272928MN_Solicitation_Documents_KLB2026.11.17.26.pdf

PDF 1 MB Posted

Attached to
Design Build for Locklear Park Improvements
Solicitation number
272928MN
Issued by
Sarasota County, Siesta Key CDP, Florida

About this file

This solicitation document pertains to a Design-Build services request issued by a Florida county for improvements at Locklear Park. The County is seeking a qualified Design-Build contractor to undertake the Project, with the Design Build Agreement to extend for the duration of the work. The solicitation requires prospective bidders to review the accompanying Solicitation Documents and Attachments, which contain minimum qualifications, detailed scope and specifications, grant documents, and insurance requirements necessary for proposal submission. Specific response dates, due dates, site visit schedules, and bidders' conference information are detailed in the referenced solicitation documents. The contract will be awarded to a single Design-Build firm selected through the competitive procurement process outlined in the solicitation materials.

The solicitation documents contain comprehensive pricing terms, evaluation criteria, and contractual requirements for the Design-Build services. Prospective bidders must demonstrate compliance with insurance requirements and minimum qualifications as specified in the attachments. The file references grant documents that may indicate funding sources for the Project; however, specific funding amounts, sources, and any set-asides are not explicitly identified within this summary document. All technical specifications, pricing parameters, and award conditions are contained within the complete Solicitation Documents and Attachments, which must be thoroughly reviewed by interested proposers prior to submission.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR PROFESSIONAL SERVICES (“RPS”) – PART I

RPS Part I Rev. 02/10/25 Page 1 of 6

RPS #: 272928MN

RPS TITLE: DESIGN BUILD FOR LOCKLEAR PARK IMPROVEMENTS

PURPOSE

In accordance with Section 287.055, Florida Statutes, Sarasota County, a political subdivision of the State of Florida, will receive proposals on the date indicated in OpenGov Procurement (OpenGov), the County’s electronic procurement portal for the purpose of selecting a qualified Proposer to provide Design Build services to include replacement of the playground, site furnishing upgrades, replacement of wooden pedestrian bridge, refurbishment of shade structure, and ADA improvements. Proposers are required to comply with Part II, Design Technical Memorandum.

OpenGov is located at https://procurement.opengov.com/portal/scgov

PROPOSER

2.1 For the purposes of this RPS, the term “Proposer” is defined as the legal entity submitting a proposal.

2.2 Proposers intending to submit a bid as a joint venture with another company must provide documentation attesting to the formation of that joint venture with their submittal. For purposes of this solicitation, all vendors who make up the joint venture will be considered together as the Proposer.

QUALIFICATIONS

3.1 The Proposer must be a Certified General Contractor, or Certified Building Contractor, licensed by the State of Florida, Department of Business & Professional Regulation (DBPR) at the time of submittal.

3.2 At least one key personnel listed in the Proposal must be a registered Professional Engineer (PE), licensed by the Florida Board of Professional Engineers at the time of submittal.

3.3 Proposals should demonstrate experience providing Design-Build services.

3.4 Preferred Qualifications

3.4.1 Proposer’s lead engineer (EOR) licensed by the Florida Board of Professional Engineers has experience in the site design of at least one (1) park project in the past seven (7) years.

3.4.2 Proposals demonstrate experience providing the following:

https://procurement.opengov.com/portal/scgov

RPS Part I Rev. 02/10/25 Page 2 of 6

a. Structural engineering, stormwater modeling, and floodplain and stormwater management

b. Design, permitting and construction of public park projects

c. Design of wooden, concrete, or pedestrian bridges over stormwater management facilities

d. Working on grant funded projects

MEETINGS & SCHEDULE

An anticipated schedule is provided in the Timeline posted in OpenGov. All meetings will take place at the time, date, and location specified in the solicitation Timeline. Short-listed Proposers should be prepared to attend presentations and/or interviews either in Sarasota, Florida or virtually, at the County’s discretion.

SUBMITTAL INSTRUCTIONS

Refer to the Submittal Instructions section in OpenGov for instructions on how to submit a proposal. Proposers are advised to review the General Terms and Conditions of Solicitations which are available in OpenGov.

VENDOR QUESTIONNAIRE

6.1 All proposers must complete the required forms and information included in the Vendor Questionnaire section of OpenGov. Completed forms and other requested documents must be uploaded with proposer’s submittal in OpenGov. Proposers who fail to complete and upload required forms and documents or fail to provide responses to questions in the Vendor Questionnaire section of OpenGov may be found non-responsive.

6.2 Grant Documents

6.2.1 This project includes Community Development Block Grant (CDBG) grant funding. All applicable grant documents will be included in OpenGov. Grant documents that require Proposer’s signature will be available in the Vendor Questionnaire section.

WRITTEN PROPOSALS

The information requested in each section below will be used by the evaluation committee to evaluate and score written proposals. All proposal documents must be submitted in the Vendor Questionnaire section in OpenGov in the format requested.

7.1 Ability of Professional Personnel

RPS Part I Rev. 02/10/25 Page 3 of 6

7.1.1 Single page letter of interest summarizing Proposer’s

qualifications.

7.1.2 Required and preferred licenses and certifications.

7.1.3 Resumes of key personnel, including subconsultants, demonstrating individual qualifications and experience.

7.2 Proposer’s Past Performance & Experience

7.2.1 Complete the Summary of Professional Experience &

Capabilities Form in the Vendor Questionnaire section of OpenGov). Projects submitted should demonstrate the experience of the Proposer, subcontractor(s), and current team members who may have worked for other firms on similar projects and provide detailed information regarding the Proposer’s capabilities, project management techniques, and project controls.

7.3 Approach

7.3.1 Project Approach – Provide a detailed project approach that includes, but is not limited to the following:

a. Project management techniques, controls, program and technologies to be employed to meet project schedule and budget requirements.

b. Assignment of personnel to provide the most efficient service.

c. Where elements of the work will be performed, and who in the organizational chart will oversee performance of the work to provide the most efficient services.

d. Anticipated impacts of the Proposer’s current and projected workload on the project.

e. Detailed information explaining how location of the firm, key personnel and sub-contractors will affect project, including how impact of any physical distance will be mitigated through the use of technology, processes or other means.

7.3.2 Workload

Complete the Current & Projected Workload Form (in the Vendor Questionnaire section of OpenGov) to identify active and awarded projects.

RPS Part I Rev. 02/10/25 Page 4 of 6

7.3.3 Organization

a. Provide an organizational chart delineating personnel assigned to the project (including subconsultants).

b. Provide an organizational chart showing the corporate management structure of the Proposer.

7.3.4 Schedule/Timeline

Provide a graphical representation of the proposed project schedule/timeline indicating major milestones and deliverables.

SELECTION PROCESS

8.1 Written Proposals

8.1.1 All timely responses meeting the criteria set forth in this RPS will be considered by the County.

8.1.2 Written proposals will be evaluated and scored by the

Professional Services Review Committee (PSRC) using the evaluation criteria in the Evaluation Criteria section of OpenGov.

8.1.3 When evaluating written proposals, the PSRC will use the scale below to score each criterion. Only whole numbers are to be used when scoring. Scores will be given weight as indicated in the evaluation criteria in OpenGov.

Score Description

5 Excellent

4 Very Good

3 Good

2 Satisfactory

1 Unsatisfactory

0 N/A

8.2 Presentations

The PSRC will conduct discussions with, and may require public presentations by, no fewer than the three (3) highest scoring Proposer

RPS Part I Rev. 02/10/25 Page 5 of 6

8.3 Ranking

Following discussions or presentations, the PSRC will rank the short-listed Proposers. When ranking short-listed Proposers, the PSRC will consider information contained in the written proposals, clarifications (if any), and information provided during discussions or presentations.

Ranking shall be determined without regard to the score established as a result of the evaluation of written proposals.

8.4 Recommendation of Award

The Proposer ranked first by the PSRC will be recommended for award.

AWARD

9.1 It is the intent of the County to award a contract to the Proposer(s) who, in the sole opinion of the County, is most qualified to perform the scope of services required.

9.2 In the event of a tie the tie-breaking procedures identified in the Sarasota County Procurement Manual will apply.

9.3 Local preference as defined in the Procurement Code section 2-215 is not applicable to this solicitation.

9.4 Contract

A draft of the contract that the successful Proposer(s) will be expected to sign (a Design Build Agreement) is posted on the Procurement website, shown below. The County may, in its sole discretion, select a different contract type or make revisions to the one referenced above following the recommended award of this solicitation.

https://www.scgov.net/government/procurement/contract-templates

CONFLICT OF INTEREST

10.1 Any Proposer who has drafted any portion of a scope of work or specifications for a project, or any entity which provides material assistance to such Proposer in such work, shall be ineligible to compete for the contract for design or construction of that project.

10.2 Selected Proposers, either directly or through an affiliate, may not have a business relationship with any entity to perform work related to a work assignment issued under any resulting contract

RPS Part I Rev. 02/10/25 Page 6 of 6

CHANGES IN PROJECT TEAM

11.1 A change in the project team of a Proposer after the submission of a proposal could result in reconsideration of the scoring of applicable evaluation criteria, at the sole discretion of the County.

11.2 Any changes in the Proposer’s Key Personnel must be brought to the attention of Procurement as soon as possible after the change is made.

The changes, the reasons for the changes, and resumes for the individuals being substituted for an original project team member, must be submitted to the Procurement Analyst identified in the Solicitation Summary prior to the scheduled evaluation committee meeting.

11.3 Decreases in scoring may result from the reconsideration of changes in the project team of a Proposer. No increases in scoring will result from the reconsideration of changes in the project team of a Proposer.

11.4 After recommendation of award, the successful Proposer shall not be allowed to substitute project team members named in this proposal without the prior written permission of the County. Substitution may, in the sole opinion of the County, be grounds for cancellation of a recommended award, or termination of agreement.

REUSE OF EXISTING PLANS

12.1 The plans on this project are subject to reuse in accordance with Section

287.055 (10), Florida Statues.

DESIGN TECHNICAL MEMORANDUM

DESIGN CRITERIA PACKAGE October 7, 2026

RPS Rev. 01/31/20 Part II - Page 1 of 8 Prepared by Capital Projects Department

PART II

TO: Carmen Gomez, Sr. Procurement & Contracts Specialist

FROM: Kimber L. Bereiter, PLA, CPRP, LEED AP BD+C Park Planning and Development Division Manager

DATE: October 07, 2026

SUBJECT: Design Criteria for Locklear Park Improvements

BACKGROUND

Locklear Park is located two blocks south of the Legacy Trail along South Lockwood Ridge Road in North Sarasota County. Named for one of Sarasota’s pioneering families who arrived in the area in the early 19th century, the park is rich in both its cultural and natural heritage. This 9.5-acre park is designed to retain stormwater, and a large boardwalk provides primary access to the park from South Lockwood Ridge Road. Other features include a small restroom building, a picnic pavilion, playground equipment, paved and unpaved trails.

Existing facilities within the project area provided as shown in Attachment 1 need to be replaced and/or expanded to meet recreation needs. This includes the replacement of aging playground equipment and enhancing the playground area by adding benches and picnic tables, refurbishment of existing share structure, improving pedestrian circulation and replacing existing bridge/boardwalk to meet current building codes.

SERVICES

Sarasota County requires a qualified Design Build firm to provide complete Design Build services per the terms of the agreement which generally include, but are not limited to, the following:

1. Project management services as required to ensure design and construction activities comply with the established scope, governmental regulations, budget, and schedule.

2. Perform existing conditions analysis, topographic survey, and geotechnical investigations as needed to support design, permitting, engineering, and construction.

3. Complete professional design and engineering services for the project scope provided including phasing as necessary to meet project budget.

4. Calculate estimates of probable construction cost.

RPS Rev. 01/31/20 Part II - Page 2 of 8

5. Complete permitting applications, submittals, and modifications as required for approvals.

6. Provide a Guaranteed Maximum Price for the proposed improvements.

7. Complete construction services, as the General Contractor, to permit/license, furnish, construct, and inspect the proposed work.

8. Provide Construction Phase Services

9. Supply a General Contractor's one-year warranty to include on-site corrections of warranty items.

10. Provide as-built plans and maintenance/warranty documentation.

DESIGN CRITERIA PACKAGE

PARK NAME AND LOCATION

Locklear Park - 821 S Lockwood Ridge Rd, Sarasota, FL 34237

INFORMATION CONCERNING THE PROJECT AND SITE

Project scope along with attachments listed below are provided in the information package (Exhibit 1):

Attachment 1 – Site Concept Plan Attachment 2 – Existing Condition Summary

INTERIOR SPACE REQUIERMENTS

There are no interior space improvements proposed within the project scope.

MATERIAL QUALITY STANDARDS

All equipment, materials and articles incorporated in the work covered by any resulting contract shall be new and of the most suitable grade for the purpose intended.

The selected Design Builder shall develop Project technical specifications identifying material quality standards for County approval including, but not limited to, the following:

Division 02 – Existing Conditions Division 03 – Concrete Division 04 – Masonry Division 05 – Metals Division 06 – Wood, Plastics & Composites Division 09 – Finishes Division 10 – Specialties Division 11 – Equipment Division 12 – Furnishings Division 13 – Special Construction Division 22 – Plumbing Division 26 – Electrical Division 31 – Earthwork Division 32 – Exterior Improvements Division 33 – Site Utilities Division 35 – Waterway & Marine Construction

RPS Rev. 01/31/20 Part II - Page 3 of 8

EXISTING PARK PLANS

Sarasota County Government will provide the awarded contractor available plans related to Locklear Park.

DESIGN AND CONSTRUCTION SCHEDULE

The primary funding source for the project is a Community Development Block Grant – CDBG HERO. Sarasota County has a deadline of August 2028. All design, construction and closeout work must be completed a minimum of 30 days prior. Firms selected for interviews will be expected to provide their strategy for the project along with an estimated schedule.

LOCKLEAR PARK PROJECT SCOPE

The Project design and construction will include, but is not limited to, the following main elements:

1. Existing facilities within the park shall be replaced or expanded as specifically identified in Part B below. The primary source of funding for this project is a Community Development Block Grant (CDBG)-HERO. Contractors shall conform with any federal requirements associated with this funding source. The project work area is limited to the portion of the park located on the west side of the two ponds on site and north of the wooded area along the property’s southern border. (See Attachments 1 and 2).

2. The Design Build Team (Contractor) shall perform the tasks required to design, permit, and construct the replacements and additions to site features based on the concept drawings provided (See Proposed Site Concept Plan in Attachment 1). Project shall include the following:

A. Existing conditions survey

i. Contractor shall provide an existing conditions survey for the area of proposed improvements and adjacent areas necessary to support design and permitting.

B. Demolition

i. Remove the existing boardwalk to the extent required for the proposed reconstruction. If the existing structure may be salvaged in part, that is an option that can be discussed with the County.

ii. Remove the existing children’s play structure (5-12 years), border and mulch.

iii. Remove the existing tot lot play structure (2-5 years), border, and mulch.

iv. Remove the existing swings, border, and mulch.

v. Remove the existing sidewalks and retaining walls where required to construct the proposed improvements.

C. Playground

i. Theme: The playground shall be visually prominent and visible from Lockwood Ridge Road, with a consistent theme of color and form. The three distinct play areas shall each be visually integrated as part of the overall playground. The playground shall accommodate all ages and abilities in play and the enjoyment of nature. See Attachment 3, Playground Design Intent.

ii. Materials and surfaces: Playground shall be designed for durability and low maintenance. With large oak tree canopies over much of the playground, designs shall avoid surfaces that require frequent clearing of leaves and debris dropped from trees.

RPS Rev. 01/31/20 Part II - Page 4 of 8

iii. While functional synthetic materials may be used, natural materials are preferred over synthetic materials made to look natural. No concrete logs, faux rocks, or plastic trees.

iv. Locations of existing age group areas may change in proposed designs;

however, all user groups shall be accommodated in the final layout.

v. Replace existing tot lot play structure (2-5-year-olds)

a. Play activities to include:

1) Swings

2) Slides

3) Climbers

4) Spring riders

5) Educational/recreational panels

6) Learning and social opportunities, play panel

7) One multi-play apparatus with other smaller pieces

8) One ADA-accessible play feature

vi. Engineered wood mulch safety surfacing, 12” deep

vii. Play area border is concrete sidewalk and 12”x12” concrete curb (no secondary border)

viii. Replace existing children’s play structure (5-12-year-olds)

a. Play activities to include:

1) Swings

2) Slides

3) Climbers (i.e., rope or vertical wall climber without the need for safety equipment);

4) One multi-play apparatus with other separate pieces

5) One ADA-accessible play feature

b. Engineered wood mulch safety surfacing, 12” deep

c. Play area border is concrete sidewalk and 12”x12” concrete curb (no secondary border)

ix. Replace existing swing structure

a. Swing types shall include:

1) Two (2) traditional belt swings

2) One (1) Tot swing

3) One (1) ADA swing/nest swing

b. Engineered wood mulch safety surfacing, 12” deep

c. Play area border is concrete sidewalk (no secondary border)

d. Play apparatus shall meet minimum Americans with Disabilities Act

(ADA) requirements for playgrounds.

e. Safety surface shall meet minimum ADA requirements for playgrounds.

f. ADA access shall be provided to nest swing.

x. Pond Overlook Area

a. Add two (2) picnic tables and one (1) bench to the open space area southeast of the pavilion to provide additional pond viewing seating.

RPS Rev. 01/31/20 Part II - Page 5 of 8

b. Add a minimum of four (4) large shade trees along pond overlook area including 2 trees along the trail.

c. Five (5) sets of trash and recycle receptacles to be added/replaced, not including those associated with 2-pole shelters.

d. Six (6) picnic tables, including two (2) accessible picnic tables

xi. Construct an ADA accessible concrete pad to accommodate 1 double sided kiosk installed by PRNR. The concrete pad with openings for posts to be constructed by Contractor per Parks, Recreation and Natural Resources (PRNR) design standards. PRNR will provide and install the kiosk.

xii. Pedestrian circulation

a. Pedestrian circulation to comply with applicable ADA accessibility requirements.

b. Bicycles and tricycles are a primary form of transportation for many residents in the area and many park visitors arrive by bike.

Bridge/boardwalk and sidewalks shall accommodate bicycle and tricycle traffic. Durable surfaces and sidewalk widths shall accommodate bicycle and tricycle traffic, and bicycle parking should be provided.

xiii. Existing Stormwater Basin

a. Contractor shall not increase the impervious area that is permitted in an existing ERP with SWFWMD. A minor modification may still be required but any change to the capacity of stormwater storage will require modeling.

b. Landscaped slopes with native habitat areas along banks of existing stormwater shall be incorporated where permitted by applicable regulatory requirements, to enhance the bridge and playground areas.

xiv. Landscaping and Irrigation

a. Provide establishment irrigation for proposed plantings.

b. All plantings should be native to the region and compatible with existing site habitat and conditions and low-maintenance conditions of the site.

c. Plant species designed specifically to attract birds and other wildlife shall be incorporated around the bridge and playground areas.

d. Crime Prevention Through Environmental Design (CPTED) standards shall be employed throughout the site.

e. All site furnishings to conform with PRNR Site Furnishings Design

Standards. See Attachment 4.

xv. Pedestrian Bridge/Boardwalk

a. The existing pedestrian boardwalk over a stormwater area through the park at the Lockwood Ridge Road boundary shall be rebuilt or replaced as determined through the Contractor's structural evaluation.

b. Design-build team must determine whether existing structure meets current building codes and may be reconstructed using the existing configuration or needs to be re-designed to meet current code requirements.

c. Deck and railings should conform to Sarasota County Parks, Recreation and Natural Resources (PRNR) Water Access Design Standards for boardwalks. See Attachment 5.

RPS Rev. 01/31/20 Part II - Page 6 of 8

d. Proposed rebuild shall include one or two widened seating areas sized to accommodate seating without obstructing pedestrian circulation for visitors to rest and look over the stormwater area and proposed wetland planting areas.

e. The Lockwood Ridge Road approach to the bridge will rebuild the existing failing retaining walls with either a landscape slope or improved seat wall. The new walls should also allow a turning radius sufficient to accommodate for bicyclists and pedestrians coming and going from the bridge.

f. Rebuild existing sidewalk and landscape area at Lockwood Ridge Road as part of bridge replacement, incorporating an ADA compliant pedestrian entry ramp meeting applicable safety requirements. entry ramp from the street to the sidewalk.

g. All proposed landscape shall meet Sarasota County Landscape Manual standards available online through the Sarasota County Planning and Development Services Unified Development Code webpage. Contractor shall evaluate the feasibility of Low Impact Development measures for street ROW plantings.

h. All accessible parking, wayfinding, park rules, and park entry signage will be incorporated into the proposed bridge redesign.

i. Shade trees to be designed along Lockwood Ridge Road Where permitted by applicable ROW, utility clearance or UDC requirements.

j. Restriping of existing ADA aisle and all parking spaces along Lockwood Ridge Road to be incorporated.

xvi. Walking Trail

a. Restore the existing shell walking trail to provide a continuous, stable walking surface trail from the playground to the east side of the ponds.

xvii. Drinking Fountain

a. Restore the existing shell walking trail to provide a continuous, stable walking surface The existing PVC drinking fountain next to the restrooms shall be removed and replaced with the PRNR standard accessible drinking fountain with bottle filler and pet waterer.

CONTRACTOR RESPONSIBILITIES

1. Every Contractor crew must have at least one employee on site that can effectively communicate in English with the County staff and with the general public.

2. Contractor is responsible for any damage to County or third-party property caused by the Contractor or their employees. Restoration shall be made to a condition equal to or better than the condition existing before the damage, subject to County acceptance.

3. Contractor is required to participate in performance and project report meetings as deemed necessary by the County. Contractor shall attend a minimum of three (3) meetings to discuss plans with PRNR staff and/or regulatory agencies. Additional meetings may be required. Contractor shall prepare meeting notes from each meeting if not provided by regulatory agencies.

4. The Contractor will be responsible for verifying all maps and data provided by the County and obtaining additional information reasonably necessary to complete design and permitting to accurately perform the Scope of Work.

RPS Rev. 01/31/20 Part II - Page 7 of 8

5. Drawings of the Existing Conditions Survey A. Survey all existing built site components within the project area necessary to design the project and obtain all necessary permits (e.g., buildings/structures, hardscape, trees, utilities, topography, surface water bodies, boundaries, easements, rights-of-way, etc.).

B. Conceptual Site Plan

i. Contractor must confirm that project elements on the Conceptual Site Plan provided are feasible based on the above surveys and utility, geotechnical, environmental, stormwater and regulatory information applicable to the proposed improvements. . Contractor will develop a revised program of improvements if required based on verified site conditions or permitting requirement.

ii. Contractor must confirm that approved project elements may be permitted through local, State and Federal regulatory agencies without changes that alter the scope, function, or intended use of the project elements changes to the program elements or without required mitigation activities.

iii. Contractor must provide a required permit list, cost, and timeline for obtaining each required permit.

C. Shop Drawings/ Permit Drawings

i. Contractor must provide shop drawings for proposed construction for approval by PRNR and permit drawings by applicable Federal (ADA), State, County, and local codes and permitting agencies prior to construction.

D. Construction Oversight and Closeout Documents.

i. Provide on-site construction oversight during construction activities as required to fulfill the construction oversight responsibilities identified herein.

ii. The Contractor shall maintain public access to designated portions of the park throughout the construction period. Areas not directly impacted by construction activities shall remain open and accessible to public, provided safe access can be maintained.

iii. The contractor shall furnish, install, and maintain a temporary six foot (6”) high chain link fence around the designated construction to secure the work area and prevent unauthorized public access.

iv. Site Supervisor to meet on-site with Sarasota County PRNR representative every other week through duration of construction to review progress.

a. Consultant shall submit written field notes to the owner within 48 hours of each site visit.

v. Deliverables – Construction Oversight and Closeout Documents

a. Field notes for each site visit

b. As-built plans/documents

c. Permit close-out documents

REQUIREMENTS

1. Contractor shall provide all personnel and equipment necessary to perform the services described herein.

2. All employees of the Contractor shall be considered to be, at all times, the sole employees of the Contractor and under the Contractor’s sole direction.

RPS Rev. 01/31/20 Part II - Page 8 of 8

3. Contractor shall ensure conditions on the work site are orderly, free of accumulated trash and any avoidable safety hazard. The Contractor shall be responsible for all trash and debris disposal from the work site.

HOURS OF WORK / INVOICING

1. Normal Business Hours are defined as Monday through Friday 7:00 a.m. - 5:00 p.m., except County observed Holidays.

2. Contractor shall be paid upon completion of work. Invoicing and payment shall be as described in the General Terms and Conditions.

WARRANTY

All work and materials provided by the Contractor shall be fully warrantied from the date of County’s acceptance of the work for a period of one year, or for the standard warranty period provided by the Contractor or by the materials manufacturer, whichever is greater.

PERMITS

The Contractor is responsible for determining if a permit is required for any work and shall obtain all necessary permits. The Contractor shall be reimbursed for the cost of the permit fee only. No percent markup shall be paid to the Contractor for permit fees.

SUBCONTRACTING

Any use of subcontractors shall be approved in writing, in advance by the County.

Kimber L. Bereiter, PLA, CPRP, LEED AP BD+C Florida Registered Landscape Architect #LA0001680 Sarasota County Parks, Recreation and Natural Resources Sarasota County Government 6700 Clark Road Sarasota, FL 34241 941-313-7060

Kimber Bereiter

KLB PLA

PART III – INSURANCE REQUIREMENTS

Insurance Template 2 Revised 05/13/16 Page 1 of 2

CONTRACTOR’S INSURANCE

Contractor shall, on a primary basis and at its sole expense, maintain in full force and effect, at all times during the life of this Contract, insurance coverage (including endorsements) and limits as described herein. These requirements, as well as the County’s review or acceptance of insurance maintained by Contractor, are not intended to and shall not in any manner limit or qualify the liabilities or obligations assumed by Contractor under this Contract.

Insurance requirements itemized in this Contract and required of the Contractor shall extend to all subcontractors to cover their operations performed under this Contract.

The Contractor shall be responsible for any modifications, deviations, or omissions in these insurance requirements as they apply to subcontractors.

Insurance carriers providing coverage required herein must be licensed to conduct business in the State of Florida and must possess a current A.M. Best’s Financial Strength Rating of A- Class VII or better.

Each insurance policy required by this Contract shall apply separately to each insured against whom claim is made and suit is brought, except with respect to limits of the insurer’s liability.

The Contractor shall be solely responsible for payment of all premiums for insurance contributing to the satisfaction of this Contract and shall be solely responsible for the payment of all deductibles and retentions to which such policies are subject.

Contractor shall furnish Certificates of Insurance to the County Administrative Agent evidencing the types and amounts of coverage, including endorsements, required by this Contract prior to commencement of work and prior to expiration of the insurance contract, when applicable. Such Certificate(s) of Insurance shall, to the extent allowable by the insurer, include a minimum thirty (30) day notice of cancellation (10 days for non-payment of premium) or non-renewal of coverage. Notwithstanding these notification requirements, the Contractor will be required to provide County with at least 5 days prior written notice of any policy cancellation or non-renewal.

The County reserves the right to review, modify, reject, or accept any required policies of insurance, including limits, coverage, or endorsements, herein from time to time throughout the term of this Contract. County reserves the right, but not the obligation, to review and reject any insurer providing coverage due to its poor financial condition or failure to operate legally.

A. WORKERS’ COMPENSATION: Contractor shall maintain Workers’ Compensation insurance in accordance with Florida Statutes, Chapter 440. Employers Liability to be included with a minimum limit of $500,000.00 per accident/per disease/per employee. If work is to be performed over or adjacent to navigable water and involves maritime exposure, applicable LHWCA, Jones Act, or other maritime law coverage shall be included.

In the event the Contractor has “leased” employees, the Contractor or the employee leasing company must provide evidence of a Workers’ Compensation policy for all personnel on the worksite.

PART III – INSURANCE REQUIREMENTS

Insurance Template Adopted 04/19/19 Page 2 of 2

B. COMMERCIAL GENERAL LIABILITY: Contractor shall maintain Commercial General Liability per ISO form CG0001 or its equivalent, including but not limited to coverage for premises and operations, personal injury, products & completed operations, liability assumed under an insured contract, and independent contractors with limits of not less than $1,000,000.00 each occurrence, $2,000,000.00 aggregate covering all work performed under this Contract. There shall be no exclusions for explosion, collapse and underground hazards.

Contractor agrees to endorse Sarasota County Government as an additional insured on the Commercial General Liability coverage.

C. BUSINESS AUTOMOBILE LIABILITY: Contractor agrees to maintain Business Automobile Liability with limits not less than $1,000,000.00 combined single limit for each accident covering all Owned, Non-Owned & Hired automobiles used in the performance of this Contract. In the event Contractor does not own automobiles, Contractor agrees to maintain coverage for Hired & Non-Owned Auto Liability, which may be satisfied by way of endorsement to the Commercial General Liability policy or separate Business Auto Liability policy.

If the Contractor is shipping a product via common carrier, the contractor shall be responsible for any loss or damage sustained in delivery/transit.

D. UMBRELLA/EXCESS LIABILITY: Contractor agrees to maintain Umbrella or Excess Liability with limits not less than $2,000,000.00 each occurrence and in the aggregate. Coverage shall follow the terms of the underlying insurance, including the additional insured provisions.

SPECIALIZED REQUIREMENTS (LIABILITY EXPOSURES)

E. PROFESSIONAL LIABILITY: Contractor shall maintain Professional Liability, or equivalent Errors & Omissions Liability, with limits not less than $1,000,000.00 per claim/occurrence for professional services rendered under this Contract. If coverage is written on a claims-made basis: a. Any retroactive date shall precede the effective date of this Contract; b. Contractor shall provide certificates of insurance evidencing the required coverage for a period of two years after final payment under this Contract is made, or provide evidence showing Contractor has obtained a two-year extended reporting period endorsement.

(END PART III)

272928MN - Part I RPS
272928MN - Part II Scope
PART II
DESIGN TECHNICAL MEMORANDUM
BACKGROUND
Locklear Park is located two blocks south of the Legacy Trail along South Lockwood Ridge Road in North Sarasota County. Named for one of Sarasota’s pioneering families who arrived in the area in the early 19th century, the park is rich in both its cul...
Existing facilities within the project area provided as shown in Attachment 1 need to be replaced and/or expanded to meet recreation needs. This includes the replacement of aging playground equipment and enhancing the playground area by adding benches...
SERVICES
DESIGN CRITERIA PACKAGE
INFORMATION CONCERNING THE PROJECT AND SITE
Project scope along with attachments listed below are provided in the information package (Exhibit 1):
Attachment 1 – Site Concept Plan
Attachment 2 – Existing Condition Summary
INTERIOR SPACE REQUIERMENTS
MATERIAL QUALITY STANDARDS
EXISTING PARK PLANS
DESIGN AND CONSTRUCTION SCHEDULE
The primary funding source for the project is a Community Development Block Grant – CDBG HERO. Sarasota County has a deadline of August 2028. All design, construction and closeout work must be completed a minimum of 30 days prior. Firms selected for i...
LOCKLEAR PARK PROJECT SCOPE
CONTRACTOR RESPONSIBILITIES
REQUIREMENTS
HOURS OF WORK / INVOICING
WARRANTY
PERMITS
SUBCONTRACTING

272928MN - Part III Insurance

2026-11-17T07:15:27-0500
Kimber Bereiter, PLA, CPRP, LEED AP BD+C