27CSP033 Project Manual.pdf

PDF 9 MB Posted

Attached to
Competitive Sealed Proposal (CSP) for Burger Activity Center Baseball Improvements
Solicitation number
24-0030 Turf
Issued by
Travis County, Austin City, Texas

About this file

This Project Manual is prepared for the Austin Independent School District (AISD) Burger Baseball Improvements project located at 3200 Jones Road, Austin, Texas. The project consists of improvements to the existing baseball complex, including replacement of natural field turf with synthetic turf, replacement of all field fencing, upgrades to field lighting, demolition and replacement of the home-side dugout with a new sunken dugout and accessible ramp, addition of drinking fountains and lighting to both dugouts, addition of bullpens and batting cages on both home and visitor sides, new sidewalks and accessible ramps, new parking lot striping, seating area improvements including painting exposed steel, replacement of the PA system, press box siding replacement, addition of HVAC to the press box, and addition of a companion seat adjacent to ADA seating. The project is being delivered under a single prime contract with a stipulated sum (lump-sum) bid structure. The prebid meeting date, bid opening date, and location are to be determined and will be provided by the Architect. Bids must be received by 2:00 p.m. local time on the specified date. The successful bidder must begin work upon receipt of Notice to Proceed and complete the work within the contract time, which is to be specified by the bidder in the bid form. Prospective bidders must be prequalified by the Owner and properly licensed under applicable laws. Online procurement and contracting documents will be provided to prime bidders only. The project is currently at 100 percent Construction Documents stage as of October 2, 2026, prepared by WRA Architects, Inc., with consultants including Encotech Engineering Consultants (mechanical, electrical, and plumbing), Kimley-Horn (civil engineer), and others.

Bid security in the amount of five percent of the bid amount must be submitted with each bid. No bids may be withdrawn for 60 days after opening. The Owner reserves the right to reject any and all bids and to waive informalities and irregularities. The bid documents incorporate AIA Document A201-2017 General Conditions of the Contract for Construction with supplementary conditions modifying certain provisions. The contract documents include detailed specifications organized by CSI divisions covering general requirements, concrete, masonry, metals, thermal and moisture protection, finishes, specialties, equipment, furnishings, plumbing, HVAC, electrical, earthwork, exterior improvements, and utilities. The project includes allowances for PA system components (speakers, amplifier, mixer) to be owner-furnished and contractor-installed, as well as four alternates related to scoreboard replacement, stadium repainting, press box siding, and visitor's dugout enhancements. Substitution requests during the bidding phase must be submitted no later than 10 days prior to bid opening. Post-award substitutions are permitted under specific conditions with Architect and Owner approval. The contract requires 10 percent retainage from progress payments, payable 30 days after substantial completion, with final payment contingent upon submission of all closeout documentation, warranties, spare parts, certificates of occupancy, and inspection tags.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TITLE PAGE

00 01 01 - 1

PROJECT MANUAL

AISD Burger Baseball Improvements Austin, Texas AISD Project No. 24-0030 Turf

October 02, 2026 100% Construction Documents

Owner Austin Independent School District Telephone: 512-414-8940

Architect WRA Architects, Inc.

6000 Headquarters Drive, Suite 600 Plano, Texas 75024 Telephone: 214-750-0077

Mechanical, Electrical and Plumbing Engineers Encotech Engineering Consultants Telephone: 512-338-1101

Civil Engineer Kimley-Horn Telephone: 512-418-1771

WRA Architects, Inc. Project Number: 2588

END OF DOCUMENT

Austin ISD Burger Baseball Improvements WRA Architects, Inc.

Austin, Texas 2588 100% Construction Documents October 2, 2026

TABLE OF CONTENTS

DIVISION 22 – PLUMBING

22 00 00 Common Work Results for Plumbing 22 01 00 Commissioning of Plumbing Systems 22 05 17 Sleeves and Sleeve Seals for Plumbing Piping 22 05 19 Meters and Gages for Plumbing Piping 22 05 23.12 Ball Valves for Plumbing Piping 22 05 23.14 Check Valves for Plumbing Piping 22 05 29 Hangers and Supports for Plumbing Piping and Equipment 22 05 33 Heat Tracing for Plumbing Piping 22 05 53 Identification for Plumbing Piping and Equipment 22 07 19 Plumbing Piping Insulation 22 11 16 Domestic Water Piping 22 13 16 Sanitary Waste and Vent Piping 22 13 19 Sanitary Waste Piping Specialties 22 13 19.13 Sanitary Drains 22 14 13 Facility Storm Drainage Piping 22 14 23 Storm Drainage Piping Specialties 22 42 00 Commercial Plumbing Fixtures

DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING

23 00 00 Heating Ventilation and Air Conditioning 23 01 00 Commissioning of Mechanical Systems 23 05 00 Common Work Results for HVAC 23 05 13 Common Motor Requirements for HVAC Equipment 23 05 93 Testing, Adjusting, and Balancing for HVAC 23 07 13 Duct Insulation 23 09 26A Direct Digital Controls for Local Building Automation Systems Tridium-BACnet Web-Based 23 09 26C Commissioning of Building Automation System (Tridium-BACnet) 23 31 13 Metal Ducts 23 33 00 Air Duct Accessories 23 37 13 Air Diffusers, Registers and Grilles 23 81 13.11 Packaged Terminal Air-Conditioners, Through-Wall Units

DIVISION 26 – ELECTRICAL

26 00 00 Common Work Results for Electrical 26 01 00 Commissioning of Electrical Systems 26 05 19 Low-Voltage Electrical Power Conductors and Cables 26 05 33 Raceways and Boxes for Electrical Systems 26 05 53 Identification for Electrical Systems 26 22 13.11 Low-Voltage Distribution Transformers - General Purpose, 150-Degree C Rise 26 24 16 Panelboards 26 27 26 Wiring Devices 26 28 16 Enclosed Switches and Circuit Breakers 26 56 19 LED Exterior Lighting

END OF TABLE OF CONTENTS

Encotech Consulting Engineers, Inc.

TBPE Firm No: F1141

Div 22 Div 23 Div 26

10/02/2026

PROGRESS PRINT

RELEASED UNDER THE AUTHORITY OF:

(NOT INTENDED FOR BIDDING, PERMIT,

OR CONSTRUCTION PURPOSES)

MANESH NAIR, P.E.

DATE: 010-02-2026

TEXAS REGISTRATION No: 128718

PROGRESS PRINT

RELEASED UNDER THE AUTHORITY OF:

(NOT INTENDED FOR BIDDING, PERMIT,

OR CONSTRUCTION PURPOSES)

MANESH NAIR, P.E.

DATE: 010-02-2026

TEXAS REGISTRATION No: 128718

09/30/26

09/30/2026

AISD Burger Baseball and Softball Improvements WRA Architects, Inc

100% Construction Documents August 26, 2026

PROFESSIONAL SEALS PAGE - CIVIL

00 01 07D - 1

DOCUMENT 00 01 07D

PROFESSIONAL SEALS PAGE

The specification sections listed below were prepared by or under the direct supervision of the Civil Engineer:

KIMLEY-HORN AND ASSOCIATES SEAL

10814 Jollyville Road Building 4, Suite 200 Austin, Texas 78759

DIVISION 31 – EARTHWORK

31 11 00 Clearing and Grubbing 31 20 00 Earth Moving 31 23 33 Excavation Trenching and Backfill 31 25 13 Erosion and Sedimentation Control

DIVISION 33 – UTILITIES

33 11 15 33 41 00

High Density Polyethylene Pipe and Fittings Storm Utility Drainage Piping

Austin ISD Burger Baseball Improvements WRA Architects, Inc

100% Construction Documents October 02, 2026

TABLE OF CONTENTS

00 01 10 - 1

DOCUMENT 00 01 10

TABLE OF CONTENTS

INDEX OF ISSUES

100% Construction Documents ...................................................................................................... 02 October 2026

NUMBER NAME ISSUE DATE REVISED DATE

INTRODUCTORY INFORMATION

00 01 01 Title Page .................................................................................. 02 Oct 26 00 01 07 Seals Page ................................................................................. 02 Oct 26

00 01 10 Table of Contents ....................................................................... 02 Oct 26

DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS

00 11 13 Advertisement for Bid ................................................................. 02 Oct 26 00 21 13 Instructions to Bidders ................................................................ 02 Oct 26 00 26 00 Procurement Substitution Procedures ........................................ 02 Oct 26 00 41 13 Bid Form - Stipulated Sum (Single Prime Contract) ................... 02 Oct 26 00 72 00 General Conditions ..................................................................... 02 Oct 26 00 73 00 Supplementary Conditions ......................................................... 02 Oct 26

DIVISION 01 – GENERAL REQUIREMENTS

01 10 00 Summary .................................................................................. 02 Oct 26 01 21 00 Allowances ................................................................................. 02 Oct 26 01 23 00 Alternates .................................................................................. 02 Oct 26 01 25 00 Substitution Procedures ............................................................. 02 Oct 26 Substitution Request Form ................................................ 02 Oct 26 01 26 00 Contract Modification Procedures .............................................. 02 Oct 26 01 29 00 Payment Procedures .................................................................. 02 Oct 26 01 31 00 Project Management and Coordination (AISD) .......................... 02 Oct 26 01 32 00 Construction Progress Documentation (AISD) ........................... 02 Oct 26 01 32 33 Photographic Documentation ..................................................... 02 Oct 26 01 33 00 Submittal Procedures ................................................................. 02 Oct 26 01 40 00 Quality Requirements ................................................................. 02 Oct 26 01 42 00 References ................................................................................. 02 Oct 26 01 50 00 Temporary Facilities and Controls (AISD) .................................. 02 Oct 26 01 60 00 Product Requirements ................................................................ 02 Oct 26 01 65 00 General Commissioning Requirements (AISD) .......................... 02 Oct 26 01 73 00 Execution .................................................................................. 02 Oct 26 01 74 19 Construction and Demolition Waste Management (AISD) .......... 02 Oct 26 01 77 00 Closeout Procedures (AISD) ...................................................... 02 Oct 26 01 78 23 Operation and Maintenance Data (AISD) ................................... 02 Oct 26 01 78 39 Project Record Documents (AISD) ............................................. 02 Oct 26 01 79 00 Demonstration and Training (AISD) ........................................... 02 Oct 26 01 81 13 Sustainable Construction Requirements (AISD) ......................... 02 Oct 26 Sustainability Scorecard .................................................... 02 Oct 26

DIVISION 02 – EXISTING CONDITIONS

02 41 13 Selective Site Demolition ............................................................ 02 Oct 26

DIVISION 03 – CONCRETE

03 30 35 Under Slab Sheet Vapor Retarder .............................................. 02 Oct 26

DIVISION 04 – MASONRY

04 20 00 Unit Masonry .............................................................................. 02 Oct 26

NUMBER NAME ISSUE DATE REVISED DATE

00 01 10 - 2

DIVISION 05 – METALS

05 50 00 Metal Fabrications ...................................................................... 02 Oct 26 05 52 13 Pipe and Tube Railings .............................................................. 02 Oct 26

DIVISION 06 – WOODS, PLASTICS, AND COMPOSITES

06 10 53 Miscellaneous Rough Carpentry ................................................ 02 Oct 26

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

07 13 26 Self-Adhering Sheet Waterproofing ............................................ 02 Oct 26 07 41 13.13 Formed Metal Roof Panels ......................................................... 02 Oct 26 07 42 13.13 Formed Metal Fence Panels ...................................................... 02 Oct 26 07 46 46 Fiber Cement Siding ................................................................... 02 Oct 26 07 92 00 Joint Sealants ............................................................................. 02 Oct 26

DIVISION 08 – OPENINGS NOT USED

DIVISION 09 – FINISHES

09 61 16 Concrete Floor Sealing ............................................................... 02 Oct 26 09 91 13 Exterior Painting ......................................................................... 02 Oct 26 09 96 00 High-Performance Coatings ....................................................... 02 Oct 26 09 96 53 Elastomeric Coatings ................................................................. 02 Oct 26

DIVISION 10 – SPECIALTIES

10 14 00 Signage .................................................................................. 02 Oct 26 10 14 19 Dimensional Letter Signage ....................................................... 02 Oct 26 10 99 00 Miscellaneous Specialties .......................................................... 02 Oct 26

DIVISION 11 – EQUIPMENT

11 68 34 Baseball and Softball Field Equipment ....................................... 02 Oct 26 11 68 43 Exterior Scoreboards .................................................................. 02 Oct 26

DIVISION 12 – FURNISHINGS

12 63 13 Stadium and Arena Bench Seating ............................................ 02 Oct 26

DIVISIONS 13 – 21 NOT USED

DIVISION 22 – PLUMBING

22 00 00 Common Work Results for Plumbing ......................................... 02 Oct 26 22 01 00 Commissioning of Plumbing Systems ........................................ 02 Oct 26 22 05 17 Sleeves and Sleeve Seals for Plumbing Piping .......................... 02 Oct 26 22 05 19 Meters and Gages for Plumbing Piping ...................................... 02 Oct 26 22 05 23.12 Ball Valves for Plumbing Piping .................................................. 02 Oct 26 22 05 23.14 Check Valves for Plumbing Piping ............................................. 02 Oct 26 22 05 29 Hangers and Supports for Plumbing Piping and Equipment....... 02 Oct 26 22 05 33 Heat Tracing for Plumbing Piping ............................................... 02 Oct 26 22 05 53 Identification for Plumbing Piping and Equipment ...................... 02 Oct 26 22 07 19 Plumbing Piping Insulation ......................................................... 02 Oct 26 22 11 16 Domestic Water Piping ............................................................... 02 Oct 26 22 13 16 Sanitary Waste and Vent Piping ................................................. 02 Oct 26 22 13 19 Sanitary Waste Piping Specialties .............................................. 02 Oct 26 22 13 19.13 Sanitary Drains ........................................................................... 02 Oct 26 22 14 13 Facility Storm Drainage Piping ................................................... 02 Oct 26 22 14 23 Storm Drainage Piping Specialties ............................................. 02 Oct 26 22 42 00 Commercial Plumbing Fixtures ................................................... 02 Oct 26

NUMBER NAME ISSUE DATE REVISED DATE

00 01 10 - 3

DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING

23 00 00 Heating Ventilation and Air Conditioning .................................... 02 Oct 26 23 05 00 Common Work Results for HVAC .............................................. 02 Oct 26 23 05 13 Common Motor Requirements for HVAC Equipment ................. 02 Oct 26 23 05 93 Testing, Adjusting, and Balancing for HVAC .............................. 02 Oct 26 23 07 13 Duct Insulation ............................................................................ 02 Oct 26 23 09 26A Direct Digital Controls for Local Building Automation Systems Tridium-BACnet Web-Based .............................. 02 Oct 26 23 31 13 Metal Ducts ................................................................................ 02 Oct 26 23 33 00 Air Duct Accessories .................................................................. 02 Oct 26 23 37 13 Air Diffusers, Registers and Grilles ............................................. 02 Oct 26 23 81 13.11 Packaged Terminal Air-Conditioners, Through-Wall Units ......... 02 Oct 26

DIVISIONS 24 – 25 NOT USED

DIVISION 26 – ELECTRICAL

26 00 00 Common Work Results for Electrical .......................................... 02 Oct 26 26 01 00 Commissioning of Electrical Systems ......................................... 02 Oct 26 26 05 19 Low-Voltage Electrical Power Conductors and Cables .............. 02 Oct 26 26 05 33 Raceways and Boxes for Electrical Systems .............................. 02 Oct 26 26 05 53 Identification for Electrical Systems ............................................ 02 Oct 26 26 24 16 Panelboards ............................................................................... 02 Oct 26 26 27 26 Wiring Devices ........................................................................... 02 Oct 26 26 28 16 Enclosed Switches and Circuit Breakers .................................... 02 Oct 26

DIVISIONS 27 – 30 NOT USED

DIVISION 31 – EARTHWORK

31 11 00 Clearing and Grubbing (C) ......................................................... 02 Oct 26 31 20 00 Earth Moving (C) ........................................................................ 02 Oct 26 31 23 33 Excavating, Trenching, and Backfilling (C) ................................. 02 Oct 26 31 25 13 Erosion and Sedimentation Control (C) ...................................... 02 Oct 26

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 13 13 Concrete Paving ......................................................................... 02 Oct 26 32 18 13 Synthetic Grass Surfacing - Baseball and Softball ..................... 02 Oct 26 32 31 13 Chain Link Fences and Gates .................................................... 02 Oct 26 32 31 30 Welded Metal Gates ................................................................... 02 Oct 26

DIVISION 33 – UTILITIES

33 11 15 High Density Polyethylene (HDPE) Pipe and Fittings (C) ........... 02 Oct 26 33 41 00 Storm Utility Drainage Piping (C) ................................................ 02 Oct 26

DIVISIONS 34 – 49 NOT USED

END OF TABLE OF CONTENTS

ADVERTISEMENT FOR BIDS

00 11 13 - 1

DOCUMENT 00 11 13

ADVERTISEMENT FOR BIDS

1.1 PROJECT INFORMATION

A. Notice to Bidders: Qualified bidders may submit bids for project as described in this Document. Submit bids according to the Instructions to Bidders.

B. Project Identification: Burger Baseball Improvements, 3200 Jones Road, Austin, Texas 78745.

C. Architect: WRA Architects, Plano, Texas.

D. Project Description: Project consists of improvements to existing baseball complex.

E. Construction Contract: Bids will be received for the following Work:

1. General Contract (all trades).

1.2 BID SUBMITTAL AND OPENING

A. Owner will receive sealed lump sum bids until the bid time and date at the location given below. Owner will consider bids prepared in compliance with the Instructions to Bidders issued by Owner, and delivered as follows:

1. Bid Date: ________________.

2. Bid Time: 2:00 p.m., local time.

3. Location: ________________.

B. Bids will be thereafter publicly opened and read aloud.

1.3 BID SECURITY

A. Bid security shall be submitted with each bid in the amount of 5 percent of the bid amount. No bids may be withdrawn for a period of 60 days after opening of bids. Owner reserves the right to reject any and all bids and to waive informalities and irregularities.

1.4 PREBID MEETING

A. Prebid Meeting: A Prebid meeting for all bidders will be held at _________ on _________ at 10:00 a.m., local time. Prospective prime bidders are requested to attend.

1. Bidders' Questions: Architect will provide responses at Prebid conference to bidders' questions received up to two business days prior to conference.

1.5 DOCUMENTS

A. Online Procurement and Contracting Documents: Obtain access after _________, by contacting Architect, or reprographic house address. Online access will be provided to prime bidders only.

1.6 TIME OF COMPLETION

A. Successful bidder shall begin the Work on receipt of the Notice to Proceed and shall complete the Work within the Contract Time.

1.7 BIDDER'S QUALIFICATIONS

A. Bidders must be prequalified by Owner.

B. Bidders must be properly licensed under the laws governing their respective trades and be able to obtain insurance and bonds required for the Work. .

INSTRUCTIONS TO BIDDERS

00 21 13 - 1

DOCUMENT 00 21 13

INSTRUCTIONS TO BIDDERS

1.1 INSTRUCTIONS TO BIDDERS

A. AIA Document A701, "Instructions to Bidders," is hereby incorporated into the Procurement and Contracting Requirements by reference.

PROCUREMENT SUBSTITUTION PROCEDURES

00 26 00 - 1

DOCUMENT 00 26 00

PROCUREMENT SUBSTITUTION PROCEDURES

1.1 DEFINITIONS

A. Procurement Substitution Requests: Requests for changes in products, materials, equipment, and methods of construction from those indicated in the Procurement and Contracting Documents, submitted prior to receipt of bids.

B. Substitution Requests: Requests for changes in products, materials, equipment, and methods of construction from those indicated in the Contract Documents, submitted following Contract award. See Section 01 25 00 "Substitution Procedures" for conditions under which Substitution requests will be considered following Contract award.

1.2 QUALITY ASSURANCE

A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.

1.3 PROCUREMENT SUBSTITUTIONS

A. Procurement Substitutions, General: By submitting a bid, the Bidder represents that its bid is based on materials and equipment described in the Procurement and Contracting Documents, including Addenda.

Bidders are encouraged to request approval of qualifying substitute materials and equipment when the Specifications Sections list materials and equipment by product or manufacturer name.

B. Procurement Substitution Requests will be received and considered by Owner when the following conditions are satisfied, as determined by Architect; otherwise requests will be returned without action:

1. Extensive revisions to the Contract Documents are not required.

2. Proposed changes are in keeping with the general intent of the Contract Documents, including the level of quality of the Work represented by the requirements therein.

3. The request is fully documented and properly submitted.

1.4 SUBMITTALS

A. Procurement Substitution Request: Submit to Architect. Procurement Substitution Request must be made in writing by prime contract Bidder only in compliance with the following requirements:

1. Requests for substitution of materials and equipment will be considered if received no later than 10 days prior to date of bid opening.

2. Submittal Format: Submit three copies of each written Procurement Substitution Request, using form bound in Project Manual.

3. Submittal Format: Submit Procurement Substitution Request, using format provided on Project

Web site.

a. Identify the product or the fabrication or installation method to be replaced in each request.

Include related Specifications Sections and drawing numbers.

b. Provide complete documentation on both the product specified and the proposed substitute, including the following information as appropriate:

1) Point-by-point comparison of specified and proposed substitute product data, fabrication drawings, and installation procedures.

2) Copies of current, independent third-party test data of salient product or system characteristics.

3) Samples where applicable or when requested by Architect.

4) Detailed comparison of significant qualities of the proposed substitute with those of the Work specified. Significant qualities may include attributes such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.

5) Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.

6) Research reports, where applicable, evidencing compliance with building code in effect for Project, from ICC-ES.

PROCUREMENT SUBSTITUTION PROCEDURES

00 26 00 - 2

7) Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed by Owner and separate contractors, which will become necessary to accommodate the proposed substitute.

c. Provide certification by manufacturer that the substitute proposed is equal to or superior to that required by the Procurement and Contracting Documents, and that its in-place performance will be equal to or superior to the product or equipment specified in the application indicated.

d. Bidder, in submitting the Procurement Substitution Request, waives the right to additional payment or an extension of Contract Time because of the failure of the substitute to perform as represented in the Procurement Substitution Request.

B. Architect's Action:

1. Architect may request additional information or documentation necessary for evaluation of the

Procurement Substitution Request. Architect will notify all bidders of acceptance of the proposed substitute by means of an Addendum to the Procurement and Contracting Documents.

C. Architect's approval of a substitute during bidding does not relieve Contractor of the responsibility to submit required shop drawings and to comply with all other requirements of the Contract Documents.

6000 Headquarters Drive, Suite 600 (214) 750-0077 Plano, TX 75024 wraarchitects.com

Substitution Request Form (During the Bidding Phase)

Project Name: Date of Request:

Architect: Requestor:

Address: Address:

Spec Section No: Contact Name:

Spec Section Name: Phone Number:

Email Address:

Please fill out information on BOTH the specified item AND the proposed substitution in order for the substitution request to be processed.

Specified Item Proposed Substitution

Product Name: Product Name:

Product Description: Product Description:

Manufacturer: Manufacturer:

Product Rep Name

(Optional):

Rep Email (Optional):

Trade Name: Trade Name:

Series or Line: Series or Line:

Model No: Model No:

Dimensions: Dimensions:

A/E’s Review and Action: A/E Reviewer:

Signature:

Date of Response:

Approved Approved as Noted Rejected – Use Specified Materials Incomplete Form – Use Specified Materials Received after 7 days before Bid Date – Use Specified Materials

Functional

Clearances:

Functional

Clearances:

Maintenance Info:

Warranty Info:

Other Info:

Attached Data

Sheets for Side-by-

Side Comparison:

Yes

BID FORM - STIPULATED SUM (SINGLE-PRIME CONTRACT)

00 41 13 - 1

SECTION 00 41 13

BID FORM - STIPULATED SUM (SINGLE-PRIME CONTRACT)

1.1 BID INFORMATION

A. Bidder: ____________________________________________________.

B. Project Name: Burger Baseball Improvements, Austin, Texs.

C. Architect: WRA Architects, Plano, texas.

1.2 CERTIFICATIONS AND BASE BID

A. Base Bid, Single-Prime (All Trades) Contract: The undersigned Bidder, having carefully examined the Procurement and Contracting Requirements, Conditions of the Contract, Drawings, Specifications, and all subsequent Addenda, as prepared by the Architect and Architect's consultants, having visited the site, and being familiar with all conditions and requirements of the Work, hereby agrees to furnish all material, labor, equipment and services, including all scheduled allowances, necessary to complete the construction of the above-named project, according to the requirements of the Procurement and Contracting Documents, for the stipulated sum of:

1. ________________________________________________ Dollars ($______________).

1.3 BID GUARANTEE

A. The undersigned Bidder agrees to execute a contract for this Work in the above amount and to furnish surety as specified within 10 days after a written Notice of Award, if offered within 60 days after receipt of bids, and on failure to do so agrees to forfeit to Owner the attached cash, cashier's check, certified check, U.S. money order, or bid bond, as liquidated damages for such failure, in the following amount constituting five percent (5%) of the Base Bid amount above:

1. ________________________________________________ Dollars ($______________).

B. In the event Owner does not offer Notice of Award within the time limits stated above, Owner will return to the undersigned the cash, cashier's check, certified check, U.S. money order, or bid bond.

1.4 SUBCONTRACTORS AND SUPPLIERS

A. The following companies shall execute subcontracts for the portions of the Work indicated:

1. Concrete Work: ________________________________________________________.

2. Masonry Work: ________________________________________________________.

3. Roofing Work: _________________________________________________________.

4. Plumbing Work: ________________________________________________________.

5. HVAC Work: __________________________________________________________.

6. Electrical Work: _________________________________________________________.

1.5 TIME OF COMPLETION

A. The undersigned Bidder proposes and agrees hereby to commence the Work of the Contract Documents on a date specified in a written Notice to Proceed to be issued by Architect, and shall fully complete the Work within <Insert number> calendar days.

1.6 ACKNOWLEDGEMENT OF ADDENDA

A. The undersigned Bidder acknowledges receipt of and use of the following Addenda in the preparation of this Bid:

1. Addendum No. 1, dated ____________________.

2. Addendum No. 2, dated ____________________.

3. Addendum No. 3, dated ____________________.

4. Addendum No. 4, dated ____________________.

BID FORM - STIPULATED SUM (SINGLE-PRIME CONTRACT)

00 41 13 - 2

1.7 CONTRACTOR'S LICENSE

A. The undersigned further states that it is a duly licensed contractor, for the type of work proposed, in <Insert Project jurisdiction>, and that all fees, permits, etc., pursuant to submitting this proposal have been paid in full.

1.8 SUBMISSION OF BID

A. Respectfully submitted this ____ day of ____________, <Insert year>.

B. Submitted By:_______________________________________(Name of bidding firm or corporation).

C. Authorized Signature:___________________________________(Handwritten signature).

D. Signed By:______________________________________________(Type or print name).

E. Title:__________________________________(Owner/Partner/President/Vice President).

F. Street Address:___________________________________________________________.

G. City, State, Zip:__________________________________________________________.

H. Phone:_________________________________________________________________.

I. License No.:____________________________________________________________.

END OF DOCUMENT 00 41 13

GENERAL CONDITIONS - 2017

00 72 00 - 1

DOCUMENT 00 72 00

GENERAL CONDITIONS

1.1 GENERAL CONDITIONS

A. The "General Conditions of the Contract for Construction", AIA Document A201, 2017 edition, Articles 1 through 15 inclusive, is a part of this Contract, and is available for review from the Architect. The General Conditions and all modifications listed in Section 00 73 00 shall apply to all various subcontracts and sub-subcontractors.

B. Refer to Document 00 73 00 for Supplementary Conditions.

C. Should the general conditions or supplementary conditions be in conflict with the Owner-Contractor agreement, the Owner-Contractor agreement shall govern.

SUPPLEMENTARY CONDITIONS

00 73 00 - 1

DOCUMENT 00 73 00

The following supplements and modifies the "General Conditions of the Contract for Construction" (AIA Document A201-2017) which is part of the Contract Documents (the "Contract").

Division 01 sections expand and delineate additional requirements contained in the general and supplementary conditions.

ARTICLE 1 GENERAL PROVISIONS

1.1 Basic Definitions

Add the following to subparagraph 1.1.3:

1.1.3.1 Observations by the Owner or Architect of "Work", as defined in subparagraph 1.1.3, shall not include temporary structures, such as scaffolding, lifts, shoring and bracing; nor shall the observations by the Owner or Architect of the "Work" be interpreted to convey responsibility to the Owner or Architect for jobsite safety.

Add the following to subparagraph 1.1.6

1.1.6.2 Division 01 sections apply to all sections of the Specifications.

Add the following to paragraph 1.1:

1.1.9 "Approved equal"; and phrases of similar meaning and intent shall require written approval of the Architect of the product or materials referred to, and no substitution or variation from the requirements of the Specification shall be made unless so approved.

1.1.10 "Provide" shall mean, except as otherwise defined, to furnish and install, including delivery, uncrating, connecting and anchor in place, complete and ready for intended use, as applicable in each instance.

1.1.11 "Furnish" shall mean to supply and/or fabricate and deliver material(s) to Site ready for unloading, unpacking, assembling and/or installing, etc. for acceptance by Owner or Architect as applicable in each instance except as otherwise defined.

1.1.12 "Install" shall describe, except as otherwise defined, operations at the project site including receiving, uncrating, unloading, unpacking, assembling, erecting, placing, connecting, anchoring, applying, working to dimension, finishing, curing, protecting, cleaning, adjusting, testing (if required), placing, and similar operations, as applicable in each instance, that complete and ready the item(s) for its intended use(s).

1.1.13 "Installer" shall refer to the entity (person or firm) engaged by the Contractor or its subcontractor or sub-subcontractor for the performance of a particular unit or erection, application and similar required operations. It is a general requirement that such entities (Installers) be expert in operations they are engaged to perform.

1.1.14 "By others", "by Owner", "NIC" (Not In Contract), or "existing" indicates work not required to be done by this Contractor under this Contract.

1.1.15 "Current" or "latest", when used in regard to building codes and manufacturer’s instructions, shall mean the edition in effect as of the date of the contract documents, unless otherwise specified or noted.

1.2 Correlation And Intent Of The Contract Documents

Add the following to paragraph 1.2:

1.2.4 Should any contradiction, ambiguity, error or inconsistency appear in or between any of the Contract Documents, the Contractor shall, before proceeding with the Work in question, notify the

00 73 00 - 2

Architect and request an interpretation. In no case shall he proceed with the affected Work until advised by the Architect.

1.2.5 If the Contractor fails to make a request for interpretation of errors, discrepancies or conflicts in the Drawings or Specifications, no excuse will be accepted for failure to carry out the work in a satisfactory manner, as interpreted by the Architect. In all cases, the Contractor will be deemed to have estimated on the highest quality materials and most expensive way of doing Work unless he has asked for and obtained written decision as to which methods or materials will be required.

1.2.6 Each and every trade or subcontractor will be deemed to have familiarized itself with existing conditions and Drawings of this Project, including Architectural, Mechanical, and Electrical Work, so as to avoid errors, omissions, and misinterpretations. No additional compensation will be authorized for alleged errors, omissions and misinterpretations, whether they are a result of failure to observe this requirement or not.

1.2.7 The Contract Documents are complementary and what is required by any one shall be as binding as if required by all. Portions of the Work which can best be illustrated by the Drawings may not be included in the Specifications, and portions best described by Specification may not be depicted on the Drawings. All items necessary to erect a complete building or to complete work specified under each separate contract, shall be provided whether specified or shown.

1.2.8 The Specifications and Drawings include the entire facility. Where items of material, equipment and labor are referred to in the singular, such item or items shall be provided in the quantity necessary for the proper completion of the facility.

1.2.9 Wherein existing field conditions are visible, i.e., accessible through normal methods of observation and investigation, and such observed conditions are at variance with or are not indicated on the Drawings, the Contractor and all his subcontractors shall be held to have verified such conditions and have accounted for same.

ARTICLE 2 OWNER

2.3 Information And Services Required Of Owner

Delete subparagraph 2.3.6 and substitute the following:

2.3.6 The Owner shall make available to the Contractor, PDF files of the Drawings and Specifications for download from the designated information exchange website. Contractor shall reproduce, at his own expense, prints he and his subcontractors, suppliers and others require to perform the Work.

ARTICLE 3

CONTRACTOR

3.2 Review Of Contract Documents And Field Conditions By Contractor

3.2.2 Add the following to subparagraph 3.2.2:

3.2.2.1 The Contractor shall carefully study and compare the Contract Documents with each other and with information furnished by the Owner pursuant to subparagraph 2.2.3, within thirty (30) days after award of Contract, and shall at once report to the Architect errors, inconsistencies or omissions discovered.

3.2.2.2 If a dimensional discrepancy exists, Contractor shall take field measurements required for proper fabrication and installation of work. Upon commencement of any item of work, Contractor shall be responsible for dimensions related to such item of Work and shall make any corrections necessary to make work properly fit at no additional cost to Owner.

3.2.2.3 Before ordering any material or doing any work, Contractor shall verify dimensions and check conditions in order to assure himself that they properly reflect those on the Drawings. Any inconsistency shall be brought to attention of the Architect. In the event that discrepancies occur between ordered material and actual conditions, of which Architect was not notified beforehand, costs to correct such discrepancies shall be borne by Contractor.

3.4 Labor And Materials

00 73 00 - 3

3.4.1 Add the following to subparagraph 3.4.1:

3.4.1.1 All materials shall be delivered and stored in authorized locations in unopened containers and in ample quantity to prevent delay. Ordering of materials shall be made well in advance so as not to hinder the progress of work. Manufacturer’s directions for storage and use shall be carefully read and followed. Grade marks, labels, etc., shall be kept readable.

Add the following to subparagraph 3.4.2:

3.4.2.1 After the Contract has been executed the Owner and the Architect will consider a formal request for the substitution of products in place of those specified only under the conditions set forth in the General Requirements (Division 01 of the Specifications), only for items not specifically listed as "No Substitutions Permitted", and only as approved in writing by both the Owner and the Architect.

3.4.2.2 Substitutions shall be made only upon written approval of the Architect and Owner. In all cases, the Architect and Owner shall be the sole judge as to whether a proposed product is to be approved, and the Contractor shall have the burden of proving that substitutions proposed are equal to the items specified, to the satisfaction of the Architect and Owner.

3.4.2.3 The Contractor shall have and make no claim for an extension of time or for damages by reason of the time taken by the Architect in considering a product proposed by the Contractor or by reason of the Architect’s failure to approve a product proposed by the Contractor.

3.8 Allowances

Add the following to paragraph 3.8:

3.8.4 The contractor shall waive all claims for additional costs related to allowance items such as permit fees, tap fees, etc. whose amounts are not specifically identified in the Bid Proposal or documents or contracts.

3.11 Documents And Samples At The Site

Add the following to paragraph 3.11:

3.11.1 The "Record" set of Drawings and Specifications shall be neatly and accurately maintained up to date at all times. All changes of every type and nature shall be recorded on the Drawings or noted in the Specifications in the form of typewritten memoranda inserted before each Section, listing all materials and equipment which are actually furnished and installed. The information given in the Specifications shall include the manufacturer’s and supplier’s names and addresses, brand name, size and style, model or catalog number and all other information necessary to identify each item completely as installed.

3.13 Use Of Site

Add the following to paragraph 3.13:

3.13.1 The Contractor shall store materials on the site where directed and in such a manner which will not damage the grounds. Material deliveries shall be scheduled so that materials are not stored any longer than necessary. All items furnished to the site by the Owner shall be stored as directed.

ARTICLE 4 ARCHITECT

4.1 General

In the second line of subparagraph 4.1.2, delete "Contractor" in its entirety.

ARTICLE 6 CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS

6.1 Owners Right To Perform Construction And To Award Separate Contracts

00 73 00 - 4

Add the following subparagraph:

6.1.5 Coordinated construction work under this Contract includes, but not be limited to, providing concealed blocking as noted for attachment of separate contract items in locations necessary for the actual items to be installed. Providing proper dimensional coordination of separate contract supplied items for general construction work and trim that is to meet and/or adjoin Furniture, Fixtures, Equipment and Accessories.

6.1.6 It is a requirement of the Contractor’s work schedule to provide the cooperation, coordination and exchange of information necessary for a timely execution of separate contract work.

ARTICLE 7 CHANGES IN THE WORK

7.2 Change Orders

Add the following subparagraphs:

7.2.2 Change order proposals shall be accompanied by itemized breakdowns. Breakdowns shall include not only General Contractor’s itemizations but also those of subcontractors and vendors. Labor rates shall be actual rates paid including only those fringes and taxes actually paid and supported by records.

7.2.3 Except as provided in this article, no oral statement, or direction of Architect or Owner shall be treated as a Change Order or entitle Contractor to an adjustment to the Contract Sum or the Contract Time.

ARTICLE 8 TIME

8.2 Progress And Completion

Add the following subparagraph:

8.2.4 The Owner shall have the right to occupy, without prejudice the rights of either party, any completed or largely completed portions of the structure or work, notwithstanding the fact that time for completing entire Work or such portions thereof may not have expired. Such occupancy and use shall not be an acceptance of that portion of the work taken or used.

8.3 DELAYS AND EXTENSION OF TIME

Add the following to subparagraphs:

8.3.4 Apart from extension of time, no payment or claim for damages shall be made to Contractor as compensation for damages for any ordinary delays or hindrances from any cause whatsoever in the progress of the Work, notwithstanding whether such delay be avoidable or unavoidable.

8.3.5 In order to claim an inclement weather delay day, Contractor must:

8.3.5.1 Document, in writing, that the weather on the particular day was of such nature (rain, wind, snow, ice, and subsequent resultant effects) that it significantly impacted its ability to make progress on critical path work items. Inclement weather delay days will not be granted for weekends or holidays unless Contractor can demonstrate that it had been and intended to work on these days.

8.3.5.2 Submit such delay claims on a weekly basis, not more than 7 days following the day of occurrence.

8.3.5.3 Summarize the number of days claimed for the entire month accompanying each month’s application for payment

00 73 00 - 5

ARTICLE 9 PAYMENTS AND COMPLETION

Add the following subparagraph:

9.3.4 Unless otherwise stated in the Owner-Contractor Agreement, the Owner will retain, until Final Payment, 10 percent of the amount due the Contractor on account of progress payments, payable 30 days after Substantial Completion and/or satisfactory evidence to the owner that all payments, bills, and claims have been paid.

9.3.5 Monthly Applications for Payment shall include waivers of liens for all work included in previous months' application for payment. Waiver of Liens for subcontractors and materialmen shall be total amount paid prior to previous months' application for payment.

9.5 Decisions To Withhold Certification

Add following Sub-subparagraphs to Subparagraph 9.5.1:

1.5.1.8 Failure to submit written plan indicating action by Contractor to regain time schedule for completion of Work within Contract Time.

1.5.1.9 Failure to keep record documents and sustainable submittals current.

9.10 Final Completion And Final Payment

Add the following new paragraph

9.10.2.1 In addition to the items listed in 9.10.2, the Contractor shall deliver the following items to the Owner before final payment will be made:

1. Other close-out submittals as specified in Division 01.

2. Project record documents as specified in Division 01.

3. Operations and maintenance data as specified in Division 01.

4. All warranties as required on specific products or portions of the Work, in format outlined in Division 01.

5. Spare parts, overages, and maintenance materials as outlined in Division 01 and described in the various technical sections.

6. Certificates of occupancy.

7. Copies of all inspection tags from authorities having jurisdiction.

8. Executed Certificate of Substantial Completion.

ARTICLE 11 INSURANCE AND BONDS

11.1 Contractor’s Insurance And Bonds

Add the following subparagraphs:

11.1.5 Within ten (10) days after execution of the Contract and prior to commencement of the work, Contractor must provide a certificate of insurance evidencing the required insurance and naming the Owner as additional insured. The work shall not commence and no payment on the contract will be made by the Owner until all insurance certificates have been filed and accepted by the Owner. The certificate must also indicate that the insurance carried by the Contractor is primary and non-contributing with any insurance coverages of the Owner. The certificate is to contain a thirty (30) day cancellation or material change in coverage. If the Contractor employs subcontractors, the Contractor must obtain certificates of insurance evidencing compliance with the same requirements specified above.

11.1.6 The Contractor must procure and maintain the following insurance coverage naming the Owner, as additional insureds. The insurance policies must be maintained with insurance companies licensed to do business in the state where the property is located.

00 73 00 - 6

SUMMARY

01 10 00 - 1

SECTION 01 10 00

SUMMARY

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Project information.

2. Work covered by Contract Documents.

3. Work performed by Owner.

4. Owner-furnished/Contractor-installed (OFCI) products.

5. Owner-furnished/Owner-installed (OFOI) products.

6. Contractor's use of site and premises.

7. Coordination with occupants.

8. Work restrictions.

9. Specification and Drawing conventions.

1.2 PROJECT INFORMATION

A. Project Identification: AISD Burger Baseball and Softball Improvements.

1. Project Location: 3200 Jones Road, Austin, Texas.

B. Owner: Austin Independent School District.

C. Architect: WRA Architects, Inc., Plano, Texas.

D. Architect's Consultants: Architect has retained the following design professionals, who have prepared designated portions of the Contract Documents:

1. Refer to Title Page.

E. Web-Based Project Software: Project software will be used for purposes of managing communication and documents during the construction stage.

1. See Section 01 31 00 "Project Management and Coordination." for requirements for using web-based Project software.

1.3 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of Project is defined by the Contract Documents and includes, but is not limited to, the following:

1. Outdoor sports pavilions and other Work indicated in the Contract Documents.

B. Type of Contract:

1. Project will be constructed under a single prime contract.

1.4 WORK PERFORMED BY OWNER

A. Cooperate fully with Owner, so work may be carried out smoothly, without interfering with or delaying Work under this Contract or work by Owner. Coordinate the Work of this Contract with work performed by Owner.

1.5 OWNER-FURNISHED/CONTRACTOR-INSTALLED (OFCI) PRODUCTS

A. Owner's Responsibilities: Owner will furnish products indicated and perform the following, as applicable:

1. Provide to Contractor Owner-reviewed Product Data, Shop Drawings, and Samples.

2. Provide for delivery of Owner-furnished products to Project site.

3. Upon delivery, inspect, with Contractor present, delivered items.

a. If Owner-furnished products are damaged, defective, or missing, arrange for replacement.

4. Obtain manufacturer's inspections, service, and warranties.

5. Inform Contractor of earliest available delivery date for Owner-furnished products.

B. Contractor's Responsibilities: The Work includes the following, as applicable:

1. Designate delivery dates of Owner-furnished products in Contractor's construction schedule, utilizing Owner-furnished earliest available delivery dates.

2. Review Owner-reviewed Product Data, Shop Drawings, and Samples, noting discrepancies and other issues in providing for Owner-furnished products in the Work.

01 10 00 - 2

3. Receive, unload, handle, store, protect, and install Owner-furnished products.

4. Make building services connections for Owner-furnished products.

5. Protect Owner-furnished products from damage during storage, handling, and installation and prior to Substantial Completion.

6. Repair or replace Owner-furnished products damaged following receipt.

C. Owner-Furnished/Contractor-Installed (OFCI) Products:

1. PA system, including:

a. Speakers: Danley OS80 – Qty. 2–3, mounted to press box steel and canopy per layout

b. Amplifier: Dynacord C2800FDi

c. Mixer: Alesis MultiMix 10 Wireless

1.6 OWNER-FURNISHED/OWNER-INSTALLED (OFOI) PRODUCTS

A. The Owner will furnish and install products indicated.

B. Owner-Furnished/Owner-Installed (OFOI) Products:

1. As indicated on Drawings.

1.7 CONTRACTOR'S USE OF SITE AND PREMISES

A. Restricted Use of Site: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.

B. Limits on Use of Site: Limit use of Project site to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Driveways, Walkways and Entrances: Keep driveways and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or for storage of materials.

a. Schedule deliveries to minimize use of driveways and entrances by construction operations.

b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

C. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.

1.8 COORDINATION WITH OCCUPANTS

A. Full Owner Occupancy: Owner will occupy Project site and existing adjacent facilities during entire construction period. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's day-to-day operations.

Maintain existing exits unless otherwise indicated.

1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and approval of authorities having jurisdiction.

2. Notify Owner not less than 72 hours in advance of activities that will affect Owner's operations.

1.9 WORK RESTRICTIONS

A. Comply with restrictions on construction operations.

1. Comply with limitations on use of public streets, work on public streets, rights of way, and other requirements of authorities having jurisdiction.

B. On-Site Work Hours: Limit work to between 7:00 a.m. to 6:00 p.m., Monday through Friday, unless otherwise indicated. Work hours may be modified to meet Project requirements if approved by Owner and authorities having jurisdiction.

1. Weekend Hours: Coordinate with Owner.

2. Early Morning Hours: Coordinate with Owner.

3. Work in Existing Building: Coordinate with Owner.

4. Hours for Utility Shutdowns: Coordinate with Owner.

5. Hours for Noisy Activities: Coordinate with Owner.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging for temporary utility services according to requirements indicated:

01 10 00 - 3

1. Notify Owner not less than two days in advance of proposed utility interruptions.

2. Obtain Owner's written permission before proceeding with…