This Invitation for Bid (IFB) document is issued by the Town of Needham, Massachusetts, Department of Public Works for the purchase and installation of a replacement truck scale system. The Town seeks bids for a complete precast concrete truck scale measuring 34 feet by 10 feet with a minimum capacity of 75 tons and concentrated load capacity of 80,000 pounds, including fabrication, installation, calibration, and removal of the existing scale. The scale must include rocker-column load cells, electronic indicators, surge protection systems, two 24-inch by 24-inch manways, and integration with existing office instrumentation. A pre-bid conference is scheduled for October 8, 2026, at 1:30 p.m. at the Recycling Transfer Station located at 1421 Central Avenue, Needham, Massachusetts. Written questions must be submitted by October 14, 2026, at 5:00 p.m., and sealed bids are due October 22, 2026, at 1:30 p.m. at the Department of Public Works Administration Office, 500 Dedham Avenue, Needham, Massachusetts. Contract award is anticipated for October 2026, with the contract term commencing upon execution and ending March 31, 2027. The selected contractor must complete fabrication, delivery, installation, and calibration within eight weeks of contract execution, with installation occurring within two consecutive working days of delivery.
Bidders must submit a 5% bid deposit with their proposals and provide proof of a minimum of three continuous years in business along with five project references of similar nature and scope completed within the last five years. The bid package includes two line items: the precast truck scale with installation priced as a lump sum and a five-year preventative maintenance and calibration agreement also priced as a lump sum. No price adjustments, fuel surcharges, or vehicle surcharges are permitted; all costs including freight must be included in the bid price and remain fixed. The selected scale manufacturer must have a minimum of 25 years of experience installing similar systems and maintain a physical servicing address no more than 50 miles from the project location. A 50% payment bond is required upon contract execution for contracts exceeding $25,000. The contractor must provide workers' compensation insurance, general liability coverage, and property damage insurance with the Town named as additionally insured, along with OSHA certification documentation and compliance with Massachusetts prevailing wage law requirements.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IFB 27DPW122C 1
Town of Needham Department of Public Works
Public Services Administration Building, 500 Dedham Avenue Needham, Massachusetts 02492
Telephone (781) 455-7550
ACKNOWLEDGEMENT OF RECEIPT
Release Date October 1, 2026
Bid Title Purchase & Installation of RTS Truck Scale
Bid Number 27DPW122C
Number of Documents
The Bid Package consists of 2 PDF documents. Returning this form confirms receipt of all the documents.
Pre-Bid Meeting October 8, 2026, at 1:30pm at the Recycling Transfer Station located at 1421 Central Ave. Needham, MA 02492
Questions Due October 14, 2026, at 5:00pm
Bids are Due October 22, 2026, at 1:30pm, Administration Office of the Department of Public Works located at the Public Services Administration Building, 500 Dedham Ave., Needham, MA, 02492
Please provide the requested information below as acknowledgment that you have received our bid package noted above. It is recommended that interested bidders complete this acknowledgment and return via email to dpwbids@needhamma.gov. Only by doing this, will the Town be able to provide notification of any addenda or answered questions relating to this bid. Only those companies or individuals shown on the Distribution Register will receive addenda to this bid. By completing and returning this acknowledgement will ensure you are recorded on the Distribution Register.
Proposals from companies or individuals not acknowledging the addenda may be rejected as not responsive.
Number of Company or Individual
Name / Title of Contact
Address
City/Town, State, Zip Code
Telephone Number
Fax Number
Email Address
Signature
Date
Addenda will be posted to the Town’s website. Please check the website for addenda before submitting your bid to the Town. Bidders who access the bid package from the Town’s website are responsible for checking the website periodically for any addenda that may be issued by the Town.
IFB 27DPW122C 2
Purchase & Installation of RTS Truck Scale
27DPW122C
Release Date October 1, 2026
Pre-Bid Conference
October 8, 2026, at 1:30pm at the Recycling Transfer Station located at 1421 Central Ave. Needham, MA 02492
Deadline for Questions October 14, 2026, at 5:00pm
Bids Due
October 22, 2026, at 1:30pm Director of Administration Public Service Administration Building 500 Dedham Ave. Needham, MA 02492
IFB 27DPW122C 3
(Advertised in the Hometown Weekly issue of Thursday October 1, 2026)
(Advertised on the MNPA’s website, Thursday October 1, 2026) (Published in Central Register issue of Wednesday September 30, 2026)
(Advertised in CommBuys on Thursday October 1, 2026)
LEGAL NOTICE
Town of Needham Invitation for Bid (IFB)
The Town of Needham is accepting sealed bids for Purchase & Installation of RTS Truck Scale. Copies of the Invitation for Bid (IFB) package will be available beginning October 1, 2026, at the Administration Office of the Department of Public Works at 500 Dedham Ave., Needham, MA 02492 during normal business hours or from the Town’s web site www.needhamma.gov/bids.aspx and will be available until submission deadline.
A pre-bid conference will be held on Thursday October 8, 2026, at 1:30pm, at the Recycling Transfer Station located at 1421 Central Ave. Needham, MA 02492. Attendance is strongly encouraged but not required.
Sealed bids must be submitted no later than 1:30PM, October 22, 2026, to the Administration Office of the Public Works Department, Town of Needham, 500 Dedham Ave., Needham, MA 02492. All bids must be accompanied by a bid deposit in an amount that is not less than five percent (5%) of the value of the bid. LATE BIDS WILL NOT BE CONSIDERED. Bids will be publicly opened after submission deadline on October 22, 2026, at 1:30pm. The Town reserves the right to reject any and all bids as determined to be in the best interests of the Town and to waive minor informalities. This legal notice is also posted on the Massachusetts Newspaper Publishers Association’s (MNPA) website at http://masspublicnotices.org/.
Kathleen King
Town Manager October 1, 2026
IFB 27DPW122C 4
Procurement in Brief
Primary Procurement Contact Katie Bamber, Administrative Analyst 781-455-7550 x72229
Contract Manager Matt DeMarrais, Superintendent: Recycling & Solid Waste Division
Bid Package Available
October 1, 2026 - Information and details of bidding requirements may be obtained at the Administration Office DPW, PSAB, 500 Dedham Ave., Needham, MA 02492, or online at the Town’s web site https://www.needhamma.gov/bids.aspx
Pre-Bid Meeting October 8, 2026, at 1:30pm - at the Recycling Transfer Station located at 1421 Central Ave.
Needham, MA 02492
Bid Deposit 5% bid deposit is required as part of bid
Deadline for Written Questions
October 14, 2026, at 5:00pm By Mail: DPW - 500 Dedham Avenue Needham, MA 02492
By Email: dpwbids@needhamma.gov Questions are to be clearly labeled as:
QUESTIONS - Purchase & Installation of RTS Truck Scale, 27DPW122C
Addenda
If any changes are made to this bid, an addendum will be issued. Addenda will be posted on the Town’s webpage and emailed to all bidders on record as having received the bid package.
When and where bids are due
October 22, 2026, at 1:30pm, Administration Office DPW, PSAB, 500 Dedham Ave., Needham, MA 02492.
LATE BIDS WILL NOT BE CONSIDERED
Where bids will be opened Charles River Room, PSAB, 500 Dedham Ave., Needham, MA, 02492, after submission deadline
Number of Required Paper Copies 1 original
Contract Award Anticipated October 2026 Approval of Town Manager and Town Counsel is
REQUIRED
Contract Length This Agreement shall be for a term commencing upon execution and ending March 31, 2027.
IFB 27DPW122C 5
Upon Award of Contract
Payment Bond 50% payment bond
Performance Bond Will NOT be Required
Insurance Refer to Contract Terms
* Submissions for written inquiries must be sent prior to the above date and time deadlines.
Any delivery received after the due date and time will not be addressed. The time/date stamp located in the receiving office will govern for the date and time requirements mentioned in the table above and throughout this document. Please allow enough time for delivery.
** The time for award may be extended by the Town. The Town reserves the right to change, delay, cancel, or expedite the contract award date. The Bidder agrees that the offer is effective for (a) at least ninety (90) calendar days from the opening date of the bids
(b) a contract is executed, or (c) this bid is cancelled, whichever of (a), (b) or (C) occurs first. The Town reserves the right to reject any and all bids as determined to be in the best interests of the Town and to waive minor informalities.
IFB 27DPW122C 6
PART 1 – GENERAL CONDITIONS AND SUBMISSION REQUIREMENTS
1.01 Intent
The Town of Needham (hereinafter referred to as the “Town”), acting through its Town Manager, invites highly qualified bidders to submit sealed bids to perform all labor necessary for Purchase & Installation of RTS Truck Scale.
All bids are subject to the provisions of M.G.L. Chapter 30, 39M. The Town will award the contract to the lowest responsible and eligible bidder as set forth in section 1.15. The Town of Needham reserves to itself the right to accept or reject any and all bids, or to allow or deny variations from these specifications.
Such actions will be deemed to be in the best interest of the Town. Unless sooner rejected or accepted, all bid proposals must be firm and continue in effect for a minimum of ninety (90) calendar days from the date of bid opening.
1.02 Proposed Contract Term
The initial term of this agreement shall commence upon execution of the contract and end March 31, 2027. The awarded vendor will be expected to build, ship, install, and calibrate a new truck scale within 8 (eight) weeks of contract execution. The successful Bidder must enter into the Form Agreement prepared by Town Counsel (Sample Available Online).
The Town may terminate the Contract at any time upon written notice for any reason including its own convenience or for cause, including but not limited to, failure to perform the work required under the contact, failure to document satisfactorily to the Town amounts being charged, failure to have any necessary local, State or Federal licenses and/or permits, failure to pay any and all required taxes, failure to comply with any local, State or Federal regulations pertaining to services to be provided, failure to promptly correct any performance or lack of performance which conflicts with the Town's use, and failure for satisfactory behavior of all staff and management. In the case of a termination for cause, the Town shall give the Contractor a written notice as provided in the Agreement.
1.03 Pre-Bid Conference and Requests for Interpretation
A pre-bid conference will be held on October 8, 2026, at 1:30pm at the Recycling Transfer Station located at 1421 Central Ave. Needham, MA 02492. Attendance is strongly encouraged but not required.
Bidders shall promptly raise the issue of any ambiguity, inconsistency or error, which they may discover upon examination of the bid documents, the work site or any other conditions which apply to the work.
Inquiries concerning any part of this Bid shall be directed to the individual(s) listed under the Procurement in Brief. Bidders should note that oral communications are not binding on the Town and only written responses by the Town will be considered. All requests/questions must be submitted in writing. Questions may be delivered by hand, or email as referenced under the Procurement in Brief by the deadline. Questions that may be asked during any pre-bid conference should also be sent in writing in order to receive an official response. Requests properly presented that in the opinion of the Town require interpretation, correction, or change in the Bid Documents will result in an issuance of an Addendum to the Bid Documents. Such Addendum shall subsequently become part of the contract. The Town will forward responses to all persons who are on record as receiving the bid package.
Questions received after the due date will not be responded to unless the Town determines it is necessary.
Bidders, please allow enough time for delivery.
1.04 Information About Changes to the Bid (Addenda)
In the event that changes/additions are made to this bid, an addendum will be issued to every person (entity) on record as receiving the bid package. Addenda will be emailed. Addenda will also be posted to the website. Please check back on the website for addendums before submitting your bid to the Town.
Bidders may not be notified individually of Addendums.
IFB 27DPW122C 7
1.05 Bid Submission
The bidder shall submit his/her proposal upon the bid forms supplied within these specifications. The bidder shall specify the unit prices as requested for each bid item. All bids shall be signed correctly with ink; in order to qualify, the bidder must provide bids for each required item within a section. All bids shall be submitted to the Director of Administration, Town of Needham, Administration Office, 500 Dedham Avenue, Needham, MA 02492. Each bid shall be sealed in an envelope on which is clearly indicated:
Name & Address of Bidder, IFB 27DPW122C, Purchase & Installation of RTS Truck Scale, due 1:30PM, October 22, 2026. All submitted bids shall include Invitation for Bids, Bid Information, Bid Scope of Work, and all Addenda issued, and all portions of the BID FORMS must be completed and submitted in order for a submission to be deemed acceptable. Bidders will submit insurance certificates validating current coverage at the time of bid submission. Bids received at the Administration Office after the time of opening of bids designated in the IFB will be returned to the bidder unopened. Bids will be publicly opened and read aloud after the bid due date in the Charles River Room at the Public Services Administration Building, 500 Dedham Avenue, Needham, MA 02492.
1.06 Bid Deposit
All bids must be accompanied by a bid deposit in an amount that is not less than five percent (5%) of the value of the bid. They shall be made payable to the Town of Needham and shall be in the form of certified check, treasurer’s or cashier’s check issued by a responsible bank or trust company, or a bid bond issued by a surety licensed to do business in the Commonwealth of Massachusetts; and shall be conditioned upon the faithful performance by the principal of the agreements contained in the bid.
1.07 Bid Form
All bids must be made on the attached bid forms.
Bids shall be firm for the duration of the contract. No price adjustments will be allowed. Fuel surcharges or vehicle charges or adjustments will not be allowed. Payment for materials and/or service will be made only after satisfactory performance or all requirements of the specification and upon approval by the Director of Public Works or his designate. The Town reserves the right to accept or reject any or all bids, wholly or in part, and to make the award in the best interest of the Town.
1.08 Bond Requirements
If the value of the contract is over $25,000 or more, the following shall apply:
LABOR & MATERIALS BOND (PAYMENT BOND)
Pursuant to M.G.L. c. 149, § 29, the Contractor shall furnish a payment bond from a surety company qualified to do business under the laws of the Commonwealth of Massachusetts and satisfactory to the Town, in an amount of one half of the total Contract price for payment for labor performed or furnished and materials used or employed therein, when the Contract is executed. The payment bond shall be on the form provided by the Town.
It is distinctly agreed and understood that any changes made in the drawings and specifications for this work, whether such changes increase or decrease the amount of work required, or any change in the manner or time of payments made by the OWNER to the CONTRACTOR, shall in no way void, release or affect the liability and surety on the bond given by the CONTRACTOR.
1.09 Insurance Requirement
Insurance Certificates indicating coverage for general liability, property damage, and workers’ compensation as outlined in Sample Agreement available online and must include the Town of Needham as additionally insured (at time of award). The selected bidder shall take out and maintain during the life of this contract Workers’ Compensation Insurance for all employees employed on the site of this project, IFB 27DPW122C 8 in a manner and to the extent provided by Chapter 152 of the General Laws and shall provide the Town with written evidence showing compliance with this statute at the time of award.
The selected Bidder shall indemnify and save the Town harmless from and against all claims, suits, damages and outlays resulting from or by reason of loss, damage or injury of or to any person or property, wherever located which shall be caused by any action or operation under this agreement.
1.10 OSHA Training
The bidder certifies that all employees to be employed at the worksite shall have successfully completed a course in construction safety and health approved by the United States Occupational Safety and Health Administration that is at least ten (10) hours in duration at the time the employee begins work and shall furnish documentation of successful completion of said course with the first certified payroll report for each employee (Chapter 306 of the Acts of 2004).
1.11 DCAMM Certification
DCAMM Certification as a General Contractor for this project is not required.
1.12 Statement of Compliance
The CONTRACTOR shall submit a Statement of Compliance stating that persons employed by the award recipient are paid in accordance with the provisions of Sections 26 to 27H of Chapter 149 of the General Laws (i.e. “The Prevailing Wage Law”).The selected Bidder will not be permitted to either assign or underlet the contract, nor assign either legally or equitably any monies there under, or its claim thereto without the previous written consent of the Town.
1.13 Prevailing Wage Rates
The state prevailing wage law, MGL Chapter 149, Section 27B requires contractors and subcontractors to submit certified payroll records to the Town. Contractors and subcontractors must submit weekly payroll records either by (1) first class mail, or (2) electronic mail. Furthermore, every weekly submittal of payroll records must contain a signed statement by the employer that indicates (1) that the records are correct, and (2) the rate of wages that each worker receives. Please feel free to contact the Department of Labor Standards at (617) 626-6953 if you have any questions. Questions about enforcement of the prevailing wage law may be directed to the Attorney General’s Fair Labor and Business Practices Division at (617) 727-3465.
1.14 Duration of Bid Prices
All bids are to remain valid for 90 days after the opening of the bids.
1.15 Contractor Selection
The Town will review all bids and will award the contract to the lowest responsible and eligible bidder.
The Town reserves to itself the right to accept or reject any and all bids, or to allow or deny variations from these specifications.
In the event that there is a tie bid between two (2) responsible and eligible bidders, the award of the contract will be determined by a coin toss. The bidder’s whose submission was received earliest shall be assigned “Heads” in the coin toss. In the event that there is a tie bid with three (3) or more responsible and eligible bidders, the award shall be made by a draw by lot limited to those bidders. The coin toss/draw by lot shall be scheduled within two (2) business days from when it was determined by the Town to be a tie bid. The bidders involved shall be given an opportunity to attend. The coin toss/drawing shall be witnessed by at least three (3) Town officials. The tie breaker event shall be held at the location of bid submission during regular business hours.
IFB 27DPW122C 9
Upon Vendor selection, the Town of Needham will mail to the selected Vendor(s), three (3) contracts to be executed by the Vendor(s) and returned to the Town of Needham with the appropriate insurance certificates. The Town of Needham will then counter execute the three (3) contracts and return one complete contract to the Vendor(s). The Town’s Standard Contract is available online. Bidders are expected to review the sample contract “Short Form Agreement”. Unless otherwise noted by the Town, the terms and conditions contained therein are NOT negotiable.
It is the intention of the Town of Needham not to award a contract under this or any other proposal if the Contractor cannot furnish satisfactory evidence that he/she has the ability and experience to perform this class of work and that he/she has sufficient capital and equipment to enable them to prosecute the work successfully and to complete it within the time named in the contract. The Town of Needham reserves the right to reject this or any other proposal or to award the contract as is deemed to be to the best interest of said Town.
1.16 General Safety, Licenses, & Performance
The contractor’s personnel working on this project must hold all necessary licenses and permits to perform the work required under this contract as required by the Town of Needham under the Commonwealth of Massachusetts regulations. The contractor must submit the names and all qualifying materials of the site supervisor that will be assigned to this project. All work will be done in accordance with applicable industry standards, codes and regulations, and/or manufacturer's specifications. Contractor is responsible for providing adequate safety measures during work to ensure protection of life and property. Any Town buildings, grounds and surrounding property damaged by the selected contractor will be restored to its original state, at the cost of the selected contractor.
The contractor shall be informed that there is a thirty (30) day cancellation clause in this contract for improper service. Complaints not rectified within a reasonable length of time from day of notice as determined by the Town may cause the Town to notify the contractor by registered or certified mail that the contract will be cancelled thirty days from the date of the letter. Any defective workmanship shown to be caused by improper or faulty installation shall cause the Contractor to correct, repair and/or replace all material and labor at no cost to the Town. The Contractor will warrant that all workmanship shall be first class and shall be performed by persons qualified and licensed in their respective trades.
Any additional work that is performed beyond this agreement must be approved by the appropriate Town authority. The absence of approval from the appropriate Town authority will be considered a violation of the contract.
1.17 Site Maintenance and Inspection
The selected contractor will be responsible for maintaining the work site in a safe and orderly fashion on a daily basis. The contractor is responsible for the proper securing of all items associated with the project, including but not limited to debris, tools, material, scaffolding, ladders, etc. The contractor is responsible for the repair or replacement of any item, equipment, space or area which may be damaged by the contractor during the execution of this project. The contractor is responsible for the removal and disposal of all debris and materials generated from this project.
1.18 Private Property
Before any work is performed on private property, the Contractor must have in his/her possession a RIGHT OF ENTRY form signed by the property owner. The Town may assist the Contractor in obtaining permission.
1.19 Dig Safe Law
Before proceeding with excavation operations, the Contractor shall notify the State of Massachusetts Underground Plant Damage Prevention System (Dig Safe) at 1-888-344-7233, and shall make such
IFB 27DPW122C 10
supplemental investigations.
1.20 Private Utilities Coordination
Coordination with private utilities is the sole responsibility of the contractor (including natural gas, electricity, telephone, cable, etc.). The contractor shall be responsible for notifying Dig Safe prior to any start of work. Any assistance the Town may offer in coordinating with private utilities shall not absolve the contractor’s responsibility to coordinate with private utilities as necessary to accomplish the contract work.
The contractor shall be responsible and liable for all damages to the existing utilities and structures.
1.21 Public Utilities Coordination
Coordination with public utilities is the sole responsibility of the contractor (including water, sewer, and drain). The contractor shall be responsible to call the Water, Sewer & Drain Inspectors at least 48 hours prior to the start of work to schedule said inspections at 781-455-7550, Mon.-Fri. during regular business hours. The Water Sewer & Drains Inspectors must inspect the work. Any assistance the Town may offer in coordinating the public utilities shall not absolve the contractor’s responsibility to coordinate with public utilities as necessary to accomplish the contract work. The contractor shall be responsible and liable for all damages to the existing utilities and structures. At the contractors request the Town will supply water from hydrants for work. The use and operation of Town of Needham fire hydrants is restricted to Town employees only. The Town will set up a fire hydrant connection assembly each day to supply water as needed. The contractor is responsible for proper connection to the hydrant assembly and may operate the click valve only.
1.22 Traffic Controls
The Contractor shall furnish all local Police Officers to direct traffic and to keep the traffic off any part of the roadway in which construction is being carried out on, as, in the opinion of the Town Engineer are necessary for such purpose. Arrangements for officers shall be made well in advance of the work schedule for each day. If for any reason the Contractor cancels work for that day, and the Needham Police Department is not given advance notice, the Contractor will be responsible for that officer's wages. If the contractor has performed work that has not been accepted by the town and has to be redone to meet the specification, then the contractor is responsible for the expense of the police details due to poor workmanship or warrantee issues. Except in the instance above, the Owner will reimburse the Contractor for all other police details. The contractor must submit payments directly to the Needham Police Department or other police department’s that have supplied officers to the job site and supply copies of invoices showing invoice has been paid to the Department of Public Works as proof of payment.
1.23 Material Disposal
The Contractor, at no additional cost to the Town, shall dispose of all material that has been removed from each location.
1.24 Quantities
Unless otherwise stated, the quantities set forth herein are ESTIMATES ONLY. Any quantities indicated on the Bid Price Form or elsewhere in the bid package are estimates only and are given solely as a basis for the comparison of bids. The Vendor shall have no claim for additional compensation, or refuse to do the work called for, or provide the requested items, by reason of the actual quantities involved being greater or lesser by any amount than those called for in the bid.
1.25 Subcontracting
The Contractor shall keep the work under his personal control and shall not assign by power of attorney or otherwise, or sublet the work or any part thereof, without the previous written consent of the Owner.
Should the Contractor require the services of one or more sub-contractors, the Contractor shall submit to the Owner, at the time of submittal of bids, the name and references for the sub-contractor(s) for review
IFB 27DPW122C 11
and approval by the Owner. Said sub-contractor(s) shall not begin any work or bring any equipment, etc., onto the site until such approval is given. Under no circumstances shall the Contractor sub-contract more than forty percent of the work on the project. The Contractor shall be responsible for the operations of any sub-contractor(s) and the sub-contractor shall be subject to the directions of the Contractor's Project Supervisor.
1.26 Invoices & Reporting
Upon verification that the work has been completed, invoices must be sent to Town of Needham, Administration Division, Department of Public Works, 500 Dedham Avenue, Needham, MA 02492 or submitted electronically to dpwadmin@needhamma.gov. Each bill shall contain a cover sheet listing the broken out labor and materials cost, and back-up documents including materials costs, and other relevant information. Certified payroll will be required. Invoices shall not be processed for payment until the above information is provided in a format acceptable to the Director of Administration or their designee. Invoices for on-call services must specify the cost of labor, hours worked, and cost of materials for each project.
Invoices shall be itemized by units and by location or project.
1.27 Payment
Payment shall be made on the amount of work performed based upon the unit prices placed on the bid forms. Payment shall be made upon submission of an invoice and acceptance of the work by the Director of Public Works, or his designated agent. The payment of these amounts shall be considered full and complete payment for all labor, material and equipment necessary, including traffic control, to perform the specified work.
The Town will not be responsible for payment of any charges not itemized to the Town’s satisfaction. Pre-payment is NOT allowed. Invoices must include the Town’s purchase order number.
Invoices for additional services must include the date and times of the work, the type of the services performed; the number of hours or units to be charged, and the name of the person who authorized the work.
1.28 CORI/SORI
See Article 30 of Sample Agreement.
1.29 Supplemental Equal Opportunity Anti-Discrimination & Affirmative Action Program
This contract is subject to the Supplemental Equal Opportunity Anti-Discrimination and Affirmative Action Program (EEO/AA) provisions attached to the Project Manual.
IFB 27DPW122C 12
1.30 Submission Requirements
Quality Requirements
All bidders must furnish proof of a minimum of three (3) continuous years in business.
All bidders must provide owner contact information for five (5) projects of similar nature and scope completed within the last five (5) years.
The bidder shall submit their proposal upon the bid forms supplied within these specifications. The bidder shall specify the unit prices as requested for each bid item. All bids shall be signed correctly with ink; in order to qualify, the bidder must provide bids for each required item within a section.
Submission Requirements
1. The bid is to be submitted and addressed as follows: Director of Administration, PSAB, 500 Dedham Ave., Needham, MA 02492.
2. The bid is to be clearly marked: IFB 27DPW122C, Purchase & Installation of RTS Truck Scale.
3. Bidder must acknowledge all addenda related to this IFB, if any.
4. Bidder must submit a completed Bid Form A: Bid Form or an exact copy, signed by an individual authorized to negotiate for and contractually bind the Bidder. All prices must be reflective of all costs for delivery. No price adjustments will be allowed. Fuel surcharges or vehicle surcharges or adjustments will not be allowed.
5. Bidder must submit a completed Bid Form B: Bidder Information Response form.
6. Bidder must submit a completed Bid Form C: Authentication Form.
7. Bidder must submit a signed Bid Form D: Certificate of Good Faith.
8. Bidder must submit a completed Bid Form E: Certificate of Compliance with Massachusetts Tax Laws or Certificate of Good Standing issued by the Massachusetts Department of Revenue.
9. Bidder must submit a completed Bid Form F: Certificate of Compliance for Public Construction More than $10,000.00.
10. Bidder must provide the required number of references. For each, provide the following: a contact person and title, customer’s name, address, telephone number, email, and a brief description of the actual services provided (sample format included in bid package).
11. Bidder must submit a completed Bid Form H: Certificate of Authority (attached) or Corporate Resolution; if applicable.
12. Bids must be received and time stamped no later than the deadline stated in the Procurement Schedule (Where and When Bids are Due). LATE BIDS WILL NOT BE CONSIDERED.
13. A Bid Deposit is required.
14. Delivery will be at the expense of the Bidder. Any and all damages that may occur due to packaging or shipping will be at the sole responsibility of the Bidder.
15. Any additional requirements as required in the Scope of Service.
The Town reserves the right to reject any and all bids as determined to be in the best interests of the Town and to waive minor informalities.
IFB 27DPW122C 13
PART 2 – SCOPE OF WORK
2.01 General
The Town of Needham is requesting bids for a replacement truck scale. The scale shall be furnished and installed completely, including the platform, load cells, indicators, surge voltage protection system, and integration with the existing office scale instrumentation and printer.
The equipment furnished and installed under this section shall be assembled, erected, and placed in proper operating condition in full conformity with the drawings, specifications, engineering data, instructions, and recommendations of the equipment manufacturer, unless otherwise noted by the Engineer.
The truck scale shall be a manufactured precast concrete truck scale and shall be furnished as a complete, integrated system by a manufacturer experienced in the design, construction, manufacture, and operation of electronic truck scale systems.
All equipment furnished under this section shall comply with the General Equipment Stipulations.
2.02 Governing Standards
The scale system shall have been issued a Certificate of Conformance by the National Type Evaluation Program (NTEP) and shall conform to all applicable federal, state, local, and industrial standards, including, but not limited to:
National Institute of Standards and Technology (NIST), Handbook 44, "Specifications, Tolerances, and Technical Requirements for Weighing and Measuring Devices."
Applicable Massachusetts regulations governing commercial weighing devices.
American Welding Society AWS D1.1, 2008.
Weighbridge structural steel and structural steel embedments shall conform to ASTM A36.
Reinforcing steel shall conform to ASTM A615, Grade 60.
Concrete mix for the scale deck shall be tested in accordance with applicable ASTM standards for air entrainment (ASTM C231), slump (ASTM C143), temperature (ASTM C1064), and compressive strength (ASTM C39).
Concrete flatwork for the scale deck shall be placed, consolidated, and finished in accordance with ACI 301. Finishing work shall conform to ACI CP-10 and shall be supervised by an ACI-certified concrete flatwork technician.
2.03 Materials, Finishes, and Electrical Requirements
All anchor bolts, nuts, and washers shall be carbon steel or comparable material and may be plated.
Sharp projections of cut or sheared ferrous metal edges that are not to be welded shall be ground as required to ensure proper paint adhesion.
All ferrous metal surfaces, except stainless steel or plated steel, shall be blast cleaned in the shop in accordance with the paint manufacturer's recommendations. All mill scale, rust, and contaminants shall be completely removed before shop primer is applied. Components of each module shall be cleaned to an SSPC-SP6 finish prior to painting.
All steel surfaces, except stainless steel or plated steel, shall be coated with PPG AUE-370 high-solids acrylic urethane, a two-component chemically cross-linked commercial coating system. The paint system shall be applied in accordance with the manufacturer's recommendations and the attached data sheet.
IFB 27DPW122C 14
Field painting beyond touch-up of damaged surfaces shall not be required.
Unless otherwise specified, the power supply to the equipment shall be a dedicated 120-volt, single-phase, 60 Hz connection. Where control voltages lower than the power supply voltage are required, suitable control power transformers shall be furnished.
2.04 Surge and Lightning Protection
The complete scale system shall be surge and lightning protected. Protection shall include a surge protection device that plugs into a standard 115 VAC outlet. Load cells shall be optically isolated and surge protected.
The scale shall have a dual-point ground rod system for grounding the weighbridge, power supply, and sectional controllers. Electrical diagrams showing the scale grounding and surge protection system shall be provided with the submittals.
The surge protection package shall be provided as a complete unit and shall be tested and approved by the scale manufacturer. Surge protection devices or components that are not designed or tested by the scale manufacturer as a complete system shall not be acceptable.
2.05 Submittals and Certified Drawings
Complete foundation and installation drawings, together with detailed specifications and data covering all materials, parts, devices, and accessories forming a part of the equipment furnished, shall be submitted in accordance with the Submittals section.
Drawings shall include all scale components, foundation details, pier loading information, and other information necessary for the design and installation of the scale foundation.
The new foundation installation shall be accompanied by six (6) sets of certified drawings prepared and certified by the manufacturer, provided in both hard copy and PDF format.
PART 3 – PRODUCTS
3.01 Scale Design and General Description
The scale shall be a 34-foot by 10-foot precast concrete deck, fully electronic truck scale with rocker-column load cells. The scale shall be a flat-top orthotropic design and shall not require side beams above the surface of the deck.
The equipment shall consist of components designed to function as an integrated system by a manufacturer experienced in the design, construction, manufacture of electronic components, and operation of equipment for the intended application.
3.02 Scale Capacity and Concentrated Load Capacity
The NTEP-approved scale shall have a minimum capacity of 75 tons and a minimum concentrated load capacity (CLC) of 80,000 pounds.
The maximum deflection for legal highway loads shall not exceed 1/1300th of the span, and bending stress in any member shall not exceed 20,000 psi at the rated CLC of 80,000 pounds.
IFB 27DPW122C 15
3.03 Weighbridge Design and Construction
The platform shall be 34 feet long and 10 feet wide and shall consist of a nominal 6-inch factory-poured and cured concrete deck reinforced by 8-inch structural steel wide-flange beam stringers running the full length of the module.
Side beams shall be 12-inch structural steel members with Nelson studs attached to the internal sides of each beam to create a composite connection between the concrete and steel.
The scale shall be an open-bottom design. Corrugated sheeting shall not be entombed within the modules.
Understructure components consisting of formed U's, bent plates, or a bottom pan shall not be used.
Steel deck scales and poured-in-place concrete deck scales will not be considered.
The scale shall be constructed to be installed in the existing 34-foot by 10-foot foundation as constructed.
No structural modifications to the existing foundation shall be required to accept the new scale unless specifically identified in the contract documents.
The truck scale deck shall be factory poured and steam cured and shall be delivered to the site ready for installation. The factory-poured deck shall have an ultimate compressive strength of 8,000 psi.
The weighbridge deck concrete system shall contain silica fume at a rate of at least 10 percent of the cementitious material and shall contain steel fiber reinforcement for tensile strength and impact protection.
A poured-in-place design will not be accepted. A weighbridge poured in place on-site and subsequently transported into the existing foundation will also not be permitted.
3.04 Galvanizing
The structural steel weighbridge, stringers, base plates, checking assembly, retrofit bumper plates, associated hardware, bumper bolts, and clamp plates shall be hot-dip galvanized steel.
The manufacturer shall provide cold galvanizing touch-up paint with delivery of the scale.
3.05 Manways
The scale deck shall incorporate two manways providing technician access to the interior of the pit.
Manways shall be located at the 20-foot end of each end module.
Each manway shall measure 24 inches by 24 inches and shall incorporate a 1/4-inch galvanized steel deck plate for egress into the existing pit foundation.
3.06 Checking System
The scale shall utilize longitudinal and lateral bumper checking and shall be completely self-checking.
Check rods and flexure checking plates shall not be used. Checking components shall be mechanically isolated from the load cells and load cell stands/base plates.
3.07 Load Cells, Controllers, and Diagnostics
The scale shall utilize rocker-column load cells. Each rocker-column load cell shall have a minimum gross rated capacity of 66,000 pounds.
IFB 27DPW122C 16
Load cells shall be constructed of stainless steel, completely hermetically sealed against moisture intrusion, and nitrogen filled to retard internal corrosion.
The load cells shall meet or exceed the following minimum specifications:
Minimum capacity: 66,000 lbs.
Design: Rocker column Rated output: 2 ± 0.1% mV/V NTEP accuracy class: IIIL, 10,000 divisions Combined error: ≤ ±0.0200% RO Temperature effect on sensitivity: ≤ ±0.0166%/°C Excitation voltage: 5 to 15 volts Zero balance: ≤ ±5.0% RO Insulation resistance: ≥5,000 megohms Compensated temperature range: -10°C to +40°C Operating temperature range: -40°C to +80°C Safe load limit: 200% of capacity Ultimate load: 300% of capacity Load cell material: Stainless steel Sealing: Hermetically sealed; cable entry sealed by glass-to-metal header Protection: NEMA 6P/IP69K
Each load cell shall be provided with shielded four-conductor cable with a polyurethane jacket. Load cell cabling shall be protected by stainless steel braided armor to protect against abrasion and rodent damage.
Load cell cables shall be hardwired to the load cells. Quick-disconnect load cell cable connectors on load cells or junction boxes shall not be acceptable.
Load cells shall have a 25-year warranty, including damage resulting from surge or lightning while the scale is being serviced by an authorized manufacturer's agent.
Load cell output shall be a DC analog signal. Digital-output load cells shall not be acceptable.
Each load cell shall be optically isolated through a smart sectional controller. PC boards shall be encapsulated in epoxy or similar material and housed in a Type 304 stainless steel enclosure rated NEMA 4X.
Access to the encapsulated board within the smart sectional controller enclosure shall be possible without the use of tools. Bolts, screws, or other hardware shall not be required to seal the smart sectional controller enclosure.
The scale shall have self-diagnostic capabilities capable of identifying load cell problems and failures and predicting potential failures to minimize downtime. Diagnostics shall measure load cell counts, not weight, and shall be used to determine reliability.
In the event of a load cell failure, the instrumentation shall identify the specific failed load cell. All troubleshooting shall be capable of being performed from within the scale house.
The new scale shall integrate with and utilize the existing instrumentation and printer.
IFB 27DPW122C 17
3.08 Delivery
The awarded contractor will be expected to build, ship, install, and calibrate a new truck scale within 8 (eight) weeks of contract execution.
PART 4 – EXISTING SCALE REMOVAL AND FOUNDATION PREPARATION
4.01 Existing Scale Removal and Foundation Preparation
The scale contractor shall remove the existing 34-foot by 10-foot steel weighbridge and place it on-site for the Town of Needham to re-purpose or scrap.
Removal of the existing weighbridge shall include disconnection and removal from the existing foundation by qualified scale technicians. Crane service required for removal shall be included in the contractor's scope.
Existing base plates and bolts shall be removed, and the existing piers shall be prepared by the manufacturer's technicians for installation of the new scale in the existing foundation.
Any sediment within the existing pit shall be removed by the Town of Needham.
Existing conduit shall be reused for load cell cabling where feasible.
PART 5 – EXECUTION
5.01 Installation Requirements
The scale shall be manufactured, furnished, and installed by a scale manufacturer with a minimum of 25 years of experience installing similar truck scale systems.
The scale manufacturer shall configure the scale system in accordance with the manufacturer's certified drawings. Anchor bolts shall be installed as required by the manufacturer's drawings.
Installation shall be performed by a scale company with a physical servicing address located no more than 50 miles from the project location.
5.02 Off-Loading and Installation
The scale manufacturer shall be responsible for off-loading and setting the new scale in the prepared foundation. A minimum 60-ton crane shall be provided as necessary for the installation.
The contractor shall coordinate removal of the existing scale, foundation preparation, delivery, off-loading, and installation so that the existing foundation is ready to receive the new weighbridge and load cells upon delivery.
5.03 Manufacturer's Field Services and Testing
Where scheduled, an experienced, competent, and authorized representative of the manufacturer shall provide field services for equipment furnished under this section.
An authorized manufacturer's representative shall provide the required scale certification for capacity and accuracy to the Engineer in accordance with applicable requirements of the Massachusetts Department of Weights and Measures and any other applicable state or county agency.
IFB 27DPW122C 18
5.04 Preventative Maintenance/ Calibration Agreement
The selected scale manufacturer must include pricing for a 5-year pre-paid maintenance agreement, which coincides with warranty. This shall include one scheduled visit per year with heavy capacity test unit with calibrations to state tolerances, paperwork deeming the scale is “legal for trade”, paperwork both emailed and written on-site illustrating calibration reports, seal on scale indicator, and any adjustments as required. This shall be priced as a lump sum for 5 years.
5.05 Personnel Training
An experienced, competent, and authorized representative of the manufacturer shall train the Owner's personnel in the operation, maintenance, and repair of the equipment specified in this section.
5.06 Warranty
The load cells shall be warranted for a minimum of 25 years, including damage resulting from lightning, while serviced by an authorized manufacturer's agent.
The weighbridge shall include a minimum five-year warranty.
All warranties shall be provided in accordance with the manufacturer's warranty statement and shall apply while the equipment is serviced by an authorized manufacturer's agent.
5.07 Installation Schedule and Freight
The new scale shall be installed and operational within two (2) consecutive working days following delivery, provided that the existing scale has been removed and the existing foundation is ready to receive the new scale.
Upon delivery of the new scale, the existing scale shall have been removed and the existing foundation shall be ready to accept the new weighbridge and load cells.
Freight costs shall be clearly identified and included as part of the bid price. Freight shall remain a fixed component of the bid price.
IFB 27DPW122C 19
PART 3 – CHECKLIST AND REQUIRED FORMS FOR SUBMISSION
Company Name: __________________________________________________
Bidder has completed and returned the Acknowledgment of Receipt form (via email).
Bidder has completed, signed, and enclosed the Bid Form A: Bid Price Form or an exact copy.
Bidder has completed, signed, and enclosed the Bid Form B: Bidder Information Response form.
Bidder has completed, signed, and enclosed the Bid Form C: Authentication Form.
Bidder has completed, signed, and enclosed the Bid Form D: Certificate of Good Faith.
Bidder has completed, signed, and enclosed the Bid Form E: Certificate of Compliance with Massachusetts Tax Laws or Certificate of Good Standing issued by the Massachusetts Department of Revenue.
Bidder has completed, signed, and enclosed the Bid Form F: Certificate of Compliance for Public Construction More than $10,000.00.
Bidder has provided at least five (5) references on the Bid Form G: Professional Reference Form of which at least three (3) are governmental units (municipal/county/regional district/state agency/special district).
If the bid submission is signed by someone other than the Owner/President of the company, a completed Bid Form H: Certificate of Authority of Corporate Resolution for the person who signed the proposal or a valid Corporate Resolution stating the individual has the authority to submit the proposal on behalf of the Company and can bind the Company to the contract if awarded.
The Bid Deposit (Bond) enclosed.
Bidder acknowledged all addenda, if any Addendum Number 1 dated ____________________ Addendum Number 2 dated ____________________ Addendum Number 3 dated ____________________ Addendum Number 4 dated ____________________ Addendum Number 5 dated ____________________
This form must be completed and filed with bid submission
IFB 27DPW122C 20
Bid Form A: Bid Sheet
27DPW122C - Purchase & Installation of RTS Truck Scale
A Precast Truck Scale: 34’x10’, 75-Ton Capacity (Lump Sum including fabrication, installation, calibration, manways, & removal of old scale)
B 5-Year Preventative Maintenance/ Calibration Agreement (Lump Sum)
C Total Proposed Contract Price (Lump Sum)
D Time of Completion (calendar days)
Bidder Acknowledges Addenda #: _______________________________
Company Name: _________________________________________ Number of Years in Business: _____
Address: _________________________________________
Authorized Signature: _________________________________________
Printed Name & Title: _________________________________________
IFB 27DPW122C 21
Bid Form B: Bidder Information Response
Legal Name of the Bidder: ____________________________________________________________
Company Name: ___________________________________________________________________
Company Address: _________________________________________________________________
City State Zip: ____________________________________________________________________
Company Web Address: _____________________________________________________________
Company Telephone: ________________________ Company Fax Number: ____________________
State of Incorporation (Date): ________________________________________________________
If the bidder is a partnership, give full names and addresses of all partners; and if an individual, give residential address if different from business address.
Company Contacts – Required
Individual submitting the bid: (This is the individual who should sign the Certificate of Good Faith)
Name: _________________________________ Title: __________________________________
Mailing Address: __________________________________________________________________
Telephone: __________________________________ Fax Number: _______________________
Email Address: ___________________________________________________________________
Individual to be contacted about the bid: (If different from the individual submitting the bid)
Name: _________________________________ Title: __________________________________
Mailing Address: __________________________________________________________________
Telephone: __________________________________ Fax Number: _______________________
Email Address: ___________________________________________________________________
Best Times to Contact: _____________________________________________________________
IFB 27DPW122C 22