Contractor shall submit a final termination settlement proposal to the Contracting Officer in the form and with the certification prescribed by the
Contracting Officer. The Contractor shall submit the proposal promptly, but no later than
1 year from the effective date of termination, unless extended in writing by the
Contracting Officer upon written request of the Contractor within this 1-year period.
However, if the Contracting Officer determines that the facts justify it, a termination settlement proposal may be received and acted on after 1 year or any extension. If the
Contractor fails to submit the proposal within the time allowed, the Contracting Officer may determine, on the basis of information available, the amount, if any, due the
Contractor because of the termination and shall pay the amount determined.
(f) Subject to paragraph (e) of this clause, the Contractor and the Contracting Officer may agree upon the whole or any part of the amount to be paid or remaining to be paid because of the termination. The amount may include a reasonable allowance for profit on work done. However, the agreed amount, whether under this paragraph (f) or paragraph
(g) of this clause, exclusive of costs shown in subparagraph (g)(3) of this clause, may not exceed the total contract price as reduced by (1) the amount of payments previously made and (2) the contract price of work not terminated. The contract shall be modified, and the
Contractor paid the agreed amount. Paragraph (g) of this clause shall not limit, restrict, or affect the amount that may be agreed upon to be paid under this paragraph.
(g) If the Contractor and Contracting Officer fail to agree on the whole amount to be paid the Contractor because of the termination of work, the Contracting Officer shall pay the Contractor the amounts determined as follows, but without duplication of any amounts agreed upon under paragraph (f) of this clause:
(1) For contract work performed before the effective date of termination, the total (without duplication of any items) of -
(i) The cost of this work;
(ii) The cost of settling and paying termination settlement proposals under terminated subcontracts that are properly chargeable to the terminated portion of the contract if not included in subdivision (g)(1)(i) of this clause; and
(iii) A sum, as profit on subdivision (g)(1)(i) of this clause, determined by the Contracting Officer under 49.202 of the Federal Acquisition
Regulation, in effect on the date of this contract, to be fair and reasonable; however, if it appears that the Contractor would have sustained a loss on the entire contract had it been completed, the
Contracting Officer shall allow no profit under this subdivision (iii) and shall reduce the settlement to reflect the indicated rate of loss.
(2) The reasonable costs of settlement of the work terminated, including -
(i) Accounting, legal, clerical, and other expenses reasonably necessary for the preparation of termination settlement proposals and supporting data;
(ii) The termination and settlement of subcontracts (excluding the amounts of such settlements); and
(iii) Storage, transportation, and other costs incurred, reasonably necessary for the preservation, protection, or disposition of the termination inventory.
(h) Except for normal spoilage, and except to the extent that the Government expressly assumed the risk of loss, the Contracting Officer shall exclude from the amounts payable to the Contractor under paragraph (g) of this clause, the fair value as determined by the
Contracting Officer, for the loss of the Government property.
(i) The cost principles and procedures of part 31 of the Federal Acquisition Regulation, in effect on the date of this contract, shall govern all costs claimed, agreed to, or determined under this clause.
(j) The Contractor shall have the right of appeal, under the Disputes clause, from any determination made by the Contracting Officer under paragraph (e), (g), or (l) of this clause, except that if the Contractor failed to submit the termination settlement proposal or request for equitable adjustment within the time provided in paragraph (e) or (l), respectively, and failed to request a time extension, there is no right of appeal.
(k) In arriving at the amount due the Contractor under this clause, there shall be deducted
(1) All unliquidated advance or other payments to the Contractor under the terminated portion of this contract;
(2) Any claim which the Government has against the Contractor under this contract; and
(3) The agreed price for, or the proceeds of sale of, materials, supplies, or other things acquired by the Contractor or sold under the provisions of this clause and not recovered by or credited to the Government.
(l) If the termination is partial, the Contractor may file a proposal with the Contracting
Officer for an equitable adjustment of the price(s) of the continued portion of the contract. The Contracting Officer shall make any equitable adjustment agreed upon. Any proposal by the Contractor for an equitable adjustment under this clause shall be requested within 90 days from the effective date of termination unless extended in writing by the Contracting Officer.
(m)(1) The Government may, under the terms and conditions it prescribes, make partial payments and payments against costs incurred by the Contractor for the terminated portion of the contract, if the Contracting Officer believes the total of these payments will not exceed the amount to which the Contractor will be entitled.
(2) If the total payments exceed the amount finally determined to be due, the
Contractor shall repay the excess to the Government upon demand, together with interest computed at the rate established by the Secretary of the Treasury under
50 U.S.C. App. 1215(b)(2). Interest shall be computed for the period from the date the excess payment is received by the Contractor to the date the excess is repaid. Interest shall not be charged on any excess payment due to a reduction in the Contractor's termination settlement proposal because of retention or other disposition of termination inventory until 10 days after the date of the retention or disposition, or a later date determined by the Contracting Officer because of the circumstances.
(n) Unless otherwise provided in this contract or by statute, the Contractor shall maintain all records and documents relating to the terminated portion of this contract for 3 years after final settlement. This includes all books and other evidence bearing on the
Contractor's costs and expenses under this contract. The Contractor shall make these records and documents available to the Government, at the Contractor's office, at all reasonable times, without any direct charge. If approved by the Contracting Officer, photographs, microphotographs, or other authentic reproductions may be maintained instead of original records and documents.
52.249-10 Default (Fixed-Price Construction). (APR 1984)
(a) If the Contractor refuses or fails to prosecute the work or any separable part, with the diligence that will insure its completion within the time specified in this contract including any extension, or fails to complete the work within this time, the Government may, by written notice to the Contractor, terminate the right to proceed with the work (or the separable part of the work) that has been delayed. In this event, the Government may take over the work and complete it by contract or otherwise, and may take possession of and use any materials, appliances, and plant on the work site necessary for completing the work. The Contractor and its sureties shall be liable for any damage to the Government resulting from the Contractor's refusal or failure to complete the work within the specified time, whether or not the Contractor's right to proceed with the work is terminated. This liability includes any increased costs incurred by the Government in completing the work.
(b) The Contractor's right to proceed shall not be terminated nor the Contractor charged with damages under this clause, if -
(1) The delay in completing the work arises from unforeseeable causes beyond the control and without the fault or negligence of the Contractor. Examples of such causes include (i) acts of God or of the public enemy, (ii) acts of the
Government in either its sovereign or contractual capacity, (iii) acts of another
Contractor in the performance of a contract with the Government, (iv) fires, (v) floods, (vi) epidemics, (vii) quarantine restrictions, (viii) strikes, (ix) freight embargoes, (x) unusually severe weather, or (xi) delays of subcontractors or suppliers at any tier arising from unforeseeable causes beyond the control and without the fault or negligence of both the Contractor and the subcontractors or suppliers; and
(2) The Contractor, within 10 days from the beginning of any delay (unless extended by the Contracting Officer), notifies the Contracting Officer in writing of the causes of delay. The Contracting Officer shall ascertain the facts and the extent of delay. If, in the judgment of the Contracting Officer, the findings of fact warrant such action, the time for completing the work shall be extended. The findings of the Contracting Officer shall be final and conclusive on the parties, but subject to appeal under the Disputes clause.
(c) If, after termination of the Contractor's right to proceed, it is determined that the
Contractor was not in default, or that the delay was excusable, the rights and obligations of the parties will be the same as if the termination had been issued for the convenience of the Government.
(d) The rights and remedies of the Government in this clause are in addition to any other rights and remedies provided by law or under this contract.
52.252-2 Clauses Incorporated by Reference. (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
https://www.acquisition.gov/
352.226-1 Indian Preference.(December 18, 2015)
(a) The Contractor agrees to give preference in employment opportunities under this contract to
Indians who can perform required work, regardless of age (subject to existing laws and regulations), sex, religion, or tribal affiliation. To the extent feasible and consistent with the efficient performance of this contract, the Contractor further agrees to give preference in employment and training opportunities under this contract to Indians who are not fully qualified to perform regardless of age (subject to existing laws and regulations), sex, religion, or tribal affiliation. The Contractor also agrees to give preference to Indian organizations and Indian-owned economic enterprises in the awarding of any subcontracts to the extent feasible and consistent with the efficient performance of this contract. The Contractor shall maintain the necessary statistical records to demonstrate compliance with this paragraph.
(b) In connection with the Indian employment preference requirements of this clause, the
Contractor shall provide reasonable opportunities for training, incident to such employment. Such training shall include on-the—job, classroom, or apprenticeship training designed to increase the vocational effectiveness of an Indian employee.
(c) If the Contractor is unable to fill its employment and training opportunities after giving full consideration to Indians as required by this clause, the Contractor may satisfy those needs by selecting non-Indian persons in accordance with the clause of this contract entitled "Equal
Opportunity."
(d) If no Indian organizations…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .